MINUTES
The
Minutes of the 89th Meeting of the Expert Appraisal
Committee for Building Construction, Coastal Regulation Zone, Infrastructure
Development and Miscellaneous projects held on 21st – 23rd July, 2010 at Fazal Chambers, SCOPE
Complex, Lodhi Road, New Delhi.
1. Opening
Remarks of the Chairman.
The Chairman welcomed the members to
the 89th meeting of the Expert Appraisal Committee and 2nd
Meeting of the newly constituted committee. Some of the members felt that the
proposals reached them quite late and they did not get much time to study
them. The Committee also noted that the
details of some of the projects had not been circulated.
The Member Secretary further informed
about the action taken on the decisions of the 85th meeting held on 25th
– 26th February, 2010 in New Delhi. He also
briefed the Committee regarding various agenda items.
2.
Confirmation of the Minutes of
the 88th Meeting of the EAC held on 28th – 29th
June, 2010 at New Delhi.
Minutes of the 88th Meeting of the EAC
held on 28th -29th June, 2010 at New Delhi were confirmed with the following
corrections.
Page No.2-4 – Item No. 3.2:
(i) Recommendations should read as “The
committee recommends the proposal for the issue of Environmental and CRZ
clearance with the above two conditions in the clearance letter for strict
compliance by the project proponent”. In place of “The committee recommends the
proposal for CRZ clearance with the above two conditions in the clearance
letter for strict compliance by the project proponent.”
Page No.108 – Item No. 5.2:
(ii) Recommendations should read as “The
committee recommends the proposal for the issue of Environmental and CRZ
clearance”. In place of “The committee recommends the proposal for the issue of
CRZ clearance.
3. Consideration
of Old Proposals:
3.1
Amendment
of the Environmental Clearance issued for all weather green field Port project
at Jaigad, Ratnagiri District Maharashtra by M/s JSW infrastructure Logistics
Ltd. [F. No. 10-17/2006-IA.III]
Member
Secretary informed that the project proponent vide letter dated 19.07.2010
informed that due to late receipt of intimation they were not in a position to
attend that scheduled meeting.
The
Committee decided to defer the project.
3.2
Environmental
Clearance for the development of HDIL Cyber City (SEZ) at 717/5 Thaikkakara
North Village, Kanayannur, Kalamassery, Earnakulam, Kerala by M/s Blue star
Realtors [21-1116/2007- IA-III]
The project
involves construction of HDIL Cyber City (684 Residential apartments and 456 villas,
84 rooms service apartments, IT Park, 200 rooms hotel, school, shopping malls,
1100 seats multiplex) on a plot area of
2,83,276 Sq.m. The total builtup area proposed is 8,95,220.7 Sq.m. The total
water requirement is 5606 KLD (fresh water requirement is 2267 KLD). The total capacity of 6 STPs proposed is 2167
KLD. Treated waste water to be used for flushing of toilets - 2303 KLD,
horticulture - 462 KLD, AC cooling - 1373 KLD.
Total solid waste generation will be 15,012 Kg/day. The power
requirement is 75 MVA. The total
parking spaces proposed are for 7573 ECS + 172 bus parking spaces. Total cost
of the project is Rs. 2000.00 Crores.
The proposal was put up for consideration in the 60th meeting held on 1st
-3rd May, 2008. The EAC after examination asked for additional
information. The details submitted by the project proponent were examined by
the committee.
During discussion, the following points
emerged:
(i)
The
Committee noted that the nearest water body is Vembanad Backwater, which is approximately 12 km from the site, and will not attract the provisions of CRZ Notification,
1991.
(ii)
Submit a copy of the master plan/development plan
indicating the land use and copy of the approved plan from local body. Also
submit details of the infrastructure available around the site.
(iii)
The revised proposal indicates the provisions of 5
STPs (750KLD, 950 KLD, 810 KLD, 1500 KLD & 530 KLD). Explore the possibilities of reducing the
number of STPs to 3. Quality
of the recycling water should be monitored periodically.
(iv)
Examine
and submit the details of the capacity of external drainage.
(v)
Submit
specific details of number of trees to be cut, retained and transplanted.
(vi)
The depth of the rain water harvesting pit should be
at least 4-5m above the highest level of ground water table.
(vii)
The stack height of diesel generating set should be
at least 3 m above the highest building within the complex.
(viii) Building
envelope should follow ECBC guidelines for U values of roof, wall and
fenestration.
(ix)
The entry and exit to the project site from the main
road shall be left in and left out with proper intersection design without
conflict point.
Provided the response of the project
proponent to the aforesaid observations (i) to (v) is to the satisfaction of
the Committee, and observations (vi) to (ix) are incorporated in the Clearance
letter for strict compliance by the project proponent, the proposal may be
considered for recommendation for Clearance.
3.3
Environmental and CRZ Clearance for the
construction of Jetty and Conveyor belt at Medhakhar, Raigad, Maharashtra by
M/s. Patni Energy Ltd. [F.No.11-47/2008-IA.III]
As presented by the project proponent, the proposal is for the construction of Jetty and Conveyor belt for 405 MW coal based Thermal Power Plant at Medhakhar, Raigad, Maharashtra. CRZ Clearance for intake of seawater and outfall of wastewater was obtained on 23.03.2010. The issue of Clearance for Jetty and conveyor belt was not considered due to Moratorium. Now, the moratorium was lifted and a policy has been introduced vide OM No.15-3/2009-IA-III dated 03.11.2009. As per the OM the proposed site i.e. Medhekhar village, Taluka Alibag is not a hotspot area in Raigad district.
The proposal involves construction of
captive lighterage coal jetty for barge unloading and storage facility - 2 nos.
(1 in each phase, for the proposed 405 MW coal based thermal power plant. The
capacity of jetty will be to handle coal around 5,520 TPD (Phase -I) and 1,480
TPD (Phase II). Escalated Conveyor System is proposed to be installed for coal
transportation from the captive jetty to Power plant site which is about 1.5
km. The total project cost estimated is about Rs. 1620 Crores.
Public hearing for the power project
was conducted on 28th March 2007 as an integrated proposal for
captive jetty, conveyor system, sea water intake and treated waste water out
fall along with 405 MW coal based thermal power plant. The environmental
clearance to Thermal power project was issued vide letter No. J-13011/24/
2007-IA.II (T) dated 31st August, 2009. The CRZ components of the
project was recommended by MCZMA vide letter dated 17th May, 2008.
During the discussion, the following
points emerged:
(i)
Submit
the details of coal spillage and management
(ii)
Submit
the detail of dust control measures at loading, unloading and storage yard of
coal.
(iii)
Closed
Conveyor system shall be used for coal transportation.
Provided the response of the project proponent to the aforesaid
observations (i) to (ii) is to the satisfaction of the Committee, and
observation (iii) is incorporated in the Clearance letter for strict compliance
by the project proponent, the proposal may be considered for recommendation for
Environmental & CRZ Clearance.
3.4
Amendment
to the CRZ clearance issued for intake and disposal pipeline for 1050 MW gas
based combined cycle Power project near Village Pipavav, Gujarat by M/s GSPC
Pipavav Power Ltd. [11-34/2008-IA-III]
The
Gujarat Coastal Zone Management Authority has recommended the proposal.
During
the discussion, the following points emerged:
(i)
The
intake sea water is proposed through a open channel of 650 m length dredged to
-2.6 mts (CD). The open channel will have adverse impact on the marine life and
is not permissible. Re- examine and revise the proposal for closed pipeline as
per the clearance issued earlier in view of the consequence impacts.
In view of the foregoing observation, the
proposal is deferred and shall be considered afresh for change of location of
intake and outfall points only, if required.
3.5
Amendment
to the CRZ clearance issued for setting up of Vessel Traffic and Port
management System at Dumas by M/s Gujarat Maritime Board and Aatash Norcontrol
Ltd. [F.No.11-85/2008 – IA-III]
As presented by the project proponent, the proposal is for setting up of Master Station of the Vessel Traffic and Port Management System at new location instead of already permitted location. CRZ clearance for setting up of Vessel Traffic and Port Management system along the Gulf of Khambhat to M/s Aatash Norcontrol Ltd. was issued vide its letter no. 11-85/2008-IA-III dated 20.10.2008. Due to obstruction in Microwave path linking MCS and also difficulty in getting land at Dumas (210 06’ 22.01” N and 720 42’ 18.49” E) where originally Master Control Station was proposed, it is proposed to locate the Master Control Station along with staff quarters at new location having coordinates 210 4.860’ N and 720 42.410’ E, which is about 2.7 km away from the old location. The CRZ map was prepared by the Space Application Centre, Ahemadabad and the approved location and proposed location were duly superimposed. The Gujarat Coastal Zone Management Authority has also recommended for issue of amendment vide letter No. Env-10-2008-611-E dated 04.05.2010.
The details submitted by the project proponent were examined by the Committee and the following point emerged:
(i) The proposed
master control station and Staff quarters are close to the coastline. Necessary
emergency evacuation and disaster management plan shall be prepared for safety
of the staff and equipments.
The
Committee recommended for the issue of amendment to the CRZ Clearance dated 20.10.2008
with the above condition in the clearance letter.
3.6
Amendment
to the CRZ clearance issued for storage of for edible oil storage tanks at
Karwar port by M/s Ruchi Infrastructure Ltd. [F.No. J/16011/55/2001 IA-III]
The
Committee decided to defer the project, since the project proponent did not
attend the meeting.
4.1
Environmental
Clearance for 4/6 laning of package II, km 43.000 to 96.714 from Kerela/ Tamil
Nadu Border to Kanyakumari of NH- 47 and Nagercoil- Kavalkinaru section of NH-
47B by M/s NHAI [5-59/2007-IA-III]
As per the presentation made by the Project proponent, the proposal is for 4/6 laning of package II, km 43.000 to km 96.714 from Kerela/ Tamil Nadu Border to Kanyakumari of NH- 47 and Nagarcoil- Kavalkinaru section of NH- 47B. The existing width of the project road is 2 lane. The present proposal is for completely new alignment of total 70.36 km except initial length of 600 m starting just before the junction of Nagarecoil Bypass and existing NH 47B. The length of Karode (Kerala/Tamil Nadu Border) to Kanyakumari of NH-47 is 53.70 km and Nagarecoil to Kavalkinaru of NH-47B is 16.60 km. The existing ROW for NH-47 section is 10 m to 20 m at location wherever the existing road is utilized.
There are 26 bridges, 141 culverts along the alignment. Bypasses are proposed at 2 locations. 20 vehicular/pedestrian/cattle underpasses, service roads have been proposed at 25 locations of built up area. Truck lay byes have been provided at 1 location. 54 Bus bays have been provided. The project road passes through 25 villages in Kanyakumari district. The entire existing NH-47 from Kerala to Kanyakumari and NH-47B Nagercoil to Kavalkinaru is heavily built-up, hence bypass/realignment has been proposed except at locations where the existing road can be widened. The alignment runs in the Deccan plateau. The average water requirement during construction will be 750 KLD and the source will be ground water. Project Road does not pass through any eco- sensitive area except only 0.88 ha forests land.
About 14273 road side trees are going to be felled for the project area, against which 43,000 trees are proposed to be planted. About 558 households, 1 industry and 5358 agricultural families are going to be affected due to the project. The entitled persons will be compensated and assisted as per the extent of Govt. of India Regulation. The capital cost of the project is Rs. 621.77million. The total cost of the Resettlement and Rehabilitation is approximately Rs. 20.12 crores.
The project proposal was considered in the EAC meting held on 24th – 25th May 2007 and a ToR was finalised. Public hearing was conducted on 21.08.2010.
During the discussion, the following
points emerged:
(i)
The road passes through forest land and
requires diversion of forest area. Necessary permission shall be obtained before
start of construction work.
(ii)
Necessary
prior permission shall be obtained for cutting of trees from the competent
authority. Compensatory afforestation shall be carried out as per stipulated
conditions of MoEF and State Forest Division.
(iii)
R& R
shall be as per the guidelines of Govt. of India.
(iv)
IRC
guidelines shall be followed for widening & up-gradation of road.
(v)
The responses/commitments made during
public hearing shall be complied with letter and spirit.
(vi)
All the
recommendation of the EMP shall be complied with letter and spirit.
The
Committee recommends the proposal for Environmental Clearance with the above
conditions in the Clearance letter for strict compliance by the project
proponent.
4.2
Environmental Clearance for 4/6 laning of Deoli -
Jhalawar section of NH-12 in the State of Rajasthan by M/s. NHAI. [F.No.
10-75/2009-IA.III].
As presented by the project proponent, the proposal involves 4/6 lanning of Deoli-Jhalawar section of NH-12 (Deoli ch 0.000, km 165/000) to JN of NH-76 on Kota Bye-pass ch 83.042 in the State of Rajasthan. It involves widening and improvement of the existing alignment and bypass with more than marginal land acquisition at some locations. It requires diversion of 67.447 ha of forests land (55.80 hec. protected forest and 10.20 hec. reserved forest). The total land required is 518.08 hec. and the available land is 72.0 hec. and the land proposed to be acquired is 446.00 hec. The existing ROW varies from 20-45 M and proposed ROW is 45-76 M. There are 6600 trees within the proposed 60 m right off way out of which 6321 trees will be affected by the widening.
The
EAC in its 81st meeting held on 29th – 30th
October, 2009 finalized additional TOR for further study. The public hearing
was held in three districts – Kota on 15th March, 2010, Bundi on 22nd
March, 2010 and Bhilwada on 4th May, 2010.
During
the discussion, the following points emerged:
(i)
The road passes through reserve
forest area and requires diversion of forest area. Necessary permission shall
be obtained before start of construction work.
(ii)
Necessary
prior permission shall be obtained for cutting of trees from the competent
authorities. Compensatory afforestation shall be carried out as per stipulated
conditions of MoEF and State Forest Division.
(iii)
R& R
shall be as per the guidelines of Govt. of India.
(iv)
IRC
guidelines shall be followed for widening & up-gradation of road.
(v)
Necessary
bus bays and road side facilities and amenities shall be provided.
(vi)
The responses/commitments made during
public hearing should be complied with letter and spirit.
(vii)
All the
recommendation of the EMP shall be complied with letter and spirit.
The
Committee recommends the proposal for Environmental Clearance with the above
conditions in the Clearance letter for strict compliance by the project proponent.
4.3
Environmental
Clearance for widening of existing 2 lane NH-8D to 4
lane divided carriageway from Jetpur to Somnath in the State of Gujarat by M/s.
NHAI [F. No. 10-60/2009-IA-III]
As presented by the project proponent,
the proposal involves widening of NH-8 D existing 2
lanes to 4 lane divided carriageway from Jetpur to Somnath, Gujarat. The project
road stretch starts at km 0.000 at Jetpur and ends at km 127.000 at Somnath in
the State of Gujarat. The proposed length of the road is 123.49 kms. The
project involves expansion from 2 lane to 4 lane of existing ROW which is 30m,
the proposed ROW is 60 m. There are two districts - Rajkot and Junagadh, 7
talukas and 9 urban settlements along the project stretch. The road runs
through plain terrain. There are 3 proposed bypasses (Junagadh, Keshod,
Veraval) and two proposed realignments (Vanthili, Agatrai) along the project
stretch. There are eleven major bridges and 79 minor bridges existing along the
project road. 3 additional minor bridges have been proposed. 4 vehicular
underpasses & 13 cattle / pedestrian underpasses have been proposed along
the project road. One unidirectional flyover has also been proposed at the
start of the project road. Service road for a total length of 26.985 km has
been proposed in urban stretches. 3 truck lay byes, 3 toll plazas and 1 way
side amenity has been proposed. About
85% of the land use along the project road is agriculture land, settlements
make up 3.7 %. Barren land comprises about 4%, pasture land about 3% and others
about 3%. There are no Reserve forests, Wild life Sanctuaries or National Parks
along the project road. Roadside plantations (within existing ROW) are notified
as Protected Forest in certain stretches. Trees notified as Protected Forest
cover are on about 89km of the project road. A total of 18,056 trees are within
the proposed alignment out of which 10951 trees are saved (Notified Protected
Forest -8544 trees & non forest stretches-9512 trees). Some roadside tree
species include Amla, Karanj, Khair, Sisam. Nine rivers cross the project road.
They are Uben (Ch 14/200), Lol (Ch 29/200), Sonrakh (Ch 30/800), Ozat (Ch
48/000), Madwati (Ch 49/200), Sabli (Ch 60/200), tributary of Sabli (73/400),
Meghal (Ch 102/000) & Devka (Ch 117/000). All rivers are non-perennial
& rainfed. The endpoint of the project road is at Ch 127/000, which is
close to the western coastline, however it is 800m away from the coastline.
Land to be acquired for the project is approximately 462.27 Ha. About 844
structures are affected in the widening of the road. The total cost of the
project is 110.93 Crores.
The
EAC in its 79th meeting held on 27th – 28th
August, 2009 finalized additional TOR for further study. The public hearing was
conducting on 15th Dec 2009 at Rajkot and on at 5th
January 2010 at Junagarh. The project also attracts the CRZ Notification,
1991. Gujarat costal zone management
authority has recommended the proposal vide letter no. CRZ - ENV-10-2010-1245-E
Dated 18th May 2010. The project proponent submitted the EIA along
with the public hearing proceedings and Costal Zone Management Authority’s
recommendations. The details were put up before the committee.
During the discussion, the following
points emerged:
(i)
Necessary
prior permission shall be obtained for cutting of trees from the competent
authorities. Compensatory afforestation shall be carried out as per stipulated
conditions of MoEF and State Forest Division.
(ii)
R& R
shall be as per the guidelines of Govt. of India.
(iii)
Necessary
conditions shall be obtained from Central Ground Water Authority if ground
water is to be used for the construction proposes.
(iv)
IRC
guidelines shall be followed for widening & up-gradation of road.
(v)
The responses/commitments made during
public hearing should be complied with letter and spirit.
(vi)
All the
recommendation of the EMP shall be complied with letter and spirit.
The
Committee recommends the proposal for Environmental and CRZ Clearance with the
above conditions in the Clearance letter for strict compliance by the project
proponent.
4.4
Environmental
Clearance for development of Municipal Solid Waste Sanitary Landfill and
composting site near Industrial area on Jhansi Laitpur Highway, Jhansi by M/s.
Jhansi Nagar Nigam. [F. No. 10-33/2009-IA-III].
The Committee decided to defer the
project to the next meeting since the project proponent has
not presented the proper TOR compliance.
4.5
Environmental
clearance for the establishment of Integrated Municipal Solid Waste Management
Facility at Narela- Bhawana, Delhi by M/s. Ramky Enviro Engineer Ltd. [F. No.
10-67/2009-IA.III].
As presented by the project proponent the proposal
involves establishment of Integrated Municipal Solid Waste Management Facility
at Narela - Bawana Notified Site for the city of Delhi. Municipal Corporation
of Delhi (MCD) being one of the largest Urban Local Bodies (ULBs) in India is
currently experiencing pressures on its already overloaded/exhausted landfill
sites. About 6,000 to 7,000 TPD of municipal solid waste is generated in Delhi.
The existing three landfill have already exhausted its capacity. Hence an
immediate requirement stems in the present situation, to take up suitable
measures to develop waste processing and treatment facilities. In view of this,
Govt. of NCT, Delhi has notified Narela - Bawana site under its Master Plan
2021 for the development of SLF. The Processing and Disposal Facility is
planned for 1,000 TPD waste. The activities involve
Segregation, Composting, RDF & SLF with Leachate Collection & Treatment
of wastes. The water requirement will be 50 KLD, which will be met from DJB. DG
sets of 2 x 500 KVA as back up. Complete Recycle & Reuse of treated
Leachate is proposed. Use of Solar Power for hot water and street lighting and
maximum use of natural light has been proposed for Administrative building in the
design, At least 15 m green belt all around the facility and Nylon wire fencing
up to a height of 10 m at the down wind of SLF & waste segregation area to
stop blowing of liters is proposed. The cost of the
project will be 70.00 Crores (Phase 1) and Rs. 378.00 Crores in (Phase 2).
The project
falls under Category ‘B’ - Project/Activity 7(i), of EIA Notification 2006.
Since the Bawana Reserved
forest is within 2.5 km radius of site, Shri Krishna Sultanpur Reserved Forest
is within 4.5 km radius of site and Haryana State boundary is within 5 km
radius of the site, the project has been categorized as ‘A’ as per EIA
Notification, 2006, General Condition.
The
EAC in its 80th meeting held on 17th - 18th September, 2009 finalized
additional TOR for further study. The public hearing was conducted on 14th
May 2010. The project proponent submitted the EIA report along with the public
hearing proceedings. The details were put up before the committee.
During
the discussion, the following points emerged:
(i)
The
proponent shall ensure that the project fulfills all the provisions of
Hazardous Wastes (Management, Handling and Trans-boundary movement)) Rules,
2008 including collection and transportation. design etc
(ii)
The gas generated from the Landfill
facility shall be collected and disposed as per rules
(iii)
The Leachate from the facility shall
be collected and treated to meet the prescribed standards before disposal.
(iv) The proponent shall obtain necessary clearance from the Ground Water Authority for the use of ground water.
(v)
The depth of the land fill site shall
be decided based on the ground water table at the site.
(vi)
An On Site Emergency Management Plan
shall be prepared and implemented.
(vii)
Periodical ground water/soil
monitoring to check the contamination in and around the site shall be carried out.
The Committee recommends the proposal
for Environmental Clearance with the above conditions in the Clearance letter
for strict compliance by the project proponent.
4.6
Environmental Clearance for the development of Integrated Solid
waste Processing Facility (1800 TPD) through windrow composting, reuse of
refused derived fuel and rapid bio-methanation and scientific landfill at
Kodungiayur landfill site, Chennai, Tamil Nadu by M/s. Corporation of Chennai
(F.No. 10-82/2009-IA.III)
As presented by the project
proponent, the proposal is for the development of Integrated Solid waste
processing facility at Kodungiayur landfill site, Chennai, Tamil Nadu. The
facility proposed includes processing through accelerated Aerobic Composting,
refuse derived fuel formation, power generation and sanitary landfill of
Non-degradable waste. The capacity of the facility will be 1800 TPD at 100
acres of land of Chennai Municipal Corporation Kodungayiur Dump site, whereas
the present waste generated per day in Chennai city is 3500 tons. The cost of
the project is Rs. 31.00 Crores.
As per EIA
Notification, 2006, the project/activity is categorized as ‘B’, however since
the project site is located within 10 km from Critically Polluted area
‘Manali’, Tamil Nadu, the project is treated as Category ‘A’.
The
EAC in its 83rd meeting held on 21st - 23rd December, 2009 finalized
additional TOR for further study. Public hearing was conducted on 18.06.2010. The
details submitted were put up before the committee.
During the discussion, the following
points emerged:
i)
The
committee noted that there is a Court Case pending in the High Court of Madras
opposing the present location of solid waste processing facility/landfill site.
Submit the details of Court case and its present status.
ii)
The
proponent shall ensure that the project fulfills all the provisions of
Hazardous Wastes (Management, Handling and Trans-boundary movement) Rules, 2008
including collection and transportation design etc.
iii)
The gas generated from the Landfill
facility shall be collected and disposed as per rules.
iv)
The
Leachate from the facility shall be collected and treated to meet the
prescribed standards before disposal.
v)
The
proponent shall obtain necessary clearance from the Ground Water Authority for
the use of ground water.
vi)
The depth of the land fill site shall
be decided based on the ground water level at the site.
vii)
Project proponent shall prepare and
implement an On Site Emergency Management Plan.
viii)
Project proponent shall carryout
periodical ground water/soil monitoring in and around the site to check the
contamination.
ix)
All the
recommendation of the EMP shall be complied with letter and spirit.
The Committee recommends the proposal
for Environmental Clearance with the above conditions in the Clearance letter
for strict compliance by the project proponent.
4.7
Environmental
Clearance for establishment of Common Facilities for Treatment and Disposal of
Common Effluent and Hazardous Solid Waste Facilities at KIADB Industrial Area,
Sompura 1st State Dobaspet, Nelamangala Taluk, Banglore Rural
District, Karnataka by M/s. Banglore Eco-Park Pvt. Ltd. [F. No.
10-2/2010-IA-III].
As presented by the project proponent,
the proposal is to establish common facilities for treatment and disposal of
hazardous solid and liquid wastes at KIADB Industrial Area, Sompura 1st
State Dobaspet, Nelamangala Taluk, Banglore Rural District to cater to the need
of nearby industries generating hazardous wastes. The company has also proposed
to establish facilities for manufacture of pollution control equipments at the
above location to meet the needs of industries and other establishments in the
region.
The proposed common waste treatment
facility shall consist of Effluent treatment plant for treatment and disposal
of Biodegradable effluent and Non-Biodegradable effluent, Incineration plant
for treatment and disposal of Hazardous Solid Waste. ETP for biodegradable
effluent will be treated by conventional methods such as neutralization,
clarification, anaerobic and aerobic methods to irrigation standards.
Non-biodegradable effluents will be treated by methods such as multi effect
evaporation, crystallization and centrifuge. The incineration plant is designed
for thermal treatment for disposal of hazardous solid wastes. The plant
consists of primary chamber, secondary chamber followed by flue gas treatment
system (scrubbing system). Hazardous solid wastes will be burnt completely in
the primary & secondary chambers of the incinerator. The flue gases
generated will be treated in scrubbing system.
The total area of the plot is 16,188
sq.m. allotted by KIADB. The total built up area proposed is - 4,920 sq.m. and
green belt - 5,503 sq.m. It is proposed to develop a Common Treatment Facility
for Bio-degradable Effluent - 300 cum / day, non-bio-degradable effluent - 60
cum/day and common incineration plant - 200 kg/hr. The capacity of boiler will
be 2 ton/hr at 15 kg/cm2.
Boiler fuel will be agro waste and the power requirement will be 125 KVA.
The fresh water requirement will be 21 KLD and source is KIADB. The total cost
of the project is Rs. 4.9 crores.
The
EAC in its 85th meeting held on 25th - 26th February, 2010
recommended for the exemption of Public Hearing since the project is located
within the notified industrial estate and finalized additional TOR for further
study.
The details submitted by the project proponent were put up before the
committee.
During
the discussion, the following points emerged:
(i)
The proponent has not
prepared the EIA properly based on the approved Terms of References. The EIA/EMP
should be revised.
(ii)
The details should also
be examined in terms of what will be the inventory for the operation of the
plant in relation to the capacity of the plant. The details should be based as
per the guidelines of CPCB/State Pollution Control Board.
(iii)
The consultant has not
submitted complete papers to Quality Council of the India and as per the Office
Memorandum dt. 28th June, 2010 was not permitted to make a presentation
before the Expert Appraisal Committee.
In view of the foregoing observations, the
committee recommended to defer the proposal.
4.8
Finalization
of TOR for 8-lane access controlled expressway on the right bank of Upper Ganga
Canal from Sanauta bridge (Great Noida) to UP – Uttarakhand border, near
Purkaji, Distt. Muzaffarnagar and construction of Link expressway by M/s Uttar
Pradesh Expressway Industrial Development Authority [F. No. 10-23/2010-IA.III]
As presented by the project
proponent, the proposal involves the construction of 8-lane access controlled expressway on the
right bank of Upper Ganga Canal from Sanauta bridge (Great Noida) to UP–
Uttarakhand border, near Purkaji Distt. Muzaffarnagar before
Uttar Pradesh -Uttarakhand border including Link expressways. The proposed project will
include Link Expressways viz: i) New alignment on south western side of Meerut
town connecting proposed Upper Ganga Canal Expressway to Meerut Airport and
proposed DFC Terminal (Approx. Length = 23.5km), ii) New alignment from Purkazi
to Deoband traversing in north western direction (Approx. Length = 16.5km) and
iii) New alignment from NH-24 near Masuri traversing in north easterly
direction to Upper Ganga Canal Expressway near Dasna fall (Approx. length
3.5km). There are 2 nos. Future Links of 25km length at later stage.
The approximate length of
UGC Expressway (8 lanes) will be approx. 147.8 km while length of Link
Expressway (6 lanes) will be approx. 68.5 km. Service road (2 lanes) will be
provided in the length of approx. 97.30 km. The proposed expressway project
will be interlinked with i) Land
parcels for township development (i) area of approx. 93 ha. (spread over 6
locations); and the area to be opted by the Concessionaire will be part of its
bid ii) Navigational Facilities (optional) along the canal for the development
of tourism and water sports, iii) Augmentation of Hydro Power generation at
Seven fall locations on the canal and iv) Repair and rehabilitation of Upper
Ganga Canal. The present proposal is only for the construction of Expressway
and separate clearances shall be obtained for other components as and when required under Environmental Impact Assessment
Notification 2009 for other interlinked projects.
The proposed project is
passing through Bulandshahr, Gautam Buddh Nagar, Ghaziabad, Meerut,
Muzaffarnagar and Saharanpur districts of Uttar Pradesh.
There is no Reserve Forest
land involved in the project, however, approx, 655 ha (for ROW) Protected
Forest land is involved. The process of obtaining Clearance for diversion of
protected forest land for non-forestry purposes under the Act has been
initiated.
The proposed project is
passing completely outside the boundary of Hastinapur Wildlife Sanctuary. The
Hastinapur Wildlife Sanctuary is situated more than 650 m away on the left bank
(opposite side of Expressway) of Upper Ganga Canal at Canal Chainage km 71.040 (at Berla).
There will be 52 nos.
underpasses and 7 nos. ROBs across the project. 138 ha will be acquired for the Expressway and 200 ha for
link expressways. 44,000 trees are likely to be cut for the project. Total Cost
for the expressway is estimated as Rs. 5064 crores.
During the discussions, the Committee
finalized the following additional TOR for further study:
i). Examine and submit a brief description of the project, project name, nature, size, its
importance to the region/state and
the country.
a. Clearly indicating whether it
passes through –
(i) Forest
Areas (as specified under Forest Conservation Act
(1980)
(ii) Wild Life (Protection) Act (1972)
(iii) Any other Ecological Sensitive Areas
specified under EPA.
b. Also indicate whether the
proposed project is -
(i) New Project
(ii) Modification/upgradation
(iii) Modification with bypasses
(iv) Whether requiring additional
RoW (a) <20m (b) >20m
c. Indicate category of the project
‘A’ or ‘B-1’
d. Whether the project is funded by
Central Govt./ADB/WB.
e. Whether construction activities
have already been started or not.
ii). Any
litigation(s) pending against the proposed project and/or any directions
or orders passed by any court of law/any statutory
authority against the project is to be detailed out.
i.
Submit detailed alignment plan, with
details such as nature of terrain (plain, rolling, hilly), land use pattern,
habitation, cropping pattern, forest area, environmentally sensitive places,
notified industrial areas, river, lake, details of villages, teshils, districts
and states, latitude and longitude for important locations falling on the
alignment by employing remote sensing techniques followed by ground truthing
and also through secondary data sources.
ii.
Describe various alternatives
(including that for route alignment) considered,
procedures and criteria adopted for selection of the final alternative with reasons.
iii.
Submit Land use map of the study
area to a scale of 1:25,000 based on recent satellite imagery delineating the
crop lands (both single and double crop),
agricultural plantations, fallow lands, waste lands, water bodies, built-up
areas, forest area and other surface features such as railway tracks, airports,
roads, and major industries etc. and
submit a detailed ground surveyed map on 1:4000 scale showing the
existing features falling within the right of way (RoW) namely trees,
structures including archeological & religious, monuments etc. if any.
iv.
If the proposed route is passing
through any sloppy terrain, examine and submit the stability of slopes, if the
proposed road is to pass through cutting of embankment /control of soil erosion
from embankment.
v.
In
case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
vi.
If
the projects is located within 10km. of the National parks, Sanctuaries,
Biosphere Reserves, migratory corridors of Wild animals, then a map duly
authenticated by Chief Wildlife Warden showing these features vis-à-vis the
project location and the recommendations or comments of the Chief Wildlife Warden
thereon should be furnished. Study the details of Alternate routes near
Sanctuary and submit justification for the identified route. Examine details of
air quality / noise and it’s impact on the Hastinapur Wildlife Sanctuary.
vii.
Study
regarding the requirement of animal bypasses/ underpasses /FOB etc. across the
habitation areas shall be carried out. Adequate cattle
passes for the movement of agriculture material shall be provided at the
stretches passing through habitation areas.
viii.
The
proposed route requires cutting of 44000 trees, the information should be
provided for exact number of trees to be cut (including their girth sizes),
their species and whether it also involved any protected or endangered species.
Also examine and submit details of compensatory afforestation. Necessary green belt shall be provided on both side
of the highway/expressway with proper central verge as per the guideline and
cost provision should be made for regular maintenance for at least 5 years
during operational phase of the project.
ix.
If
the proposed route is passing through a city or town, with houses and human
habitation on the either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal should also
indicate the location of wayside amenities, which should include petrol
station/service centre, rest areas including public conveyance, telephone
booths and ambulance/first aid centers etc. Submit the details of noise control measures
viz. noise reflector/ barriers at the Sanctuary area/ thickly populated area.
x.
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges as per
the relevant IRC guidelines.
xi.
Assess
whether there is a possibility that the proposed project will adversely affect
the existing road traffic in the surrounding areas both during construction and
operation phases. (e.g. by causing increases in traffic congestion and traffic
accidents). Using primary traffic data, traffic forecasting methods as
indicated in IRC guidelines.
xii.
Examine and
submit the details of use of fly ash as per the revised fly ash rules (2009) in
the road construction, if the project road is located within the 100 km from the
Thermal Power Plant as per the relevant IRC guidelines.
xiii.
Examine and
submit the details of sand quarry borrow area and rehabilitation and mark them
on the layout plan.
xiv.
Examine
in detail the climate and meteorology of the area (max and min temperature,
relative humidity, rainfall); the nearest IMD meteorological station from which
climatological data have been obtained to be indicated.
xv.
Examine
and submit road safety audit as per the guidelines of Ministry of Road
Transport of Highway.
xvi.
Hydrology
study should be carried out and examine the impact on the canal system.
xvii.
The
air quality monitoring should be carried out both before and during the
construction phase and also expected increase/decrease after the construction
as per the EIA guidance manual.
xviii. Identify project
activities during construction and operation phases, which will affect the
noise levels and the potential for increased noise resulting from this project.
Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact at critical locations if any. Prediction of noise levels should be done by
using mathematical modeling at different representative locations, suitable for
Indian conditions clearly indicating the various inputs used in the world.
xix.
Examine
the impact of the project during the construction phase due to generation of
fugitive dust from crusher units, air emissions from hot mix plants and
vehicles used for transportation of materials and prediction of impact on
ambient air quality using appropriate mathematical model, description of model,
input requirement including ARA/ CBCP
emission factors and on site meteorological
parameters) and reference of derivation, distribution of major
pollutants and presentation in tabular form for easy interpretation shall be
carried out.
xx.
Also
examine and submit the details about the protection to existing habitations
from dust, noise, odour etc. both during construction and operation stages.
xxi.
If the proposed route involves
cutting of earth, the details of area to be cut, depth of cut, locations, soil
type, volume and quantity of earth and other materials to be removed with
location of disposal/ dump site along with necessary permission.
xxii. If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
xxiii. Examine and submit the
details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges. Provision of
speed breakers, safety signals, service lanes and foot paths should be examined
at appropriate locations through out the proposed road to avoid the accidents
as per the relevant IRC guideline.
xxiv. Submit the details of
source of water, availability and utilizable quantity, usage and impact on
other competitive users.
xxv.
If
there will be any change in the drainage pattern after the proposed activity,
details of changes shall be examined and submitted.
xxvi. Examine and submit details of
highest ground water table and soil characteristics. Provide details of Rain Water
Harvesting (RWH), which should be designed as per CGWB provisions. RWH pit
should be at least > 5 m. above the highest ground water table. Provision
shall be made for oil and grease removal from surface runoff.
xxvii. If there is a
possibility that the construction/widening of road will cause adverse impacts
such as destruction of forest, poaching, reductions in wetland areas, if so,
examine the impact and submit details.
xxviii. Submit the details of
road safety measures proposed both during construction and operation phases
with the details of signage, service roads, vehicular under passes, accident
prone zone. IRC guidelines shall be followed for widening & up gradation of
road.
xxix. Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns.
xxx.
Submit
traffic management plan during construction phase including the diversions etc.
xxxi. Provide details of
“Accident Prone “Areas (if any).
Further Accident data and geographic distribution should be reviewed and
analyzed to predict and identify trends – incase of expansion of the existing
highway and provide Post accident
emergency assistance and medical care to accident victims.
xxxii. If the proposed
project involves any land reclamation, details to be provided for which
activity land to reclaim and the area of land to be reclaimed.
xxxiii.Submit details of social impact
assessment of the project due to the proposed construction of road.
xxxiv. Estimated cost of the
project including environmental monitoring cost and funding agencies, whether
governmental or on the basis of BOT etc
for at least 5 years after the construction and provide details of
budget provisions (capital & recurring) for the project specific R&R
Plan (if applicable). Separate SIA has
to be carried out (if required). No. of
PAFs exceeds the no. as specified under NRRP (2007).
xxxv. Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
xxxvi. Detailed R&R plan
with data on the existing socio-economic status of the population in the study
area and broad plan for resettlement of the displaced population, site for the
resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific
xxxvii. Submit details of
Corporate Social Responsibility (CSR). Necessary provisions should be made in
the budget and clearly delineated.
xxxviii. Project proponent
should also clearly submit that no construction activity /tree cutting will be
taken –up before the project the “Project EC” has been accorded as per the
provision of EIA notification 2006 (as amended in 2009).
xxxix. Submit environmental
management and monitoring plan for all phases of the project viz. construction
and operation for at least 5 years.
xl.
Any further clarification on carrying out the above studies including anticipated
impacts due to the project and mitigative measures, Project proponent is advised
to refer to the EIA guidance manual available on Ministry’s website” http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 (as amended in 2009) in all the districts
separately and the issues raised by the public should be addressed in the
Environmental Management Plan.
A detailed draft
EIA/EMP report should be prepared as per the above additional TOR and should be
submitted to the Ministry as per the Notification.
4.9
Finalization
for TOR for rehabilitation, upgradation and strengthening of SH-84 (Ghogha–
Barahat) in the State of Bihar by M/s BSR Devl Corp. Ltd. [F. No. 10-25/2010-IA.III]
As presented by the project
proponent, the proposal involves rehabilitation,
up gradation and strengthening of SH-84 (Ghogha – Barahat). The
project road of SH- 84 starts at km 150 of NH-80 about 22 km away from center
of Bhagalpur town from Gol Sadak Chowk Ghogha in Bhagalpur District and ends at
Barahat in Banka District. The design length of road is 53.073 km. The road
portion falls within Bhagalpur District is 21.5 km and remaining in the Banka District.
The major settlements on the project road are Ghogha, Sanhaula, Kurma hat,
Dhoriya, Panjwara, Lakhpura and Barahat in the districts of Bhagalpur and
Banka. Apart from these, the road also passes through number of smaller
settlements. Existing RoW is 6m to 24.39 m and in Built-up sections it varies
from 6 to 10m. The proposed ROW is 30 m except in settlements/built up areas
where it has been restricted to 12 m to save structures. The topography of the
region is plain with slight undulation in small stretches. The land use pattern
is predominantly agricultural followed by settlement and built up section. The
proposed development work involves up gradation to two lane standards with 7.0
m pavement and 2.5 m earthen shoulder on either side, provision of longitudinal
drains, rehabilitation/ reconstruction of existing culverts and bridges etc.
Alternative sites were examined at two realignments locations (Km 23.400 –
24.000 and Km 45.430 – 45.700) and three Bypasses have been proposed at
congested settlements/location of Gogha (km 0.825 to 2.260), Kurmahat (Km 25.600 to 27.160) and Bikrampur (Km
44.470 to 45.430).
The
existing road has 106 culverts and 12 minor bridges. It is proposed to have
additional 22 culverts, 1 bridge and 2 ROBs. The main river crossing the
project road is Gehra at km 16.4. The project road falls in seismic zone IV
i.e. High Damage Risk Zone. There is no wildlife sanctuary or national park
along the project road; about 610 trees
present within proposed ROW, are likely to be affected due to the
widening activity; 206 Buildings will require to be cleared and 35.58 Ha. of
Land will need to be acquired. The road side plantation has been declared as
protected forest as per Forest & Environment Department of Bihar State
Government notification dated 28.08.1997. Therefore forest clearance is
required.
During the discussions, the Committee
finalized the following additional TOR for further study:
i) Examine and
submit a brief description of the project, project name, nature, size, its importance
to the region/state and the country.
a. Clearly indicating whether it
passes through –
(i) Forest
Areas (as specified under Forest Conservation Act
(1980)
(ii) Wild Life (Protection) Act (1972)
(iii) Any other Ecological Sensitive Areas
specified under EPA.
b. Also indicate whether the
proposed project is -
(i) New Project
(ii) Modification/up-gradation
(iii) Modification with bypasses
(iv) Whether requiring
additional RoW (a) <20m (b) >20m
c. Indicate category of the project
‘A’ or ‘B-1’
d. Whether the project is funded by
Central Govt./ADB/WB.
e. Whether construction activities
have already been started or not.
ii). Any
litigation(s) pending against the proposed project and/or any directions
or orders passed by any court of law/any statutory
authority against the project is to be detailed out.
iii) Submit
detailed alignment plan, with details such as nature of terrain (plain,
rolling, hilly), land use pattern, habitation, cropping pattern, forest area,
environmentally sensitive places, notified industrial areas, river, lake,
details of villages, teshils, districts and states, latitude and longitude for
important locations falling on the alignment by employing remote sensing
techniques followed by ground truthing and also through secondary data sources.
iv)
Describe various alternatives
(including that for route alignment) considered,
procedures and criteria adopted for selection of the final alternative with
reasons.
v)
Submit Land use map of the study
area to a scale of 1:25,000 based on recent satellite imagery delineating the
crop lands (both single and double crop),
agricultural plantations, fallow lands, waste lands, water bodies, built-up
areas, forest area and other surface features such as railway tracks, airports,
roads, and major industries etc. and
submit a detailed ground surveyed map on 1:4000 scale showing the
existing features falling within the right of way (RoW) namely trees,
structures including archeological & religious, monuments etc. if any.
vi)
If the proposed route is passing
through any sloppy terrain, examine and submit the stability of slopes, if the
proposed road is to pass through cutting of embankment /control of soil erosion
from embankment.
vii)
In
case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
viii)
If
the projects is located within 10km. of the National parks, Sanctuaries,
Biosphere Reserves, migratory corridors of Wild animals, then a map duly authenticated
by Chief Wildlife Warden showing these features vis-à-vis the project location
and the recommendations or comments of the Chief Wildlife Warden thereon should
be furnished. Study the details of Alternate routes near Sanctuary and submit
justification for the identified route. Examine details of air quality / noise and
it’s impact on the Wildlife Sanctuary, if any.
ix)
Study
regarding the requirement of animal bypasses/ underpasses /FOB etc. across the
habitation areas shall be carried out. Adequate cattle
passes for the movement of agriculture material shall be provided at the
stretches passing through habitation areas.
x)
If
the proposed route requires cutting of trees, the information should be
provided for exact number of trees to be cut (including their girth sizes),
their species and whether it also involved any protected or endangered species.
Also examine and submit details of compensatory afforestation. Necessary green belt shall be provided on both side
of the highway/expressway with proper central verge as per the guideline and
cost provision should be made for regular maintenance for at least 5 years
during operational phase of the project.
xi)
If
the proposed route is passing through a city or town, with houses and human
habitation on the either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal should also
indicate the location of wayside amenities, which should include petrol
station/service centre, rest areas including public conveyance, telephone
booths and ambulance/first aid centers etc. Submit the details of noise control measures
viz. noise reflector/ barriers at the Sanctuary area/ thickly populated area.
xii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges as per
the relevant IRC guidelines.
xiii)
Assess
whether there is a possibility that the proposed project will adversely affect
the existing road traffic in the surrounding areas both during construction and
operation phases. (e.g. by causing increases in traffic congestion and traffic
accidents). Using primary traffic data, traffic forecasting methods as
indicated in IRC guidelines.
xiv)
Examine and
submit the details of use of fly ash as per the revised fly ash rules (2009) in
the road construction, if the project road is located within the 100 km from
the Thermal Power Plant as per the relevant IRC guidelines.
xv)
Examine and
submit the details of sand quarry borrow area and rehabilitation and mark them
on the layout plan.
xvi)
Examine
in detail the climate and meteorology of the area (max and min temperature,
relative humidity, rainfall); the nearest IMD meteorological station from which
climatological data have been obtained to be indicated.
xvii)
Examine
and submit road safety audit as per the guidelines of Ministry of Road
Transport of Highway.
xviii) Hydrology study should
be carried out and examine the impact on the canal system.
xix)
The
air quality monitoring should be carried out both before and during the
construction phase and also expected increase/decrease after the construction
as per the EIA guidance manual.
xx)
Identify
project activities during construction and operation phases, which will affect
the noise levels and the potential for increased noise resulting from this
project. Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact at critical locations if any. Prediction of noise levels should be done by
using mathematical modeling at different representative locations, suitable for
Indian conditions clearly indicating the various inputs used in the world.
xxi)
Examine
the impact of the project during the construction phase due to generation of
fugitive dust from crusher units, air emissions from hot mix plants and
vehicles used for transportation of materials and prediction of impact on ambient
air quality using appropriate mathematical model, description of model, input
requirement including ARA/ CBCP
emission factors and on site meteorological
parameters) and reference of derivation, distribution of major
pollutants and presentation in tabular form for easy interpretation shall be
carried out.
xxii) Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. both during construction and operation stages.
xxiii) If the proposed route involves cutting of earth, the
details of area to be cut, depth of cut, locations, soil type, volume and
quantity of earth and other materials to be removed with location of disposal/
dump site along with necessary permission.
xxiv) If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
xxv)
Examine
and submit the details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges. Provision of
speed breakers, safety signals, service lanes and foot paths should be examined
at appropriate locations through out the proposed road to avoid the accidents
as per the relevant IRC guideline.
xxvi) Submit the details of
source of water, availability and utilizable quantity, usage and impact on
other competitive users.
xxvii) If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
xxviii) Examine and submit details of
highest ground water table and soil characteristics. Provide details of Rain
Water Harvesting (RWH), which should be designed as per CGWB provisions. RWH
pit should be at least > 5 m. above the highest ground water table.
Provision shall be made for oil and grease removal from surface runoff.
xxix) If there is a
possibility that the construction/widening of road will cause adverse impacts
such as destruction of forest, poaching, reductions in wetland areas, if so,
examine the impact and submit details.
xxx)
Submit
the details of road safety measures proposed both during construction and
operation phases with the details of signage, service roads, vehicular under
passes, accident prone zone. IRC guidelines shall be followed for widening
& up gradation of road.
xxxi) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns.
xxxii) Submit traffic
management plan during construction phase including the diversions etc.
xxxiii)Provide details of
“Accident Prone “Areas (if any).
Further Accident data and geographic distribution should be reviewed and
analyzed to predict and identify trends – incase of expansion of the existing
highway and provide Post accident
emergency assistance and medical care to accident victims.
xxxiv) If the proposed
project involves any land reclamation, details to be provided for which
activity land to reclaim and the area of land to be reclaimed.
xxxv) Submit details of social impact
assessment of the project due to the proposed construction of road.
xxxvi) Estimated cost of the
project including environmental monitoring cost and funding agencies, whether
governmental or on the basis of BOT etc
for at least 5 years after the construction and provide details of
budget provisions (capital & recurring) for the project specific R&R
Plan (if applicable). Separate SIA has
to be carried out (if required). No. of
PAFs exceeds the no. as specified under NRRP (2007).
xxxvii) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
xxxviii) Detailed R&R plan
with data on the existing socio-economic status of the population in the study
area and broad plan for resettlement of the displaced population, site for the
resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
xxxix) Submit details of
Corporate Social Responsibility (CSR). Necessary provisions should be made in
the budget and clearly delineated.
xl)
Project
proponent should also clearly submit that no construction activity /tree
cutting will be taken –up before the project the “Project EC” has been accorded
as per the provision of EIA notification 2006 (as amended in 2009).
xli)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation for at least 5 years.
xlii)
Any further clarification on carrying out the above studies including anticipated
impacts due to the project and mitigative measures, Project proponent is advised
to refer to the EIA guidance manual available on Ministry’s website” http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 (as amended in 2009) in all the districts
separately and the issues raised by the public should be addressed in the
Environmental Management Plan.
A detailed draft
EIA/EMP report should be prepared as per the above additional TOR and should be
submitted to the Ministry as per the Notification.
4.10
Finalization
for TOR for rehabilitation, up gradation and strengthening of SH-85 (Akbarnagar
- Amarpur) in the State of Bihar by M/s BSR Devl Corp. Ltd. [F. No. 10-26/2010-IA.III]
As presented
by the project proponent, the proposal involves Rehabilitation,
Up-gradation and Strengthening of SH-85 from Akbarnagar
to Amarpur Section in the State of
Bihar. The entire project road is confined to Bihar State only. The project
road of SH- 85 starts at km 113 of NH-80 from Akbarnagar in Bhagalpur District
and ends at km 34.000 at Amarpur in Banka District. The design length of road
is 29.304 km. The major settlements on the project road are Akbarnagar,
Panchrukhi, Sakund, Amba, Pawai and Amarpur in the districts of Bhagalpur and
Banka. Apart from these, the road also passes through a number of smaller
settlements.Existing RoW is 6m to 24.39 m and in Built-up sections it varies
from 6 to 10m. The PROW is 30 m except in Settlements/Built up areas where it
has been restricted to 12 m to save structures.The topography of the region is
plain with slight undulation in small stretches. The land use pattern is
predominantly agricultural followed by settlement and built up section.
The
proposed development work involves upgradation to two lane standards with 7.0 m
pavement and 2.5 m earthen shoulder on either side, provision of longitudinal
drains, rehabilitation/ reconstruction of existing culverts and bridges etc.
Alternative sites were examined and realignment at one location (Km 21.510 –
21.760) and a one bypass have been
proposed at congested settlements of Chapre (km 24.580 to km 25.780). The
existing road has 76 culverts; 1 major bridge and 4 minor bridges. It is
proposed to have additional 9 culverts and one 2-lane bridge proposed to be
replaced. The main river crossing the project road is Chanan river at km
3.8.The project road is prone to floods particularly from Akbarnagar to Milky
and falls in seismic zone IV i.e. High Damage Risk Zone.
There is
no wildlife sanctuary or national park along the project road; about 325
trees present within proposed ROW, are
likely to be affected due to the widening activity; 223 Buildings will require to be cleared and
15.57 Ha. of Land will needed to be acquired. The road side plantation has been
declared as protected forest as per Forest & Environment Department of
Bihar State Government notification dated 28.08.1997. Therefore forest
clearance is required.
During the discussions, the Committee
finalized the following additional TOR for further study:
i) Examine and
submit a brief description of the project, project name, nature, size, its importance
to the region/state and the country.
a. Clearly indicating whether it
passes through –
(i) Forest
Areas (as specified under Forest Conservation Act
(1980)
(ii) Wild Life (Protection) Act (1972)
(iii) Any other Ecological Sensitive Areas
specified under EPA.
b. Also indicate whether the
proposed project is -
(i) New Project
(ii) Modification/up-gradation
(iii) Modification with bypasses
(iv) Whether requiring
additional RoW (a) <20m (b) >20m
c. Indicate category of the project
‘A’ or ‘B-1’
d. Whether the project is funded by
Central Govt./ADB/WB.
e. Whether construction activities
have already been started or not.
ii). Any
litigation(s) pending against the proposed project and/or any directions
or orders passed by any court of law/any statutory
authority against the project is to be detailed out.
iii) Submit
detailed alignment plan, with details such as nature of terrain (plain,
rolling, hilly), land use pattern, habitation, cropping pattern, forest area,
environmentally sensitive places, notified industrial areas, river, lake,
details of villages, teshils, districts and states, latitude and longitude for
important locations falling on the alignment by employing remote sensing
techniques followed by ground truthing and also through secondary data sources.
iv)
Describe various alternatives
(including that for route alignment) considered,
procedures and criteria adopted for selection of the final alternative with
reasons.
v)
Submit Land use map of the study
area to a scale of 1:25,000 based on recent satellite imagery delineating the
crop lands (both single and double crop),
agricultural plantations, fallow lands, waste lands, water bodies, built-up
areas, forest area and other surface features such as railway tracks, airports,
roads, and major industries etc. and
submit a detailed ground surveyed map on 1:4000 scale showing the
existing features falling within the right of way (RoW) namely trees,
structures including archeological & religious, monuments etc. if any.
vi)
If the proposed route is passing
through any sloppy terrain, examine and submit the stability of slopes, if the
proposed road is to pass through cutting of embankment /control of soil erosion
from embankment.
vii)
In
case the road passes through a flood
plain of the river, the details of micro drainage, flood passages and
information on flood periodicity at least of last 50 years in the area should
be examined.
viii)
If
the projects is located within 10km. of the National parks, Sanctuaries,
Biosphere Reserves, migratory corridors of Wild animals, then a map duly
authenticated by Chief Wildlife Warden showing these features vis-à-vis the
project location and the recommendations or comments of the Chief Wildlife
Warden thereon should be furnished. Study the details of Alternate routes near
Sanctuary and submit justification for the identified route. Examine details of
air quality / noise and it’s impact on the Wildlife Sanctuary, if any.
ix)
Study
regarding the requirement of animal bypasses/ underpasses /FOB etc. across the
habitation areas shall be carried out. Adequate cattle
passes for the movement of agriculture material shall be provided at the
stretches passing through habitation areas.
x)
If
the the proposed route requires cutting of trees, the information should be
provided for exact number of trees to be cut (including their girth sizes),
their species and whether it also involved any protected or endangered species.
Also examine and submit details of compensatory afforestation. Necessary green belt shall be provided on both side
of the highway/expressway with proper central verge as per the guideline and
cost provision should be made for regular maintenance for at least 5 years
during operational phase of the project.
xi)
If
the proposed route is passing through a city or town, with houses and human
habitation on the either side of the road, the necessity for provision of
bypasses/diversions/under passes shall be examined and submitted. The proposal should also
indicate the location of wayside amenities, which should include petrol
station/service centre, rest areas including public conveyance, telephone
booths and ambulance/first aid centers etc. Submit the details of noise control measures
viz. noise reflector/ barriers at the Sanctuary area/ thickly populated area.
xii)
Submit
details about measures taken for the pedestrian safety and construction of
underpasses and foot-over bridges along with flyovers and interchanges as per
the relevant IRC guidelines.
xiii)
Assess
whether there is a possibility that the proposed project will adversely affect
the existing road traffic in the surrounding areas both during construction and
operation phases. (e.g. by causing increases in traffic congestion and traffic
accidents). Using primary traffic data, traffic forecasting methods as
indicated in IRC guidelines.
xiv)
Examine and
submit the details of use of fly ash as per the revised fly ash rules (2009) in
the road construction, if the project road is located within the 100 km from
the Thermal Power Plant as per the relevant IRC guidelines.
xv)
Examine and
submit the details of sand quarry borrow area and rehabilitation and mark them
on the layout plan.
xvi)
Examine
in detail the climate and meteorology of the area (max and min temperature,
relative humidity, rainfall); the nearest IMD meteorological station from which
climatological data have been obtained to be indicated.
xvii)
Examine
and submit road safety audit as per the guidelines of Ministry of Road
Transport of Highway.
xviii) Hydrology study should
be carried out and examine the impact on the canal system.
xix)
The
air quality monitoring should be carried out both before and during the
construction phase and also expected increase/decrease after the construction
as per the EIA guidance manual.
xx)
Identify
project activities during construction and operation phases, which will affect
the noise levels and the potential for increased noise resulting from this
project. Discuss the effect of noise levels on near by habitation during the
construction and operational phases of the proposed highway. Identify noise
reduction measures and traffic management strategies to be deployed for
reducing the negative impact at critical locations if any. Prediction of noise levels should be done by
using mathematical modeling at different representative locations, suitable for
Indian conditions clearly indicating the various inputs used in the world.
xxi)
Examine
the impact of the project during the construction phase due to generation of
fugitive dust from crusher units, air emissions from hot mix plants and
vehicles used for transportation of materials and prediction of impact on
ambient air quality using appropriate mathematical model, description of model,
input requirement including ARA/ CBCP
emission factors and on site meteorological parameters) and reference of derivation, distribution of major
pollutants and presentation in tabular form for easy interpretation shall be
carried out.
xxii) Also examine and
submit the details about the protection to existing habitations from dust,
noise, odour etc. both during construction and operation stages.
xxiii) If the proposed route involves cutting of earth, the
details of area to be cut, depth of cut, locations, soil type, volume and
quantity of earth and other materials to be removed with location of disposal/
dump site along with necessary permission.
xxiv) If the proposed route is passing through low lying areas,
details of fill materials and initial and final levels after filling above MSL,
should be examined and submit.
xxv)
Examine
and submit the details of measures taken during constructions of bridges across
river/canal/major or minor drains keeping in view the flooding of the rivers
and the life span of the existing bridges. Provision of
speed breakers, safety signals, service lanes and foot paths should be examined
at appropriate locations through out the proposed road to avoid the accidents
as per the relevant IRC guideline.
xxvi) Submit the details of
source of water, availability and utilizable quantity, usage and impact on
other competitive users.
xxvii) If there will be any
change in the drainage pattern after the proposed activity, details of changes
shall be examined and submitted.
xxviii) Examine and submit details of
highest ground water table and soil characteristics. Provide details of Rain
Water Harvesting (RWH), which should be designed as per CGWB provisions. RWH
pit should be at least > 5 m. above the highest ground water table.
Provision shall be made for oil and grease removal from surface runoff.
xxix) If there is a
possibility that the construction/widening of road will cause adverse impacts
such as destruction of forest, poaching, reductions in wetland areas, if so,
examine the impact and submit details.
xxx)
Submit
the details of road safety measures proposed both during construction and
operation phases with the details of signage, service roads, vehicular under
passes, accident prone zone. IRC guidelines shall be followed for widening
& up gradation of road.
xxxi) Examine road design
standards, safety equipment specifications and Management System training to
ensure that design details take account of safety concerns.
xxxii) Submit traffic
management plan during construction phase including the diversions etc.
xxxiii)Provide details of
“Accident Prone “Areas (if any).
Further Accident data and geographic distribution should be reviewed and
analyzed to predict and identify trends – incase of expansion of the existing
highway and provide Post accident
emergency assistance and medical care to accident victims.
xxxiv) If the proposed
project involves any land reclamation, details to be provided for which
activity land to reclaim and the area of land to be reclaimed.
xxxv) Submit details of social impact
assessment of the project due to the proposed construction of road.
xxxvi) Estimated cost of the
project including environmental monitoring cost and funding agencies, whether
governmental or on the basis of BOT etc
for at least 5 years after the construction and provide details of
budget provisions (capital & recurring) for the project specific R&R
Plan (if applicable). Separate SIA has
to be carried out (if required). No. of
PAFs exceeds the no. as specified under NRRP (2007).
xxxvii) Details of the
properties, houses, businesses etc. activities likely to be effected by land
acquisition and their financial loses annually.
xxxviii) Detailed R&R plan
with data on the existing socio-economic status of the population in the study
area and broad plan for resettlement of the displaced population, site for the
resettlement colony, alternative livelihood concerns/ employment and
rehabilitation of the displaced people, civil and housing amenities being
offered, etc and the schedule of the
implementation of the project specific.
xxxix) Submit details of
Corporate Social Responsibility (CSR). Necessary provisions should be made in
the budget and clearly delineated.
xl)
Project
proponent should also clearly submit that no construction activity /tree
cutting will be taken –up before the project the “Project EC” has been accorded
as per the provision of EIA notification 2006 (as amended in 2009).
xli)
Submit
environmental management and monitoring plan for all phases of the project viz.
construction and operation for at least 5 years.
xlii)
Any further clarification on carrying out the above studies including anticipated
impacts due to the project and mitigative measures, Project proponent is advised
to refer to the EIA guidance manual available on Ministry’s website” http://moef.nic.in/Manual/highways”
Public
hearing to be conducted for the project as per provisions of Environmental
Impact Assessment Notification, 2006 (as amended in 2009) in all the districts
separately and the issues raised by the public should be addressed in the
Environmental Management Plan.
A detailed draft
EIA/EMP report should be prepared as per the above additional TOR and should be
submitted to the Ministry as per the Notification.
4.11
Finalization
of TOR for development of a green field Airport in
Sindhudurg, Maharashtra by IRB Sindhudurg Airport Pvt. Ltd. [F.No.
10-27/2010-IA.III].
As presented by the project
proponent, the proposal involves development of a green field Airport in
Sindhudurg, Maharashtra. The site is located between village Chippi-vadi and
village Parul, 23 km west of Kudal, district Head Waauter of Singhudurg. The
airport site reference coordinates are Latitude 16000’ N and
Longitude 73032’ E.
The first evaluation of an
international airport site at Sindhudurg was undertaken by the Airports
Authority of India, who after evaluating various locations recommended a site
at Mahapen located approximately 20 km south of Kudal. This site was
re-examined by RITES, who reported insufficient land for development of an
international airport. Another site between village Chippi-vadi and village
Parule was located 23 km west of Kudal, it was observed that the site was
suitable for development of an airport. MIDC subsequently acquired about 271 ha
of land for the site of proposed airport. 271 ha of land has been acquired. The
site is located on Lateritic Plateau with small mounds and valleys. In principle approval for the
Greenfiled domestic airport project from the Ministry of Civil Aviation has
been obtained vide letter dated 29.09.2008 and site approval from DGCA vide
letter dated 17.05.2008. NOC from Ministry of Defense has been obtained vide
letter dated 09.09.2008.
The proposed runway length is 3450 m, width is 45 m to service D type
aircraft. A half length parallel taxiway of 1565m which will be added in phase
II and the separation of runway and taxiway will be 176m. ATC tower, Technical
building and metrological lab is also proposed. One level terminal building has
been designed at a norm of 20 sqm per peak hour passenger. About 61 KLD water
is required during construction phase and 350 KLD during operational phase
which will be met from Dhampur, which is 20 km away from the site. Power supply
will be obtained through dedicated lines of Kudal and Dhampur. Standby DG set
of 3X1500 KVA are proposed. Expected sewage generated will be 180 KLD. No eco
sensitive area is within 10 km. radius.
Sea coast is appox. at 4 km
distance and creek is about 1 km from the site. The total project cost
is 186 Crores.
During the discussions, the Committee
finalized the following additional TOR for further study:
i)
Examine
and submit a brief description of the project, nature, size location, geology,
hydrology, topography, climate and connectivity by road/rail of the project including land
description/ plot/ survey / khasra nos, village, tehsil, district, State &
extent of the land, project coverage, Master Plan, phasing of the project and scope and its importance to the local
and national level.
ii)
Submit
the copy of the techno economic feasibility report submitted to the Ministry of
Civil Aviation
iii)
Any
litigations pending against the proposed project site and / or any directions
or orders passed by any court of law against the project are to be detailed out.
iv)
In case
of expansion/ modernization of the project, the environmental compliance status
for the existing project should be explained.
v)
Examine
and submit details of the study area
(project area and area 10 km around its boundary) delineating the major
topographical features such as land use, drainage, locations of habitats, major
constructions including roads, railways, pipelines, major industries, if any. The details should also include
environmental sensitive areas, including the cropping pattern, waste land,
forest area and built up area etc.
vi)
Examine
and submit baseline data of existing situation including description of
terrain, hill, slopes and elevation.
vii) Submit the baseline data on flora and
fauna based on field survey clearly indicating the details of site and within
10 km radius.
viii) Provide the historical and climatic
data such as climatic conditions, rainfall, wind pattern, history of cyclones,
storms surges, visibility etc.,
ix)
Submit
the meteorological data consisting of climatic conditions, wind pattern, wind
speed, history of cyclones, storms surges, wind direction, rainfall, temperature, cloud cover, (amount and
height), and humidity of in an area of
10km radius.
x)
Examine
and submit details of impact of the project both during construction and
operation phase on the soil nearby settlements, surface drainage etc. Soil data
should include type, classification, characteristics, properties, etc.
xi)
Submit
the baseline data on nearby ground water, surface water bodies, lakes, their
dimensions, present quality and their utility.
Baseline data on ground water its quality and depth of the ground water
table.
xii) Submit details of storm waters,
drainage of the site and surrounding area. Also examine the discharge of trade
effluents and sewage, run off from cargo storages and toxic or harmful
substances, and their percolation to underground water. Examine the impact of
airport operations on surface water sources, contamination due to cargo
operations, impact on utility of surface water resources by the neighboring
colonies, impact on surface water flow (flooding) due to any anticipated
obstructions and spillages etc.
xiii) Submit the water requirement, use of
treated waste water along with detailed water balance and flow chart of water
use during construction and operation phases.
xiv) Rain water harvesting proposals should
be made with due safeguards for ground water quality. Maximize recycling of
water and utilization of rain water.
xv)
Examine the details of the energy requirement and
conservation measures using alternate source of energy.
xvi) Submit the layout plan/site plan of
the proposed project development,
activity areas with facilities including terminal building runways, taxi/link taxi ways, air traffic
control tower, Repair& Servicing(R&S) hangars, AC plants, DG set rooms,
operational buildings such as RADAR and Instrument Landing System(ILS)
structures, administrative buildings, utilities such as main and stand by power,
water supply installations, cargo storage facilities, Petrol Oil Lubricant
(POL) stores, Aviation Turbine Fuel (ATF) store and Bulk Petroleum installation
aprons, drainages, sewage disposal, navigation facilities, communication
facilities, airfield lighting, crash fire & rescue facilities, car parking,
access/approach roads, refueling facilities, boundary wall, meteorological
observatory, landscape, waste disposal etc.
xvii) Examine and submit details of levels,
quantity required for filling, source of filling material and transportation
details etc.
xviii) Examine and Submit the details of Borrow
/quarry sites for development keeping in view the following:
a.
Appropriate
measures must be taken while undertaking digging activities to avoid any likely
degradation of water quality.
b.
No
excavation or dumping on private property is carried out without written
consent of the owner.
c.
No
excavation or dumping shall be allowed on wetlands, forest areas or other
ecologically valuable or sensitive locations.
d.
Excavation
work shall be done in close consultation with the Soil Conservation and
Watershed Development Agencies working in the area, and
e.
Construction
spoils including bituminous material and other hazardous materials must not be
allowed to contaminate water courses and the dump sites for such materials must
be secured so that they shall not leach into the ground water.
xix)
The
construction material should be obtained only from approved quarries. In case new quarries are to be opened,
specific approvals from the competent authority shall be obtained in this
regard.
xx)
Adequate precautions should be taken
during transportation of the construction material so that it does not affect
the environment adversely.
xxi)
A
detailed traffic and transportation study should be made for existing and
projected passenger and cargo traffic. Road connectivity to the site and its
adequacy shall be examined. Examine the details of parking requirement for
various type of vehicles and circulation plan.
xxii)
Examine
and submit the details on types of waste, which are generated, can be
classified into construction or demolition waste and municipal waste, i.e.,
biodegradable and recyclable waste, hazardous waste and waste. Details of
authorized Municipal solid waste facilities and hazardous waste disposal facilities
in the area are to be given.
xxiii)
Provide the
details of Ambient Air Quality (AAQ) based on the many other factors such as,
background pollution levels, other sources of pollution, weather and proximity
of residential areas.
xxiv)
Thick
green belt of adequate width shall be planned all around the airport site
especially near the settlements to mitigate noise and vibrations. The
identification of species/ plants shall be made based on the botanical studies.
xxv)
Examine
and submit the details of impact on the local population, utilities, settlements, infrastructure
facilities in the existing and relocated area, economic conditions in the
existing and relocated area, cultural and archaeological assets etc. Regulation should be made for
development around the airport to avoid the bud manus and authorized
development.
xxvi)
Provide
details on R&R plan with data on the existing socio-economic status of the
population in the project area and broad plan for resettlement of the displaced
population, site for the resettlement colony, alternative livelihood
concerns/employment for the displaced people, civil and housing amenities being
offered, etc and the schedule of the implementation of the project specific
R&R Plan if any is to be given.
xxvii)
Examine
and submit the details of activities associated with airport construction and
operations such as Occupational hazards due to exposure, Fire and / or
explosion, Leakage of flammable material, Release of toxic material.
xxviii)
Submit
the details on estimated cost of development of the project, environmental
costs, funding agencies, whether governmental or on the basis of BOO or BOT
etc., manpower, time frame etc required for the completion of the project.
xxix)
Examine separately the
details for construction and operation phases both for Environmental Management
Plan and Environmental Monitoring Plan with cost and parameters.
xxx)
Submit
details of Corporate Social Responsibilities (CSR).
xxxi)
Examine and submit information on
Administrative and technical set up for management of environment, In built
mechanism of self monitoring of compliance of environmental regulations,
Institutional arrangements proposed with other organizations/ Govt. authorities
for effective implementation of environmental measures proposed in the EIA,
Safe guards/mechanism to continue the assumptions/field conditions made in the
EIA, for arriving the site suitability.
Public hearing to be conducted for the project as per provisions of Environmental Impact Assessment Notification, 2006 (as amended in 2009) in all the districts separately and the issues raised by the public should be addressed in the Environmental Management Plan.
A
detailed draft EIA/EMP report should be prepared as per the above additional
TOR and should be submitted to the Ministry as per the Notification.
4.12
Finalization
of TOR for laying Kochi-Kayankulam subsea pipeline
project to transport R-LNG from PLL, LNG terminal, Vyapeen, Kochi to NTPC,
Kayankulam, Kerala by GAIL (India) Ltd [F. No. 10-33/2010-IA.III].
The proposal involves for laying Kochi-Kayankulam subsea pipeline to transport
re-gasified LNG from proposed PLL LNG re-gasification terminal at Vyapeen Kochi
to NTPC, Kayamkulam, Kerala. NTPC has planned to setup a 1050 MW gas based
power plant at Kayamkulam for which GAIL has to supply R-LNG from PLL terminal
at Kochi. The pipeline will be laid from GAIL terminal in the vicinity of
nearby area of PLL terminal for around 1.2 km onshore and thereafter it will
take offshore route to Kayankulam. The coordinate for the LFP-1 at starting
point from PLL LNG terminal Vyapeen is Latitude 9’ 58” 54.9 N Longitude 76’ 13”
20.59 E and LFP-2 at end point of NTPC Kayamkulam is latitude 9’ 14” 18.9 N and
Longitude 76’ 24” 57.52 E. Pipeline from dispatch terminal at Kochi is aligned
westwards toward Vyapeen seashore and is located onshore. It crosses the shore
approach area up to a water depth of (-)30 to (-)35 meter and then southward.
Pipeline then runs parallel to the shore up to Kayamkulam. It then turns
eastward till Kayamkulam coast. Beyond coast line the pipeline continues in the
same direction till it reaches NPTC-Kayamkulam Power Plant. Pipeline length is
estimated to be 93.5 km (based on desk top study). Out of this length on-shore
portion in each coast is approx. 3.5 km and balance is located onshore
(including 2.0 km HDD to cross Kochi shipping channel). The Kayamkulam LFP will
further traverse through the National Waterways – III to NTPC. The total cost
of the project is Rs. 906.44 Crores.
During the discussions, the Committee
finalized the following additional TOR for further study:
(i)
Submit
the recommendation of Kerala Coastal Zone Management Authority.
(ii)
Submit
the details of fishing activities and impact due to the activity.
(iii)
Submit
the details of the applicability of MSIHS rules and preparedness shall be addressed
in the DMP.
(iv)
Submit
Disaster Management Plan including risk assessment. The details should address
natural calamities viz Cyclone, earthquake, Tsunami and damage due to other
ship/ vessels movement.
Public hearing to be conducted for the
project as per provisions of Environmental Impact Assessment Notification, 2006
and the issues raised by the public should be addressed in the Environmental
Management Plan.
A detailed draft EIA/EMP
report should be prepared as per the above additional TOR and should be
submitted to the Ministry as per the Notification.
4.13
Finalization
of ToR for Construction of new Integrated building at Veer Savarkar Airport,
Port Blair, Andaman & Nicobar island by M/s Airport Authority of India [F.
No. 10-39/2010-IA-III]
The Committee decided to defer the
project, since the project proponent did not circulate the documents.
4.14
CRZ
Clearance for proposed intake and outfall for Coal based (2x150 MW) Power plant
at Village Bhadreshwar, Taluka Mundra, District Kutch, Gujarat by M/s OPG Power
Gujarat Pvt. Ltd. [F. No.11-7/2010-IA.III].
As presented
by the project proponent, the proposal involves construction of intake
point and discharge line to the coal based Power plant village Bhadreshwar,
Taluka Mundra, District Kutch, Gujarat. It is proposed to use seawater for
cooling and discharge the warm water into the adjoining Gulf of Kuch. The proposed marine facilities will
consist of: i) intake of seawater from
the Gulf by a dredged channel, ii) construction of intake ponds with pump
houses and iii) marine outfall for the discharge of warm water by five numbers
of offshore pipelines with diffuser ports.
The total volume of seawater intake will be 4500 m3/hour
during Phase I, additional 10000 m3/hour during Phase II and another
10000 m3/hour during Phase III. The channel of required cross
section has to be dredged to meet the design flow. The intake ponds with a pump
house will be constructed close to High tide line.
The volume of return water will be 3500
m3/hour during Phase I, another 8000 m3/hour during Phase
II and another 8000 m3/hour during Phase III. The outfall will be
located at 1250 m distance for Phase I discharge, 1400 m discharge for Phase II
discharge and 1550 m distance for Phase III discharge. The warm water will be
carried back into the sea by pipelines of size 1 × 900 mm dia. for Phase I,
additional 2 × 900 mm dia. for Phase II and another 2 x 900 mm dia. for Phase
III. The pipelines will be buried below the seafloor and it will have multiple
port diffuser arrangement of each line consisting 15 nos. x 200 mm dia. for
Phase I, 18 nos. x 200 mm dia. ports for
each Phase II and Phase III. The return water temperature will not
exceed 3°C higher
than the ambient water while salinity will be 1 ppt higher. The chlorine dosage
of 3 ppm will be given to the seawater drawn and the return water discharged
into the sea will have a concentration around 0.5 ppm.
During
the discussion, the following points emerged:
(i)
The committee noted that the proposal is for
the construction of an open channel for intake within the CRZ area. Due to
various environmental problems including the adverse impact on the marine life
the present proposal is not acceptable.
(ii) There are presence of sand dunes and mangroves in certain areas
and the construction is proposed which will destroy the sand dunes which is not
permissible.
(iii)
The
committee suggested that:
a.
For
intake water, the pipeline should be considered instead of a open channel.
b.
Fresh
recommendations from Gujarat State Coastal Zone Management Authority should be
obtained for the revised proposal.
In view of the above, the committee
recommended rejecting the present proposal.
4.15
CRZ
clearance for the construction of coal conveyor from
Coal Jetty and pipeline of cooling water intake and outfall at Vanagiri
Village, Nagapattinam District, Tamil Nadu by M/s PEL Power Ltd.,
Hyderabad [F. No. 11-9/2010-IA.III]
As presented
by the project proponent, the proposal involves construction of coal conveyor from Coal Jetty
and pipeline of cooling water intake and outfall at Vanagiri Village for their
proposed 3x350 (1050 MW) Coal based
power Plant at Marudampallam village in Nagapattinam district, Tamil
Nadu. The sea shore is about 1 Km distance from the eastern boundary of
the project site. The sea shore is covered with sand and there are no mangroves
in this area. The coal from Indonesia shall be transported by sea route up to
the captive coal jetty near the project site. The imported coal from the ships
will be unloaded into the hoppers, which would be positioned over the belt
conveyers to convey the coal to the proposed site. The coal handling system
will have design capacity of 1200 ton/h with two conveyers (one operating and
the other stand-by). The water requirement at the project site for heat cycle
make-up, chilling plant make-up, sweet water etc. would be met from
desalination and demineralization of sea water.
Total land requirement for the project
is 185 Acres which has already been acquired. Environment Clearance for the Power
plant has been issued by the Ministry vide letter dated 26.03.2010. No
Objection Certificate for stack height obtained from Airport Authority of India
vide letter dated 21.12.2009. Forest
& Wild Life clearance from Wildlife Warden, Nagapattinam obtained vide letter
dated 11.06.2010. Tamil Nadu Maritime Board accorded permission for drawal of
sea water vide letter dated 06.07.2009.
Government of Tamil Nadu issued G.O. on
07.01.2010 notifying the coordinates of jetty/port. Tamil Nadu Maritime Board allotted water front area within the
port limits and License Agreement was signed on 03.06.2010.
During the discussion, the following
points emerged:
(i)
The
project attracts both EIA, Notification, 2006 and CRZ Notification, 1991. The
proponent has stated that Jetty is Category ‘B’ project since the coal handling
capacity is only 4.5 MTPA which is less than 5MTPA, hence requires clearance
from SEIAA and has submitted application to SEIAA for clearance. The proponent avoided
making a presentation of the details of Jetty for consideration of CRZ
Clearance. The committee was of the opinion that both the activities are
interrelated and project should be considered as whole both for Environmental
and CRZ Clearance.
(ii)
The site
is at Vanagiri, which is close to Poombuhar, a hot spot as per OM
No.15-3/2009-IA-III dated 03.11.2009, a Comprehensive EIA should be prepared for
three season data.
(iii)
A model study should be carried out to
examine the shoreline changes and impact of erosion.
(iv)
The
committee suggested that a letter should be written SEIAA Tamil Nadu in the
reference to the Office Memorandum dated 03.11.2009 that the proposals of Jetty
less than 5 MTA should be considered in the light of the hot spot identified in
the ICMAM studies.
(v)
The
committee further suggested that several coal based thermal power project are
coming up in the close vicinity of the above project and it will be necessary
that an overall EIA assessment should be carried out to examine the impact of
those project in the comprehensive manner. Ministry may write to State Govt. of
Tamilnadu to undertake a study to examine the adverse impacts of the projects
including the erosion of the coast line.
In view of the above, the proposal is deferred
and shall be considered afresh after the above studies are carried out and
submitted for both EIA / CRZ Clearance.
4.16 CRZ
clearance for the construction of Eco-restoration of Adyar creek and estuary in Chennai, Tamilnadu by M/s Adyar Poonga
Trust, Chennai. [F. No. 11-10/2010-IA.III]
As presented by the Project proponent, the proposal
involves development of
Eco-Restoration Park at Adyar Creek in Chennai. The total area covered under
the project is 58 Acres. The aim of the project is to restore the Adyar Poonga
and preserve it for the benefit of the public by building it as an
Environmental Education Canter. The various components in the proposed
Construction of Eco –restoration Park are a) Development of Landscaping, b)
Aforestation and shrub maintenance including edge plants, mangroves, water
plants, reeds, medicinal plants etc., c) Pedestrian walkways, swales etc., d)
Activity spaces such as children interactive learning spaces, amphitheater and
dune garden, e) Nursery & education center and f) Parking lots. The project
dose not proposes any permanent structure other than tiny sheds required to
maintain and for convenience of the visitors.
As per Tamil Nadu State Costal Zone
Management Plan approved by Ministry of Environment and Forest, Government of
Tamil Nadu vide. No J-17011/16/93-IA-lll dated 27th September 1996,
para A(xvi) Park, Play Grounds, regional parks, green zones and other and non
buildable area falling within Coastal Regulation Zone –ll are classified as
CRZ-III as per Costal Regulation Zone Notification 1991 vide para 6(2) Coastal
Regulation Zone –lll. (i) Activities such as setting up of garden, parks, play
fields, forestry and horticulture are permissible activities in Coastal
Regulation Zone-lll.
The proposal was placed before the 55th
meeting of the Tamil Nadu State Coastal Zone Management Authority held on
11.12.2009 and the Authority recommended the proposal for the construction of
the Eco-restoration Park to Ministry of Environment and Forest, Government of
India subject to the certain conditions since the cost of the project is above
Rs. 5 Crores. The cost of the project is Rs. 20 Crores.
During the discussion, the following
points emerged:
i)
There
shall be no construction of permanent structure within the above project area.
Only such activities shall be carried out which are permissible under CRZ
Notification, 1991.
ii)
Before
commencing development of Phase–II, the proponent shall obtain clearance since
it likely to involve dredging activity. Complete Master Plan shall be submitted
along with the Phase-II proposal.
The
Committee recommends the proposal for CRZ Clearance with the above conditions
in the Clearance letter for strict compliance by the project proponent.
4.17
CRZ
clearance for Kudankulam Nuclear Power Plant unit 3-6 at Kudankulam, Tamil Nadu
M/s Nuclear Power Corp. of India Limited. [F. No. 11-25/2010-IA.III]
The Committee decided to defer the
project, since the project proponent did not attend the meeting.
4.18
CRZ
clearance for construction and maintenance of beach resort at SF No. 60/1 to 60/8,
60/1, 62/2, 62/7, 62/9, 63, 64/1, 66/1, 67/1A, 68/3A & 68/4A of Panichamedu
village, Tindivanam Taluk, Villupuram district by M/s Parabola Hotels Pvt. Ltd.
[F. No. 11-32/2010-IA.III]
As presented by the project proponent the proposal involves construction of a beach resort at SF No. 60/1 to 60/8, 60/1, 62/2, 62/7, 62/9, 63, 64/1, 66/1, 67/1A, 68/3A & 68/4A of Panichamedu village, Tindivanam Taluk, Villupuram district consisting of 10.74 ha. The total built up area 21,418 sq.m. It is proposed to 85 guest rooms, ground floor - 54 and 1st floor – 31 along with Spa Block, suites, villas, swimming pool and car parking. Out of the total area of the project site of 107400 sqm, the applicant proposed to construct 21,418 sqm with FSI of 20%. The project area is falling in between 200 mts and 500 mts from HTL and also outside 500 m from HTL i.e. outside Coastal Regulation Zone.
The total water requirement proposed is 130 KLD (fresh water requirement 75 KLD). The capacity STP proposed is 75 KLD. Treated waste water to be used for flushing of toilets – 30 KLD, horticulture – 26 KLD and HVAC – 16 KLD. The water requirement will be met from the three proposed bore wells, which are falling outside Coastal Regulation Zone. The Central Ground Water Authority, Ministry of Water Resources, Govt. of India in their order No. 21-4(158)/SECR/CGWA/2009-1035 dated 07.11.2009, has permitted the applicant for the drawl of ground water from the above three bore wells. The IRS, Anna University have duly superimposed the layout, bore wells together with other proposed constructions and facilities on the CRZ map. Total cost of the project is Rs. 33.00 crores.
As per the approved Coastal Zone Management Plan map the site is falling in Coastal Regulation Zone-III. The Tamil Nadu State Coastal Zone Management Authority held on 29.01.2010 has recommended the proposal.
During the discussion, the following
points emerged:
(i)
There
shall be no disturbance to the sand dunes.
(ii)
All the
solid waste shall be handled as per the Solid waste Management Rules.
(iii) Construction shall be carried out
strictly as per the provisions of CRZ Notification, 1991. No construction work
other than those permitted in Coastal Regulation Zone Notification shall be
carried out in Coastal Regulation Zone area
(iv)
Sewage shall be treated and the
Treatment Facility shall be provided in accordance with the Coastal Regulation
Zone Notification, 1991. The disposal of treated water shall confirm the
regulation of Tamil Nadu Pollution Control Board. There shall be no disposal of untreated
waste water into the coastal area.
The
Committee recommends the proposal for CRZ Clearance with the above condition in
the Clearance letter for strict compliance by the project proponent.
4.19
Finalization
of TOR for the project (i) development of East query –IA (EQ-1A) berth on south
side of EQ-1 (ii) development of East query –1 (EQ-1) by replacing the existing
EQ-1 berth and part of EQ-2 berth by M/s Visakhapatnam Port Trust [F. No.
11-33/2010-IA.III]
As presented by the project proponent the proposal involves development of East query –IA (EQ-1A) berth on south side of EQ-1 for the cargo handling capacity of 5.95 MTPA (ii) development of East query –1 (EQ-1) for the cargo handling capacity of 7.40 MTPA by replacing the existing EQ-1 berth and part of EQ-2 berth in Visakhapatnam Port Trust. Port land of about 1.77 ha. will be utilized for construction of EQ-1. A quality of 1.75 lakhs (approx.) cum of dredging is to be carried out for berthing of the vessels. The dredged material will be dumped in the designated dumping ground. The dumping ground is approved by CWPRS, Pune after carrying of the detailed study. The existing dumping ground being used for dumping dredged material of maintenance dredging every year. The additional quantity of 1.75 lakhs (approx.) cum of dredging will not have significant affect.
The water required for the proposed berths will be 1000 KLD and which will be procured from Greater Visakhapatnam Municipal Corporation, Visakhapatnam. The sewage sludge from the existing 10 KLD STP will be transported and disposed at identified municipal dumping grounds at Kapuluppada. The power supply requirement will be in the range of 1.5 to 2 MVA, which will be obtained from AP Transco. The total cost of the project (i) development of East query –IA (EQ-1A) berth on south side of EQ-1 is Rs. 265.52 Crores (ii) development of East query –1 (EQ-1) is Rs. 269.71 Crores.
EAC noted that the Vishakapatinam is a
Critically Polluted area (CEPI is
above 70), as per the OM No.J-11013/5/2010-IA-II(I) dated 15.03.2010, there is
temporary moratorium. However, since the present proposal is only for
finalization of ToR, the Committee decided to consider the Finalisation of ToR.
During
the discussions, the Committee finalized the following additional TOR for
further study:
(i)
Submit
the recommendations of Andhra Pradesh Coastal Zone Management Authority.
(ii)
Details
of fishing activities and impact due to the activity.
(iii)
Submit
the details of inputs used in different models for prediction of impacts.
(iv)
Submit
the details of Comprehensive cargo handling, quantify expected benefit due to
the mechanization
(v)
Submit
the Risk Assessment and DMP
(vi)
Submit
the details of proposed Corporate Social Responsibilities.
(vii)
Examine
and submit details of the land use and the physiography of the site and the
surrounding area.
(viii) Submit details of input and parameters
considered while carrying out the modeling studies.
(ix)
Submit
details of the cargo handling facilities including the storage facilities if
any.
(x)
Submit
details of the dust separation systems.
(xi)
Examine
and submit details of the transport management plan because increase of cargo
handling facilities.
(xii)
Examine
and submit details of ambient air quality. The monitoring stations should be
located at the site and also near the residential areas.
(xiii) Submit details of Disaster Management
Plan including Risk assessment and emergency evacuation plan.
(xiv)
Submit
details of corporate social responsibility.
Public hearing to be conducted for the project as per provisions of Environmental Impact Assessment Notification, 2006 (as amended in 2009) in all the districts separately and the issues raised by the public should be addressed in the Environmental Management Plan.
A
detailed draft EIA/EMP report should be prepared as per the above additional
TOR and should be submitted to the Ministry as per the Notification.
3rd Day: 23rd July,2010
4.20
CRZ
clearance for modernization of Nagapattinam Fishing Harbor, Nagapattinam
District by M/s Dept. of Fisheries, Government of Tamil Nadu [F. No.
11-28/2010-IA.III]
As presented by the project proponent
the proposal involves modernization of fishing harbour project on the banks of
Kaduvaiyar river of Akkaraipettai, Vadakkupoigainallur village of Nagapattinam
District.Nagapattinam District, Tamil Nadu. As part of Tsunami rehabilitation
works, it was decided to redesign the fishing industry in a better and more
sustainable way, which includes developing of new fish landing centres of
International standards. Under the Tsunami Rehabilitation Project sponsored by
Government of India, Ministry of Agriculture, Department of Animal Husbandry,
Dairying and Fisheries, New Delhi vide letter No:33015-6/2004-FY(H) dated
03.04.2006 had proposed to develop 10 new fish landing centres in Tamil Nadu
with a view to improve the standard of
life of fishermen and to add hygiene to
the environment. The proposed sites were selected in consultation with Central
Institute of Coastal Engineering for Fishery, Bangalore and six of the proposed
sites have been cleared by the MoEF.
The activities to be undertaken are
construction of Diaphram wall -810 m, Retaining wall – 683m, Dredging, Auction
hall-3 nos, Net mending shed – 2 nos, Gear locker shed, administrative
building, Solid waste Management system, sewage treatment facility, etc. Dredging required for -0.3 m and estimated
quantity is 4, 03, 645 Cum. The dredged material will be utilized for
reclamation of lands. The total water requirement is 50 KLD and will be met
from local body supply. STP of 50 KLD is proposed. The treated wastewater will
be recycled for gardening and flushing.
The cost of the project is Rs.36.39 crores.
The State Coastal Zone Management
Authority recommended the proposal for CRZ clearance with certain conditions.
During the discussion, the following
points emerged:
(i)
Oil waste
shall be separately collected, treated and recycled.
(ii)
All the
recommendations of the EMP shall be strictly complied with.
(iii)
Construction
activity shall be carried out strictly as per the provisions of CRZ
Notification, 1991. No construction work other than those permitted in Coastal
Regulation Zone Notification shall be carried out in Coastal Regulation Zone
area.
The
Committee recommends the proposal for CRZ Clearance with the above conditions
in the Clearance letter for strict compliance by the project proponent.
4.21
CRZ
clearance for construction of Fish Landing Center at Ennore, Mugathuvarakuppam
village, Tiruvallur District by Dept. of Fisheries, Government of Tamil Nadu
[F. No. 11-29/2010-IA.III]
As presented by the project proponent
the proposal involves construction of Fish Landing Center in Survey no’s 15
& 235/1 of Ennore Mugathuvarakuppam village, Tiruvallur District, Tamil
Nadu. As part of Tsunami rehabilitation works, it was decided to redesign the
fishing industry in a better and more sustainable way, which includes
developing of new fish landing centres of International standards. Under the
Tsunami Rehabilitation Project sponsored by Government of India, Ministry of
Agriculture, Department of Animal Husbandry, Dairying and Fisheries, New Delhi
vide letter No:33015-6/2004-FY(H) Dated: 03.04.2006 had proposed to develop 10
new fish landing centres in Tamil Nadu with a view to improve the standard of life of fishermen and to add hygiene to the environment. The proposed sites were
selected in consultation with Central Institute of Coastal Engineering for
Fishery, Bangalore and six of the proposed sites have been cleared by the
MoEF. The cost of the project was
arrived at Rs.5.44 crores.
The activities to be undertaken are
construction of Auction hall, Net mending shed, berthing structures, Security
Room, Chill room facility. Toilet facilities, Solid waste collection area,
sewage treatment facility, etc. The total project area is ha. It is indicated that TWAD Board
will supply the required fresh water of 15.0 KLD. It is proposed to extract
9.60 KLD of seawater per day for fish washing and market cleaning. It is
indicated that quantity of effluent generation from the project shall be 24.6
KLD. The capacity of STP will be 25 KLD. Total solid waste generation will be
400 kg/day.
The State Coastal Zone Management
Authority, during the meeting held on 28.08.2009, for clearance of similar
FLCs, suggested providing improved/ modern techniques to handle the liquid and
solid waste generated within the proposed FLC.
Accordingly, sewage treatment plant, using latest Fluidized bed
bio-reactor and Solid waste management using Organic Waste Converter, oil
spillage mitigation measures have been included.
During the discussion, the following
points emerged:
(i)
There
shall be no disposal of untreated waste water into the coastal area.
(ii)
All the
solid waste shall be handled as per the Solid waste Management Rules.
(iii) Construction activity shall be carried
out strictly as per the provisions of CRZ Notification, 1991. No construction
work other than those permitted in Coastal Regulation Zone Notification shall
be carried out in Coastal Regulation Zone area
(iv) There
shall be no drawl of ground water.
(v)
Washing from Auction Hall /Sewage
shall be treated and the Treatment Facility shall be provided in accordance
with the Coastal Regulation Zone Notification, 1991. The disposal of treated
water shall confirm the regulation of Tamil Nadu Pollution Control Board.
(vi) Putrefied
and discarded parts of fishes shall be removed from the Fish Landing Centre and
disposed off in the approved landfill / used as manure / poultry feed.
(vii) Oil
spills if any shall be properly collected and disposed as per the Rules.
The
Committee recommends the proposal for CRZ Clearance with the above condition in
the Clearance letter for strict compliance by the project proponent.
4.22
CRZ
clearance for construction of Fish Landing Center and infrastructure facilities
at Uvari, Radhepuram Taluk in Tiruneveli District by Dept. of Fisheries,
Government of Tamil Nadu [F. No. 11-30/2010-IA.III]
As presented by the project proponent
the proposal involves construction of Fish Landing Center and infrastructure
facilities at unsurveyed land below Survey no’s 686,429&430 area of 2.30
acres of Uvari village, Radhepuram Taluk, which is one of the Fishing Village
in Tirunelveli District, Tamil Nadu. As part of Tsunami rehabilitation works,
it was decided to redesign the fishing industry in a better and more
sustainable way, which includes developing of new fish landing centres of
International standards.Under the Tsunami Rehabilitation Project sponsored by
Government of India, Ministry of Agriculture, Department of Animal Husbandry,
Dairying and Fisheries, New Delhi vide letter No:33015-6/2004-FY(H)
Dated:03.04.2006 had proposed to develop 10 new fish landing centres in Tamil
Nadu with a view to improve the
standard of life of fishermen and to add hygiene to the environment. The proposed sites were selected in
consultation with Central Institute of Coastal Engineering for Fishery,
Bangalore and six of the proposed sites have been cleared by the MoEF. The cost of the project was arrived at
Rs.4.04 crores.
The activities to be undertaken are
construction of Auction hall, Net mending shed, Retaining wall, Compound wall,
Security Room, Chill room facility. Toilet facilities, Solid waste management
system, sewage treatment facility, etc. The State Coastal Zone Management
Authority, during the meeting held on 28.08.2009, for clearance of the earlier
six FLCs, suggested providing improved/ modern techniques to handle the liquid
and solid waste generated within the proposed FLC. Accordingly, sewage
treatment plant, using latest Fluidized bed bio-reactor and Solid waste
management using Organic Waste Converter, oil spillage mitigation measures have
been included.
It is indicated that TWAD Board will
supply the required fresh water of 14.0 KLD. It is proposed to extract 11.2 KLD
of seawater per day for fish washing and market cleaning. It is indicated that
quantity of effluent generation from the project shall be 25.2 KLD. The
capacity of STP will be 25 KLD. Total solid waste generation will be 380
kg/day.
During the discussion, the following
points emerged:
(i)
There
shall be no disposal of untreated waste water into the coastal area.
(ii)
All the
solid waste shall be handled as per the Solid waste Management Rules.
(iii)
Construction
activity shall be carried out strictly as per the provisions of CRZ
Notification, 1991. No construction work other than those permitted in Coastal
Regulation Zone Notification shall be carried out in Coastal Regulation Zone
area
(iv)
There shall be no drawl of ground
water.
(v)
Washing from Auction Hall /Sewage shall
be treated and the Treatment Facility shall be provided in accordance with the
Coastal Regulation Zone Notification, 1991. The disposal of treated water shall
confirm the regulation of Tamil Nadu Pollution Control Board.
(vi)
Putrefied and discarded parts of
fishes shall be removed from the Fish Landing Centre and disposed off in the
approved landfill / used as manure / poultry feed.
(vii)
Oil spills if any shall be properly
collected and disposed as per the Rules.
The
Committee recommends the proposal for CRZ Clearance with the above condition in
the Clearance letter for strict compliance by the project proponent.
4.23
CRZ
clearance for construction of Fish Landing Center at Kadalur Periyakuppam in
Kancheepuram District by Dept. of Fisheries, Government of Tamil Nadu [F. No.
11-31/2010-IA.III]
As presented by the project proponent
the proposal involves construction of Fish Landing Center at survey no’s 608,
609, 615, 621,an area of 3.56 Acres of Kadalur periyakuppam village, which is
one of the Fishing Village in Kanchipuram
District, Tamil Nadu. As part of Tsunami rehabilitation works, it was
decided to redesign the fishing industry in a better and more sustainable way,
which includes developing of new fish landing centres of International
standards.Under the Tsunami Rehabilitation Project sponsored by Government of
India, Ministry of Agriculture, Department of Animal Husbandry, Dairying and
Fisheries, New Delhi vide letter No:33015-6/2004-FY(H) Dated:03.04.2006 had
proposed to develop 10 new fish landing centres in Tamil Nadu with a view
to improve the standard of life of
fishermen and to add hygiene to the
environment. The proposed sites were selected in consultation with Central
Institute of Coastal Engineering for Fishery, Bangalore and six of the proposed
sites have been cleared by the MoEF.
The cost of the project was arrived at Rs.4.75 crores.
The activities to be undertaken are construction
of Auction hall, Net mending shed, Retaining wall, Compound wall, Security
Room, Chill room facility. Toilet facilities, Solid waste management system,
sewage treatment facility, etc. It is indicated that TWAD Board will supply the
required fresh water of 17.0 KLD. It is proposed to extract 13.2 KLD of
seawater per day for fish washing and market cleaning. It is indicated that
quantity of effluent generation from the project shall be 24.8 KLD. The
capacity of STP will be 25 KLD. Total solid waste generation will be 425
kg/day.
The State Coastal Zone Management
Authority, during the meeting held on 28.08.2009, for clearance of the earlier
six FLCs, suggested to provide improved/ modern techniques to handle the liquid
and solid waste generated within the proposed FLC. Accordingly, sewage
treatment facility, using latest Fluidized bed bio-reactor and Solid waste
management system using Organic Waste Converter, oil spillage mitigation
measures have been included.
During the discussion, the following
points emerged:
(i)
There
shall be no disposal of untreated waste water into the coastal area.
(ii)
All the
solid waste shall be handled as per the Solid waste Management Rules.
(iii)
Construction
activity shall be carried out strictly as per the provisions of CRZ
Notification, 1991. No construction work other than those permitted in Coastal
Regulation Zone Notification shall be carried out in Coastal Regulation Zone
area
(iv)
There shall be no drawl of ground
water.
(v)
Washing from Auction Hall /Sewage
shall be treated and the Treatment Facility shall be provided in accordance
with the Coastal Regulation Zone Notification, 1991. The disposal of treated
water shall confirm the regulation of Tamil Nadu Pollution Control Board.
(vi)
Putrefied and discarded parts of
fishes shall be removed from the Fish Landing Centre and disposed off in the
approved landfill / used as manure / poultry feed.
(vii)
Oil spills if any shall be properly
collected and disposed as per the Rules.
The
Committee recommends the proposal for CRZ Clearance with the above condition in
the Clearance letter for strict compliance by the project proponent.
4.24
Environmental
Clearance for consideration of the representations
against Angamalai -Azhutha Railway line project at Kerala as per the Order of
Hon’ble High Court of Kerela. (F.No.10-13/2010-IA.III)
In a W.P No. 735 of 2008 filed in the
Hon’ble High Court of Kerala challenging the proposed Angamali - Azhutha
Railway Line, mainly on the ground that the project is formulated with out
conducting a proper Environment Impact Assessment Report, the Hon’ble High
Court has directed that Ministry of Environment and Forests (Respondent No. 1)
and Ministry of Railways (Respondent No.2) to consider the comprehensive
representation made by the petitioners and all the interested persons.
Respondents 1 and 2 are also at liberty to constitute Expert Committee, if
necessary in this regard and take up proper decision within the time frame
indicated. The representatives of
Railways informed that a large number of representations were received from
public against the proposal. They (petitioners)
also got a report prepared through the Forest Research Institute, Trivandrum.
The total length of the railway line is 130 km, mostly undulated terrain, hilly
terrain, passes through Wetlands, agriculture lands and settlements.
In
W.P. (C) No.735/2008, the Court has mentioned:
“The
W.P. is filed challenging the proposal Angamali-Azhutha Railway line, mainly on
the ground that the project is formulated and proposed without conducting
proper Environmental Impact Assessment.
After
hearing counsel on both sides and perusing the Environmental Impact Studies
said to have been conducted by the Kerala Forest Institute, instead of going
into the details of the arguments of both sides, we propose to direct
respondents 1 & 2 to consider the comprehensive representation to be made
by the petitioners and all the interested persons within four weeks from today
after filing of the comprehensive representation and documents, if any,
respondents 1 & 2 shall consider the same within three months
thereafter. Respondents 1 & 2 are
at liberty to constitute Expert Committee, if necessary in this regard and take
up proper decision within the time frame indicated.
The
Writ Petition disposed off as above”.
The
present proposal was put up for consideration of the representations made by
the public in the EAC meeting held on 25th – 26th March
2010. On the instructions of the Ministry the proposal is put up again for
consideration. The committee while discussing the representations with the
representative of Ministry of Railways noted that the following are the major
points raised in the representations:
i)
The
proposed railway line is 142.9 km long and it passes through:
a.
Midland,
hills, six rivers, 64 streams and seven irrigation canals in three revenue
districts of Kerela, viz. Ernakulam, Idukki and Kottayam.
b.
Total of
1,273 residential buildings would be destructed and about 515 ha. of land
including prime agricultural land would be acquired.
c.
About 12
km of the rail line would pass through the Eco-Sensitive area of Periyar Tiger
Reserve.
d.
EIA
conducted by Kerala Forests Research Institute (KFRI) concludes that “The
prevalence of an exceptional road network connecting Sabarimala to various
destinations renders the new rail proposal at such colossal costs and
ecological and social disruptions unviable and superfluous. Hence the project is
not recommended”
Sr. Officer from Ministry of Railways (Shri
Surendra Kumar Director (Works) informed that the earlier proposal of the railway
line was proposed which passes through the Reserve Forests/ Periyar Tiger
Reserve and buffer area. Now, it is proposed to end the route at Azhutha
avoiding Reserve Forests/ Periyar Tiger Reserve and buffer area. The others
issues raised are mainly related with the rehabilitation and resettlement of
the affected people which will be decided by the Ministry of Railways as per
the existing rehabilitation and resettlement policy.
The committee discussed the various
representations and found that most of them are for opposing the proposed
railway line and suggested that Ministry of Railways should undertake a Social
Impact Assessment (SIA) study of the project as per the National Rehabilitation
and Resettlement Policy 2007 of Ministry of Rural Development published in the
Gazette of India dated 31st October 2007, and decision of
construction of railway line may be taken after taking in confidence the local
residents / affected peoples.
As per as the Environment Impact
Assessment is concerned the construction of the railway line is not within the preview
of EIA Notification, 2006.
The committee recommended that the Ministry
of Railways should take up further necessary action.
4.25
Environmental
Clearance for construction of SEZ for proposal Oil & Gas, Petrochemical
sector at GIDC – Vilayat (Vagra) Indusrial Estate, Vilayat, Bharuch District,
Gujarat by M/s Gujarat Hydrocarbons and Power SEZ Ltd (No. 21-16/2009-IA.III)
The
project involves construction of SEZ for Oil, Petrochemical sector project on a
plot area of 248 ha SEZ will have 2 components, Zone-I ( 210 ha) will
have processing zone, utilities, infrastructure corridor etc. and Zone-II (38
ha.) will have non-processing zone (administrative complex, club/guest house,
training centre, commercial complex to support SEZ activities, green belt,
roads). The total water requirement is 3 MLD. The capacity of STP proposed is 2
MLD. Total solid waste generation will be 1103.95 Kg/day. The power requirement
is 6.25 MVA. Total cost of the project is Rs. 1,735 Crores.
During
discussions following points emerged:
(i)
Project proponent
is not confirmed about the types of industries likely to be set up in the proposed
SEZ, so the EIA & EMP prepared is based on the assumptions which are not
correct. The committee suggested that the project proponent carry out a demand
survey and the EIA and EMP should be prepared on the basis of the demand (at
least minimum of 50 to 60% industrial plots).
(ii)
The EIA /
EMP should be prepared on the basis of the ToR as finalize by the Ministry.
The committee recommended to defer the project.
4.26
Environmental
Clearance for construction of shopping mall, multiplex and hotel Grand – The
International Mall at Khatta no. 150, Mouza no. 6, Dhanbad by M/s Prabhatam
Build Well Ltd. (No. 21-10/2010-IA.III)
The
Committee deferred the project since the project site is located in the critically polluted area as per Office
Memorandum J-11013/5/2010 dated 15.03.2010 and there is a temporary moratorium
for the consideration of projects till August 2010.
4.27
Environmental
Clearance for construction of Taj Vivanta Hotel at Guwahati, Assam by M/s The
Indian Hotels Company Ltd. (No. 21-14/2010-IA.III)
The project involves construction of Hotel “Taj Vivanta”
plot area of 20,146.57 Sq.m. The total built-up area is 33112.46 Sq.m. The
total water requirement is 243 KLD (domestic water requirement is 137 KLD). Wastewater generation is 118 KLD. The
capacity of STP proposed is 180 KLD. Treated waste water to be used for
flushing of toilets – 30 KLD, horticulture – 6 KLD, HVAC cooling - 70 KLD.
Total solid waste generation will be 1200 Kg/day. The power requirement
is 1737 KW. The total parking spaces proposed are for 262 ECS. Total cost of
the project is Rs. 75 .0 Crores. RWH of 800 Cum . 21.75 % energy saving. DG
sets of 2 nos of 750 KVA.
During the discussion, the following
points emerged:
(i)
The
proposed site is located within the Veterinary Science Department area. The
necessary change of land use shall be obtained from the competent authority for
the construction of hotel.
(ii)
Submit
the details of land features of the site and immediate adjacent area with
slopes and drainage pattern.
(iii)
Submit
the details of areas covered under Non-FSI.
(iv)
Submit
the details of sludge generation and its disposal.
(v)
Parking
proposed is inadequate. Re-examine and submit the details based on the number
of rooms, seating capacity of the restaurant and banquet halls. Provision
should also be made for bus parking taxies and staff parking.
Provided the response of the project
proponent to the aforesaid observations is to the satisfaction of the
committee, the proposal may be considered for recommendation for
Clearance.
4.28
Environmental
Clearance for construction of shopping mall-cum-convention center & hotel
at Re. Sy. No. 4/3B, 4/4B, 4/5, Kottooli Village, Kozikode Taluk, Kozikode,
Kerala by M/s Sree Gokulam Hotels India Pvt. Ltd. (No. 21-15/2010-IA.III)
The project involves construction of Special
Residential-cum-Commercial Complex on a plot area of 1.2126 ha. The total
built-up area is 52,273.91 Sq.m. The proposed complex will have 2 basements +
Ground + 9 Floors. The complex will have retail area, office area, hotel
restaurant & other facilities like video gaming hall, exhibition hall and
assembly hall, pool table, dining hall etc. The total water requirement is
262.765 KLD (domestic water requirement is 129.205 KLD). The capacity of STP proposed is 284 KLD.
Treated waste water to be used for flushing of toilets 133.56 KLD, horticulture
- 5 KLD, AC cooling – 76.269 KLD. Total
solid waste generation will be 1103.95 Kg/day. The power requirement is 2,700
KVA. The total parking spaces proposed are for 432 cars + 200 two wheelers + 2
buses + 2 mini buses. Total cost of the project is Rs. 82.132 Crores.
During the discussion, the following
points emerged:
(i)
Parking
proposed is inadequate. Re-examine and submit details separately retail areas,
office area hotel and restaurants. Provision should be made for bus parking
taxies and staff parking. Parking facility should also include parking for
physically challenged people.
(ii)
Submit
the details of transportation and disposal of excavated earth.
(iii)
Re-examine
and submit details of energy saving and compliance with ECBC guidelines. Building envelope should follow ECBC
guidelines for U values of roof, wall and fenestration.
(iv)
Submit
the details of measures taken for seepage since the ground water table is at 1m
depth and the proposal indicate the construction of two basements.
(v)
Re-examine
and submit the circulation plan. Entry and exit should be left in and left out.
Provided the response of the project
proponent to the aforesaid observations is to the satisfaction of the
committee, the proposal may be considered for recommendation for
Clearance.
4.29
Environmental
Clearance for construction of Medical Collage & 500 bedded hospital complex
at Plot A-1, Biada, Bhita Patna, Bihar by M/s Employees State Insurance
Corporation (No. 21-17/2010-IA.III)
The project involves construction of
ESIC Medical College and Hospital Complex on a plot area of 10,1150 sq.m. The
total built-up area is 1,97,649.43 Sq.m. The total water requirement is 1,061
KLD (domestic water requirement is 504 KLD).
The capacity of STP proposed is 750 KLD. Treated waste water to be used
for flushing of toilets – 216 KLD, horticulture - 75 KLD, DG + HVAC cooling –
266 KLD. Total solid waste generation
will be 2,811.75 Kg/day. The power requirement is 12,250 KVA. The total parking
spaces proposed are for 922 ECS.
During the discussion, the following
points emerged:
(i) The site is L shape having a hospital in the front area and medical college along with staff quarters and hostel in the rear side. Re-examine the circulation network including parking provisions for hospital, medical college etc.
(ii)
Submit a
copy of the master plan/development plan indicating the land use and copy of
the approved plan from local body. Also submit details of the infrastructure
available around the site.
(iii) Examine and submit the details of the site and the surrounding area along with the drainage pattern with the help of a contour map and also disposal with invert levels.
(iv) Examine the impact of the surrounding land use on the proposed project and also the impact of the project on the surrounding development.
(v) Re-examine and submit the details of by Medical waste and other solid waste and it’s collection treatment and disposal.
(vi) Submit details of energy requirement and saving in energy by using alternate source of energy including solar energy.
(vii) Submit details of the building materials proposed to be used.
In view of the foregoing observation, the
proposal is deferred and shall be considered afresh.
4.30
Evironmental
and CRZ Clearance for establishment of Navi Mumbai International Airport by
M/s. City & Industrial Development Corporation of Maharashtra Ltd.
[F.No.10-53/2009-IA.III].
As presented by the project proponent,
the proposal involves the development of Navi Mumbai International Airport
situated on National Highway No.4B at a distance of approx. 35 kms. from the
existing airport near Panvel in the geographical centre of Navi Mumbai having
longitude of 73º.4’.18’ and latitude
18º.59’.03’.
The proposal was earlier put up for finalisation
of ToR in the 78th meeting of the expert appraisal committee held on
20th-22nd July 2009, and issued a ToR on 4th
August 2009. The committee visited the site on 23rd December 2009
and based on the site visit, an additional ToR issued on 8th
February 2010. The public hearing was conducted on 5th May 2010 at
Panvel Taluka, Distt. Raigad. Maharastra Coastal Zone Management Authority
considered the project in their meeting held on 16.07.2009 and again on 5th
July 2010 and recommended the project for further necessary action.
The proposal along with EIA/EMP was
submitted on 06.07.2010 which was put up for appraisal in the 89th
meeting of the EAC held on 21st-23rd July 2010.
During discussions following points
emerged:
(i)
The committee
noted that the present airport at Santa Cruz is experiencing congestion due to
constraints on airfield capability and further scope of expansion is limited
due to non-availability of land. The Ministry of Civil Aviation (MOCA),
Government of India as well as Government of Maharashtra granted in principal
approval for setting-up second airport at Navi Mumbai through
Public-Private-Participation (PPP). CIDCO is the Nodal Agency for implementing
the project.
(ii)
CIDCO
informed that the Technical Committee appointed by Ministry of Civil Aviation
had also approved the Navi Mumbai Site for Airport. Submit a copy of the report
prepared by the Technical Committee who has recommended the Navi Mumbai site.
(iii)
The
committee wanted to know the reasons for selecting the site with details of
alternatives sites examined earlier and rejected/ selected on merits with
comparative statement. The committee also wanted to know if any other site
within a radius of about 100 km from Mumbai has been examined outside the CRZ
area with scientific studies, with a check list for selection or rejection and
if so the details of the sites and if not why, and asked to submit a map based
on the latest satellite imagery.
(iv)
The Committee
observed that Social Impact Assessment (SIA) study had not been carried out as
per the National Rehabilitation and Resettlement Policy 2007, issued by
Ministry of Rural Development, published in the Gazette of India dated 31st
October 2007, which says:
“4.3.1. Where it is
required as per the provisions of any law, rules, regulations or guidelines to
undertake environmental impact assessment also, the SIA study shall be carried
out simultaneously with the Environmental Impact Assessment (EIA) study.”
(v) The Committee also observed that the CRZ map has not been
prepared though an authorised agency on 1:4,000 scale. The old map of 1996 in
1:15,000/1:25,000 scale has been enclosed with the EIA/EMP. The CZMP of Mumbai including
that of Navi Mumbai were prepared and approved in 1996. These maps which are on
1:25,000 or 1:50,000 scale are based on the satellite images of 1990 prepared
by Space Application Centre, Ahmedabad. After 1990, these areas have undergone
several changes. Simply by enlarging or blowing up these CZMP maps which are on
1:25,000 or 1:50,000 does not indicate the finer details/ the land use pattern
of the area. Further, the project involves training and diverting of rivers
including reclamation of tidal influenced water bodies which are affected by
the CRZ Notification, 1991. To understand the changes in the CRZ area it would
be imperative that the CRZ maps in cadastral scale be prepared indicating HTL,
LTL, CRZ boundary and superimpose the project layout. This map needs to be
approved by the MCZMA in accordance with the CRZ Notification, 1991.
Submit a copy of the map prepared by an authorised agency
demarcating fresh High Tide Line (HTL) and Low Tide Line (LTL) and superimposed the project layout on the map.
(vi) The committee also felt that a
representative from Airport Authority of India/ Director General Civil Aviation
may be invited/co-opted for the examination of technical suitability of the
site i.e. descending angle required for clear vision of the flights including
other technical aspects.
In view of the foregoing observation,
the proposal is deferred and shall be reconsidered after submission of above
information.
4.31 Construction of Dabolim Apartments and Club House at Plot No. 1,
2, 3, 4, Survey No.43/1, village Dabolim, Mormugao Taluka, South Goa by M/s.
Saravati Builders and Constructions Pvt. Ltd. (No.21-192/2008-IA.III)
Ministry
has issued an Environmental Clearance for the construction of apartments in
Debolim Goa on 11th January 2010.
A Writ Petition No. 13/2010 was filed in the Hon’ble High Court of
Bombay at Goa by The Goa Foundation in which Ministry was also one of the respondents.
The issues raised in the petition were regarding cutting of trees, the entire
project area is a private forest and project site is having a gradient more
than 25% where the construction is not permissible as per Town and Country
planning rules. Ministry has put the Environmental Clearance issued on 11th
January 2010 in abeyance on 15th April 2010.
The Hon’ble High Court has taken note
of Ministry’s action of keeping the clearance in abeyance and further
examination of the matter by the Ministry.
The proposal was put up for
examination of issues raised by The Goa Foundation in the Expert Appraisal Committee
meeting held on 22nd-24th July 2010 in which the
representative of The Goa Foundation and M/s Saravati
Builders and Constructions Pvt. Ltd.
were also called. During discussions The Goa Foundation represented by Dr.
Claude Alvares informed that:
(a) The area is a forest and therefore prior
permission under the Forest Conservation Act requires to be obtained. This
aspect was not put up before the Expert Appraisal Committee earlier.
(b) That the area is a steep slope and hence the law
prevailing in Goa banning development/ construction on steep slopes prohibits
construction of the project in the said area.
(c) It was also informed that there is severe
water shortage in the vicinity of the proposal. Further, many illegal bore
wells were made. The River juari is about 500 m from the site and the proposed
extraction of ground water may lead to sea water intrusion.
In respect of the above issues he
presented photographs of the area indicating the extent of natural vegetation
of the plot. He further informed that three permissions were obtained for
cutting of trees and a total of 200 trees were cut in the last three years.
The representatives of M/s. Saravati Builders and
Constructions Pvt. Ltd. informed that
(a) As per the records of Goa Government, the site is not declared as
Forest and this was confirmed by the Government of Goa in their affidavit filed
in the Hon’ble High Court.
(b) Only 92 trees were felled with required permission. A Committee
constituted by Town Planning Department including the petitioner has visited
and surveyed and based on the survey, an affidavit has been filed which states
that the slop is within norms.
They further informed that the Local
body has given permission for supply of 314 KLD of water from Public supply, 95
KLD will be met from the two Nos. bore wells. The site is about 1000 feet above
the river level; hence the possibility of sea water intrusion is remote.
The EAC after deliberation sought the
following information:
(i)
Submit
the details of trees cut down with their permissions, certifying that no other
trees will be cut.
(ii)
Submit a
copy of the contour map superimposing the layout plan of the site with clear
spot levels authenticated by the Local Town Planning Department.
(iii)
Submit a
copy of the permissions for cutting of the trees and a certificate form DFO
that the area is not declared as forest under Forest Conservation Act.
The committee deferred the project and
shall reconsider after the submission of above information.
4.32 CRZ Clearance for car
depots at Charkop and Mankhurd along with alignment of 32 Km through Mahim
creek, Mithi river and Vakola Nalla, Village Mahim, Mumbai by M/s. Metropolitan
Commissioner, MMRDA, Mumbai [F.No. 11-97/2009-IA.III]
As presented by the project proponent,
the proposal involves establishment of Car Depots at Mankhurd and Charkop
‘Bandra’ Mankhurd corridor under Mumbai Metro Rail Project. The master plan for
Mumbai Metro proposed by DMRC along with its phased implementation includes
nine corridors covering a length of 146.50 km out of which 32.50 km is proposed
underground and rest would be elevated. The Charkop-Bandra-Mankhurd corridor is
second corridor providing West to East connectivity in greater Mumbai covering
length of 31.871 km. it consists of 27 stations. As per the Traffic forecast,
daily boarding will be 12.75 lakhs, 18.77 lakhs and 22.16 lakhs in the years
2.11, 2021 and 2031 respectively. The proposal is being implemented on BOT/PPP
basis. Two maintenance depots are proposed at Charkop and Mankhurd with area
requirement of 19.69 ha. and 24 ha. respectively. Govt. of India has already accorded
approval for Rs. 1532 Cr.
The proposal (F.No.11-45/2009-IA.III)
was earlier considered in the 78th meeting of the EAC held on 20th
- 22nd July, 2009, 82nd meeting held on 23rd-
24th November 2009, and again in the 86th
meeting of the EAC held on
25th – 26th March, 2010. A sub committee also visited the
site on 22nd December 2009.
During discussions following points
emerged:
(i) The committee noted that as per CRZ
Notification 1991, the project falls in CRZ–II (i), CRZ–I (ii), CRZ–II &
CRZ-III. Effluent generation activities and construction activities are not permissible
in CRZ-I (i) and CRZ-I (ii) areas.
(ii) The also noted that MMRDA has made changes
in the project and has proposed an elevated corridor for the metro line and depots
are in order to avoid disturbing the mangroves. It was also clarified that a
limited number of piles will be constructed without damaging a single mangrove.
There will be sufficient gaps and open spaces for sun light and ventilation. They
stressed that construction of car depots on stilt, with railway lines/ bridges
on stilts crossing CRZ-I areas is a permissible activity and the requirement of
CRZ Notification are fully met.
(iii) It was also informed that in the WP No
1643/2009 was admitted in the court and affidavit has already been submitted to
Hon’ble High Court on 07.04.2010, all the petitions are related to alignment
(Overhead v/s Underground metro rail) and do not relate to matter under
consideration namely CRZ clearance for the locations of the car depots, no stay
has been granted for metro rail construction by the Hon’ble High Court.
(iv) MMRDA also committed to undertake
compensatory afforestation at proposed Ecological and Conservation Zone at
Monori, Gorai, Uttan region before implementation of the project. It was also
informed that MMRDA has already appointed as SPA for Manori, Gorai, Uttan
Region. In the proposed land use prepared by MMRDA for the said region, 500 ha
of land has been proposed to be developed as Mangrove Park.
(v) The MCZMA has re-examined the proposal. As per the Minutes of
MCZMA, no other suitable location is available for Charkop Depot site as well
as economically viable. Further authority noted that, Charkop and Mankhurd Car
Depot are falling in CRZ-I area wherein said activity is not allowed as per the
CRZ Notification, 1991. However, MMRDA committed that Car Depots will be
constructed on stilt and ensured that all arrangement will be provided to abate
the pollution of creek area. They will also obtain permission of Hon’ble High Court
since area under consideration is affected by its order and also committed to
regenerate the mangroves along with compensatory afforestation. Maharashtra
Coastal Zone Management Authority has recommended the revised proposal vide
letter no. MCZMA 2009/CR16/MCZMA dated 7th July 2010 for further
necessary action.
The
committee suggested that:
(i)
The construction
activities for proposed metro lines on stilts should be carried out without destruction /damaging the mangroves and
also no disturbance to the
free flow of water in the creek. The Car Depot and workshop activities should
be relocated in non-CRZ areas since these are not permissible under the Costal
Regulation Zone Notification, 1991.
(ii)
MMRDA shall
obtain necessary permission from the Hon’ble High Court of Bombay in the W.P.
No. 3246/2004 and 87/2006 prior to the commencement of the work on ground.
(iii)
Proposed
site is also appears to be affected by declared mangroves forest and permission
from Forest Department shall be obtained.
(iv)
Compensatory
mangroves plantation, shall be carried out before the implementation of the
proposed project and details of area existing number of species, duration of
plantation etc. should be submitted to MCZMA with copy to MoEF.
(v)
MMRDA
shall not carry out any reclamation of land for the proposed activity since it
is prohibited activity as per CRZ Notification, 1991.
(vi) Proper
rehabilitation of the project affected people shall be carried out prior to the commencement of the work on ground.
The
Committee recommends the proposal for CRZ Clearance with the above conditions
in the Clearance letter for strict compliance by the project proponent.
5. Recommended
projects
5.1
CRZ
Clearance for the construction of Hotel at Plot bearing F.P.No.1211 on TPS-4,
Mahim Division, Prabhadevi, Mumbai by M/s. Chaitra Realty Ltd. [F. No.
11-66/2009-IA.III]
The project involves construction of a
star category hotel/business centre on a plot area of 21,489.30 Sq.m. The plot
was earlier used as Hindustan Spinning and Weaving Mills Ltd., which was closed
down and at this location no polluting industry or SEZ is permitted to develop.
All around the plot is residential houses within 150 m. The total built-up area
proposed is 2,14,644.83 Sq.m. (3 basements + 77 storeys). It is proposed to
construct a 320 rooms hotel with 630 service apartments and 84 business
centers. The total water requirement is 1580 KLD and the waste water generation
will be 1035 KLD. (fresh water requirement is 1150 KLD). The capacity of STP proposed is 1343 KLD.
Treated waste water to be used for flushing of toilets - 504 KLD, horticulture
- 127 KLD, and Air-conditioning - 510 KLD. Total solid waste generation will be
2081 Kg/day. The total car parking spaces proposed are 4,614. Total cost of the
project is Rs. 522.28 Crores.
The proposal was also considered by
the additional Expert Appraisal Committee for Building Construction and Area
Development Projects in its 19th meeting held in the month of July,
2007 and 21st EAC meeting held in the month of September, 2007 and
the Committee recommended the project for the issue of Environmental Clearance
subject to obtaining approval under CRZ Notification, 1991.
The proposal was considered by
Maharashtra Coastal Zone Management Authority in its 52nd meeting
held on 14.05.2009. The above plot falls under CRZ-II as per CZMP, 2000 and the
plot is towards the landward side of existing authorized buildings prior to
1991.
The
project was put up earlier for appraisal in the EAC in its 81st
meeting held on 29th - 30th October, 2009 and site visit
was also undertaken by the EAC on 22nd December, 2009 and made
certain recommendations. The response
of the project proponent on the recommendations of the site visit report and
also observations made earlier by the Expert Appraisal Committee were discussed
in the meeting held on 25th – 26th February 2010 and made
certain points. The details
submitted by the project proponent were discussed by the Committee.
During the discussion, the following
points emerged:
i) The development shall confirm to the local
regulation on land use.
The
Committee recommends the proposal for Environmental and CRZ Clearance with the
above condition in the Clearance letter for strict compliance by the project
proponent.
5.2
Environmental Clearance for the
construction of Group housing project at Sy. No. 280/5, 70/9, 70/8, 71/2, Desom
village, Chengamanadu Panchayat, Aluva
Taluk, Ernakulam District, Kerala by M/s. Skyline Foundations & Structures
Pvt. Ltd. (No:21-11/2010-IA.III)
The project involves construction of
group housing complex on a total plot area is 0.6402 Hectares. The total
built-up area is 28,839.15 sq. m. It is proposed to construct 143 dwelling
units (1 Br – 26 and 2 BR + study – 117) with recreational area and swimming
pool in 2 towers (Basement +Gr. Floor+13 floors). The total water requirement
is 102.525 KLD (Fresh water requirement
is 66.85 KLD). The capacity of STP proposed is 111 KLD. Treated waste water to
be used for flushing of toilets 36.175 KLD, horticulture/irrigation 6.843 KLD,
and balance 40.022 KD will be used for nearby plantations. Total solid waste
generation will be 286 Kg/day. The power requirement is 857.87 KVA. The total
parking proposed for 157 cars and 129 two wheelers. Total cost of the project
is Rs 48.84 Crore.
The project was considered in the 85th
meeting of EAC held on 25-26th February, 2010 and 28th –
29th June, 2010. The details
submitted by the project proponent were examined by the Committee and found
them in order.
The Committee recommends the
proposal for issue of Environmental Clearance
5.3 Environmental Clearance for construction
of Group housing Complex at Sy.no.22/14, Chengamanadu Village, Aluva Taluk,
Ernakulam District, Kerala by M/s. Skyline Foundation & Structures Pvt. Ltd
( No.21-9/2010-IA.III).
The project involves construction of
group housing complex on a total plot area is 0.6567 Hec. The total built-up
area proposed is 28,795.42 sq. m. It is proposed to construct 226 dwelling
units (1 BR – 136 and 2 BR – 90) in 2 towers (Basement +Ground floor + 11
floors) with recreational area and swimming pool. The total water requirement is 161.55 KLD (Fresh water
requirement is 105.70 KLD). The capacity of STP proposed is 175 KLD. Treated
waste water to be used for flushing of toilets 56 KLD, horticulture/irrigation
5.72 KLD, Balance 68.28 KLD will be used for nearby plantation. Total solid
waste generation will be 452 Kg/day. The power requirement is 1332.45 KVAMW.
The total parking proposed for 249 cars and 100 two wheelers. Total cost of the
project is Rs 45.80 Crores.
The project was earlier considered in
the 88th meeting of EAC held on 28th – 29th
June, 2010. The details
submitted by the project proponent were examined by the Committee and found
them in order.
The Committee recommends the
proposal for issue of Environmental Clearance
5.4 Environmental
Clearance for the construction of Commercial Building ‘Maria Park’ at
S.No.143/10A2, 143/10A5, 143/10C, 143/11A, 145/7A, Village Edapally South,
Taluk Kanayannur, Ernakulam District, Kerala by M/s. Unique Estates Development
Co. Ltd. [F.No.21-3/2010-IA.III)
The project involves construction of a commercial project on a
plot area of 17,339.978 sq. mts.
The total built-up area of the project proposed is 53,408.6 Sq.m, (lower
basement+ upper basement +Ground +9 floors). The total water requirement is 371
KLD. (Fresh water requirement is 137 KLD, The capacity of STP proposed is
315 KLD. Treated waste water to be used for flushing of toilets 205 KLD;
horticulture 393.5 KLD and AC Cooling 23 KLD. Total solid waste
generation will be 1.8 ton/day. Total power requirement will be 11,000 KVA. The
total parking provisions are made for 909 cars (Lower basement-258, upper
basement-221 and surface 430 parking). Total cost of the project is Rs. 85.9
Crores.
The project was considered in the 85th
meeting of EAC held on 25-26th February, 2010 and 28th –
29th June, 2010. The details
submitted by the project proponent were examined by the Committee and found
them in order.
The Committee recommends the
proposal for issue of CRZ Clearance
89th
Meeting
of the Expert Appraisal Committee for Infrastructure Development, Coastal
Regulation Zone and Miscellaneous projects held on 22nd - 24th
June, 2010 at Fazal
Chambers, SCOPE Complex, Lodhi Road, New Delhi.
List of Participants/ Expert Committee
1.
Shri Naresh Dayal, IAS(Rtd) Chairman
2.
Dr. M.L.Sharma, IFS(Retd) Vice Chairman
3.
Shri Kathirvel Dharmalingam Member
4.
Dr. S.P. Bansal Member
5.
Dr. Apurba Gupta Member
6.
Dr. H.S.Ramesh Member
7.
Dr. Y.Basavaraju Member
8.
Shri G Bala Subramanyam Member
9.
Dr. Suresh Kumar Rohilla Member
10.
Dr. Niraj Sharma (Rep. of CRRI) Member
11.
Dr. R.S.Mahawar (Rep. of CPCB) Member
12.
Shri Bharat Bhushan Member Secretary
Supporting Staff
15. Shri E. Thirunavukkarasu - Dy. Director, MoEF
16.Dr. P.V. Subba Rao – Research Associate, MoEF
Project Authorities:
Representatives from M/s. Blue star Realtors
Representatives
from M/s. Patni
Energy Ltd.
Representatives
from M/s. GSPC Pipavav Power Ltd
Representatives from M/s. GMB & Aatash Norcontrol Ltd
Representatives
from M/s. NHAI
Representatives from M/s. Ramky Enviro Engineer Ltd.
Representatives
from M/s. Corporation of Chennai
Representatives
from M/s. Banglore Eco-Park Pvt. Ltd.
Representatives from M/s. U.P.
Expressway Ind. Dev. Authority
Representatives from M/s. BSR Devl Corp. Ltd.
Representatives from M/s. IRB Sindhudurg Airport Pvt. Ltd.
Representatives from M/s. GAIL (India)
Ltd
Representatives
from M/s. Dept. of Fisheries, Govt of Tamil Nadu
Representatives
from M/s. Ministry of Railways.
Representatives from M/s. Gujarat
Hydrocarbons and Power SEZ Ltd.
Representatives from M/s. Metropolitan
Commissioner, MMRDA