Minutes
The Minutes of the
104th Meeting of the Expert Appraisal Committee for Building/
Construction Projects/ Township and Area Development Projects, Coastal
Regulation Zone, Infrastructure Development and Miscellaneous Projects held on
17th –19th August, 2011 at Fazal Chamber, Scope Complex,
New Delhi.
1.
Opening
Remarks of the Chairman.
The Chairman
welcomed the members to the 104th meeting of the EAC. Member
Secretary informed about the action taken on the decisions of the 103rd
meeting held on 13th –15th July, 2011 in New Delhi.
2. Confirmation
of the Minutes of the 103rd Meeting of the EAC held on 13th
–15th July, 2011 at New Delhi.
Minutes
of the 103rd Meeting of the EAC held on 13th – 15th
July, 2011 at New Delhi were confirmed with the following corrections/
amendments.
(i) In
item No. 4.7 - CRZ
clearance for construction of seawater intake and outfall pipeline facilities,
coal corridor, bridge over Buckingham Canal, power evacuation corridor and
approach road from Painapuram, Nellore District, Andhra Pradesh by M/s NCC
Power Projects Ltd [F.No. 11-44/2011-IA-III].
In Para, 5, the water requirement
shall be read as 12, 870 Cum per hour instead of 11,370 Cum per hour. Also
following additional conditions are added.
i)
Effluent from the ash pond shall not be discharged into the marine or
any other recipient system and it will be recycled/ reused completely.
ii)
Online monitoring facilities to monitor parameters such as temperature,
salinity, residual chlorine shall be provided for the effluent discharged
through marine out fall.
iii)
Greenbelt of 50 –150 meters width shall be developed all around the
plant.
iv)
The PP shall submit the details of MOUs entered with cement units shall
be submitted to RO of MoEF and SPCB with in six months.
v)
The PP shall submit specific action plan for of the engineering tools
for to be used for trenching and installation of the pipes/ controlled method
of dredging with latest techniques, to the RO of MoEF and to SPCB with in two
months.
vi)
The budget committed by the project proponent of Rs 33.29 crores towards
CSR in fixed time frame activities shall be maintained. The implementation of
CSR shall be submitted to Ministry and regional office of MoEF every 6 months.
vii)
The
outfall shall have proper diffuser of necessary configuration and length with
well separated ports to achieve non-mixing plumes, required initial dilution
and marine water quality under maximum discharge condition. The sea water
intake shall have appropriate filter so that marine organisms are not sucked in
and fishes can escape from its flow field.
viii)
5% of the
total project cost shall be earmarked towards the corporate social
responsibility (CSR and item-wise details along with time bound action plan
shall be prepared and submitted to the Ministry’s Regional Office.
Implementation of such program shall be ensured accordingly in a time bound
manner.
The Committee recommended addition of the above conditions.
(ii) In item No. 4.18 of the minutes of the EAC
meeting held on 5th –6th April, 2011, Environmental Clearance
for the project (i) development of East quay –IA (EQ-1A) berth on south side of
EQ-1 (ii) development of East quay –1 (EQ-1) by replacing the existing EQ-1
berth and part of EQ-2 berth at Visakhapatnam Port by M/s Visakhapatnam Port
Trust.
The proponent vide letter dated
03.06.2011 has requested for the following amendment in condition no. (xii):
Conditions stipulated by EAC. |
Amendment requested |
(xii)
The coal storage shall be in closed shed to minimize the fugitive emissions
and the drawings shall be submitted to MoEF and SPCB |
The
coal storage shall be enclosed
to minimize the fugitive emissions and the drawings shall be submitted to
MoEF and SPCB |
The Committee recommended
amendment in the minutes subject to the condition that adequate and proper dust
suppressiion measures will be provided and their effective operation will be
ensured.
(iii) In item no. 4.8 of the minutes of 95th
EAC meeting held on 18th – 20th January, 2011-
Finalization of ToR for rehabilitation and upgrading of existing carriageway to
4-lane with paved shoulders configuration of NH-6 from Aurang to Saraipalli in
the state of Chhattisgarh [F. No. 10-80/2010-IA.III].
The EAC considered the above-mentioned project wherein
NHAI presented the salient features of the project as 4-lane with paved
shoulders configuration. MoEF vide
letter dated 28.2.2011 finalized the TOR of the said section for up-gradation
to 2-lane with paved shoulder. NHAI requested to amend the ToR to 4-lane
with paved shoulder instead of 2-lane with paved shoulder.
The Committee recommended
acceptance of the above amendment.
3. Consideration of Old Proposals:
3.1 CRZ and Environment Clearance for the
construction of residential building ‘Cochin Residential Development Project’
at Sy. No. 843 of Ernakulam Village Kerala by M/s TRIF Kochi Projects Ltd
[F.No.11-11/2011-IA-III]
The Committee recommended to defer the
project as requested by the Project Proponent.
3.2 Amendment to the CRZ Clearance issued
for the construction of Sea Water Intake facilities and discharge including
construction of wharf for internal transshipment of coal, Chillakuru Mandal,
Andhra Pradesh by M/s. Simhapuri Energy Pvt. Ltd. (F.No. 11-139/2008-IA.III)
As
presented by the project proponent that the Environmental Clearrnce for setting
up of 540 MW coal based
Thermal Power Project at Thammenapatnam and Momidi villages, Chillakuru Mandal
SPSR Nellore Districtwas issued by the Ministry vide No.J-13011/17/2008-IA-II(T), dated
03.07.2008 and CRZ clearance was issued for intake and outfall facility.
Now, it is understood that the same machineries, the capacity can be enhanced
up to MW. However, there will be no additional water drawal and discharge.
The Committee examined the details
submitted and presented by the project proponent and noted that the changes
proposed are only in the Power plant capacity and there is no change in the CRZ
components, intake and outfall etc., On the basis of material presented and
after discussions, the Committee decided
that no amendment is required. However, the consequential changes, if any,
arising out of increased power plant capacity, to the boundary conditions
assumed in the model for the determination of optimum conditions of mixing and
dilution of the return water from marine environmental considerations shall be
monitored with a view to ensuring that the resulting situation is well within
the acceptable parameters, and conform to the prescribed standards. The fact of
compliance of this specific aspect reflecting the ground realities shall be reported
to the Ministry at the appropriate stage.
4.
Consideration of New Proposals:
4.1
Environmental
Clearance for the development of a green field
Airport at Sindhudurg, Maharashtra by M/s IRB Sindhudurg Airport Pvt. Ltd. [F.No.
10-27/2010-IA.III].
As presented by the project
proponent, the proposal involves development of a green field Airport at
Sindhudurg, Maharashtra. The site is located between village Chippi-vadi and
village Parul, 23 km west of Kudal, district Headquater of Singhudurg. The
airport site reference coordinates are Latitude 16000’ N and
Longitude 73032’ E.
The first evaluation of an
international airport site at Sindhudurg was undertaken by the Airports
Authority of India, who after evaluating various locations, recommended a site
at Mahapen located approximately 20 km south of Kudal. The above site was
examined by RITES, who reported insufficient land for development of an
international airport. Another site between village Chippi-vadi and village
Parule was located 23 km west of Kudal, it was observed that the site was
suitable for development of an airport. MIDC subsequently acquired about 271 ha
of land for the proposed airport. The site is located on Lateritic Plateau with
small mounds and valleys. In
principle approval for the Green field domestic airport project from the
Ministry of Civil Aviation has been obtained vide letter dated 29.09.2008 and
site approval from DGCA vide letter dated 17.05.2008. NOC from Ministry of
Defence has been obtained vide letter dated 09.09.2008.
The proposed runway length is 3450 m, width is 45 m
to service D type aircrafts. A half length parallel taxiway of 1565m which will
be added in phase II and the separation of runway and taxiway will be 176m. ATC
tower, Technical building and metrological lab is also proposed. One level
terminal building has been designed at a norm of 20 sqm per peak hour
passenger. About 61 KLD water is required during construction phase and 350 KLD
during operational phase which will be met from Dhampur, which is 20 km away from
the site. Power supply will be obtained through dedicated lines of Kudal and
Dhampur. Standby DG set of 3X1500 KVA are proposed. Expected sewage generated
will be 180 KLD. No eco sensitive area is within 10 km. radius. Sea coast is appox. at 4 km distance and creek is about 1 km from the
site. The total project cost is 186 Crores.
ToR
for the project was finalized by the EAC in its meeting held on 21st
– 23rd July, 2010 and Public hearing was conducted on 15th
December, 2010 at Chippiwadi, Parule, Tehsil Venguria, District- Sindudurg.
There is a moratorium for the
consideration of projects in Sindhudurg District, however, since the project was received prior to the
imposing the re-examine with reference to OM. Moratorium in August, 2010, the
project is considered as per OM dated 04.07.2011.
The Committee examined the details submitted and presented.
During the discussions, the following points emerged:
i)
Proponent shall examine
the demand/ feasibility of the project taking into consideration of the proposed
Airport in Goa which is at about 100 km distance.
ii)
The waste
water generated from the aircraft maintenance hangers may contain hazardous
materials like lead, chromium, Sulphates, Phenolic compounds, V.O.C’s etc. The
surface runoff from the airport area shall also contain oils, grease, Sulphates
etc, which cannot be sent directly to sewage treatment plant for the treatment.
A separate treatment plant for managing the waste water shall be specified and
adopted.
iii)
Standard instrument arrival and
departure procedure shall be designed to minimise the noise levels within the
permissible limits for the area falling in the funnel near the airport on
either side.
iv)
Energy conservation to the extent of
20% shall be incorporated including water
conservation (reuse/recycle, rain water harvesting and water efficient
fixtures) and other green building practices for various buildings proposed
within the airport complex. The Company shall adopt ECBC Guidelines 2009 to
achieve the energy – efficient design.
v)
The Company shall prepare a detailed traffic management plan to
take care of increased vehicular traffic which should also cover/ clearly
delineate widening/ increasing the existing roads and associated road
infrastructure approving/ installation of road safety features/ pedestrian
facility/FOB/under passes etc (that can be done by carrying out road safety
audits). Measures shall be taken to prevent encroachment along/within the ROWs
on connecting/ main arterial roads. Parking requirements
shall be re-examined and worked out along with circulation plan before the
start of construction work.
vi)
Traffic
Management during construction phase shall be clearly planned so that the
traffic situation is not worsened on the existing connecting roads.
Installations of Noise barrier/ Green Belts should be clearly indicated in the
plan (After identifying critical locations).
vii)
In addition to the above the proponent shall
ensure that all the risks (such as fire, hazardous material waste handling, oil
spills and waste – both liquid/solid wastes) associated/ resultant risks during
various stages of development (like planning, construction, operation) are
managed within the airport area. In case of any unforeseen event as stated
above the liability – environmental and social will rest with the proponent,
the decision of the high level Committee, stipulated below will be full and
final for liability fixations.
viii)
At
least 5% of the total cost of the project shall be earmarked towards the
corporate social responsibility (CSR) and item-wise details along with time
bound action plan shall be prepared and submitted to the Ministry’s Regional
Office at Bhopal and SPCB. Implementation of such program shall be ensured
accordingly in a time bound manner.
ix)
Environment Management Plan or associated monitoring
plan shall ensure that mitigation measures detailed out in terms of role,
responsibility, budgetary provisions, timeline for completion, frequency of
monitoring and compliance etc.
x)
The
Proponent shall review recommendations of ‘Gadgil Committee” and implement the
related/ applicable recommendations if any.
The
Committee recommends the proposal for Environmental Clearance with the above
conditions in the Clearance letter for strict compliance by the project
proponent.
4.2
Environmental
Clearance for the extension/modernization of Agatti Airport, Lakshadweep
Islands by M/s Airport Authority of India. (F. No. 10-70/09-IA III)
Project proponent informed that the Public
Hearing could not be conducted and requested for deferment.
The committee deferred
the project.
4.3
Environmental
Clearance for the development of Phase -II of Gangavaran Port, Visakhapatnam
District, Andhra Pradesh by M/s Gangavaram Port Ltd. [F.No.11-91/2010-IA-III].
As presented by the project proponent,
Gangavaram Port is developed as all
weather multipurpose deepest port in India to handle super cape size vessels
located on the East coast of India approximately 15 km south of Visakhapatnam
Port and acting like gateway port to the existing and green field projects in
the hinterland. At Gangavaram Port presently five berths are under operation to
handle variety of cargoes such as Coal / Iron ore, Fertilizer, Limestone, Food
Grains, and Steel Products etc.
It is
proposed to expand the port facilities from 16.54 MTPA to 41 MTPA to cater for
future cargo within the existing port premises at Gangavaram Village,
Pedagantyada mandal, Visakhapatnam District, Andhra Pradesh. The existing
Project already received Environmental Clearance under EIA & CRZ
notifications vide letter No.10-14/2009-IA.III dt.19th March, 2010.
The following facilities proposed to be planned at Gangavaram port to handle
the above mentioned future traffic up to year 2015, (i) One mechanized coal
berth to handle cape size coal carrier and (ii) Three multipurpose berths to
handle multipurpose/General cargo.
Dredging
to the extent of 4.88 million cubic meters will be carried out in front of the
berths and near the turning basin. The
dredged material will be pumped onshore for reclamation of the port backup
areas.The other associated facilities like Buildings, Storage, roads, railways,
water, power, drainage, sewage, pollution control including Dust suppression
system, greenery fire fighting system etc. are planned to be provided.
Additional Rail sidings will be
developed within port premises to take on additional cargo evacuation. No
additional land requirement as sufficient land is available within existing
port premises. The water requirement will be 1000 m3/day in addition
to existing 600 m3/day of Phase I and will be sourced from Visakha
International Water Supply Company. The Power requirement will be 5 MVA in
addition to 9 MVA of existing Phase – I and will be sourced from APTRANSCO.
Adequate dust suppression measures will be installed in addition to existing
sprayers. Zero waste water discharge shall be maintained by utilising treated
waste water for dust suppression & green belt development. Total
development green belt is 106 acres and further 40 acres will be developed
before January, 2011. The total cost of the project is Rs. 800 crores.
ToR for the project was finalized by the EAC in its 94th Meeting held on 30
November, 1st –2nd December, 2010.
There is a compliant from Forum for Sustainable Development alleging that
GPL has not obtained any change of land use as per the provisions of VUDA
Master Plan, no permission from Greater Municipal Corporation for
construction. No public Hearing was
held, the project is part of cluster of industrial projects, Cumulative EIA to
be conducted, water courses have been affected duo to construction and
resulting flooding. Failed to comply with consent conditions- cleaning/ dust
control along road.
Proponent has
responded to the above issues and submitted the copy of the compliance status
which was submitted to Regional Office of the Ministry at Bengaluru. Public
Hearing was conducted on 12.05.2011
near the main Gate of the Port, Gangavaram.
The details submitted and presented were examined by the
Committee. During the discussions, the following points emerged:
i)
The Environmental
parameters monitored reveals that all the parameters are within the permissible limits. However,
the proponent has not compared the present environmental parameters with the
data prior to the commissioning of the Port. Proponent shall submit the details
of the incremental environmental parameters due to operation of the Port with
reasons for such increment, to the Ministry.
ii)
As the development is
conceived in several stages to reach the full designed/planned capacity of the
port, it shall be necessary to prepare and put in place a master EMP for the
full scale development and fit in the phase-wise creations as modules forming
part of the entire system. This shall facilitate a harmonious planning of
environmental requirements to be put in place in a phased manner in accordance
with preset goal and objective as outlined in the overall environmental plan
for the port in its totality.
iii)
The 4.88 million cum of
dredged material shall be used for shore reclamation subject to its
suitability. Any unsuitable/ excess
dredged material shall be disposed at dumpsite. Port shall identify suitable
dumping spot for disposal of unsuitable material offshore on the basis of
appropriate modeling study.
iv)
The green belt area
proposed is about 10 % only. Proponent shall enhance the area of green belt.
Width of the green belt shall be minimum 50 m. The present stage of development
of 40 acres of land for green belt which should have been completed before
January 2011 shall be reported to the Ministry together with the programme
adopted for implementation.
v)
The Committee observed
that there will be a quantum jump of port traffic from the existing level of
16.54 MTPA to 41 MTPA after completion of the proposed developments and this is
likely to register further leap when full scale planned capacity is reached
later; it is therefore necessary even now to plan appropriate measures to
ensure that will be no mismatch between the planned capacity and the external
logistic requirements in the overall transportation chain/network commensurate
with the demand. A long range vision
would be necessary to achieve a smooth flow of cargo traffic both within and
outside port limits.
vi)
Submit the Risk
Assessment and Disaster Management Plan for handling the liquid caustic soda
for all scenario including leakages and accidental spillages, to the Ministry.
vii)
The Company shall enhance the allocation for the CSR activities from 2. 5 to 5 %
of the total cost and
item-wise details along with time bound action plan shall be prepared and
submitted to the Ministry’s Regional Office at Bangalore. Implementation of
such program shall be ensured accordingly in a time bound manner.
The
Committee recommends the proposal for CRZ and Environmental Clearance with the
above conditions in the Clearance letter for strict compliance by the project
proponent after submission of the information as required above.
4.4
CRZ
clearance for reconstruction of Madre-De-Deus Church, at survey no. 2701 of
Kadakampalli village, Vettucaud, Thiruvananthapuram, Kerala by M/s. Parish Pariest,
Madre-De-Deus Church, Vettucaud Ltd. (F.No. 11-118/2010 – IA.III).
As presented by the project proponent
the proposal is for reconstruction of Madre-De-Deus Church, Vettucaud
Thiruvananthapuram. The church was more than 2 centuries old and was in
dilapidated condition; hence it was decideded to reconstruct the same. The
existing church was demolished and construction was started. Based on a stay
from the Hon’ble Munsiff Court, the construction was stopped.
The plot area of the Church is 1.4271 ha with built up area of 520
Sqm and the proposed construction area is 4180 Sq.m. Maximum Height is 22.1m
and the FSI consumed is 0.18. The water requirement is 16.20 KL/day and the
source is Municipal Corporation, Thiruvandrum. The Sewage generation is about
14.58 KLD which will be treated in the Existing Treatment Plant and the treated
water is used for gardening and flushing. The solid waste generation will be
about 180 kg/day. Bio- degreadable waste will be sent to the existing bio- gas
generation plant along with the sludge from STP and the bio- gas generated will
be consumed in the Kitchen. A D.G set of 62.5 KVA will be located in Sound
proof chamber. Total Cost of the project is Rs. 3.69 Crores.
The HTL demarcation has been done by
the CESS.
Member Secretary informed that Ministry
has received a complaint from Fr. Laberin Yesu. R alleging that the existing
church building is demolished and construction has been started without
obtaining prior permission in the protected Zone of CRZ, Hon’ble Munsiff Court
vide order dated 8th September, 2010, stayed the demolition and
construction until further orders, but the construction is continuing.
Proponent informed that they were not aware of the requirement of CRZ
clearance. As soon as this fact came to their knowledge, they have stopped the
work and will not start without obtaining the clearance.
The
details submitted and presented were examined by the committee. During the
discussion, the following points emerged:
(i)
The Committee noted that as per the recommendation
of the Kerala Coastal Zone Management Authority dated 27.06.2011, the site is
in CRZ –II and landward side of the imaginary line connecting the existing
structure, hence it is a permissible activity under the CRZ Notification, 2011
but the old Church building has been demolished and construction has been
started prior to the clearance which is a violation.
(ii)
The constructions carried out without obtaining
prior CRZ Clearance under CRZ Notification 1991/ 2011. The above constructions/
development are in violation of Environmental (Protection) Act 1986. The
violation has to be dealt as per OM No. No.J-11013/41/2006-IA. II (I) dated 16th
November 2010.
(iii)
Proponent shall incorporate all the necessary
architectural features in the building design.
(iv)
Proponent shall put in place a Disaster Management
Plan including obtaining clearance from the Fire Department in view of the
expecting gathering of about 5000 people once in a week for mess prayers.
(v)
Submit the details of requirement of water
including the treatment of existing and proposed use along with the method of
disposal of treated waste water.
(vi)
Submit landscape plan including parking and
circulation plan etc.
(vii)
Submit details / status of the Court case.
The
Committee recommended the proposal for the CRZ clearance, subject to submission
of above information and suggested for action against violation as per OM dated
16.11.2010.
4.5
Finalization
of ToR for Multipurpose all weather port at Tadadi, Karnataka by M/s Karnataka
Industrial and Infrastructure Development Corporation Ltd [F.No.
11-28/2011-IA-III]
The proposed
Greenfield port is located in Latitude 140 13.50’ N. The Aghanashini
river flows adjacent to the project area and proposed port is situated on the
estuarine zone of the Aghanashini River at a distance of about 50 km from
Karwar, 24 km from Belekeri and 35 km from Honnnavar. A major portion of the
development falls under CRZ-III. The proposed site is not prone to earthquake,
subsidence, landside, etc but erosion & flooding may occur occasionally. No adverse or extreme climatic conditions
are expected based on the climatic history.
This land does not fall in the “Hot Spot”. A preliminary study of three
alternative sites has been carried out, considering both the inner and outer
locations viz. (i) an inner harbour in the Aghanashini Estuary, (ii) an outer
harbour on the northern side and (iii) an outer harbour on the southern
side. A multi criteria analysis of the
three locations has confirmed that the alternative location in the Aghanashini
estuary is most suitable.
The nearest
railway station to Tadadi is at Gokarna which is 5 km from Tadadi on Konkan
Railway. The Konkan Railway line passes through the project site, but does not
connect Tadadi to the hinterland. The
National Highway 17 passes very close to the proposed port area. National Highway 63, State Highway 69 and
the proposed Hubli Ankola Railway lines are other infrastructure facilities
that will support all round development of the port and the region. The air
connectivity is through the airports located at Mangalore & Goa. The port
is being designed to initially handle about 34.25 million tonnes of cargo.
Major cargo expected to be handled by the port is export of iron ore, finished
steel products, fertilizers, etc. and import of coal.
The total
project area is approximately 610 hectares (1400 acres). The land identified
for the project has been acquired for industrial/ infrastructure purpose, quite
some time ago and now vests with the Government. This land is a barren land
presently inundated, which can be utilized for development of sea port and
related facilities. The port envisages facilities for storage and handling of
cargo, like warehouses, open storage yards, etc. Dredging for channel, turning
circle & basin is proposed, with minimum of 18m of water depth below chart
datum at the entrance channel, 16 m in the turning circle and 15.5 m at berth
locations. Major portion of the dredged material will be used for reclamation
of land/ low lying area/ land and remaining will be discharged at the outer sea
as per MoEF notification/ guidelines.
The details submitted and presented were examined by Committee. During
the discussions, the Committee finalized the following additional TOR for
further study:
i)
Submit the details of the
site selection studies with justification pertaining all the three alternate
sites examined with particular focus on environmental issues,
ii)
Submit the details of the
eco-sensitive areas, if any.
iii)
Examine and submit the
details of water bodies including the seasonal ones within the corridor of
impacts along with their status, volumetric capacity and quality, likely
impacts on them due to the project.
iv)
Submit the details of the
fishing activity and likely impact due to the activity.
v)
Submit the details of the
Hydrodynamic study with particular reference to the estuarine location and its
stability due to natural processes.
vi)
Submit the details of
anticipated impact due to the growth scenario/ induced developments because of
the green field Port. Impact
due to influx of people due to port and all other associated activities or
otherwise may be carefully projected and estimated. Commitments for
environmental and ecological protection shall be made quantitatively and
chronologically.
vii)
Submit details of Risk
Assessment, Disaster Management Plan including emergency evacuation during
natural and man-made disaster like floods, cyclone, tsunami and earth quakes
etc.
viii)
Submit the details of Oil
Spill Contingent Management Plan.
ix)
The possibility of
transplanting the existing oyster bed in case disturbance on account of port
activity.
x)
Submit the details of dredging
sludge quantity quality in terms of its toxic metals (atleast Cr+6, Arsenic,
Mercury, and lead) and its disposal with quantity (reclamation/ dredging
disposal site) If disposal is in sea, location, the justification for selecting
such location, the dispersal of dumping material, its effect on marine
environment, effect of fishes.
xi)
Submit the details of change
in estuarine environment such as salinity intrusion, existence of saline wedge
phenomenon etc.
xii)
Submit the details of study
on connectivity and its carrying capacity (both road and railway).
xiii)
Submit the details of existing
port and proposed new ports in west cost on either side of Tadadi with in a
distance of 200 Km.
xiv)
Submit
the details of impact on salt pan existing on the surrounding area.
xv)
Confirm that the proposed
development does not involve court cases.
xvi)
The
mangrove exists about 10 km from the project site. Because of the anthropogenic
activities and human settlement, mangroves are likely to spread in the area. A
study on possible alteration of flora and fauna over long term may be taken up.
xvii)
Although
it was mentioned that there is no forest land in the project area but the area
is very green. No of trees to be cut may be estimated with photographic record.
xviii)
Quantitative
and chronological CSR plan shall be delineated in detail.
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as
per provisions of Environmental Impact Assessment Notification, 2006 and the
issues raised by the public should be addressed in the Environmental Management
Plan.
A
detailed draft EIA/EMP report should be prepared as per the above additional
TOR and should be submitted to the Ministry as per the Notification.
4.6
Finalization
of ToR for setting up of LNG terminal at Ennore, Tamil Nadu by M/s Indian Oil
Corporation [F.No. 11-30/2011-IA.III]
As
presented by the project proponent, the proposal involves setting up of LNG terminal at
Ennore. As a part of diversification
strategy to provide complete fuel solutions to it’s customers, IOCL started
RLNG marketing in the year 2004, as one of the major off takers of RLNG from
Dahej LNG import terminal of Petronet LNG Limited (PLL- a Joint Venture Company
of IOCL, BPCL, GAIL and ONGC). IOCL is marketing around 2.25 MMTPA of LNG on
long term contract from PLL’s Dahej terminal and additional RLNG through short
term contracts and spot cargos also from time to time based on market demand.
IOCL also has a marketing share of 30% of RLNG in the upcoming PLL’s Kochi LNG
terminal which is expected to be operational by end 2012. Ennore Port is an all
weather port with all the infrastructure facilities already in place. Ennore
Port has already earmarked water front for LNG Jetty and land for LNG storage
and re-gasification terminal with in the port premises in their master plan. On
completion of the project RLNG would reach the gas starved Southern states of
India particularly Tamil Nadu and some parts of Karnataka and Andhra Pradesh.
RLNG from the terminal is
proposed to be supplied to customers through extensive pipeline network to the
existing and new power plants, Fertilizer plants, existing and new industries,
CNG/LCNG, CGD etc. LNG would also be supplied by road through cryogenic LNG road tankers to
customers who are far away and not connected with gas pipeline networks.
Earlier in
August 2010, IOCL had signed an MOU with Tamil Nadu Industrial Development Corporation
Ltd. (TIDCO) for jointly setting up the LNG import and re-gasification terminal
including marine facilities, RLNG based Power Plants, Gas Grid in Tamil Nadu in
addition to participating in city gas distribution business in the State of
Tamil Nadu. Government of Tamil Nadu (GOTN) has granted fiscal incentives and
State support for the project including facilitation for setting up City Gas
Distribution (CGD) networks and Gas pipeline Networks etc. in the State.
The details submitted and presented were examined by the
Committee. During the discussions, the
Committee finalized the following additional TOR for further study:
(i)
Submit
site map showing the existing land use surrounding the proposed facility,
layout showing the location/size of the proposed facilities vis a vis the port
constructed, approaches to the port, pipe line routing etc.
(ii)
Submit
the details on the applicability of various rules and regulation and proposed
compliance.
(iii)
Submit
the recommendations of Tamil Nadu CZMA.
(iv)
Submit
a copy of layout superimposed on the HTL/LTL map demarcated by an authorized
agency on 1:4000 scale.
(v)
Submit
details of Risk Assessment and Disaster Management Plan including emergency
evacuation during natural and man-made disaster like floods and other natural
causes including cyclone, tsunami and earth quakes etc.
(vi)
Submit details of safety aspects
associated with handling of LNG vis a vis other cargo in other facilities
within the port.
(vii)
Submit details of storage and
regasification, distribution network etc and vulnerability of human habitation
vis a vis LNG associated risks.
(viii)
Submit phase-wise development
details of the proposed facility in line with the corporate objectives and the
implementation plan.
(ix)
Type of LNG carriers proposed taking
into account the future growth in vessel sizes beyond the present day market
trend and the handling aspects of such vessels from environmental
considerations.
(x)
Submit
details of Environmental Management Plan and Environmental Monitoring Plan with
parameters and costs.
(xi)
Submit
the details of court cases, if any.
(xii)
Submit
the details of the compliance to the conditions of the earlier clearance.
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as per provisions of
Environmental Impact Assessment Notification, 2006 and the issues raised by the
public should be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.7 Finalization
of TOR for the development of all weather Port at Vanagiri, Sirkali,
Nagapattinam District, Tamil Nadu by M/s NSL Nagapatinam Power and Infratech P.
Ltd [F.No. 11- 98/2008-IA-III]
As
presented by the project proponent, the proposal involves development
of all weather Port at Vanagiri, Sirkali, Nagapattinam District, Tamil Nadu. NPIL is developing 2 x 660 MW Coal
based Tehrmal Power Plant, 15 MLD Captive Desalination Plant at Thalachangadu
Village, Thrangambadi Taluk, Nagapatinam District, Tamil Nadu. Environmental
Clearance for the Power plant was obtained vide letter No.
J-13012/74/2008-IA-II (T) dated 13.10.2010. Earlier, ToR was obtained on
06.11.2008 for the development of 15 MTPA captive offshore jetty at a distance
of 2.4 kms from the coastline. Present
proposal is to develop all Weather Port at the same location with Handling
capacity of 30 MTPA including 21 MTPA Coal and export of 9 MTPA Coal Ash.
The
design vessel size will be up to 120,000 DWT for Coal and 10,000 to 20,000 DWT
for Ash. The facility will have approach channel of 3815 x 200 m with 18.6 m
depth, Turning Circle of 510 m with 17.8 m, Four nos. of berths with 2 No. of
600 x 25 and 470 x 25m. Northern breakwater of 1450 m and Southern breakwater
of 980 m are proposed. Dredging of 11 Mcum is expected out of which 4-5 M cum
will be utilized for reclamation and the remaining will be disposed offshore.
The Sea water intake location will be South of Southern breakwater and Outfall
will be North of Northern breakwater.
Tamil
Nadu Maritime Board has allotted 864 m of water front and lands available on
shore with the water front vide G.O Ms No. 147 dated 29.07.2009. The project
site comprises mostly barren lands. It is proposed to provide 6 km long of 2/4
lane road from NH- 45 A to the port site to provide better access to the Power
Plant and the Port. There are no Reserve Forests within the project site. The
Estimated cost is Rs. 1235 Crores.
The
details submitted and presented were examined by the committee. During the
discussions, the Committee finalized the following additional TOR for further
study:
(i)
Submit the details of the
site selection with justification along with details of alternate sites examined.
(ii)
Study the impact of
similar facilities coming up in the vicinity so as to evaluate the cumulative
impact on this project and the impact
of the proposed development on other projects.
(iii)
Submit details of port
limits declared by the State Government authorities for the proposed
development and any development philosophy imposed by State authorities and the
compliance thereon in the planning process.
(iv)
Conduct the shore line change study to
examine the erosion status. If site falls in high erosion zone, the project is
not permissible as per the CRZ Notification, 2011.
(v)
Submit the details of dredging, quality
including its toxic metals (Cr+Arsenic, Mercury and lead), and method of its
disposal.
(vi)
Appropriate littoral drift study will be
required taking into consideration the impact of similar facilities coming up
in the region and having some influence or the other on the proposed
development on environmental aspects.
(vii)
Submit the details of dredging, quality,
method of disposal.
(viii)
Submit the details of Tide gauge and velocity
profile to check the model calculations. Tide and Velocity measurement shall be
simultaneous.
(ix)
Selection of the sampling location for air
shall be based on the wind rose. Submit
the details.
(x)
Marine Traffic should not affect others,
submit the analysis.
(xi)
Examine and submit details of connectivity to
the site through rail/road network.
(xii)
Submit details of type of cargo expected to be
handled in the port.
(xiii)
Submit the recommendations of the SCZMA. The
proponent shall submit the HTL/LTL map of 1: 4000 scale prepared by an
authorized agency superimposed with the layout.
(xiv) Study
the likely impact on Marine Environment (MEIA) and submit EMP with budgetary
provisions and Study the impact on the Fishing activity Total number
of people engaging in fishing /other fisheries related activities in the study
area.
(xv) Submit
the details of back up stockyard and dust suppression measures.
(xvi) Submit
the details of green belt development.
(xvii) Submit
the details of leachate collection and treatment.
(xviii) Submit the details of solid waste and management.
(xix) Submit
the details of water requirement and source.
(xx) Submit
the details of the channel and breakwater.
(xxi) Submit the details of the ships to be handled.
(xxii) Submit the details of the layout plan.
(xxiii) Submit the details of R&R
and social issues.
(xxiv) Submit the details of land
filling.
(xxv) Submit
the details of land breakup along with land use plan.
(xxvi) Submit the details on the
wastewater treatment.
(xxvii) Submit details of Risk Assessment and
Disaster Management Plan including emergency evacuation during natural and
man-made disaster like floods, cyclone, tsunami and earth quakes etc.
(xxviii) Submit details of Environmental
Management Plan and Environmental Monitoring Plan with parameters and costs.
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as per provisions of
Environmental Impact Assessment Notification, 2006 and the issues raised by the
public should be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.8
Finalization
of ToR for Multipurpose Jetty within Navalakhi Port, Maliya, Rajkot District,
Gujarat by M/s DMCC Oil Terminal (Navlakhi) Ltd. [F.No. 11-45/2011-IA-III]
As presented by the Project proponent,
the proposal involves development of Multipurpose
Jetty within Navalakhi Port, Maliya, Rajkot District, Gujarat. The handling
capacity will be 4.5 MMT of various types of cargo viz. Coal, Fertilizers,
Steel/scrap, Timber & General Cargo. It is also proposed to export Food
grains, steel, Salt, DOC & General Cargo. The construction involves a
finger jetty 440 x 42 m length at the 1700 m inside the creek, 3 km long
(1700 m long in water + 1300 m on land) of approach trestle, Temporary Storage
area of about 40 acres and a 288 m long road bridge over Sui creek. The bed
level available at the berth is about –12.0 m and the required depth for the
vessel to be berthed is 12 m, hence no dredging is required. Total area for the
project is 53.53 ha which barren / saline and muddy land is. The water
requirement for the project will be about 435 KLD which will be met from GWSSB.
The Gujarat Coastal Zone Management
Authority has examined the project and recommended vide letter No.
ENV-10-2010-98-E dated 19.05.2011 and provided further information on letter
No. ENV-10-2011-98-E dated 30.07.2011. The GCZMA has stated that as per the
approved CZMP and the CRZ maps prepared by the Space Application Centre, the
proposed site for the development of the Port Terminal and related facilities
fall mainly in the inter tidal area, Categorised as CRZ –I (B) and CRZ-IV as
well as the CRZ –I (A), (due to existence of some mangrove patches)
The details submitted and presented were examined by the
Committee. During the discussions, the Committee finalized the following
additional TOR for further study:
i)
Submit the details of the
site selection with justification along with details of alternate sites
examined.
ii)
Submit the details of the
eco-sensitive areas in the vicinity
iii)
Marine Traffic should not
affect others, submit the analysis.
iv)
Submit the details of the
Hydrodynamic study
v)
Submit details of port
limits declared by the State Government authorities for the proposed
development.
vi)
Submit the details of Oil
Spill Contingent Management Plan.
vii)
Submit the details of
dredging, quality, method of disposal.
viii)
Submit the details of
Tide gauge and velocity profile to check the model calculations. Tide and
Velocity measurement shall be simultaneous.
ix)
Selection of the sampling
location for air shall be based on the wind rose. Submit the details.
x)
Examine and submit
details of connectivity to the site through rail/road network.
xi)
Submit details of type of
cargo expected to be handled and cargo-wise environmental issues and mitigation
measures and appropriate monitoring mechanism to contain adverse impact if
any.
xii)
Submit details of storage
of cargo, handling equipment for evacuation and mitigation measures to contain
surface runoff with due to rains.
xiii)
Submit details whether
the proposed trestle of 1700m long inside the creek will affect its normal
functions for small crafts and the type of construction (piled structure).
xiv)
Study possibility of
improvising/optimizing the facilities available at the Navalakhi Port to meet
the traffic demand before zeroing in on an offshore jetty at the new location;
a techno-economic feasibility study would be desirable with special emphasis on
environmental issues.
xv)
Submit the
recommendations of the SCZMA.
xvi)
Study the likely impact
on Marine Environment (MEIA) and submit EMP with budgetary provisions and Study
the impact on the Fishing activity Total
number of people engaging in fishing /other fisheries related activities in the
study area.
xvii)
Submit the details of
green belt development.
xviii)
Submit the details of
leachate collection and treatment.
xix)
Submit the details of
water requirement and source.
xx)
Submit the details of the
channel.
xxi)
Submit the details of the
ships to be handled.
xxii)
Submit the details of the
layout plan.
xxiii)
Submit details of adverse
impact if any, on creek hydraulic regime, its preservation to maintain its
dynamic equilibrium conditions.
xxiv)
Submit the details of
R&R and social issues.
xxv)
Submit the details of
land filling.
xxvi)
Submit the details of
land breakup along with land use plan.
xxvii) Submit the details on the wastewater treatment.
xxviii) Submit details of Risk Assessment and Disaster Management Plan
including emergency evacuation during natural and man-made disaster like
floods, cyclone, tsunami and earth quakes etc.
xxix)
Submit details of
Environmental Management Plan and Environmental Monitoring Plan with parameters and
costs.
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as per provisions of
Environmental Impact Assessment Notification, 2006 and the issues raised by the
public should be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.9
Finalization
of ToR for expansion of Port facility at Hazira Surat, Gujarat by M/s Essar
Bull Terminal Ltd [F.No. 11-46-2011-IA-III]
As presented by the Project proponent,
the proposal involves expansion of the existing port facility of the Essar Bulk
Terminals Limited (EBTL) on the Tapi estuary at Hazira. EBTL constructed a Deep
Water Berth, a 6.2 km long
and 8 m deep Navigational Channel with a Turning Circle of radius of 600 m to
meet the increasing demand of Essar Steel which is being expanded and other
Essar establishments. The
Environmental Clearance for these developments was granted by the MoEF in
September 2007. Subsequently, in December 2007 the MoEF gave EC for reclamation
of 350 ha to accommodate back-up facilities by utilizing dredged material.
Although the EC was granted for 350 ha reclamation, Essar could reclaim only
186 ha. Because of the shortfall in back-up area the expansion plan of the
steel complex and other Essar establishments at Hazira would be severely
hampered. It is, therefore, proposes to reclaim another intertidal area of 164
ha – the balance of the approved 350 ha. However, there is a mangrove patch to
the south of the area already reclaimed. Hence, it is proposed to reclaim the
area (164 ha) to the south of the mangrove patch.
In addition, it is proposed to expand the Port Terminal further by
developing additional facilities such as (i) Reclamation of another 170 ha for
storing fuel for ships, petroleum products and bulk chemicals such as glycols,
paraffin, butanol etc. (ii) Extending channel from 6.2 to 17.6 km, deepening
from 8 to 16 m and broadening from 180-230 to 300-350 m the Navigational Channel,
(iii). Use of the dredged material for reclamation of 334 ha of the intertidal
area. (iv) Utilization of the water front for Container and Break Bulk Berth
(1100 m) for loading containerized and unit cargo; General Cargo Berth (700 m)
for import of heavy machinery and evacuation of heavy fabricated cargo; Liquid
Cargo Berth (500m) for petroleum products and chemicals ; Bulk Berth (700 m)
for handling increased cargo throughput; Berths for offshore support vessels
(500 m) for support to oil and gas prospecting operations; Dry Dock and Berth
for Ship Repairs (700 m); Trestle Berth (600 m) connecting the reclamation
already completed and the proposed to ensure free flow of seawater in the
mangrove area. All berths will be provided with required topside equipment. Gantry Cranes
will be fitted with enclosed hopper, covered discharge hood and water
sprinkling system to reduce dust generation.
EBTL
has an Oil Pollution Contingency Plan (OPCP) and Tier –I facilities which will
be modified to include proposed expansion. EBTL has a Waste Management Plan
that will be extended to the proposed expansion. Ships will not be allowed to dispose their garbage, solid and oily wastes
while at berth and, if required, facilities for pickup of these wastes will be
provided. The collected waste will be disposed as per the norms of the GPCB. It
will be ensured that the deep-sea ships visiting the berths have onboard sewage
treatment facility. The Port expansion will be on the reclamation area
hence, there are no R&R issues. The total preliminary costing of the Port Expansion.
The cost of the Project is estimated at Rs. 7050 Crores.
During
the discussions, the Committee finalized the following additional TOR for
further study:
(i)
Conduct the shore line change study to know the erosion
status. If site fall in high erosion zone, the project is not permissible as
per the CRZ Notification, 2011.
(ii)
Submit the details of
compliance of conditions of Environmental Clearance.
(iii)
Study cargo-wise impact
and provide appropriate mitigation measures
(iv)
Develop a master EMP
encompassing all aspects of environmental issues for a harmonious development
and implementation in modular form to achieve the desired goal on environmental
upgradation.
(v)
Submit the layout of the
proposed
facilities.
(vi)
Submit the layout showing the mangroves area along
with photos/ Google image/ satellite image with mangrove protection plan and
the area of reclamation.
(vii)
Submit the details of dredging, quantity, quality including its toxic metals
(Cr+Arsenic, Mercury and lead), and
method of its disposal.
(viii)
Submit the details of reclamation, quantity, source
of material and likely impacts.
(ix)
Submit the details of proposed cargo
handling including the details of storage, Transportation etc.
(x)
Submit the details of comparison of baseline data
(prior to construction of port facilities) with the present baseline data on
account of development of existing port.
(xi)
Submit the details of Possibility of change in the
river course on account of deepening of channel.
(xii)
Submit the details of disposal/ treatment of bilge
water, ballast, water used for surface cleaning before painting, Rust removed
from ship before painting etc.
(xiii) Submit the
details of dredging quantity and its disposal with quantity (reclamation/
dredging disposal site) If disposal is in sea, location, the justification for
selecting such location, the dispersal of dumping material, its effect on
marine environment, effect of fishes.
(xiv)
Submit the details of details of existing port and
proposed new ports in Gujarat cost on either side of the existing port, with in
a distance of 200 Km.
(xv)
Submit the details of Environmental impact on
account of induced developments.
(xvi)
Submit the details of Risk analysis and Disaster
Management Plan incase of handling inflammable material and hazardous cargo.
(xvii)
Submit the details of disposal of sludge removed
from the ship, which is
taken for repair at dry dock.
(xviii)
Study
accretion and erosion problems and maintenance thereon
(xix)
Study the
ways and means to preserve and maintain the hydraulic regime of Tapi creek
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as per provisions of
Environmental Impact Assessment Notification, 2006 and the issues raised by the
public should be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.10 Finalization of ToR for development of
proposed Common Effluent Treatment and recovery Plant at Kainduwal, Himachal
Pradesh by M/s Baddi Infrastructure [F.No. 10-53/2011-IA-II]
As presented by
the project proponent, the project involves establishment of common effluent
treatment and recovery plant at Baddi, Himachal Pradesh. The site is located on
a flat terrace surrounded by Dharampur range, Surajpur-Haripur-Mandhala range
and Shivalik hills. The nearest town
Baddi is 750 mts. The CEPI index is just below 70. There are about 1262 industrial units/plots in the industrial
area of Baddi- Barotiwala. The type of industries are Textile, Dyeing &
Spinning -27, Pulp & paper – 3, Pharma – 169, Soap & Detergents – 37,
Food & Beverages – 30, Electroplating & Pickling – 9 and Miscellaneous
– 987. The total sewage load is 4102.4
KLD. The Bio Sludge is 6 tonnes/ day
and Inorganic Sludge is 24 tonnes/ day. The total cost of the project is Rs.60
crores.
The proposal was considered by the EAC in its meeting held on 23rd- 24th June, 2011 but deferred as the project proponents were not clear about details.
The details submitted and presented were examined by the
Committee. During the discussions, the Committee finalized the following
additional TOR for further study:
i)
Submit
the details of effluent collection system at member units level to meet the
inlet norms for the CETP.
ii)
Submit
the effluent conveyance system from the member units to CETP.
iii)
Submit
the details of the CETP with design parameters.
iv) Proper meters with recording facility shall be provided to monitor the effluent sent from member industries to CETP and from CETP to the final effluent pipeline of HPIDC on daily basis.
v) Member industries shall treat the effluent to meet the CETP inlet norms stipulated under EP Act provisions.
vi)
Submit a
copy of MoU made between the Member units.
vii)
Submit
details of storage facility available at the CETP.
viii)
Submit
the details for recycling possibility of the waste.
ix)
Examine
and submit details of sludge generation and method of disposal.
x)
Submit
details of solid waste generated and its disposal.
xi)
Submit
the details of water requirement and water balance chart and how to reduce the
quantity of water required.
General Guidelines
(i)
The EIA
document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On the
front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader
of the EIA study shall also be mentioned.
(v)
All the
TOR points as presented before the Expert Appraisal Committee (EAC) shall be
covered.
Public hearing to be conducted for the project as per provisions of
Environmental Impact Assessment Notification, 2006 and the issues raised by the
public should be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be
prepared as per the above additional TOR and should be submitted to the
Ministry as per the Notification.
4.11 Finalization
of ToR for Municipal Solid Waste Management facility of shillong, Meghalaya by
M/s. SIPMIU, Shillong (F.No. 10-50/2011-IA. III)
As presented by the project
proponent, the proposal involves establishment of the Municipal Solid Waste
landfill site at Umsawli, Shillong,
Meghalaya. The total land available is 21 ha. The land has already been
allotted by the Government of Meghalaya. The land is barren land and there is
no forest, agriculture lands and water bodies. The site is not a flood plain
area. The ground water table is 3 m to
5 m. The design period is for 30 years.
The facility will cater to the Shillong Urban agglomeration of 27.8 sqkm
and Greater Shillong Planning area of 174 sqkm for the design population (2041)
of 675137. The project component involves, collection of wastes from households
using satellite vehicles, setting up of Transfer Stations etc. The Secondary
collection will be through 4.5 Cum capacity trucks and 8.5 cum capacity garbage
trucks.
The details submitted and
presented were examined by the Committee. During the discussions, the Committee
finalized the following additional TOR for further study:
(i)
Submit
a 10 km. radius map (on survey of India toposheet) showing co-ordinates of
project site, national highway, state highway, district road/approach road,
river, canal, natural drainage; protected areas, under Wild Life (Protection)
Act, archaeological site, natural lake, flood area, human settlements (with
population), industries, high tension electric line, prominent wind direction
(summer and winter), effluent drain, if any and ponds etc. should be presented
and impacts assessed on the same.
(ii)
Submit
a copy of the topography of the area contours, slopes indicating whether the
site requires any filling, if so, the details of filling, quantity of fill
material required, its source and transportation, etc.
(iii)
Submit
a copy of the land use certificate from the competent authority.
(iv)
Submit
a copy of the status of ambient air quality and surface and ground water
quality, soil type, cropping pattern, land use pattern, population,
socio-economic status, anticipated air and water pollution.
(v)
Submit
a copy of the layout plan of project site showing solid waste storage, green
belt (width & length, 33% of the project area), all roads, prominent wind
direction, processing plant & buildings etc. should be provided.
(vi)
Examine
and submit details of monitoring of water quality around the landfill site. Water
analysis shall also include for nitrate and phosphate.
(vii)
Examine
and submit details of the odour control measures.
(viii)
Examine
and submit the details of surface hydrology and water regime and impact on the
same.
(ix)
Examine
and submit the details of one complete season AAQ data (except monsoon) with
the dates of monitoring, impact of the project on the AAQ of the area
(including H2S, CH4).
(x)
Submit
the details of sanitary land fill site impermeability and whether it would be
lined, if so details thereof.
(xi)
Examine
and submit the details of impact on environmental sensitive areas.
(xii)
Submit
the details of green belt and buffer between the proposed university and the
site. Submit the details of the road network likely impacts due to
transportation. Submit the details of the MSW Rules compliance.
(xiii)
Submit
Environmental Management Plan and Environmental Monitoring Plan with costs and
parameters.
General Guidelines
(i)
The
EIA document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
(v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should
be prepared as per the above additional TOR and should be submitted to the
Ministry as per the Notification.
4.12 Environmental Clearance for the construction of Control
tower and Technical block at Birsa Munda Airport at Ranchi, Jharkhand by M/s
Airports Authority of India [F.No. 10-64/2011-IA-III].
As presented by the project proponent,
the proposal is for construction of control tower and Technical block at Birsa
Munda Airport at Ranchi, Jharkhand. The Environmental Clearance
for the construction of new Terminal block which
is under construction was obtained vide letter no. 10-73/2008 dated 11.11.2008.
The block after construction will restrict the vision of the Runway & Apron
from the Control Tower partially. This would create problem in handling large
flights, hence it was decided to build a new Control Tower. The Technical block
will have G + 7 floors with area of 1883 sqm.
Committee noted that the proposal is
for shifting/ relocating of the existing Control Tower and technical block and
it will not be considered as expansion/ addition of facility and therefore will
not require a TOR or clearance under 7 (a) of the EIA Notification, 2006.
On the request of the Project Proponent
the committee examined the details under category 8(a) of the EIA Notification
2006, Building/ Construction projects. All the details submitted and presented
were examined by the committee.
The Committee recommended the project
for Environmental Clearance.
4.13 Finalisation
of ToR for the CETP at Village Shrirampur, Tehsil Gamharia District, Saraikella
Kharasawan Jharkhand by M/s Adityapur Auto Cluster [F.No. 10-67/2011-IA-III]
The
Committee deferred the project, as the project proponent did not attend the
meeting.
4.14 Finilisation
of TOR for waste to energy plant at Integrated Solid Waste Management facility
at Narela Bawana, Delhi by M/s Delhi MSW Solution Ltd (F.No.10-67/2009)
As
presented by the Project proponent, M/s. Delhi Waste Management Solutions Ltd.
has established an Integrated Solid waste Management Facility at Narela Bawana
notified site for the management of Municipal Solid Waste generated in Delhi.
Environmental Clearance was earlier issued for 4,000 TPD MSW Integrated MSW
Facility including Collection, Transportation, Storage, Composting, RDF and
Landfill on 25th October, 2010 (F.No.10-67/2009-IA.III).
The
project proponents informed that the proposal submitted to the Ministry had
already proposed to set up Waste to Energy plant of 36 MW in the Phase–II and
has carried out the public hearing accordingly, the Clearance letter did not
indicate the waste to energy plant. They claimed that the details of public
hearing are already available with the Ministry. They requested for the
amendment of the clearance to include the Waste to Energy plant at the proposed
site.
The
Committee examined the details submitted and presented and decided that
amendment to the earlier clearance can not be considered and finalise the TOR
for further study. The project
proponent is required to submit EIA report covering the following TORs for
Waste to Energy.
(i)
Examine
and submit a 10 km. radius map (on survey of India toposheet) showing
co-ordinates of project site, national highways, state highways, district
roads/approach roads, river, canal, natural drainage; protected areas under
Wild Life (Protection) Act, archaeological site, natural lake, flood area,
human settlements (with population), industries, high tension electric line,
prominent wind direction (summer and winter), effluent drain, if any and ponds
etc. should be presented and impacts assessed on the same.
(ii)
Submit
the layout showing the proposed facility and land use details around the site
with photos/ Google / Satellite imageries
(iii)
Submit
the details of the technology selected along with the justification. Examine
and submit details of alternative technologies for Waste to Energy (WtE).
(iv)
Examine
and submit details of storm water/ waste water generation from the WtE Plant.
(v)
Examine and submit details of monitoring of water
quality around the landfill site. Water analysis shall also include for nitrate
and phosphate.
(vi)
Examine and submit details of the odor control
measures.
(vii)
Examine and submit details of impact on water
bodies/rivers/ ponds and mitigative measures during rainy season.
(viii)
Submit a copy of the layout plan of project site
showing WtE plant area, green belt (width & length, a minimum of 33% of the
project area should be reserved under greenbelt), all roads, prominent wind
direction, processing plant & buildings etc. should be provided.
(ix)
Submit a copy of the status of ambient air
quality and surface and ground water quality, soil type, cropping pattern, land
use pattern, population, socio-economic status, anticipated air and water
pollution.
(x)
Submit a copy of the topography of the area
indicating whether the site requires any filling, if so, the details of
filling, quantity of fill material required, its source and transportation,
etc.
(xi)
Examine and submit the details of surface
hydrology and water regime and impact on the nearby habitats/ settlements
(surroundings).
(xii)
Examine and submit the details of AAQ data
(except monsoon) with the dates of monitoring, impact of the project on the AAQ
of the area (including H2S, CH4).
(xiii)
Submit a copy of detailed plan for management of
residues.
(xiv)
Submit
the details of the waste segregation for the project along with the calorific
values and details of enhancement of calorific value if any.
(xv)
Submit the details of disposal of incineration
ash from WtE Plant
(xvi)
Submit the details of Soil analysis including
soil texture. Examine soil
permeability.
(xvii)
Submit
details of WtE technology used to generate energy & measures adopted to
segregate plastics from the waste.
(xviii) Submit a contour map with slope analysis and drainage pattern.
(xix)
Submit the details of Hydrology of the site.
(xx)
Submit the details of Transportation and parking
facilities
(xxi)
Submit the details of Monitoring protocol.
(xxii)
Provide details of air pollution control systems
to reduce air emissions.
(xxiii) Examine and submit the details of impact on environmental sensitive
areas, in the vicinity of the project.
(xxiv) Submit Environmental Management Plan and Environmental Monitoring Plan
with costs and parameters.
General Guidelines
(i)
The
EIA document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
(v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
The
committee recommended to exempt the public hearing as it was earlier conducted
as per provisions of Environmental Impact Assessment Notification, 2006 for
Integrated Solid Waste Management facilities project and the proposed waste to
energy project is to be located within the site allotted by DDA.
A detailed draft EIA/EMP report should be prepared as per
the above additional TOR and should be submitted to the Ministry as per the
Notification.
2nd Day : 18th
August, 2011
Consideration of
Old Proposals, contd…
3.3
Amendment
to Environmental Clearance issued to M/s Mangalore SEZ Ltd. Phase-I project, at
Mangalore (F. No. 21-383/2007-IA III)
As presented by the project proponent, the Mangalore SEZ Phase-I involves (a) MRPL Phase-III
Refinery (b) Aromatic Complex and (c) Olefin Complex in 1800 acres of land. The
proposed MSEZ is planned adjacent to the existing MRPL refinery complex on
north & eastern sides and proposed to connect NMPT with a dedicated 70/100
m vide road-cum-pipeline for movement of cargo, crude and products between New
Mangalore Port and MSEZ.
The environmental clearance
for this project was of issued on 3.4.2008. Now, the project proponent applied
for an amendment of the Environmental Clearance. The MSEZ Phase-I involved (a)
MRPL Phase-III Refinery (b) Aromatic Complex and (c) Olefin Complex over an
area of 1800 acres of land. The following amendments need to be done:
As the Olefin project is shelved due
to non-availability of LNG, the area allocated for Olefin complex is proposed
for downstream Petrochemical units which will consist of (i) P-Xylene based,
O-Xylene based, Benzene based, (ii) Propylene + Benzene based, Pet Coke,
Synthetic Gas-I, (iii) Plastic Park, (iv) Speciality Chemicals and (v)
Synthetic Textiles.
To detach MRPL Phase III Expansion
project from MSEZ Phase I project as MRPL expansion is not part of MSEZ and is
being developed in Domestic Tariff Area (DTA).
The
details submitted and presented were examined by the Committee. During the
discussion, the following points emerged:
(i)
Submit authorized map showing the details of area
earmarked for various activities as per the clearance, changes proposed and
also the CRZ areas.
(ii)
Submit the details of compliance of conditions of
Environmental Clearance.
(iii)
Submit an undertaking to the effect that only the
sector specific units will be permitted in the SEZ and those units shall obtain
separate Environmental Clearance as applicable.
(iv)
Proponent shall enhance
the allocation for the CSR activities from 2. 5 to 5 % of the total cost and item-wise details
along with time bound action plan shall be prepared and submitted to the
Ministry’s Regional Office at Bangalore. Implementation of such program shall
be ensured accordingly in a time bound manner.
(v)
The green belt area
proposed is about 10 % only. Proponent shall enhance the area of green belt.
Width of the green belt shall be minimum 50 m.
The committee suggested that Comments on the
compliance of conditions may also be obtained from the Regional Office of the
Ministry at Bangalore. In case of adding the Olefin Complex in future, the
proponent shall obtain fresh Environmental clearance.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
3.4
Environmental Clearance for Commercial Project at
Plot No.M-1, Village Smaspur, Wazirpur, Tigra, Bindapur, Adampur, Sector-51,
Mayfield Garden, Gurgaon, Haryana by M/s. Sunvision Builders Pvt. Ltd
[F.No.212/SEIAA(H)/2011-IA.III].
The project involves
construction of a commercial complex project on a plot area of 10,896.16 Sq.m.
The total built up area of the project proposed is 32,331.99 Sq.m. The project
will have 2 basements with a maximum height of the building is about 30 m. The
total water requirement proposed is 114 KLD. The capacity of STP is about 110
KLD. Treated water will be used for HVAC cooling/ flushing/ horticulture/ DG
cooling/ gardening–73 KLD. The total power requirement is 2300 KW. The total
parking spaces for group housing proposed are 382 ECS. The total cost of the
project is about Rs. 92.9 Crores.
The proposal was considered by the State
Level Expert Appraisal Committee (SEAC) in its meetings held on 22.10.2009,
19-20th May, 2010, 13.11.2010, 28-29th December, 2010 and 22.1.2011.
The SEIAA in its meeting held on 22.1.2011 observed that the project is for
setting-up of residential colony on an area of 19.069 acres which was granted
by Town & Country Planning Department to M/s. Sheetal International Pvt.
Ltd. The SEIAA noticed that M/s. Sunvision Builders Pvt. Ltd. has applied for a
commercial project on an area of 2.69 acres, out of 19.069 acres project which
was already submitted by M/s. Sheetal International Pvt. Ltd. During the
meeting, the M/s. Sunvision Builders Pvt. Ltd pleaded that they have obtained
conveyance deed of this area from M/s. Sheetal International. However, there
was no valid documental proof available on the file.
The Chairman, SEIAA written a letter to
Town & Country Planning Department, Haryana on 4.3.2011 for a
clarification. The Town & Country Planning department has clarified that
the building plans have not been approved so far for M/s. Sunvision Builders
Pvt. Ltd.
The details submitted and
presented were examined by the committee. During the discussion, the following
points emerged:
(i)
Submit the google image of the site including number of trees.
(ii)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(iii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iv)
Examine and submit the details of water bodies
including the seasonal ones- ponds, lakes, low lying areas within the corridor
of impacts along with their status, volumetric capacity, and quality likely
impacts on them due to the project.
(v)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(vi)
Operation and Maintenance of the STP, Solid Waste Management
of the apartments shall be ensured even after sale.
(vii) Proposal
indicates 114 KLD of fresh water, without assured source of water supply. Overexploited groundwater
and impending severe shortage of water supply in the region requires the
developer to redraw the water and energy conservation
plan. Developer shall submit details of good practices that have been
included in the project to reduce the overall footprint of the proposed
development including a detailed water balance along with source and quantities
of potable and non-potable water requirement (including water
requirement during construction phase) incorporating water
efficiency/savings measures as well as water reuse/recycling within 3 months to
the Ministry/ Regional office at Chandigarh before the start of construction.
(viii) In view of water
resources sustainability and severe constraints of water supply augmentation in
the region the developer will submit NOC from CGWA specifying water
abstraction quantities and NOC from HUDA/ utility provider indicating source of
water supply and quantity of water with details of intended use of water -
potable and non-potable and shall be submitted within 3 months to the Ministry/
Regional office at Chandigarh before the start of construction.
(ix) Submit details of
the ground water table.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
3.5
Environmental Clearance for township project at
Sonepat, Haryana, by M/s. Jindal Realty Private [F.No.327/SEIAA
(H)/2011-IA.III].
The project involves
construction of a Residential plotted colony/township on a plot area of 44.62
ha (4,46,214.8 sqm). The total built up area of the project proposed is
2,33,482.8 Sq.m. The total water requirement proposed is 2454 KLD (fresh water
requirement -1664 KLD). The capacity of STP is about 2000 KLD. Treated water
will be used for HVAC cooling/ flushing /horticulture/ DG cooling /
gardening–1289 KLD. The total power requirement is 11.35 MW. Total solid waste
generation will be 6712 Kg/day. The total parking spaces for group housing
proposed are 1015 ECS. The total cost of the project is about Rs. 102 Crores.
The
proposal was considered by the State Expert Appraisal Committee for New
Construction Projects in its meetings held on 13.10.2010, 25.11.2010, 25.1.2011
and 28-29th March, 2011 at Haryana State Pollution Control Board, Panchkula and
recommended the proposal for environmental clearance after examining the
details sent by the project proponent by imposing specific and general
conditions and awarded “Gold” grading to the project
The details submitted
and presented were examined by the committee. During the discussion, the
following points emerged:
(i)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(ii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iii)
Examine and submit the details of water bodies
including the seasonal ones- ponds, lakes, low lying areas within the corridor
of impacts along with their status, volumetric capacity, and quality likely
impacts on them due to the project.
(iv)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(v)
Operation and Maintenance of the STP, Solid Waste
Management of the apartments shall be ensured even after sale.
(vi)
Proposal indicates 1664 KLD of fresh water, without assured source
of water supply. Overexploited groundwater and impending severe shortage of
water supply in the region requires the developer to redraw the water and
energy conservation plan. Developer shall submit details of good
practices that have been included in the project to reduce the overall
footprint of the proposed development including a detailed water balance
along with source and quantities of potable and non-potable water
requirement (including water requirement during construction
phase) incorporating water efficiency/savings measures as well as water
reuse/recycling within 3 months to the Ministry/ Regional office at Chandigarh
before the start of construction.
(vii)
In view of water resources sustainability and severe
constraints of water supply augmentation in the region the developer will
submit NOC from CGWA specifying water abstraction quantities and NOC from HUDA/
utility provider indicating source of water supply and quantity of water with
details of intended use of water - potable and non-potable and shall be
submitted within 3 months to the Ministry/ Regional office at Chandigarh before
the start of construction.
(viii)
Energy conservation plan with details of percentage saving in energy
shall be submitted to the Ministry/ Regional office at Chandigarh before the start of
construction.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
3.6
Environmental Clearance for the Group Housing
Complex namely “Ninex City” at Sector-76, Gurgaon, Haryana by M/s. Ninex
Developers Ltd [F.No.323/SEIAA(H)/2011-IA.III].
The project involves
construction of a Group Housing Complex on a total plot area 6.806 ha
(68063.129 Sq.m). The total built-up area of the project is 1,61,429.92 Sq. m.
The height of the proposed project is 42.78 mtrs (2 Basements + GF + 13
Floors). The total water requirement is 647 KLD (fresh water requirement -318
KLD). The capacity of STP is about 550 KLD. Treated sewage water will be used
for flushing/horticulture/DG cooling–329 KLD. The total power requirement is
5706 KW. Total solid waste generation is 1658 Kg/day. The total parking spaces
proposed are 1376 ECS. The total cost of the project is about Rs. 219 Crores.
The proposal was considered by the
State Expert Appraisal Committee for New Construction Projects in its meetings
held on 12.11.2010, 9.12.2010, 11.1.2011 and 10.3.2011 and recommended the
proposal for environmental clearance after examining the details sent by the
project proponent and awarded “Gold” grading to the project.
The details submitted
and presented were examined by the committee. During the discussion, the
following points emerged:
(i)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(ii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iii)
Examine and submit the details of water bodies
including the seasonal ones- ponds, lakes, low lying areas within the corridor
of impacts along with their status, volumetric capacity, and quality likely
impacts on them due to the project.
(iv)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(v)
Operation and Maintenance of the STP, Solid Waste
Management of the apartments shall be ensured even after sale.
(vi)
Proposal indicates 318 KLD of fresh water, without assured source
of water supply. Overexploited groundwater and impending severe shortage of
water supply in the region requires the developer to redraw the water and
energy conservation plan. Developer shall submit details of good
practices that have been included in the project to reduce the overall
footprint of the proposed development including a detailed water balance
along with source and quantities of potable and non-potable water
requirement (including water requirement during construction
phase) incorporating water efficiency/savings measures as well as water
reuse/recycling within 3 months to the Ministry/ Regional office at Chandigarh
before the start of construction.
(vii)
In view of water resources sustainability and severe
constraints of water supply augmentation in the region the developer will
submit NOC from CGWA specifying water abstraction quantities and NOC from HUDA/
utility provider indicating source of water supply and quantity of water with
details of intended use of water - potable and non-potable and shall be
submitted within 3 months to the Ministry/ Regional office at Chandigarh before
the start of construction.
(viii)
Energy conservation plan with details of percentage saving in
energy shall be submitted to the Ministry/ Regional office at Chandigarh before the start of
construction.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
4. Consideration
of New Proposals, Contd…
4.15 Environmental
Clearance 0f Group Housing Complex “Seven Lamps” at Sector-82, Gurgaon, Haryana
by M/s. Alden Developers Pvt. Ltd [F.No.21-34/2011-IA.III]
The Committee decided to defer the
project, since the project proponent did not attend the meeting.
4.16 Environmental
Clearance of Group Housing Complex at Village Behrampur, Sector-73, Gurgaon,
Haryana, by M/s. Today Homes and Infrastructure Pvt. Ltd. [F.No.21-35/2011-IA.III]
The project involves the construction of a Group Housing
Complex on a plot area of 43,746.23 Sq.m. The total build-up area is
1,05,215.814 Sq. m. The total water requirement is-490 KLD. The capacity of STP
proposed is- 450 KLD. The treated water will be reused for flushing/gardening/
HVAC & DG cooling and miscellaneous purpose- 200 KLD. The total power
requirement of the project will be 2725.4 KW. Total solid waste generation will
be 1696 Kg/day. The total parking spaces proposed are 1040 ECS. The total cost of the project is 190 Crores.
During the discussion, the following points emerged:
(i)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(ii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iii)
Examine and submit the details of water bodies including
the seasonal ones- ponds, lakes, low lying areas within the corridor of impacts
along with their status, volumetric capacity, and quality likely impacts on
them due to the project.
(iv)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(v)
Operation and Maintenance of the STP, Solid Waste
Management of the apartments shall be ensured even after sale.
(vi)
Proposal indicates 490 KLD of fresh water, without assured source
of water supply. Overexploited groundwater and impending severe shortage of
water supply in the region requires the developer to redraw the water and
energy conservation plan. Developer shall submit details of good
practices that have been included in the project to reduce the overall
footprint of the proposed development including a detailed water balance
along with source and quantities of potable and non-potable water
requirement (including water requirement during construction
phase) incorporating water efficiency/savings measures as well as water
reuse/recycling within 3 months to the Ministry/ Regional office at Chandigarh
before the start of construction.
(vii)
In view of water resources sustainability and severe
constraints of water supply augmentation in the region the developer will
submit NOC from CGWA specifying water abstraction quantities and NOC from HUDA/
utility provider indicating source of water supply and quantity of water with
details of intended use of water - potable and non-potable and shall be
submitted within 3 months to the Ministry/ Regional office at Chandigarh before
the start of construction.
(viii)
Submit the details of the Solid Waste Management
including the consent of the HUDA for taking the wastes.
(ix)
Form1 and Form 1A shall be revised as discussed
during the meeting and shall be submitted to the ministry. The form should
clearly list all government policies, acts, notifications and guidelines –such
as Central Ground Water Authority notification, statutory NCR Regional Plan and
Bureau of Energy Efficiency notification etc.
(x)
The Form 1 and Form 1A and the EIA report should
clearly provide details pertaining to water resources quantity and quality
environment in terms of resources sustainability for the area/site including
details on groundwater depth (per /post monsoon), fluctuation over 4 decades,
available utilizable reserves (specifying for potable and/or other uses) and
quality of groundwater.
(xi)
The
sources of water need to be include quantity, source surface/ground) – in case
of an agency or supplier also. The agency, supplier and permission from CGWA if
required has to specify quantity of water supplied/ extraction permitted,
quality of water with particular use specified and time period commitment to
supply or for making water available to developer.
(xii)
In view
of the water/energy scarcity the developer need to submit details of design and
planning of project with alongwith energy and resource efficiency (including
water efficiency) to reduce footprint of the project. Details on building
material used from embodied energy point of view need to be provided.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
4.17 Environmental
Clearance of Group Housing Complex at Sector-86, Gurgaon, Haryana, by M/s. M/s.
Deepanshu Projects Pvt. Ltd. [F.No.21-36/2011-IA.III]
The project Proponent requested to defer the project they
have revised the project and their total built up area is now more than
1,50,000 sqm and they will be submitting a revised proposal for obtaining
Environmental Clearance.
The Committee decided to defer the
project.
4.18 Environmental
Clearance of Retail cum Office Complex at Sector 114, Gurgaon, Haryana by M/s.
VSR Infratech Pvt. Ltd. [F.No.21-37/2011-IA.III]
The project involves the construction of a
retail-cum-office complex on a plot area of 12,011.05 Sq.m. The total build-up
area proposed is 41,429 Sq.m. The total water requirement is-378 KLD. (Fresh
water requirement is-241 KLD). The capacity of STP proposed is 175 KLD. The
treated waste water will be used for flushing/horticulture/HVAC and DG
cooling-137 KLD. The total power requirement will be 3291 KVA. Total solid
waste generation will be 1141 Kg/day. The total parking spaces proposed are 570
ECS. The total cost of the project is 60 Crores.
The details submitted and presented were examined by the
committee. During the discussion, the following points emerged:
(i)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(ii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iii)
Examine and submit the details of water bodies
including the seasonal ones- ponds, lakes, low lying areas within the corridor
of impacts along with their status, volumetric capacity, and quality likely
impacts on them due to the project.
(iv)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(v)
Operation and Maintenance of the STP, Solid Waste
Management of the apartments shall be ensured even after sale.
(vi)
Proposal
indicates 241 KLD of fresh water, without assured source of water supply. Overexploited groundwater and impending
severe shortage of water supply in the region
requires the developer to redraw the water and energy conservation
plan. Developer shall submit details of good practices that have been
included in the project to reduce the overall footprint of the proposed
development including a detailed water balance along with source and quantities
of potable and non-potable water requirement (including water
requirement during construction phase) incorporating water efficiency/savings
measures as well as water reuse/recycling within 3 months to the Ministry/
Regional office at Chandigarh before the start of construction.
(vii)
In view of water resources sustainability and severe
constraints of water supply augmentation in the region the developer will
submit NOC from CGWA specifying water abstraction quantities and NOC from HUDA/
utility provider indicating source of water supply and quantity of water with
details of intended use of water - potable and non-potable and shall be submitted
within 3 months to the Ministry/ Regional office at Chandigarh before the start
of construction.
(viii)
Energy conservation plan with details of percentage saving in
energy shall be submitted to the Ministry/ Regional office at Chandigarh before the start of
construction.
(ix)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
4.19 TOR for establishment of Mega
Industrial and Energy Park for inclusive growth in District Rewa M/s. Welspun
Energy Park Pvt. Ltd. [F.No.21-38/2011-IA.III].
Member
Secretary informed that the project file is transferred to Power sector for
further necessary action.
4.20 Environmental
Clearance for proposed Group Housing Project Golden Opulence, Poona Mallu
Byepass Road, Poona Mallu Taluk, Thinallur Dist., Tamil Nadu by M/s. Golden Homes
Pvt. Ltd. [F.No.21-40/2011-IA.III].
The project involves
construction of a group housing project a plot area of 32,950 Sq.m. The total
built up area of the project proposed is 1,21,402 Sq.m. Total number of
apartments proposed are 815. The total water requirement proposed is 364.45 KLD
(fresh water requirement 272.875 KLD). The capacity of STP is about 394 KLD.
Treated water will be used for flushing-91.575 KLD, horticulture-25 KLD, club
requirement-6 KLD and public use- 178.625 KLD. The total power requirement is
5000 KVA. Total solid waste generation will be 1630 Kg/day. The total parking
spaces proposed are 1117 Cars + 501 two wheelers. Total cost of the project is
envisaged Rs. 222.152 Crores.
The details submitted and presented were examined by the
committee. During the discussion, the following points emerged:
(i)
Submit the details of the
source, quantity and time line by the supplier with clearance for the water
supply.
(ii)
Submit the details of the
Solid Waste Management including the consent of the Municipality for taking the
wastes.
(iii)
Submit the details of
land use as per the Master plan.
(iv)
The excess treated water shall be disposed into the
drain. The details of the drain along with the consent for such discharge shall
be worked out.
Provided the response of the project
proponent to the aforesaid observations is to the satisfaction of the
committee, the proposal may be considered for recommendation for Clearance.
4.21 Environmental
Clearance for proposed Housing Project at Sy. No. 183/2B, 183/3, 183/4,
Chembarabakkam Vill. & Panchayat, Poonamallu Taluk, Thiruvallur Dist. Tamil
Nadu by M/s. VME Realty Pvt. Ltd. [F.No.21-41/2011-IA.III].
The project involves
construction of a housing project a plot area of 17,004 Sq.m. (1.702 ha). The total built up area of the
project proposed is 29,647.86 Sq.m. total number of apartments proposal are
358. The total water requirement proposed is 162.94 KLD (fresh water
requirement 119.35 KLD). The capacity of STP is about 180 KLD. Treated water
will be used for flushing-43.59 KLD, horticulture-15 KLD, club requirement-3
KLD and nearby plantation-73.41 KLD. The total power requirement is 100 KVA.
Total solid waste generation will be 716 Kg/day. The total parking spaces
proposed are 394 cars +71 two wheeler. Total cost of the project is envisaged
Rs. 35 Crores.
The details submitted and presented were
examined by the committee. During the discussion, the following points emerged:
(i)
Submit the details of the
source, quantity and time line
by the supplier with clearance for the water
supply.
(ii)
Submit the details of the
Solid Waste Management including the consent of the Municipality for taking the
wastes.
(iii)
The excess treated water will be disposed into the
drain. Submit the details of the drain along with the consent for such
discharge.
Provided
the response of the project proponent to the aforesaid observations is to the
satisfaction of the committee, the proposal may be considered for
recommendation for Clearance.
4.22 Finalisation
of ToR for 4 laning with dual carriageway configuration for Km 50.000 to
209.500 (Patiala – Sangrur – Bamala
Bathinda Section) of NH – 64 in Punjab State by M/s Central Works
Division, PWD, B&R, Patiala (F.No.10-70/2011-IA-III)
As presented
by the project proponent, the proposal involves 4 laning with dual carriageway configuration for Km 50.000
to 209.500 (Patiala – Sangrur – Bamala Bathinda Section) of NH – 64 in Punjab
State. The
terrain along the project road is plain except a small stretch of rolling
terrain near Bathinda. Existing length of project road is about 159.500 km.
Proposed length of project road including bypasses is about 166.445 km. The
project road passes through Patiala, Sangrur, Barnala and Bathinda districts in
the state of Punjab. Existing ROW width varies from 15 to 45 m. The proposed
ROW width will be minimum 45 m except proposed Bus Bay, Truck lay byes and toll
plaza locations. For four laning of the existing project road, no Reserve
Forest land diversion will be required. However, 281.3229 ha PF declare on
NH-land may be diverted. There are two
wildlife sanctuaries situated within 10km radius of project road viz. Bir
Motibagh WLS (located 50m-300m away from project road), Patiala and Bir Aishwan
WLS, Sangrur (located 250m -300m away from project road). Project road does not
involve diversion/acquisition of Wildlife Sanctuary. No National Park and
critically identified area exist within the 10km radius of the project road.
For
four laning of the project road, from Patiala- Bathinda including Southern Patiala Bypass, proposed Sangrur
Bypass and Dhanoula Bypass will require felling of 64746 trees (girth size >29cm) and 21094 plants(girth size
<30cm) within the ROW of the project road and 1160 tree in agriculture land. Three
Bypass proposed out of them Southern Patiala Bypass (in between km
50.644 to km 64.200) of NH-64 is existing 2-lane road maintained by BRO and
rest two are new alignment proposed in agriculture land in between km 106.750
to km 116.000 (Sangrur Bypass) and km138.075 to km 142.810 (Dhanoula Bypass) of
project road. Approximately 172.8900 ha
of non forest land may be acquired for four laning of the project road
including bypasses. There will be 1 nos. of major bridges, 29 (23 on Main
Carriageway and 6 on Service Road) minor bridges and 279 culverts in the
project road. In the four laning of the project road, 10 vehicular underpasses
and 20 pedestrian/cattle underpasses have been provided. In the project road,
flyovers have been proposed at 12 locations. The service roads have been
provided in the length of 105 Km (both side) at 33 locations. Bus bays have been provided at
60 locations (LHS+RHS) and truck lay byes at 2 locations. All major junctions (10) and minor junction
(38) will be improved in the project road. Toll plaza is proposed at 3 locations
in the project road. About 540
structures will be affected.
The budget
for environment management, monitoring and including compensatory afforestation
has been earmarked as approximately Rs. 439,728,001. The estimated cost for
Resettlement & Rehabilitation is approximately
Rs. 3,680,000,000. The estimated capital cost
of the project road is Rs. 17,421,698,860.
During the discussions, the Committee finalized the
following additional TOR for further study:
i)
Examine and submit a brief description of the
project, project name, nature, size, its importance to the region/state and the
country.
ii)
Any litigation(s) pending against the proposed
project and/or any directions or orders passed by any court of law/any
statutory authority against the project is to be detailed out.
iii)
Submit detailed alignment plan, with details
such as nature of terrain (plain, rolling, hilly), land use pattern,
habitation, cropping pattern, forest area, environmentally sensitive places,
mangroves, notified industrial areas, sand dunes, sea, river, lake, details of
villages, tehsils, districts and states, latitude and longitude for important
locations falling on the alignment by employing remote sensing techniques
followed by ground truthing and also through secondary data sources.
iv)
Describe various alternatives considered,
procedures and criteria adopted for selection of the final alternative with
reasons.
v)
Submit Land use map of the study area to a
scale of 1: 25,000 based on recent satellite imagery delineating the crop lands
(both single and double crop), agricultural plantations, fallow lands, waste
lands, water bodies, built-up areas, forest area and other surface features
such as railway tracks, ports, airports, roads, and major industries etc. and submit a detailed ground surveyed map on
1:2000 scale showing the existing features falling within the right of way
namely trees, structures including archeological & religious, monuments
etc. if any.
vi)
If the proposed route is passing through any
hilly area, examine and submit the stability of slopes, if the proposed road is
to pass through cutting or embankment/ control of soil erosion from embankment.
vii) If the proposed
route involves tunnelling, the details of the tunnel and locations of
tunnelling with geological structural fraction should be provided. In case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
viii) Study regarding the
Animal bypasses / underpasses etc. across the habitation areas shall be carried
out. Adequate cattle passes for the movement of agriculture material shall be
provided at the stretches passing through habitation areas.
ix)
It is indicated that 64746
trees are proposed
to be cut, the information should be provided about their species and whether
it also involved any protected or endangered species. Necessary green belt
shall be provided on both side of the highway with proper central verge and
cost provision should be made for regular maintenance.
x)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
xi)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
xii)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
xiii)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data collection.
xiv)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
xv)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
xvi)
Climate and
meteorology (max and min temperature, relative humidity, rainfall, frequency of
tropical cyclone and snow fall); the nearest IMD meteorological station from
which climatological data have been obtained to be indicated.
xvii)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
xviii) Identify project activities during construction and
operation phases, which will affect the noise levels and the potential for
increased noise resulting from this project. Discuss the effect of noise levels
on near by habitation during the construction and operational phases of the
proposed highway. Identify noise reduction measures and traffic management
strategies to be deployed for reducing the negative impact if any. Prediction of noise levels should be done by
using mathematical modelling at different representative locations.
xix)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
xx)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
xxi)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
xxii)
If the proposed route
is passing through low lying areas, details of fill materials and initial and
final levels after filling above MSL, should be examined and submit.
xxiii) Examine and submit the water bodies including the seasonal
ones within the corridor of impacts along with their status, volumetric
capacity and quality likely impacts on them due to the project.
xxiv) Examine and submit details of water quantity required and
source of water including water requirement during the construction stage with
supporting data and also classification of ground water based on the CGWA
classification.
xxv)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges. Provision of speed breakers, safety signals, service lanes and
footpaths should be examined at appropriate locations through out the proposed
road to avoid the accidents.
xxvi) If there will be any change in the drainage pattern after
the proposed activity, details of changes shall be examined and submitted.
xxvii) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
xxviii) If there is a possibility that the construction/widening
of road will cause impact such as destruction of forest, poaching, reductions
in wetland areas, if so, examine the impact and submit details.
xxix) Submit the details
of road safety, signage, service roads, vehicular under passes, accident prone
zone and the mitigation measures.
xxx)
IRC
guidelines shall be followed for widening & up-gradation of road.
xxxi) Submit details of
social impact assessment due to the proposed construction of road.
xxxii) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
xxxiii) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
xxxiv)
If
the proposed project involves any land reclamation, details to be provided for
which activity land to reclaim and the area of land to be reclaimed.
xxxv)
Details
of the properties, houses, businesses etc. activities likely to be effected by
land acquisition and their financial loses annually.
xxxvi)
Detailed
R&R plan with data on the existing socio-economic status of the population
in the study area and broad plan for resettlement of the displaced population,
site for the resettlement colony, alternative livelihood concerns/ employment
and rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the implementation of the project specific.
xxxvii) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
xxxviii) Estimated cost of
the project including environmental monitoring cost and funding agencies,
whether governmental or on the basis of BOT etc and provide details of budget
provisions (capital & recurring) for the project specific R&R Plan.
xxxix) Submit environmental
management and monitoring plan for all phases of the project viz. construction
and operation.
General Guidelines:
i)
The
EIA document shall be printed on both sides, as for as possible.
ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.23 Finalisation
of ToR for Gadhuli – Santalpur SH project Padan District, Gujarat by Katchh
Road and Building Division [F.No.10-65/ 2011-IA-III]
As presented by the project proponent,
the proposal involves the construction of Gadhuli
– Santalpur State Highway, Gujarat. The Road and Building Department of Gujarat State
has proposed to construct a linking road. The proposed road is required to
connect the Ghaduli village to Santhalpur. Total length of the road is 255.013
Km out of which 237.05 Km passes through Kutch district and 17.963 Km pass
through Patan district. The villages covered in this project are Gadhuli, Zara,
Zumara, Hajipir, Luna, Odma, Khavada, Kunaria, Tagdibet, Dholavira, Balasar,
Bela, Mauvana, Gadkabet, Vauva and Santhalpur. There are two linking roads in
this project one connecting from Kunharia to Dholavira village and second
Mauvana village to Santhalpur, the total distance of which is 63.30 Km. The
distance of two links is 30.50 km and 32.8 km respectively. Along the proposed
road alignment, most of the stretch is mud road. This road starts from Gadhuli
village on Bhuj Lakhapt SH No.42 in Kutch district and passes through Zara,
Jumara, Hajipir, Luna, Odama, Khavada, Kunaria, Tagribet, Dholavira, Balasar,
Bela, Mauvana, Gadkhabet, Vauva and meets Santhalpur on NH 15 at Santhalpur
village. One of the key purposes of the project is to provide infrastructural
facilities to the security near Pakistan border and promote development of the
locality in rural areas. This road will mainly help in improving the current operational
and administrative requirements of the Border Security Force (B.S.F). It passes
through the great Rann of Kutch, so it will be beneficial for the journey of
military vehicles and reduce the expenditure in fuel and also reduction in
emission of pollutant gases. Presently the way of Dholavira to Kunaria and
Maunava to Vauva is a very long Rann (nearly about 300 km). After construction
of this road, the distance will considerably reduce and a lot of time will be
saved. After construction of this road the saline land problem, too, will get
addressed. Since up-check flow of sea water converts fresh area into saline
land, the existing fresh land will be prevented from becoming saline land.
The proposed road is very near to the
International border and it will be useful for operational and administrative
requirement of Border Security Forces. As it passes through the desert area of
great Rann of Kutch, the movement of vehicles will increase traffic and journey
will become speedy and also reduce expenditure in fuel subsequently reducing
the pollution in the area. Completion of this road will reduce the distance
drastically and will avoid traffic passes through congested area of villages on
the way and through Nakhatrana & Bhuj city.
There is increase in activity on
border and it is required to construct another highway partly across the
desert. There is no parallel link with the border of Pakistan in the area
(Gadhuli to Khavada and Kunariya to Dholavira to Santhalpur) and hence, it is
required to construct this road. Dholavira is the place of Dholavira Harappan
civilization– a very important place from tourism point of view and it has
gained attention at international level. The proposed road will help in access
to Dholavira. The road link between Dholavira to Kunaria and Mauvana to Vauva
will reduce nearly 300 km travel distance.
Although
the road falls under Category ‘B’, 34.9 and 16 km passes through Kutch Desert
Wild Life Sanctuary and Wild Ass Sanctuary respectively. 79.474 ha of forest
land diversion is required, that is why it is treated as Category ‘A’.
During the discussions, the Committee finalized the
following additional TOR for further study:
i)
Examine and submit a brief description of the
project, project name, nature, size, its importance to the region/state and the
country.
ii)
The proposal indicates the acquisition of 79.474 ha forest land. Necessary stage –I forestry clearance shall
be obtained as per OM dated 31.03.2011 and submitted along with final EIA
report.
iii)
Any litigation(s) pending against the proposed
project and/or any directions or orders passed by any court of law/any
statutory authority against the project is to be detailed out.
iv)
Submit detailed alignment plan, with details
such as nature of terrain (plain, rolling, hilly), land use pattern,
habitation, cropping pattern, forest area, environmentally sensitive places,
mangroves, notified industrial areas, sand dunes, sea, river, lake, details of
villages, tehsils, districts and states, latitude and longitude for important
locations falling on the alignment by employing remote sensing techniques
followed by ground truthing and also through secondary data sources.
v)
Describe various alternatives considered,
procedures and criteria adopted for selection of the final alternative with
reasons.
vi)
Submit Land use map of the study area to a
scale of 1: 25,000 based on recent satellite imagery delineating the crop lands
(both single and double crop), agricultural plantations, fallow lands, waste
lands, water bodies, built-up areas, forest area and other surface features
such as railway tracks, ports, airports, roads, and major industries etc.
and submit a detailed ground surveyed
map on 1:2000 scale showing the existing features falling within the right of
way namely trees, structures including archeological & religious, monuments
etc. if any.
vii) If the proposed
route is passing through any hilly area, examine and submit the stability of
slopes, if the proposed road is to pass through cutting or embankment/ control
of soil erosion from embankment.
viii) If the proposed
route involves tunnelling, the details of the tunnel and locations of
tunnelling with geological structural fraction should be provided. In case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
ix)
The project road of length 34.9 and 16 km passes
through Kutch Desert Wild Life Sanctuary and Wild Ass Sanctuary respectively. Clearance should
be furnished at the stage of EC.
x)
Study regarding the Animal bypasses/
underpasses etc. across the habitation areas shall be carried out. Adequate cattle passes for the movement of
agriculture material shall be provided at the stretches passing through
habitation areas.
xi)
Examine and submit details of trees are
proposed to be cut; the information should be provided about their species and
whether it also involved any protected or endangered species. Necessary green
belt shall be provided on both side of the highway with proper central verge
and cost provision should be made for regular maintenance.
xii)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
xiii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
xiv)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
xv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data collection.
xvi)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
xvii)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
xviii) Climate and meteorology (max and min temperature, relative
humidity, rainfall, frequency of tropical cyclone and snow fall); the nearest
IMD meteorological station from which climatological data have been obtained to
be indicated.
xix)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
xx)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical
modelling at different representative locations.
xxi)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
xxii)
Also examine and
submit the details about the protection to existing habitations from dust, noise,
odour etc. during construction stage.
xxiii)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
xxiv) If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
xxv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
xxvi) Examine and submit details of water quantity required and
source of water including water requirement during the construction stage with
supporting data and also classification of ground water based on the CGWA
classification.
xxvii)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and foot
paths should be examined at appropriate locations through out the proposed road
to avoid the accidents.
xxviii) If there will be any change in the drainage pattern after
the proposed activity, details of changes shall be examined and submitted.
xxix) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
xxx)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
xxxi) Submit the details
of road safety, signage, service roads, vehicular under passes, accident prone
zone and the mitigation measures.
xxxii) IRC guidelines shall
be followed for widening & up-gradation of road.
xxxiii) Submit details of
social impact assessment due to the proposed construction of road.
xxxiv) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
xxxv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
xxxvi) If the proposed
project involves any land reclamation, details to be provided for which
activity land to reclaim and the area of land to be reclaimed.
xxxvii) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
xxxviii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
xxxix) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
xl)
Estimated
cost of the project including environmental monitoring cost and funding
agencies, whether governmental or on the basis of BOT etc and provide details
of budget provisions (capital & recurring) for the project specific R&R
Plan.
xli)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation.
General Guidelines:
i)
The
EIA document shall be printed on both sides, as for as possible.
ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.24
Finalisation
of ToR widening and improvement of existing carriageway to 2-Lane with paved
shoulders configuration of NH-43 in the section Dhamtari to Jagdalpur from Ch.
82.000 to Ch. 298.000 in the State of Chhattisgarh by M/s NHAI.
[F.No.10-23/2011-IA-III ]
As presented by the project proponent, the proposed road
starts from km 82 of NH-43 near Dhamtari and ends at Jagdalpur km 298 covering
length about 216 kilometers. The project road falls in Dhamtari, Durg, Kanker
and Baster district of Chhattisgarh. The project road mainly passes through
plain & rolling terrain except in Keshkal & Charama Ghat where it is
hilly for about 9.50 km length. Land use pattern of the project area is mainly
agriculture and forest. There are built up areas along project corridor of
residential & commercial purpose. There is no Major industrial area along
project corridor except Iron & Steel Plant of NMDC. The project road
section passes mainly through built up areas of Chitod, Purur and Balodgahan in
Durg district and Charama, Lakhanpuri, Makdi, Kanker, Singarbhat in Kanker
district and Keshkal, Pharasgaon, Boregaon, Kondagaon, Baniyagaon, Bhanpuri,
Baster and Jagdalpur in Jagdalpur district.
The
existing carriageway of the existing alignment is 7.00m with 1.0m to 2.0m soft
shoulder. The riding surface condition of existing carriageway in general is in
good condition. Existing RoW of the project road in km 82 to 84 is 24.40m, km
85 to 105 it is 36.58m and from km 106 to 298 it is 24.0m. The proposed right
of way (RoW) is 45m for existing alignment and 60m is kept for bypasses and 30m
for forest area on existing alignment & on bypasses. Approximately 590
hectare land is proposed to be acquired for the improvement of project road, which includes forest land of about 196
hectare. The length affected due to forest is about 92.0km. Tree cutting
mainly within existing RoW will be required for the construction of 2 lane
road, Proposal for cutting of trees standing on proposed RoW shall be submitted
to State Govt. The project road does not pass through any eco-sensitive areas.
There is no wild life sanctuary or National Park on the project highway.
Approximately 25218 trees proposed to be felled
for the improvement of project road, against which about 75000 trees shall be
planted as avenue plantation apart from statutory requirement. There are
existing 10nos. of major bridges, 50 nos. minor brides, 140 nos. of slab/arch
culvert and 119 nos. of pipe culverts. Out of which 7 nos of major bridge and
17 nos. of minor bridges are proposed for new construction and 7nos. of minor
bridge proposed for reconstruction. The 67nos. and 93nos. of culverts are
proposed for new construction and reconstruction respectively. No ROB/RUB and
fly over is proposed. There are 6 major junctions and 148 minor intersections
on the project highway. The 10 no. of road junctions are proposed for
improvement as per IRC – 41.
Prominently
59 villages are lying on the project road and other effected villages fall in
the road corridor combining together to 107 villages. Out of which 2 villages
in Dhamtari district, 8 villages in Durg district, 31 villages in Kanker
district and 66 villages in Jagdalpur distinct. At about 9 location service
road is proposed in a length of about 4053 m on either side. 9 nos. of under
passes in villages where school going children and other persons cross the
project road have been provided. Truck lay byes have been proposed at 2-
locations on both sides of the road. Ch. 156/30 RHS & Ch. 240/400 LHS. Bus
bays & shelters have been proposed near all the villages/towns. 4 nos. of
bypasses of about 37.0 km in length have been proposed out side of Charama town
(length is 5.50 km), Kanker town (Length 11.30km), Keshkal town (length
10.20km) and Kondgaon (length 9.5 km) due to congestion in these built up town
portions. The average daily traffic on project road based on traffic count at
seven traffic count stations is 8161 PCU. Four no. of Toll Plazas are proposed
at locations in km 128/6, km188/8, km 255/6 and km 286/2 of the project road.
About 250 to 350 KLD water shall be required during construction including
plantation and dust suppression. Fly
ash will be used for construction of road from Bhilai Steel Plant and
NTPC Sail power Plant as per MoEF notification.
The approximate budget for Environmental
Impact & Mitigation measures during construction and operation phase is
about Rs.12.90 crores. The cost Budget for Resettlement and Rehabilitation is
about Rs.101.52 crores. Which includes land & other structures cost i/c
assistance to the affected people. The total civil cost of the project is
Rs.685.72 crores and total project cost is Rs.792.00
During the discussions,
the Committee finalized the following additional TOR for further study:
(i)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(ii)
The proposal indicates
the acquisition of 196 ha forest land. Necessary stage –I forestry clearance
shall be obtained as per OM dated 31.03.2011 and submitted along with final EIA
report.
(iii)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(iv)
Submit detailed
alignment plan, with details such as nature of terrain (plain, rolling, hilly),
land use pattern, habitation, cropping pattern, forest area, environmentally
sensitive places, mangroves, notified industrial areas, sand dunes, sea, river,
lake, details of villages, teshils, districts and states, latitude and
longitude for important locations falling on the alignment by employing remote
sensing techniques followed by ground truthing and also through secondary data
sources.
(v)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(vi)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural
plantations, fallow lands, waste lands, water bodies, built-up areas, forest
area and other surface features such as railway tracks, ports, airports, roads,
and major industries etc. and submit a
detailed ground surveyed map on 1:2000 scale showing the existing features
falling within the right of way namely trees, structures including
archeological & religious, monuments etc. if any.
(vii)
The proposed route is
passing through hilly area, examine and submit the stability of slopes, if the
proposed road is to pass through cutting or embankment/ control of soil erosion
from embankment.
(viii)
The proposed route
involves tunnelling, the details of the tunnel and locations of tunnelling with
geological structural fraction should be provided. In case the road passes through a flood plain of the river, the
details of micro drainage, flood passages and information on flood periodicity
at least of last 50 years in the area should be examined.
(ix)
Study regarding the
Animal bypasses / underpasses etc. across the habitation areas shall be carried
out. Adequate cattle passes for the movement of agriculture material shall be
provided at the stretches passing through habitation areas.
(x)
It
is indicated that 25218 trees are
proposed to be cut, the information should be provided about their species and
whether it also involved any protected or endangered species. Necessary green
belt shall be provided on both side of the highway with proper central verge
and cost provision should be made for regular maintenance.
(xi)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
(xii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
(xiii)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xiv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data collection.
(xv)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
(xvi)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xvii)
Climate and meteorology
(max and min temperature, relative humidity, rainfall, frequency of tropical
cyclone and snow fall); the nearest IMD meteorological station from which
climatological data have been obtained to be indicated.
(xviii)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xix)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical
modelling at different representative locations.
(xx)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
(xxi)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxii)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
(xxiii) If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
(xxiv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
(xxv)
Examine and submit
details of water quantity required and source of water including water
requirement during the construction stage with supporting data and also
classification of ground water based on the CGWA classification.
(xxvi)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and foot
paths should be examined at appropriate locations through out the proposed road
to avoid the accidents.
(xxvii) If there will be any change in the drainage pattern after
the proposed activity, details of changes shall be examined and submitted.
(xxviii) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
(xxix)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
(xxx)
Submit
the details of road safety, signage, service roads, vehicular under passes,
accident prone zone and the mitigation measures.
(xxxi)
IRC
guidelines shall be followed for widening & up-gradation of road.
(xxxii) Submit details of
social impact assessment due to the proposed construction of road.
(xxxiii) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
(xxxiv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxv)
If
the proposed project involves any land reclamation, details to be provided for
which activity land to reclaim and the area of land to be reclaimed.
(xxxvi) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
(xxxvii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the implementation of the project specific.
(xxxviii)Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
(xxxix) Estimated cost of
the project including environmental monitoring cost and funding agencies,
whether governmental or on the basis of BOT etc and provide details of budget
provisions (capital & recurring) for the project specific R&R Plan.
(xl) Submit environmental
management and monitoring plan for all phases of the project viz. construction
and operation.
General Guidelines:
i)
The
EIA document shall be printed on both sides, as for as possible.
ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.25 Finalisation
of ToR widening and improvement of existing carriageway to 4/6 – Laning of
Meerut-Bulandshahar section (Km 0+0000 to Km 66+482) of NH-235 in Uttar Pradesh
by M/s NHAI. [F.No. 10-24/2011-IA-III]
As presented by the project
proponent, the proposal involves Bookman Old Style. The project road starts at Km 7.469 near Meerut
city limits and ends at Km 66.482 at Bulandshahar town. The project road is
situated in Meerut, Ghaziabad and Bulandshahar districts in the State of Uttar
Pradesh. There are 4 congested
stretches where bypass have been proposed in totaling length of 25.903 km.
There is no realignment on the proposed alignment. The land use along the
project road is predominantly agricultural and built-up villages and towns. The
tentative percentage distribution of land use is 10%, 43% & 47% for Semi Built-up,
Built-up, and agricultural, respectively.
The existing Right of Way (RoW) is approx. 30 m - 35 m except in
semi-urban and urban stretches where it varies from 20 m to 25m. The proposed
ROW is 60m except in built-up areas where it is 45m. Approximately 253.6 ha of
land will be acquired for four laning of the project road; which includes 105.5
ha for widening and toll plaza and 148.1 ha land for bypasses.
The project road does not pass
through Reserved Forest. However, project road will involve 88.63 ha diversion of
protected forest land. Due to four laning of the project road, approximately
11432 trees are likely to be felled.
The project road does not pass through any sensitive area like wildlife sanctuary,
national park and bio-reserve. There is no environmental sensitive location
within 10 km distance from the project road.
Four laing of the project road will not impact any pond or water body. There are 1 major bridge, 6
minor bridges, 67 culverts (pipe, slab and box culverts) on the project road. The
proposed alignment will have 1 major bridge, 6 nos. minor bridges, 1 ROB and 58
nos. culverts. Three vehicular underpasses and four cattle/pedestrian
underpasses have been proposed in the alignment. Bus bay at 4 nos. locations
and bus shelters have been proposed at 11 nos. locations. Truck lay byes have
been provided at 1 no. location. There are 10 major junctions and 68 minor
junctions, which are proposed to be improved. One Toll plaza is proposed at
near km 43.
The project road passes
through 17 villages and towns, out of which 8 villages/towns are in Meerut
District, 4 villages/towns are in Ghaziabad District and 5 villages/towns are
in Bulandshahr District. Due to four laning of the project road, about 146
structures (houses and shops) may be affected and compensated as per National
Highways Act. Tentative cost of
implementation of EMP will be Rs 7.65 Crores. Land
Acquisition and R&R Cost is estimated as Rs. 70.7 Crores. The civil
construction cost of project is Rs. 417.77 Crores as per 2010-2011 prices.
During the discussions, the Committee finalized the
following additional TOR for further study:
(i)
Submit the details of
accident prone area and mitigation proposed
(ii)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(iii)
The proposal indicates
the acquisition of 88.63 ha forest land. Necessary stage –I forestry clearance
shall be obtained as per OM dated 31.03.2011 and submitted along with final EIA
report.
(iv)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(v)
Submit detailed
alignment plan, with details such as nature of terrain (plain, rolling, hilly),
land use pattern, habitation, cropping pattern, forest area, environmentally
sensitive places, mangroves, notified industrial areas, sand dunes, sea, river,
lake, details of villages, teshils, districts and states, latitude and
longitude for important locations falling on the alignment by employing remote
sensing techniques followed by ground truthing and also through secondary data
sources.
(vi)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(vii)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural
plantations, fallow lands, waste lands, water bodies, built-up areas, forest
area and other surface features such as railway tracks, ports, airports, roads,
and major industries etc. and submit a
detailed ground surveyed map on 1:2000 scale showing the existing features
falling within the right of way namely trees, structures including
archeological & religious, monuments etc. if any.
(viii) If the proposed
route is passing through any hilly area, examine and submit the stability of
slopes, if the proposed road is to pass through cutting or embankment/ control
of soil erosion from embankment.
(ix) If the proposed
route involves tunnelling, the details of the tunnel and locations of
tunnelling with geological structural fraction should be provided. In case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
(x)
The projects is located within 10km. of the
sanctuary a map duly authenticated by
Chief Wildlife Warden showing these features vis-à-vis the project location and
the recommendations or comments of the Chief Wildlife Warden thereon should be
furnished at the stage of EC.
(xi)
Study regarding the Animal bypasses /
underpasses etc. across the habitation areas shall be carried out. Adequate cattle passes for the movement of
agriculture material shall be provided at the stretches passing through
habitation areas.
(xii)
It is indicated that 11432 trees are proposed
to be cut, the information should be provided about their species and whether
it also involved any protected or endangered species. Necessary green belt
shall be provided on both side of the highway with proper central verge and
cost provision should be made for regular maintenance.
(xiii) If the proposed route is passing through a city or town,
with houses and human habitation on the either side of the road, the necessity
for provision of bypasses/diversions/under passes shall be examined and
submitted. The proposal should also indicate the location of wayside amenities,
which should include petrol station/service centre, rest areas including public
conveyance, etc.
(xiv)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
(xv)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xvi)
Clearly
indicate/provide details regarding the location, date (along with site photographs
with the background of monitoring equipments and/or sample collection in
process) and protocol adopted for sampling and analysis of various
environmental parameters as a part of the baseline data collection.
(xvii) Examine and submit
the details of use of fly ash in the road construction, if the project road is
located within the 100 km from the Thermal Power Plant.
(xviii)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xix)
Climate and
meteorology (max and min temperature, relative humidity, rainfall, frequency of
tropical cyclone and snow fall); the nearest IMD meteorological station from
which climatological data have been obtained to be indicated.
(xx)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xxi)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical
modelling at different representative locations.
(xxii) Examine the impact
during construction activities due to generation of fugitive dust from crusher
units, air emissions from hot mix plants and vehicles used for transportation
of materials and prediction of impact on ambient air quality using appropriate
mathematical model, description of model, input requirement and reference of
derivation, distribution of major pollutants and presentation in tabular form
for easy interpretation shall be carried out.
(xxiii)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxiv)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
(xxv) If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
(xxvi) Examine and submit the water bodies including the seasonal
ones within the corridor of impacts along with their status, volumetric
capacity and quality likely impacts on them due to the project.
(xxvii) Examine and submit details of water quantity required and
source of water including water requirement during the construction stage with
supporting data and also classification of ground water based on the CGWA
classification.
(xxviii)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and foot
paths should be examined at appropriate locations through out the proposed road
to avoid the accidents.
(xxix)
If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
(xxx) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
(xxxi) If there is a possibility that the construction/widening
of road will cause impact such as destruction of forest, poaching, reductions
in wetland areas, if so, examine the impact and submit details.
(xxxii) Submit the details
of road safety, signage, service roads, vehicular under passes, accident prone
zone and the mitigation measures.
(xxxiii) IRC guidelines shall
be followed for widening & up-gradation of road.
(xxxiv) Submit details of
social impact assessment due to the proposed construction of road.
(xxxv)
Examine
road design standards, safety equipment specifications and Management System
training to ensure that design details take account of safety concerns and
submit the traffic management plan.
(xxxvi) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxvii) If the proposed
project involves any land reclamation, details to be provided for which
activity land to reclaim and the area of land to be reclaimed.
(xxxviii) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
(xxxix) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
(xl)
Submit
details of Corporate Social Responsibility. Necessary provisions should be made
in the budget.
(xli)
Estimated
cost of the project including environmental monitoring cost and funding
agencies, whether governmental or on the basis of BOT etc and provide details
of budget provisions (capital & recurring) for the project specific R&R
Plan.
(xlii) Submit environmental
management and monitoring plan for all phases of the project viz. construction
and operation.
General Guidelines:
(i)
The
EIA document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
(iv)
While
submitting the EIA/EMP reports, the name of the experts associated with/involved
in the preparation of these reports and the laboratories through which the
samples have been got analysed should be stated in the report. It shall clearly
be indicated whether these laboratories are approved under the Environment
(Protection) Act, 1986 and the rules made there under (Please refer MoEF office
memorandum dated 4th August, 2009). The project leader of the EIA study shall
also be mentioned.
(v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.26 Finalisation
of ToR For 6 lanning of Krishnagiri- Walajapet section of NH- 46 from km 0.000
to km 148.30 in the State of Tamil Nadu by M/s NHAI [F.No. 10-66/2011-IA-III]
As presented by the project proponent, the proposal involves 6 lanning of Krishnagiri- Walajapet
section of NH- 46 from km 0.000 to km 148.30 in the State of Tamil Nadu. The project
road is widening of existing 4 lane highway into 6-lane from Krishnagiri –
Walhajpet, Section (Km 0.000 to Km 148.000) of NH-46 in Tamil Nadu State. The
project road starts from Krishnagiri at Km 0.000 and ends near Walahjpet at Km
148.000 on NH-46. Total length of the project road is 148.000 km. The project
road for most of its length passes through plain terrain. The project road
passes through Krishnagiri, and Vellore districts of Tamil Nadu State. The
project road passes through settlements namely, Krishnagiri, Vaniyamvadi,
Ambur, Pallikonda, Vellore, Vasur, Ratnagiri and Ranipet. Existing ROW width
varies from 35 to 60m generally and 60m right-of-way is proposed. From km
23.000 to km 26.000 of the project road is passes though Nandibada Reserve
Forest. Sufficient ROW is available for six laninig work therefore no forest land diversion is proposed.
The major land use pattern along the project road is agriculture with patches
of built-up, commercial and industrial use in scattered matter. Project road
crosses River “Pallar” at location km
141.500.
The project road does not pass through any wildlife sanctuary or
national park or bio-reserve under Wild Life Protection Act within 10 km
distance from the project road. One critically polluted area “Ranipet SIPCOST
Industrial Complex, Vellor (North Arcot)” is located within the 10km radius
from the project road. No international or interstate boundary within 10 km
distance from the project road. The proposed widening of road activities will
be carried out within the 20m strip of land acquisition. Also there is no
proposal envisaged for bypass and realignment. About 34003 trees (33182 are <30cm in girth size and 821are >30cm
in girth size) exist within the ROW out of them 29000 trees may need to be cut
for up-gradation of the project road. About 48 hact land will be acquired for
up-gradation of the project road. Out of which major portion is agricultural.
There are 2 no. of major bridge, 6 ROBs (4 exist & 2 proposed), 44 minor
bridges, 12 minor bridges on service roads (4 exists & 12 proposed) 356
culverts, 3 Grade separated structures, 31 Vehicular underpasses (16 exist
& 15 proposed) 13 pedestrian/cattle underpasses (I exists & 12
proposed) in the project road. There are about 46.450km length of service road
exist and 23m km length additionally proposed. Bus Bays have been provided at
26 locations and truck lay bye at 4 locations.
All major junctions (20 no) and minor junction (31) will be improved in
the project road. About 929 properties will be get affected by the proposed
widening. This includes Residential, Commercial and Industrial properties.
The budget for environment management and
monitoring has been earmarked as approximately Rs. 6,42,03,594.00. The
estimated cost for Resettlement & Rehabilitation is approximately Rs 33.20
Crores. The estimated cost of the civil works for the project is approx.
Rs1000.47 Crores.
During
the discussions, the Committee finalized the following additional TOR for
further study:
(i)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(ii)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(iii)
Submit detailed
alignment plan, with details such as nature of terrain (plain, rolling, hilly),
land use pattern, habitation, cropping pattern, forest area, environmentally
sensitive places, mangroves, notified industrial areas, sand dunes, sea, river,
lake, details of villages, tehsils, districts and states, latitude and
longitude for important locations falling on the alignment by employing remote
sensing techniques followed by ground truthing and also through secondary data
sources.
(iv)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(v)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural
plantations, fallow lands, waste lands, water bodies, built-up areas, forest
area and other surface features such as railway tracks, ports, airports, roads,
and major industries etc. and submit a
detailed ground surveyed map on 1:2000 scale showing the existing features
falling within the right of way namely trees, structures including
archeological & religious, monuments etc. if any.
(vi)
If the proposed route
is passing through any hilly area, examine and submit the stability of slopes,
if the proposed road is to pass through cutting or embankment/ control of soil
erosion from embankment.
(vii)
If the proposed route
involves tunnelling, the details of the tunnel and locations of tunnelling with
geological structural fraction should be provided. In case the road passes through a flood plain of the river, the
details of micro drainage, flood passages and information on flood periodicity
at least of last 50 years in the area should be examined.
(viii)
The projects is
located within 10km. of the sanctuary a map duly authenticated by Chief
Wildlife Warden showing these features vis-à-vis the project location and the
recommendations or comments of the Chief Wildlife Warden thereon should be
furnished at the stage of EC.
(ix)
Study
regarding the Animal bypasses / underpasses etc. across the habitation areas
shall be carried out. Adequate cattle
passes for the movement of agriculture material shall be provided at the
stretches passing through habitation areas.
(x)
It
is indicated that 34003 trees are proposed to be cut, the information should be
provided about their species and whether it also involved any protected or
endangered species. Necessary green belt shall be provided on both side of the
highway with proper central verge and cost provision should be made for regular
maintenance.
(xi)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
(xii)
Submit
details about measures taken for the pedestrian safety and construction of underpasses
and foot-over bridges along with flyovers and interchanges.
(xiii)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xiv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data
collection.
(xv)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
(xvi)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xvii)
Climate and
meteorology (max and min temperature, relative humidity, rainfall, frequency of
tropical cyclone and snow fall); the nearest IMD meteorological station from
which climatological data have been obtained to be indicated.
(xviii)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xix)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical
modelling at different representative locations.
(xx)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
(xxi)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxii)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
(xxiii)
If the proposed route
is passing through low lying areas, details of fill materials and initial and
final levels after filling above MSL, should be examined and submit.
(xxiv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
(xxv)
Examine and submit
details of water quantity required and source of water including water
requirement during the construction stage with supporting data and also
classification of ground water based on the CGWA classification.
(xxvi)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and footpaths
should be examined at appropriate locations through out the proposed road to
avoid the accidents.
(xxvii)
If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
(xxviii) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
(xxix)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
(xxx)
Submit
the details of road safety, signage, service roads, vehicular under passes, accident
prone zone and the mitigation measures.
(xxxi)
IRC
guidelines shall be followed for widening & up-gradation of road.
(xxxii) Submit details of
social impact assessment due to the proposed construction of road.
(xxxiii) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
(xxxiv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxv)
If
the proposed project involves any land reclamation, details to be provided for
which activity land to reclaim and the area of land to be reclaimed.
(xxxvi) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
(xxxvii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
(xxxviii) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
(xxxix) Estimated cost of
the project including environmental monitoring cost and funding agencies,
whether governmental or on the basis of BOT etc and provide details of budget
provisions (capital & recurring) for the project specific R&R Plan.
(xl)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation.
General Guidelines:
(i)
The
EIA document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii) On the front page of
EIA/EMP reports, the name of the consultant/consultancy firm along with their
complete details including their accreditation, if any shall be indicated. The
consultant while submitting the EIA/EMP report shall give an undertaking to the
effect that the prescribed TORs (TOR proposed by the project proponent and
additional TOR given by the MoEF) have been complied with and the data
submitted is factually correct (Refer MoEF office memorandum dated 4th August,
2009).
(iv) While submitting the
EIA/EMP reports, the name of the experts associated with/involved in the
preparation of these reports and the laboratories through which the samples
have been got analysed should be stated in the report. It shall clearly be
indicated whether these laboratories are approved under the Environment
(Protection) Act, 1986 and the rules made there under (Please refer MoEF office
memorandum dated 4th August, 2009). The project leader of the EIA study shall
also be mentioned.
(v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addressed in the Environmental Management Plan.
A detailed draft EIA/EMP report should be prepared
as per the above additional TOR and should be submitted to the Ministry as per
the Notification.
4.27 Finalisation
of ToR for Construction of Kolkata – Dhanbad Expressway on NH-2 in the State of
West Bengal and Jharkhand by M/s NHAI (F. No.10-68/2011-IA III)
As presented by the project proponent, the proposal
involves Construction of Kolkata – Dhanbad Expressway on NH-2 in the State of
West Bengal and Jharkhand. The expressway is proposed to start near Indrakhali
village at km 637+500 of NH-2 and terminate near Dhanbad at km 411+800 of
NH-2. The expressway will have a spur
to Haldia, which will take off from the expressway at Hazipur and terminate on
NH-6 near Mecheda. A second spur will
originate the expressway at Harmadih.and connect proposed Dhanbad Ring
Road. The total length of the proposed
expressway including the two spurs is 298 km. The Expressway passes through the
districts of Hooghly, West Medinipur, East Medinipur, Bankura & Purulia in
West Bengal and the district of Dhanbad in Jharkhand. The alignment mainly
passes through agricultural lands. The proposed ROW will be 90 m. The design
speed is 100-120 kmph. The expressway will be fully access controlled. It will
have a 4-lane configuration initially, with provision of widening to 6-lane in
future. The total area of land acquisition will be 2680 hectares. This
comprises 2090 hectares of agricultural land, 350 hectares of forest land and
240 hectares of barren land.
6000 Nos. of trees will be required to
be felled for construction of the proposed expressway. A length of 35 km of the
expressway passes through protected forest. There is no Wildlife Sanctuary or
National Park along the proposed expressway. Proposal for diversion of the
forest land has been submitted to the State Government. There will be 12 major
bridges, 36 minor bridges and 901 nos. of box culverts on the proposed
expressway. There will be 6 ROBs, 4 Overpasses, 74 Vehicular Underpasses and 84
Pedestrian Underpasses. There will be 11 Interchanges. There will be 9 Toll
plazas with roadside amnesties including medical facilities and ambulance. The
expressway passes through 319 mouzas, out of which 83 mouzas lie in Hooghly,
110 mouzas in Bankura, 44 mouzas in West Medinipur, 16 mouzas in East
Medinipur, 36 mouzas in Purulia and 30 mouzas lie in Dhanbad district. 400 Nos.
of structures (pucca/semi pucca/Kancha) will be required to be demolished for
construction of the proposed expressway. Adequate lighting arrangements will be
provided where necessary. Total demand of water will be 50000 KL.
The estimated civil cost of the project is Rs 5236 crores. Other costs including LA, EMP, R&R and
utility shifting will be Rs 632 crores.
During discussions, the Committee
finalized the following additional ToR for further study:
(i)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(ii)
The proposal indicates
the acquisition of 350 ha forest land. Necessary stage –I forestry clearance
shall be obtained as per OM dated 31.03.2011 and submitted along with final EIA
report.
(iii)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(iv)
Submit detailed
alignment plan, with details such as nature of terrain (plain, rolling, hilly),
land use pattern, habitation, cropping pattern, forest area, environmentally
sensitive places, mangroves, notified industrial areas, sand dunes, sea, river,
lake, details of villages, teshils, districts and states, latitude and
longitude for important locations falling on the alignment by employing remote
sensing techniques followed by ground truthing and also through secondary data
sources.
(v)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(vi)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural
plantations, fallow lands, waste lands, water bodies, built-up areas, forest
area and other surface features such as railway tracks, ports, airports, roads,
and major industries etc. and submit a
detailed ground surveyed map on 1:2000 scale showing the existing features
falling within the right of way namely trees, structures including
archeological & religious, monuments etc. if any.
(vii)
If the proposed route
is passing through any hilly area, examine and submit the stability of slopes,
if the proposed road is to pass through cutting or embankment/ control of soil
erosion from embankment.
(viii)
If the proposed route
involves tunnelling, the details of the tunnel and locations of tunnelling with
geological structural fraction should be provided. In case the road passes through a flood plain of the river, the
details of micro drainage, flood passages and information on flood periodicity
at least of last 50 years in the area should be examined.
(ix)
The projects is
located within 10km. of the sanctuary a
map duly authenticated by Chief Wildlife Warden showing these features
vis-à-vis the project location and the recommendations or comments of the Chief
Wildlife Warden thereon should be furnished at the stage of EC.
(x)
Study regarding the Animal bypasses/
underpasses etc. across the habitation areas shall be carried out. Adequate
cattle passes for the movement of agriculture material shall be provided at the
stretches passing through habitation areas.
(xi)
It is indicated that 6000 trees are proposed to
be cut, the information should be provided about their species and whether it
also involved any protected or endangered species. Necessary green belt shall
be provided on both side of the highway with proper central verge and cost
provision should be made for regular maintenance.
(xii)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
(xiii) Submit details about
measures taken for the pedestrian safety and construction of underpasses and
foot-over bridges along with flyovers and interchanges.
(xiv)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data
collection.
(xvi)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
(xvii)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xviii)
Climate and
meteorology (max and min temperature, relative humidity, rainfall, frequency of
tropical cyclone and snow fall); the nearest IMD meteorological station from
which climatological data have been obtained to be indicated.
(xix)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xx)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical modelling
at different representative locations.
(xxi) Examine the impact
during construction activities due to generation of fugitive dust from crusher
units, air emissions from hot mix plants and vehicles used for transportation
of materials and prediction of impact on ambient air quality using appropriate
mathematical model, description of model, input requirement and reference of
derivation, distribution of major pollutants and presentation in tabular form
for easy interpretation shall be carried out.
(xxii)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxiii) If the proposed route involves cutting of earth, the
details of area to be cut, depth of cut, locations, soil type, volume and
quantity of earth and other materials to be removed with location of disposal/
dump site along with necessary permission.
(xxiv)
If the proposed route
is passing through low lying areas, details of fill materials and initial and
final levels after filling above MSL, should be examined and submit.
(xxv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
(xxvi)
Examine and submit
details of water quantity required and source of water including water
requirement during the construction stage with supporting data and also
classification of ground water based on the CGWA classification.
(xxvii) Examine and submit the details of measures taken during
constructions of bridges across river/canal/major or minor drains keeping in
view the flooding of the rivers and the life span of the existing bridges. Provision of speed breakers, safety signals,
service lanes and foot paths should be examined at appropriate locations
through out the proposed road to avoid the accidents.
(xxviii)
If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
(xxix) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water table.
Provision shall be made for oil and grease removal from surface runoff.
(xxx)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
(xxxi) Submit the details
of road safety, signage, service roads, vehicular under passes, accident prone
zone and the mitigation measures.
(xxxii)IRC guidelines shall
be followed for widening & up-gradation of road.
(xxxiii) Submit details of
social impact assessment due to the proposed construction of road.
(xxxiv) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
(xxxv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxvi) If the proposed project
involves any land reclamation, details to be provided for which activity land
to reclaim and the area of land to be reclaimed.
(xxxvii) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
(xxxviii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
(xxxix) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the budget.
(xl)
Estimated
cost of the project including environmental monitoring cost and funding
agencies, whether governmental or on the basis of BOT etc and provide details
of budget provisions (capital & recurring) for the project specific R&R
Plan.
(xli)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation.
General Guidelines:
(i)
The
EIA document shall be printed on both sides, as for as possible.
(ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
(iii) On the front page of
EIA/EMP reports, the name of the consultant/consultancy firm along with their
complete details including their accreditation, if any shall be indicated. The
consultant while submitting the EIA/EMP report shall give an undertaking to the
effect that the prescribed TORs (TOR proposed by the project proponent and
additional TOR given by the MoEF) have been complied with and the data
submitted is factually correct (Refer MoEF office memorandum dated 4th August,
2009).
(iv) While submitting the
EIA/EMP reports, the name of the experts associated with/involved in the
preparation of these reports and the laboratories through which the samples
have been got analysed should be stated in the report. It shall clearly be
indicated whether these laboratories are approved under the Environment
(Protection) Act, 1986 and the rules made there under (Please refer MoEF office
memorandum dated 4th August, 2009). The project leader of the EIA study shall
also be mentioned.
(v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addresses in the Environmental Management Plan.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
4.28 Finalisation
of ToR for rehabilitation and up gradation of existing carriageway to 2-lane
with paved shoulder from Ner-Chowk (km 190.000) to Km to Manali (km 308.650) of
NH-21 in the State of Himachal Pradesh by M/s NHAI (F. No. 10-69/2011-IA III)
As
presented by the project proponent, the proposal involves rehabilitation and up gradation of
existing carriageway to 2-lane with paved shoulder from Ner-Chowk (km 190.000)
to Km to Manali (km 308.650) of NH-21 in the State of Himachal Pradesh. The proposed project is part of NHDP Phase IV B and
has total length of existing road is 118.650 km. The project road starts at km
190.000 on NH 21 near Ner Chowk in Mandi district of Himachal Pradesh and ends
at km 308.650 in Kullu district. The existing right of way varies between 10 to
27 m. The proposed right of way (ROW) is 24 m. Project road passes through
hilly terrain. The land use pattern of the project area is mostly agricultural
and built up. The Project Road does not pass through any Reserve forest,
National Park and Sanctuary; however Roadside plantation along the NH-21 is
notified as protected forest.
Approximately
1,768 trees falling along the roadside are likely to be affected. The project
road is passing through protected forest areas for length of 7.7 kms. Total
Land acquisition is 103.2685 ha which private land is. The 33.2760 ha of land
is required to be acquired for proposed realignments and 69.9925 ha of land
will be acquired for widening. There are 28 existing bridges on the project
road, 4 are major bridges and 25 are minor bridges. There are 576 nos. of culverts. The proposed corridor will have 3
new major bridges and 9 new minor bridges. A 75m long flyover is proposed at
the realignment of village Patlikul (proposed chainage is 287+568). There are
11 nos. bus shelters existing on the project road. It is proposed to provide 14 nos. of new bus bays & bus
shelters. Also there would be 3 truck
lay byes. There is one Toll Plaza and two Toll Plaza has been proposed. There
are 3 Major Junctions. Approximately 2500 Kl / day water for construction
period shall be required for construction and other purpose including
plantation and dust suppression. The water shall be abstracted from perennial
sources like Beas River and Paravati River. The nearest Thermal Power Plant is
in Ropar (Punjab) which is beyond 100 kms radius. Also in there are many Cement
Industries, which are using flyash from this thermal power plant. Retaining walls and breast walls exist
at a number of locations. Depending
upon the widening proposal, some of the retaining walls and breast walls will
have to be dismantled and new retaining walls will be proposed on valley
side. Breast walls have been proposed
on hillside locations of sliding zones. Parapet Walls have been proposed for
safety purpose on valley side where retaining walls are not required.
The
budget for environment management plan during construction and operation phases
works out to be approximately Rs. 5.0 crores.
Approximately 562 structures will be affected. The total cost for
Resettlement and Rehabilitation is approximately Rs. 51.97 crores. Total cost
of the proposed project is Rs. 711.30 crores.
During discussions, the Committee
finalized the following additional ToR for further study:
(i)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(ii)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(iii)
Submit detailed alignment
plan, with details such as nature of terrain (plain, rolling, hilly), land use
pattern, habitation, cropping pattern, forest area, environmentally sensitive
places, mangroves, notified industrial areas, sand dunes, sea, river, lake,
details of villages, tehsils, districts and states, latitude and longitude for
important locations falling on the alignment by employing remote sensing
techniques followed by ground truthing and also through secondary data sources.
(iv)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(v)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural plantations,
fallow lands, waste lands, water bodies, built-up areas, forest area and other
surface features such as railway tracks, ports, airports, roads, and major
industries etc. and submit a detailed
ground surveyed map on 1:2000 scale showing the existing features falling
within the right of way namely trees, structures including archeological &
religious, monuments etc. if any.
(vi)
As the proposed route
is passing through any hilly area, examine and submit the stability of slopes,
if the proposed road is to pass through cutting or embankment/ control of soil
erosion from embankment.
(vii)
If the proposed route
involves tunnelling, the details of the tunnel and locations of tunnelling with
geological structural fraction should be provided. In case the road passes through a flood plain of the river, the
details of micro drainage, flood passages and information on flood periodicity
at least of last 50 years in the area should be examined.
(viii)
The projects is
located within 10km. of the sanctuary a map duly authenticated by Chief
Wildlife Warden showing these features vis-à-vis the project location and the
recommendations or comments of the Chief Wildlife Warden thereon should be
furnished at the stage of EC.
(ix)
Study regarding the
Animal bypasses / underpasses etc. across the habitation areas shall be carried
out. Adequate cattle passes for the
movement of agriculture material shall be provided at the stretches passing
through habitation areas.
(x)
It is indicated that 1768 trees are proposed to be cut, the
information should be provided about their species and whether it also involved
any protected or endangered species. Necessary green belt shall be provided on
both side of the highway with proper central verge and cost provision should be
made for regular maintenance.
(xi)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
(xii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
(xiii)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xiv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data collection.
(xv)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
(xvi)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xvii)
Climate and
meteorology (max and min temperature, relative humidity, rainfall, frequency of
tropical cyclone and snow fall); the nearest IMD meteorological station from
which climatological data have been obtained to be indicated.
(xviii)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xix)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any. Prediction of noise levels should be done
by using mathematical modelling at different representative locations.
(xx)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
(xxi)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxii)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
(xxiii)
If the proposed route
is passing through low lying areas, details of fill materials and initial and
final levels after filling above MSL, should be examined and submit.
(xxiv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
(xxv)
Examine and submit
details of water quantity required and source of water including water
requirement during the construction stage with supporting data and also
classification of ground water based on the CGWA classification.
(xxvi)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and footpaths
should be examined at appropriate locations through out the proposed road to
avoid the accidents.
(xxvii)
If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
(xxviii) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
(xxix)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
(xxx)
Submit
the details of road safety, signage, service roads, vehicular under passes,
accident prone zone and the mitigation measures.
(xxxi)
IRC
guidelines shall be followed for widening & up-gradation of road.
(xxxii) Submit details of
social impact assessment due to the proposed construction of road.
(xxxiii) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
(xxxiv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxv)
If
the proposed project involves any land reclamation, details to be provided for
which activity land to reclaim and the area of land to be reclaimed.
(xxxvi) Details of the properties,
houses, businesses etc. activities likely to be effected by land acquisition
and their financial loses annually.
(xxxvii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
(xxxviii) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
(xxxix) Estimated cost of
the project including environmental monitoring cost and funding agencies,
whether governmental or on the basis of BOT etc and provide details of budget
provisions (capital & recurring) for the project specific R&R Plan.
(xl)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation.
General Guidelines:
i)
The
EIA document shall be printed on both sides, as for as possible.
ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addresses in the Environmental Management Plan.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
4.29 Finalisation
of ToR for upgradation of existing carriageway to 2-lane with paved shoulder
from Jabalpur-Mandla-Chilpi section of NH-12A in the State of Madhya Pradesh by
M/s NHAI. [F.No. 10-71 /2011-IA-III]
As presented by the project
proponent, the proposal involves upgradation of existing carriageway to 2-lane with paved shoulder
from Jabalpur-Mandla-Chilpi section of NH-12A in the State of Madhya Pradesh.
The project road starts at km 3/ 4 on NH-12A district Jabalpur and ends at Km
192/4, Chilpi Boarder, District Mandla. The existing length of the project road
is 189 km and it has rolling and Hilly Terrain. The road design length of road
is 175.75 km. The road passes through Jabalpur, Mandla and Balaghat District of
Madhya Pradesh. Existing ROW of project road is 11 –54 mtr. the proposed ROW is
18m-60m in revenue area and 30 m except in forest area with 60-75m at 4-5
locations due to embankment & cutting. And nil in Wildlife Sanctuary for
road project but, if Animal underpass proposed by Standing Committee of NBWL.
The project road passes along the Periphery of Kanha National Park in the
length of about 6.8 km. The project alignment has agriculture-54.5 %; Barren
land – 0.3 %, built up – 17.5 % and forest lands of 18.23 ha. The total land
acquisition is 354 ha. The ROW proposed is 60 mtr in the byepass and existing +
Toe line within forest area. Bus lay byes have been provided at 16 locations on
both sides and Bus Shelters have been provided at 48 locations on both sides. 2
wayside amenities and 3 toll plaza have been provided. There are 386 PAPs and
200 PDFs due to improvement of project road. The entitled persons would be
compensated according to the provisions of NH Act 1956. High Mast lighting
arrangements/ solar lighting shall be provided as per IRC Guideline. Average
demand of water would be approx. 325 KLD during construction. Fly ash shall be
used for construction of embankment.
The capital cost of the project is 578.316 crores, cost of land acquisition
& other is 11.19 crores, cost of EIA & EMP is 8.15 crores, the total
cost proposed is – 598.96 crores.
Out of 14315 trees 5836 trees proposed to be felled for
improvement of project road, against 17508 trees shall be planted as avenue
plantation apart from the statutory requirement. There are existing 7 major bridge, 40 minor bridge and 361
culverts. There are proposed 6 major bridges which will be improved and 41
minor bridges (23 New and 16 will be reconstructed). There are 8 number of
major junction, 14 number of minor junction and 93 number of other junction on
the project road which have been proposed for improvement. There is provision of 1 number of vehicular
underpasses & 4 number of pedestrian & cattle underpasses have been
made. Additional 5 underpasses are proposed for animal crossing in Wildlife
area.
During discussions, the Committee
finalized the following additional ToR for further study:
(i)
Examine and submit a
brief description of the project, project name, nature, size, its importance to
the region/state and the country.
(ii)
Any litigation(s)
pending against the proposed project and/or any directions or orders passed by
any court of law/any statutory authority against the project is to be detailed
out.
(iii)
Submit detailed
alignment plan, with details such as nature of terrain (plain, rolling, hilly),
land use pattern, habitation, cropping pattern, forest area, environmentally
sensitive places, mangroves, notified industrial areas, sand dunes, sea, river,
lake, details of villages, tehsils, districts and states, latitude and
longitude for important locations falling on the alignment by employing remote
sensing techniques followed by ground truthing and also through secondary data
sources.
(iv)
Describe various
alternatives considered, procedures and criteria adopted for selection of the
final alternative with reasons.
(v)
Submit Land use map of
the study area to a scale of 1: 25,000 based on recent satellite imagery
delineating the crop lands (both single and double crop), agricultural
plantations, fallow lands, waste lands, water bodies, built-up areas, forest
area and other surface features such as railway tracks, ports, airports, roads,
and major industries etc. and submit a detailed ground surveyed map on 1:2000
scale showing the existing features falling within the right of way namely
trees, structures including archaeological & religious, monuments etc. if
any.
(vi)
If the proposed route
is passing through any hilly area, examine and submit the stability of slopes,
if the proposed road is to pass through cutting or embankment/ control of soil
erosion from embankment.
(vii)
If the proposed route
involves tunnelling, the details of the tunnel and locations of tunnelling with
geological structural fraction should be provided. In case the road passes through a flood plain of the river, the
details of micro drainage, flood passages and information on flood periodicity
at least of last 50 years in the area should be examined.
(viii)
The projects is
located within 10km. of the sanctuary a map duly authenticated by Chief
Wildlife Warden showing these features vis-à-vis the project location and the
recommendations or comments of the Chief Wildlife Warden thereon should be
furnished at the stage of EC.
(ix)
Study
regarding the Animal bypasses / underpasses etc. across the habitation areas
shall be carried out. Adequate cattle passes for the movement of agriculture
material shall be provided at the stretches passing through habitation areas.
(x)
It
is indicated that 5836 trees are proposed to be cut, the information should be
provided about their species and whether it also involved any protected or
endangered species. Necessary green belt shall be provided on both side of the
highway with proper central verge and cost provision should be made for regular
maintenance.
(xi)
If the proposed route
is passing through a city or town, with houses and human habitation on the
either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal
should also indicate the location of wayside amenities, which should include
petrol station/service centre, rest areas including public conveyance, etc.
(xii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges.
(xiii)
Assess whether there
is a possibility that the proposed project will adversely affect road traffic
in the surrounding areas (e.g. by causing increases in traffic congestion and
traffic accidents).
(xiv)
Clearly
indicate/provide details regarding the location, date (along with site
photographs with the background of monitoring equipments and/or sample
collection in process) and protocol adopted for sampling and analysis of
various environmental parameters as a part of the baseline data collection.
(xv)
Examine
and submit the details of use of fly ash in the road construction, if the
project road is located within the 100 km from the Thermal Power Plant.
(xvi)
Examine and submit the
details of sand quarry, borrow area and rehabilitation.
(xvii)
Climate and meteorology
(max and min temperature, relative humidity, rainfall, frequency of tropical
cyclone and snow fall); the nearest IMD meteorological station from which
climatological data have been obtained to be indicated.
(xviii)
The air quality
monitoring should be carried out as per the new notification issued on 16th
November, 2009.
(xix)
Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact if any.
Prediction of noise levels should be done by using mathematical
modelling at different representative locations.
(xx)
Examine
the impact during construction activities due to generation of fugitive dust
from crusher units, air emissions from hot mix plants and vehicles used for
transportation of materials and prediction of impact on ambient air quality
using appropriate mathematical model, description of model, input requirement
and reference of derivation, distribution of major pollutants and presentation
in tabular form for easy interpretation shall be carried out.
(xxi)
Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. during construction stage.
(xxii)
If the proposed route
involves cutting of earth, the details of area to be cut, depth of cut,
locations, soil type, volume and quantity of earth and other materials to be
removed with location of disposal/ dump site along with necessary permission.
(xxiii)
If the proposed route
is passing through low lying areas, details of fill materials and initial and
final levels after filling above MSL, should be examined and submit.
(xxiv)
Examine and submit the
water bodies including the seasonal ones within the corridor of impacts along
with their status, volumetric capacity and quality likely impacts on them due
to the project.
(xxv)
Examine and submit
details of water quantity required and source of water including water
requirement during the construction stage with supporting data and also
classification of ground water based on the CGWA classification.
(xxvi)
Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges.
Provision of speed breakers, safety signals, service lanes and footpaths
should be examined at appropriate locations through out the proposed road to
avoid the accidents.
(xxvii)
If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
(xxviii) Rain water
harvesting pit should be at least 3 - 5 m. above the highest ground water
table. Provision shall be made for oil and grease removal from surface runoff.
(xxix)
If there is a
possibility that the construction/widening of road will cause impact such as
destruction of forest, poaching, reductions in wetland areas, if so, examine
the impact and submit details.
(xxx)
Submit
the details of road safety, signage, service roads, vehicular under passes,
accident prone zone and the mitigation measures.
(xxxi)
IRC
guidelines shall be followed for widening & up-gradation of road.
(xxxii) Submit details of
social impact assessment due to the proposed construction of road.
(xxxiii) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns and submit the
traffic management plan.
(xxxiv) Accident data and
geographic distribution should be reviewed and analyzed to predict and identify
trends – incase of expansion of the existing highway and provide Post accident
emergency assistance and medical care to accident victims.
(xxxv)
If
the proposed project involves any land reclamation, details to be provided for
which activity land to reclaim and the area of land to be reclaimed.
(xxxvi) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
(xxxvii) Detailed R&R
plan with data on the existing socio-economic status of the population in the
study area and broad plan for resettlement of the displaced population, site
for the resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
(xxxviii) Submit details of
Corporate Social Responsibility. Necessary provisions should be made in the
budget.
(xxxix) Estimated cost of
the project including environmental monitoring cost and funding agencies,
whether governmental or on the basis of BOT etc and provide details of budget
provisions (capital & recurring) for the project specific R&R Plan.
(xl)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation.
General Guidelines:
i)
The
EIA document shall be printed on both sides, as for as possible.
ii)
The
status of accreditation of the EIA consultant with NABET/QCI shall be
specifically mentioned. The consultant shall certify that his accreditation is
for the sector for which this EIA is prepared.
iii)
On
the front page of EIA/EMP reports, the name of the consultant/consultancy firm
along with their complete details including their accreditation, if any shall
be indicated. The consultant while submitting the EIA/EMP report shall give an
undertaking to the effect that the prescribed TORs (TOR proposed by the project
proponent and additional TOR given by the MoEF) have been complied with and the
data submitted is factually correct (Refer MoEF office memorandum dated 4th
August, 2009).
iv)
While
submitting the EIA/EMP reports, the name of the experts associated
with/involved in the preparation of these reports and the laboratories through
which the samples have been got analysed should be stated in the report. It
shall clearly be indicated whether these laboratories are approved under the
Environment (Protection) Act, 1986 and the rules made there under (Please refer
MoEF office memorandum dated 4th August, 2009). The project leader of the EIA
study shall also be mentioned.
v)
All
the TOR points as presented before the Expert Appraisal Committee (EAC) shall
be covered.
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 and the issues raised by the public should
be addresses in the Environmental Management Plan.
Any further
clarification on carrying out the above studies including anticipated impacts
due to the project and mitigative measure, project proponent can refer to the
model ToR available on Ministry website “http://moef.nic.in/Manual/highways”
3rd Day: 19th
August, 2011
4.30 Environmental
Clearance for proposed Group Housing Project at Sec. 112, Gurgaon, Haryana, by
M/s. Aurochem Build Prop Pvt. Ltd. [F.No.21-42/2011-IA.III].
The project involves
construction of a Group Housing on a plot area of 40757 Sq.m. The total built
up area of the project proposed is 81,377.77 Sq.m. The total water requirement
proposed is 344 KLD (fresh water requirement 186 KLD). The capacity of STP is
about 280 KLD. Treated water will be used for HVAC
cooling/flushing/horticulture/DG cooling/ gardening 205.2 KLD. The total power
requirement is 5050 KVA. Total solid waste generation will be 1419.70 Kg/day.
The total parking spaces for group housing proposed are 1,103 ECS.
The details submitted and presented were examined by the Committee.
During the discussions, the following points emerged:
(i)
The information with
respect to Ground water depth, various rules/ regulations applicable to the
project has not been provided in the application Form. Revised Form addressing
the above including their compliance shall be submitted.
(ii)
Examine and submit the details of the impact on
traffic due to the project during construction and operation phases.
(iii)
Examine and submit the details of water bodies
including the seasonal ones- ponds, lakes, low lying areas within the corridor
of impacts along with their status, volumetric capacity, and quality likely
impacts on them due to the project.
(iv)
NOC/Clearance from fire department shall be obtained
prior to start of work.
(v)
Operation and Maintenance of the STP, Solid Waste
Management of the apartments shall be ensured even after sale.
(vi)
Submit details about the source and quantity of
water required, also submit the water balance chart.
Proposal indicates 186 KLD of fresh water, without assured source of water
supply. Overexploited
groundwater and impending severe shortage of water supply in the region
requires the developer to redraw the water and energy conservation
plan. Developer shall submit details of good practices that have been
included in the project to reduce the overall footprint of the proposed
development including a detailed water balance along with source and quantities
of potable and non-potable water requirement (including water requirement
during construction phase) incorporating water efficiency/savings measures
as well as water reuse/recycling within 3 months to the Ministry/ Regional
office at Chandigarh before the start of construction.
(vii)
In view of water resources sustainability and severe constraints
of water supply augmentation in the region the developer will submit NOC
from CGWA specifying water abstraction quantities and NOC from HUDA/ utility
provider indicating source of water supply and quantity of water with details
of intended use of water - potable and non-potable and shall be submitted
within 3 months to the Ministry/ Regional office at Chandigarh before the start
of construction.
(viii)
Energy saving should be increased to at least more
than 20%. Quantify the saving in
energy. Energy
conservation plan with details of percentage saving in energy shall be
submitted to the Ministry/ Regional office at Chandigarh before the start of
construction.
(ix)
No discharge shall be made in the nearby pond/water
body.
Provided the response of the project
proponent to the aforesaid observations is to the satisfaction of the
committee, the proposal may be considered for recommendation for Clearance.
4.31 Finalisation of ToR development of New Industrial Area, chak No. 123, at village – Ghiloth
Dabarwas, Partapur Behror Distt. Alwar, Rajasthan by M/s. Rajasthan State
Industrial Development & Investment Corporation Ltd.
[F.No.21-43/2011-IA.III].
The project involves development of new Industrial Area on
a plot area of 749.15 ha. (Barren land-76.78 ha + agricultural land-485.08 ha +
grazing land-12.66 ha + wasteland-160.61 ha + others-14.02 ha). The Inter-state
boundary of Rajasthan and Haryana is within 10 km. The total water requirement
proposed is 9000 KLD. The total power requirement is taken from 40 MVA line.
Two high tension electric transmission lines (400 KV & 132 KV) are passing
through the proposed project area. Total solid waste generation will be 2000
Kg/day. Affected trees are 5544 & affected structures are-112. In case of
availability of natural gas in the proposed area, RIICO has earmarked 0.59 ha
of land for gas station. Total cost of the project is envisaged Rs. 768 Crores.
During discussions, the Committee
finalized the following additional ToR for further study:
(i)
Submit
details of the co-ordinates of the site to verify about the location of the
project with reference to Rajasthan and Haryana borders.
(ii)
Alternative sites also should have been evaluated on relevant
parameters in which impact on the nearby settlements should be examined including
the impacts on the agricultural productivity of land. Describe the
environmental concerns addressed in the site selection.
(iii)
Examine in detail the proposed site with reference to impact on
infrastructure covering water supply, storm water drainage, sewerage, power,
etc., and the disposal of treated/raw wastes from the park on land/water body
and into sewerage system.
(iv)
Evaluate the availability of ground water. Necessary permission
shall be obtained from Central Ground Water Authority.
(v)
Submit revised documents/application form as per the presentation
documents.
(vi)
Submit details about the solid and liquid wastes, their
collection, treatment and disposal.
(vii)
Examine and submit details about the energy efficiency and
conservation and use of renewable energy.
(viii)
Submit details of development of greenbelt and open spaces.
(ix)
Submit details of Disaster Management Plan especially for storage
of petroleum products against fire, chemical spill, risk analysis and
evaluation, natural and man-made off site and on site.
(x)
Examine and submit details of Air quality monitoring as per latest National Ambient Air
Quality standards as notified by the Ministry on 16th November, 2009.
(xi)
Examine
and submit details of the impacts on the water bodies and the canal which is
passing nearby. NOC shall be obtained
from Public Health Department.
(xii)
Examine
and submit details of requirement of water including use of treated waste
water.
(xiii) Examine the land use of
the area with reference to Master plan/developmental plan of the area to
ascertain whether the development plan requires any changes.
(xiv)
Study the existing flora and fauna of the area.
(xv)
Sources
of water and their potential should be clearly identified. Proposals for
conservation of water and harnessing rain water harvesting potential should be
incorporated in the project.
(xvi)
Study the hydrological
and geo-hydrological conditions of the project area. Include a contour plan indicating
slopes and showing drainage pattern and outfall.
(xvii) Examine and
submit details about the resettlement and rehabilitation of project-affected
persons, in the nearby villages, in accordance with the national resettlement and
rehabilitation policy.
(xviii) Consider the application
of industrial ecology concept for planning.
(xix)
Submit development strategy. Industries should be grouped on the
basis of their nature e.g. water polluting near STP, air polluting according to
metrological consideration with respect and large size industries.
(xx)
Storm water drainage and outfall may be described.
(xxi)
Rain water harvesting proposals should be made with due
safeguards for ground water quality. Maximize recycling of water and
utilization of rain water.
(xxii) Examine soil
characteristics, topography, rainfall pattern and soil erosion.
&nb