Minutes of the 11th MEETING OF THE EXPERT
APPRAISAL COMMITTEE-1 (INDUSTRY) HELD
DURING 24th, 25th & 26th JUNE, 2010 at Scope Complex, Core 6, 7th Floor, Core VIII,
CEC, ONGC Conference Hall, Lodhi Road, New Delhi - 110 003
11.0
Opening Remarks of the Chairman
At the outset Chairman welcomed the members of the Expert Appraisal
Committee. Thereafter, agenda items were taken up for discussion.
11.1 Confirmation of the Minutes of the 10th
Meeting of the Expert Appraisal Committee-1 (Industry) held on 17th-18th
MAY, 2010
Minutes of the last meeting held during 17th- 18th
May, 2010 were confirmed.
11.2.0 Consideration of the Projects
24th June, 2010
Proposals for
Environmental clearance
11.2.1 Enhancement in Cement production (3.9 MTPA to 4.48 MTPA)
at Awarpur Cement Works, Taluka Korpaba, District Chandrapur, Maharashtra by
M/s Ultra Tech Cement Limited (EC)
The project authorities and their consultant J.M. Environet Pvt. Ltd, Gurgaon gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (TORs) awarded during the 1st
Meeting of the Expert Appraisal Committee-1 (Industry) held during 20th -
21st July, 2009 for preparation of EIA/EMP. All cement plants more than 1.0 MTPA
are covered under Category ‘A’ at Sl. No. 3(b) of Schedule of the EIA
notification 2006 and appraised at central level. Public hearing was
exempted since the expansion is proposed
by addition of fly ash only, no clinker plant will be installed, no additional
water will be required, and 35% of the plant area
will be covered under green belt.
M/s Ultratech Cement Ltd. (M/s Grasim
Industries Ltd.) have proposed for enhancement in the cement production from
3.9 MTPA to 4.48 MTPA by addition of fly ash at Awarpur Cement Works, Taluka
Korpaba, District Chandrapur, Maharashtra. The enhancement in capacity will be
by addition of fly ash through grinding only.
Total project area is 307.35 ha.
No extra land is required for the expansion and proposed expansion will
be carried out in the same premises. No additional construction of structures
will be carried out. Environment
clearance for the cement plant (3.9 MTPA) was obtained vide Ministry’s letter
no. J-11011/146/2003-IA-II(I) dated 8th April, 2005. Environment
clearances for the lime stone mine, captive power plant and coal washery have
also been accorded by the Ministry vide letter dated 11th April,
2005, 7th May, 1997 and 2nd January, 2009
respectively. Total cost of the project
is Rs. 48.95 Crores of which Rs. 45.5
Crores has been earmarked towards environment protection measures.
PPC production will increase from 2.73 to 4.48 MTPA. Clinker and OPC production will remain same. Gypsum requirement
will enhance from 0.07 to 0.09 MTPA and sourced from Hindalco, Dahej, Gujarat
(1,020 km) and CFL, Visakhapatnam, Andhra Pradesh (
The high efficiency
ESP / bag house and bag filters have been installed to recover input materials
and reduce particulate matter from the gaseous emissions from the stack. ESP to kilns, coolers, cement mill, bag
filters to coal mill have been provided.
Dust collectors will be provided at transfer points. Dust suppression will be done to control
fugitive dust emissions. Fly ash will be
stored in silos. Material conveying system will be covered to eliminate any
dust generation. The water requirement of
6041 m3/d for the existing plant is being met from Amal Nallah. Permission for
water drawl has been obtained from Chandrapur Irrigation Department vide their
letter no. /Rajswa T-1 dha.UltraTech
Amal Nallah agreement /4305/05 dated 30th December, 2005. No additional water will be required for the
proposed enhancement. All the effluent
will be treated and used in cement manufacturing process and / or suppression
and green belt development. No effluent
will be discharged and ‘zero’ discharge will be adopted. No additional sewage sludge will be
generated. Fly ash from thermal power plants will be used in manufacture of
cement. No industrial waste will be
generated due to increase in cement production.
All the solid waste generated will be recycled / reused in the process.
Out of
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
11.2.2 Ferro Alloy Plant (60
MVA, 1,40,000 TPA) along with Captive Power Plant (65 MW) at Khasra No. 837, 841 and 841/1 Sirgitti Industrial Area, District
Bilaspur, Chhattisgarh by M/s Vandana Global Ltd. (EC)
The project
authorities and their consultant
EMTRC Consultant Pvt. Ltd. gave a detailed presentation on the salient features
of the project and proposed environmental
protection measures to be undertaken as per Terms of References (TORs) awarded
during the 95th
Meeting of the Expert Appraisal Committe (Industry) held
during 15th – 17th June, 2009 for
preparation of EIA/EMP. All
the Ferro Alloy plants are listed at S.No. 3(a) under Primary Metallurgy
Industries under Category ‘A’ and appraised at the Central level. Public hearing was exempted since the project is located
in notified Sirgitti
Industrial Area.
M/s
Vandana Global Ltd. have proposed for the Ferro Alloy Plant (Fe-Mn & Fe-Si, 60 MVA, 1,40,000 TPA) along with
Captive Power Plant (65 MW) at Khasra No. 837, 841 and
841/1, Sirgitti Industrial Area, District Bilaspur, Chhattisgarh. Total project
area acquired is 12.06 acres. PAs
informed that CSIDC vide letter no. CSIDC/BSP/Dev/2005/58 dated 19th April, 2005 has transferred 1,74,570
sq.ft of land in Sector B, Sirgitti Industrial area which is not a banned area
by the State Govt. of Chhattisgarh. No R & R is involved. No national park,
wildlife sanctuary and reserve forests are located within 10 km. radius of the project. River Arpa flows at a distance of 8 km. Total cost of the project is Rs. 496.0
Crores. Rs. 6.0 Crores and
Rs. 1.0 Crores are earmarked towards capital cost and recurring cost / annum
for environment pollution control measures.
Mn ore (3,64,000 TPA), Coal (28,000 TPA), Quartzite (4,200 TPA) and DRI Char + Coal fines &
middlings
from Coal Washery (3,67,200 TPA) will be used as raw
material for ferro alloy plant to manufacture Fe-Mn & Fe-Si. Mn ore, quartzite, coal and coal fines
etc. will be transported by rail / road. Coal from mines and dolochar from
Sponge Iron Plant located in Raipur will be used in CFBC boiler. Ferro Manganese will be manufactured
in submerged arc furnace. CFBC boiler (260 TPH) will be installed.
Electrostatic Precipitator (ESP) to captive power plant (CPP) and fume
extraction system with bag filters to ferro alloy plant will be provided to
control particulate emissions. Fugitive
dust emissions will be controlled using water sprinkling system, closed
conveyors and bag filters.
Total
water requirement from CSIDC will be 30m3/hr and necessary
permission will be obtained. Alternatively,
ground water will be sourced from bore wells. Air-cooled condenser will be
provided to CFBC to reduce water consumption. All the effluent will be treated
in effluent treatment plant (ETP) and used for ash handling, dust suppression
and green belt development. Storm
water (during rainfall) will be collected separately and recharged using rain waster
harvesting structures. No effluent will be discharged and ‘Zero’ discharge will
be adopted. Domestic
wastewater will be treated in septic tank followed by soak pit.
Coal
ash (2,01,960 TPA) from boiler will be utilized for filling abandoned mines,
brick and cement making. Slag (16,800 TPA) from submerged arc furnace will be
used for road making and land filling. ETP sludge will be generated from
wastewater treatment plant. Spent oil and lubricants will be given to
authorized recyclers/ reprocessors. Coal, char and washery middlings and fines
will be used in AFBC boiler based Power Plant. Green belt will be developed in
33% area. Noise generating equipments will be provided with enclosures. Total
power requirement will be 65 MW through Captive Power Plant.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
14. At least
5 % of the total cost of the project should be earmarked towards the corporate
social responsibility and item-wise details along with time bound action plan
(need based) should be 11.3.6prepared and submitted to the Ministry’s Regional
Office at Bhubaneswar. Implementation of such program shall be ensured
accordingly in a time bound manner.
11.2.3 Expansion of Steel
Plant at Plot No. 15, Gondpur Industiral
Area, Phase-III, Paonta Sahib, District Sirmour, Himachal Pradesh by M/s. T I
Steel Private Limited (EC).
The project authorities and their consultant M/s Eko Pro Engineers Pvt. Ltd., Ghaziabad gave a
detailed presentation on the salient features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (TORs) awarded during the 1st Meeting
of the Expert Appraisal Committee-1 (Industry) held during 20th - 21st
July, 2009 for preparation of EIA/EMP. All the Steel Plants with IF, EAF, SAF & Cupola
(with capacity >30,000 TPA) are covered under secondary metallurgical
industries and and are listed at Sl. No. 3 (a) of EIA Notification, 2006 and
its amendment of December, 2009. The location of project is at
M/s TI Steels Pvt Limited have proposed to expand its Steel Plant at Plot No.
15, Gondpur Industiral Area, Phase-III, Paonta Sahib, District Sirmour,
Himachal Pradesh. Total land requirement is 4.14 acres of which 1.4 acres is
earmarked for green belt. PAs have
submitted a letter from the Govt. of H.P. dated 7th June, 1989
indicating Gondpur Industrial area as an extension to the existing industrial
area of Paonta Sahib. A copy of lease deed singed with the Govt. of H. P. dated
17th January, 2004 has also been submitted. Expansion will be carried out in the vacant
land within the existing plant premises. Total cost of the proposed expansion
will be Rs.
54.0 Crores. Rs. 2.9 Crores and 0.45 crores are earmarked towards capital cost and recurring cost / annum
for environment pollution control measures. Following are the details of existing and proposed
facilities:
Units |
Product |
Existing |
Proposed |
Total |
Induction furnace |
Steel Ingots |
2x10 T/ 5 MW (51,200 TPA) |
-- |
2x10 T/5 MW (51,200 TPA) |
Electric Arc Furnace |
Liquid Steel |
-- |
1x 12 T /5 MW (46,080 TPA) |
1x 12 T /5 MW (46,080 TPA) |
AOD Convertor |
Stainless Steel |
1x25 T (96,000 TPA) |
-- |
1x25 T (96,000 TPA) |
CCM |
SS Billets |
-- |
1x2 Strand (92,200 TPA) |
1x2 Strand (92,200 TPA) |
Wire Rod Mill |
SS Wire Rods |
1x12 TPH |
-- |
28,800 TPA |
Product mix envisaged from the plant after proposed expansion will be as
given below:
S.No. |
Product |
Capacity |
1 |
Steel
Ingots |
39,680
TPA |
2 |
Stainless
Steel billets |
62,200
TPA |
3 |
Stainless
Wire rods |
28,800
TPA |
Pig Iron (14,000 TPA), DRI (38,000 TPA), Scrap (71,150 TPA), Fe-Mn
(13,400 TPA), Copper (1,200 TPA), Calcined Lime (14,200 TPA), Calcined Dolo
(10,000 TPA), Si-Mn (2,600 TPA), Fe-Cr (7,700 TPA), Fe-Si (4,600 TPA) and Fe-Ni
(3,600 TPA) will be used as raw materials. Sponge
Iron, pig Iron and scrap will be charged into the electric arc furnace (EAF).
Burnt lime and burnt dolo will be charged as flux. The hot metal from EAF along
with part of hot metal from existing induction furnace will be charged into the
existing AOD convertor, where refining of steel takes place by de-carbonization
reactions. Ferro alloys and copper will also be added at this stage. Stainless
steel will be casted into billets in a 2 - strand billet caster. Part of the
billets will be rolled to SS wire rods in a rolling mill.
Bag filters are
provided to existing Induction furnaces and Rolling mill. Exhaust gases from
Reheating furnace will be released through a stack of adequate height.
Water-cooled side draft hood, spark arrestor, Trombone gas cooler, bag filter,
ID fan and stack will be provided to Electric Arc Furnace. Water-cooled swivel,
cone hood with forced draft cooler, spark arrestor, bag filter, ID fan and
stack will be provided to AOD convertor. Flue gases after passing through bag
filters will be discharged through a stack of adequate height. Fugitive emissions
envisaged during handling, transfer and storage of raw materials and products
will be controlled by dry fog dust suppression system/water sprinkling
system.
Total water
requirement of 48 m3/hr (including existing) will be met from the Industrial
Area Development Agency, Gondpur Industrial Area, Paonta Sahib, Himachal
Pradesh. Wastewater (4.75 m3/hr) generated will be treated for
oil/grease removal, neutralization, settling and used for green belt
development & dust suppression. Cooling water will be completely recycled.
Effluent generated from Cooling tower blow down, boiler blow down, soft water
regeneration will be treated properly and reused for dust suppression,
greenbelt and ash moistening. Domestic effluent will be discharged to soak pit
via septic tank. Zero discharge will be adopted in the proposed plant. Scrap
from Continuous Casting Machine and Rolling Mill will be recycled back to SMS.
Slag will be used for road making and filling of low-lying areas. Flue dust
generated will be reused in the Induction Furnace. Solid waste generated will
be composted and used as manure for gardening and greenbelt development. Noise
enclosures will be provided to noise generating equipments. Power requirement
of 18 MW will be met the State Grid. LSHS (300 KLPA) will be used as fuel in
Rolling Mill and Reheating Furnace.
The Committee
discussed the details regarding the source of raw materials and name of
suppliers and solid waste management and equipment used for analysis of AAQ and
method for monitoring of water quality. Detailed breakup of amount earmarked
and expenditure incurred towards the community development was also asked. The
proponent have provided the details in this regard.
After detailed deliberations, the Committee recommended the proposal
for environmental clearance subject to stipulation of following specific
conditions along with other environmental conditions:
1.
Compliance to all the specific and general conditions stipulated
for the existing plant(s) by the Central/State Govt. should be ensured and
regular reports submitted to the Ministry’s Regional Office at Chandigarh.
2.
Adequate air pollution control devices viz bag filters, dry fog
suppression system, water sprinkling system
etc. shall be provided to keep the emission levels below 50 mg/Nm3
and by installing energy efficient technology.
4.
Gaseous emission levels including secondary fugitive emissions
from all the sources shall be controlled as per Ministry vide G.S.R. 414(E) dated 30th
May, 2008 within the latest permissible limits issued
by the Ministry and regularly monitored. Guidelines / Code of Practice issued
by the CPCB should be followed.
5.
Total water requirement from the Industrial Area Development Agency,
Gondpur Industrial Area should not exceed 48 m3/hr.
6.
The
water consumption should not exceed as per the standards prescribed for the
steel plants.
7.
Commitment for Solid waste disposal and membership of Shivalik
waste disposal facility needs to be submitted to the ministry
8.
As proposed, green belt should be developed in at least 33 % of
the project area.
9.
At least 5 % of the total cost of the project should be earmarked
towards the corporate social responsibility and item-wise details along with
time bound action plan should be prepared and submitted to the Ministry’s
Regional Office at Chandigarh.
Implementation of such program should be ensured accordingly in a time
bound manner.
11.2.4 Integrated Steel Plant (0.14 MTPA) along with
Captive Power Plant (22 MW) at Jamadoba, Post Bankati, PS Kansa, District
Burdwan, West Bengal by M/s. Jagdamba
Fiscal Services Limited. (EC)
The project authorities and their consultant M/s Global Experts,
Bhubaneswar gave a detailed presentation on the salient features of the project
and proposed environmental protection measures to
be undertaken as per Terms of References (TORs) awarded during the 87th
Meeting of the Expert Appraisal Committee (Industry)
held during 25th – 26th November, 2008 for
preparation of EIA/EMP. All the Integrated Steel Plants have been listed
at Sl. No. 3(a) of Schedule of EIA Notification, 2006 as Category ‘A’ and have to be appraised by
the Central Govt.
M/s
Jagdamba Fiscal Services Ltd. have proposed for the Integrated Steel Plant (0.14 MTPA) along with
Captive Power Plant (22 MW) at Jamadoba, Post Bankati, P.S. Kansa, District
Burdwan, West Bengal. The ToRs were issued for Integrated Steel Plant (0.32
MTPA) along with Captive Power Plant (16 MW). PAs vide their letter dt.
15.02.2010 informed that West Bengal Pollution Control Board (WBPCB) suggested that keeping in view the Environmental
Impacts, the scope of the project should
be curtailed from 10X100 TPD DRI Plants to 4X100 TPD DRI Plants and total
finished steel production, accordingly should be brought down to 1,40,000 TPA.
As per the advice of WBPCB, the project capacity curtailed the capacity from
0.32 MTPA to 0.14 MTPA and the EIA/EMP report was submitted for Public Hearing.
Total
project area of 38.23 acres is already acquired. No national parks/wild life
sanctuary/reserve forests are located within
Major Units |
Capacity |
Product |
End Use |
DRI
Kiln |
4x100
TPD (1,20,000 TPA) |
Sponge
Iron |
SMS |
SMS-I
(IF) |
4 x 12T
(1,45,000
TPA) |
Steel
Billets |
Rolling
Mill |
Rolling
Mill |
1,40,000
TPA |
TMT |
Sale |
CPP
(FBC) |
14 MW
(2X 7 MW) |
Power |
Internal
Use |
CPP
(WHRB) |
8 MW |
Power |
Internal
Use |
The major
raw materials required for the integrated steel and power unit are Iron ore
& Iron ore fines, DRI Grade Coal, raw coal, fluxing agents like limestone,
Dolomite and Quartzite. The process follows typical rotary kiln operations.
Considering the several benefits like good communication, infrastructural
facilities, possibility of low capacity kilns, capital cost etc. it is decided
to adopt DRI technology with waste heat recovery kiln process for the proposed
project.
ESP
will be provided to FBC power plant to control gaseous emissions. The exhaust
gas from DRI kiln would be cleaned by dry gas cleaning system (ESP/bag
filters). Fume extraction and gas cleaning system with water cooled duct, gas
cooler, bag house, ID fan and stack will be provided for induction furnace to
control dust. FE system and bag filter
will be provided to SMS and IF & LF.
Dust suppression and dust extraction system like bag filters will be
provided to raw material handling section, screen, conveyer transfer etc. Total water requirement from Ajay/Kunur River
will be 2,110 m3/day. Cooling tower blow down will be treated. Demineralization plant will be installed to
meet the requirement of boiler. Oil and
gas will be separated from the rolling mill and wastewater will be recycled and
reused. All the effluent will be treated
and used for ash handling, dust suppression and green belt development. No effluent will be discharged and zero
discharge will be adopted. Domestic effluent will be treated in STP.
DRI Char
and Coal fines will be used as fuel feed in FBC-CPP. SMS scrap will be recycled and reused in the
process. Iron ore fines will be sold to
sinter and pelletization units. SMS
scrap will be recycled. Bottom ash will be used in road making and land
filling. Kiln dust, kiln accretion and
scale will be used for land filling. Out of 38.23 acres, 13 acres (34 %) is
earmarked for the green belt development along the plant boundary. Total power
requirement will be 25 MW. 22 MW captive power will be generated and 3 MW will
be sourced from State GRID. Furnace Oil
(FO)/LDO (10,000 KL) will be used as fuel for lime plant, SMS, CCM, DRI plant
and power plant.
Public hearing/Public consultation meeting was conducted by the West Bengal Pollution Control Board on 18th August, 2009. The
Committee deliberated upon the issues raised during the public
hearing including protection of agricultural land, effective air pollution
control measures, development activities, storm water management system, 100%
char utilization etc. and have satisfactorily been incorporated in the final
EIA/EMP report.
The Committee discussed the issues relating to the impact of the
project on the forests area within 10 km
distance of the project, cumulative impact assessment due to other industries,
impact on the ground water and details regarding CSR activities.
After detailed
deliberations, the Committee sought following additional information for
reconsideration of the project without calling the project proponent
·
Permission from
Irrigation Department for water supply
·
Site
specific meteorological data (hourly) at least for one season and AAQ modeling shall
be based on hourly data.
·
Cumulative
impact on the AAQ due to the proposed project and other industries in the
vicinity of the project.
·
Impact
of the ground water due to the proposed project and ground water management
plan.
·
5
% of the total cost shall be earmarked for CSR activities and detailed action
plan in this regard shall be submitted to the Ministry.
The
Committee deferred
the proposal and that on receipt of above
information proposal will be reconsidered without calling the project
authority.
11.2.5 Expansion
of Steel Plant along with Coal Washery (1,25,000 TPA), Captive Power Plant
(bio-mass based, 20 MW), Fly Ash Brick making Plant at Siltara Industrial
Growth Centre, Raipur, Chhattisgarh by M/s Baldev Alloys Pvt. Ltd. (EC).
Project authorities didn’t attend
the meeting and, therefore, it was decided that proposal should be considered
afresh whenever requested by the PAs.
11.2.6 Setting up of cement grinding plant (900 TPD) at DAG no.
109, 110 & 111, Patta no. 21, 12th mile, G.S. Road, N.H. 40, Village
Ambher, Taluka Sonapur, District Kamrup, Assam by M/s JSB Cement Limited. (EC)
The project authorities and their consultant M/s En-vision Enviro
Engineers Ltd., Surat gave a detailed presentation on the salient features of
the project and proposed environmental protection
measures to be undertaken as per Terms of References (TORs) awarded during the 1st
Meeting of the Expert Appraisal Committee-1 (Industry) held during 20th
–21st July, 2009 for preparation of EIA/EMP. All stand alone cement grinding units are covered under Category ‘B’ as
per para 3(b) of the Schedule of the EIA notification 2006, but due to absence
of SEIAA for Assam, the proposal was considered and appraised at central level.
Public
hearing is exempted as per para 7(i) III Stage (3) (i) (e) of the EIA
Notification, 2006 as the unit is categorized as ‘B-2’ category.
M/s JSB Cement has
proposed for setting up of cement grinding plant (900 TPD) at DAG no. 109, 110
& 111, Patta no. 21, 12th mile, G.S. Road, N.H. 40, Village
Ambher, Taluka Sonapur, District Kamrup, Assam. The
total cost of the project will be Rs. 20.45 Crores. Rs. 60 Lakhs and Rs. 5
Lakhs will be earmarked towards total capital cost and recurring cost/annum for
environmental pollution control measures. The total land requirement for the
proposed plant is 9.5 ha which is already in
the possession of the project proponent. About 3.2 ha of plant area will be
developed under green belt. No forest land is involved. The Umtru River flows
at a distance of 7 km in the eastern direction of the project site. State
boundary of Meghalaya is across the road NH 40. Site is in Zone-V category of
earth quake.
The
manufacturing process of cement consists of mixing, drying and grinding of
clinker, gypsum & fly ash. The raw materials required for the proposed plant will be
Clinker (675 TPD), Gypsum (14.4 TPD) and fly ash (225 TPD). Raw materials will
be procured from various places and transported by road through trucks.
Source of
air pollution from the proposed plant will be Cement Mill and packing plant.
For control of air pollution, twin cyclone separator followed by reverse pulse
jet type bag filter will be provided. The total water requirement for the proposed plant will be
12 KLD which shall be met through ground water using Bore Well. There is
no wastewater generation due to the process. Domestic wastewater @ 4.0 KLD will
be generated which will be discharge through septic tank and soak pit. The waste collected in control equipments will be recycled
in the process and the spent lube oil will be given to registered recyclers.
The total
power requirement for the proposed plant will be 2200 KW which will be sourced
from Assam State Electricity Board. A DG set of 750 KVA will be installed to
meet the emergency power requirement.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
1. Continuous
stack monitoring facilities to monitor gaseous emissions from all the stacks
should be provided. Particulate emissions shall be controlled within 50 mg/Nm3 by installing adequate air pollution
control system viz. Bag
filters and stacks of adequate height etc. Data on ambient air, fugitive and
stack emissions shall be submitted to the Ministry’s Regional Office at
Shillong, Assam State Pollution Control Board (ASPCB) and CPCB regularly.
2. The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be followed.
3.
Gaseous emission levels including secondary fugitive emissions from all the sources shall be controlled
within the latest permissible limits issued by the Ministry and regularly
monitored. Guidelines/Code of Practice issued by the CPCB should be followed.
4. The
company should install adequate dust collection and extraction system to
control fugitive dust emissions at various transfer points, raw mill handling
(unloading, conveying, transporting, stacking), vehicular movement, bagging and
packing areas etc. All the raw material stock piles should be covered. A closed clinker stockpile system
shall be provided. All
conveyers should be covered with GI sheets. Covered sheds for storage of raw
materials and fully covered conveyers for transportation of materials should be
provided besides coal, cement, fly ash and clinker should be stored in
silos. Pneumatic
system should be used for fly ash handling.
5. Asphalting/concreting of roads and water
spray all around the stockyard and loading/unloading areas in the cement plant
should be carried out to control fugitive emissions. Regular water sprinkling
should be carried out in critical areas prone to air pollution and having high
levels of SPM and RPM such as haul road, loading and unloading points, transfer
points and other vulnerable areas. It
should be ensured that the ambient air quality parameters conform to the norms
prescribed by the Central Pollution Control Board in this regard.
6. Efforts shall be made to reduce impact of
the transport of the raw materials and end products on the surrounding
environment including agricultural land. All the raw materials including fly
ash should be transported in the closed containers only and should not be
overloaded. Vehicular emissions should be regularly monitored.
7. Total water requirement for cement plant
from bore wells shall not exceed 12 m3/day as per the Permission
accorded by the CGWA / SGWB and efforts should be made to further reduce water
consumption by using air cooled condensers. All the treated wastewater should
be recycled and reused in the process and/or for dust suppression and green
belt development and other plant related activities etc. No process wastewater
shall be discharged outside the factory premises and ‘zero’ discharge should be
adopted.
8. Efforts should be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement should be
met from other sources.
9. All the bag filter dust, raw meal dust,
coal dust, clinker dust and cement dust from pollution control devices should
be recycled and reused in the process used for cement manufacturing. Spent oil
and batteries should be sold to authorized recyclers / reprocessors only.
10. Green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
11. A
Risk and Disaster Management Plan along with the mitigation measures shall be prepared
and a copy submitted to the Ministry’s Regional Office at Shillong, ASPCB and CPCB within 3
months of issue of environment clearance letter.
12. At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details along with time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Shillong. Implementation of
such program should be ensured accordingly in a time bound manner.
11.2.7 Expansion of Steel Plant by installation of Coke Oven
(1.2 MMTPA, Recovery Type) at Hazira, Choryasi Taluka, Surat District, Gujarat by M/s. Essar Steel (Hazira) Limited (EC)
The project
authorities and their consultant Vimta Labs Ltd., Hyderabad gave
a detailed presentation on the salient features of the project and proposed environmental protection measures to be
undertaken as per Terms of References (TORs) awarded during the 95th Meeting of the Expert Appraisal Committe (Industry) held
during 15th – 17th June, 2009 for
preparation of EIA/EMP. All the Coke Oven Plants (>2,50,000 TPA) are listed
at S. No. 4 (b) under Category ‘A’ in EIA Notification, 2006 and appraised at
the Central level. Public hearing was exempted since the project is located
in notified Hazira Industrial Area, Hazira, Surat, Gujarat.
M/s Essar
Steel (Hazira) Limited have
proposed to expand its Steel Plant by installation of Coke Oven (1.2 MMTPA,
Recovery type) at notified Hazira Industrial Area, Hazira, District Surat,
Gujarat. The Ministry accorded environmental clearance for 5.0 MMTPA integrated
steel plant and 270 MW coal based power plant at Hazira in Surat vide
Ministry’s letter no. J-11011/714/2008 dated 29th December, 2008.
Total land required for the proposed project will be 17.8 ha located within the
Essar complex. Tapi estuary and Arabian sea are at within
Proposed coke oven plant comprises of two batteries of 60
ovens each of
Blended
coal from coal handling plant will be transferred to coal tower, where it will
be fed into a charging car and then stamped by a hammer stamping machine. The
stamped coal cake will be charged into oven, where it will undergo high
temperature carbonization at about 950-1050 0C. After approx. 23
hours of carbonization, ready coke will be transferred to wet quenching tower
for quenching. After quenching and
cooling, cooled coke will be transferred to coke sorting plant. The raw gas
produced during carbonization goes through gas off take system and converge
into gas collecting main, where ammonia liquor will be sprayed on the raw gas
to bring down the gas temperature from 800 OC to around 82-84 OC.
The gas then goes to the by-products plant through tar box and suction main. In
the by-product recovery plant, coke oven will successively pass through primary
gas cooler, electrostatic tar precipitator, H2S and NH3
scrubber, Naphthalene scrubber etc. The
vapors containing mainly H2S, NH3 and HCN coming out of
removal of impurities from coke oven gas, by-products like crude tar and
elemental Sulphur will be recovered. In addition H2S stripper will
go to NH3 cracking unit followed by Sulphur recovery unit. After the
to that, naphthalene-scrubbing unit will be provided to remove residual
naphthalene from coke oven gas.
Air
emissions from the proposed plant will be discharged through stacks of adequate
height. Land based pushing emission control system comprising of spark arrester
followed by bag filters and stack will be provided to control the flue gas and
dust generated when red hot coke is pushed from oven. Sulphur recovery unit is envisaged in the
by-products plant for recovery of sulphur from coke oven gas. Fugitive
emissions from doors will be controlled by leak proof doors with flexible
sealing strips. HPLA system will be provided to control charging emissions.
Modified wet quenching system using treated water will be adopted in the
proposed coke oven plant.
Total water requirement of 350 m3/hr will be met from ESHL
water supply facility. Irrigation Department, Govt. of Gujarat has granted
permission for drawl of water up to 15 MGD. For future expansion activities,
application-seeking drawl of additional water is submitted to Irrigation
Department. Effluent from coke oven
plant will be contaminated with ammonia, phenol, tar, oil, cyanide etc. and
will be treated in ETP. Effluent
Treatment Plant (ETP) will comprise of effluent collection sump, tar and oil
separation unit, equalization tank, dissolved air flotation unit, ammonia
stripping facility, ammonia fixing facility, biological treatment unit for
removal of different biodegradable constituents, sludge settling, separation
facility along with sludge drying bed etc. ‘Zero’ discharge will be adopted in
the proposed plant. Treated effluent
from ETP will be used for coke quenching and gas cooling in the coke oven
complex. Sewage from the process unit buildings will be conveyed through
separate drains to septic tanks and soak pits. The H2S and NH3
enriched liquor from both the scrubbers will go to stripping section where
enriched liquor is steam stripped. Excess flushing liquor from gas condensation
plant enter to top of the Ammonia stripper and caustic soda is added to the
same stripper from middle part for removal of fixed Ammonia salt. The major
portion of lean liquor coming out of Ammonia stripper will be reused in NH3
scrubber and remaining part is sent to ETP. Similarly, H2S free lean
liquor from H2S stripper will be sent to H2S scrubber as
scrubbing medium. Tar decanter sludge and BOD sludge will be mixed with coal
charge blend and charged in the coke ovens. Used oil will be sold to registered
recyclers.
Green belt
will be developed in 5.9 ha (33%) out of the 17.8 ha of plant area. Acoustic enclosures, hoods, laggings and
screens will be provided to noise generating equipments. Personnel working in
high noise prone areas will be provided with ear muffs. Power requirement of 9
MW will be met from existing 33 KV switchyard of ESHL main receiving station.
Surplus coke oven gas will be used as a fuel in the ESHL steel plant. DG set of
320 KVA capacity will be installed for emergency lighting purpose.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
1.
Compliance to all the specific and general conditions stipulated
for the existing plant by the Central/State Govt. shall be ensured and regular
reports submitted to the Ministry and its Regional Office at Bhopal.
2. Efforts shall be made to reduce particulate emissions in the ambient
air and a time bound action plan shall be submitted. On-line ambient air
quality monitoring and continuous stack monitoring facilities for all the stacks should
be provided and sufficient air pollution control devices viz. Bag filter, bag house, spark arrester etc. should be provided to keep the
emission levels below 50 mg/Nm3 by
installing energy efficient technology. Low NOx burners should be installed to
control the NOx emissions.
11.2.8 Ferro Alloy Plant (4x10 MVA SAF; Fe-Mn 54,000
MTPA; Si-Mn 2,52,000 MTPA) at Radhamadab Chawk, Haldia Industrial Zone, P.O.
Haldia, District Purba Medinipur, West Bengal by
M/s Cosmic Ferro Alloys Limited – environmental clearance reg.
The project
authorities gave a detailed presentation on the salient features of the
project and proposed environmental protection
measures to be undertaken as per Terms of References (ToRs) awarded during the 6th Meeting of the Expert Appraisal Committee-1 (Industry)
held during 22nd–23rd December, 2009 for
preparation of EIA/EMP. All
the Ferro alloy plants are listed at S.No. 3(a) under Primary Metallurgy
Industry under Category ‘A’ and appraised at Central level. The
committee also noted that in case PAs submit a copy of ‘notification’
indicating location of the project in notified Haldia Industrial Area issued by
the Government of West Bengal at a later date, proposal may be considered
accordingly for the exemption of the public hearing as per EIA Notification,
2006. The PAs have submitted a letter dated 23rd August, 2008 from
the CEO, Haldia Development Authority informing that the project area is in
Haldia Industrial Zone of Haldia Planning Area. Hence, Public hearing was exempted.
M/s
Cosmic Ferro Alloys Ltd. have proposed to Ferro Alloy Plant (4x10 MVA
SAF, Fe-Mn, 54,000 MTPA; Si-Mn, 2,52,000 MTPA) at Radhamadab Chawk, Haldia
Industrial Zone, P.O. Haldia, District Purba Medinipur, West Bengal. Total
land acquired is 17.68 acres. Haldia Development Authority vide Memo No.
2558/HDA/VII-E-274/08 dated 31st October, 2008 has
allotted 17.68 acre land at J. L. No. 128, Mouza Alichak and J. L.
No. 130, Mouza Radhaballvchawk, P.S. Durgachak, Haldia. The unit is located at
a distance of 21 km from the Haldia which has been designated as critically
polluted area. Total cost of the proposed project is Rs. 137.20 Crores. Rs. 8.0
Crores are earmarked towards environmental pollution control measures.
Following are the details of facilities and products from existing and proposed
expansion:
S.N. |
Facility |
Plant Configuration |
Product |
Production Capacity (TPA) |
Existing : |
||||
1 |
Submerged Arc Furnace |
5x9 MVA |
Ferro Manganese Silico Manganese |
72,000 |
Proposed : |
||||
2 |
Submerged Arc Furnace |
4x 10 MVA |
Ferro Manganese Silico Manganese |
65,000 |
Manganese ore, coal / coke, dolomite, Quartzite,
electrode paste will be used as raw materials. Ferro alloys will be
manufactured in Submerged Electric Arc Furnace. Raw materials will be charged
into furnace, where smelting of the ore will take place with coal / coke. Pulse jet
bag filters will be provided to the submerged arc
furnace. Total water requirement of 175 KLD will be met from
Haldia Municipal Corporation. Haldia Development Authority vide Memo No.
2267/HAD/IX-A-14/I/CFAL/08 dated 30th September, 2008 have
agreed to supply the water required for the proposed Ferro alloy
plant. Ferro Manganese slag will be used in the manufacture of
Silico-Manganese. Silico-Manganese slag will be used for road and area
development. Green belt will be developed in 33% of total plant
area. Existing power requirement of 27.5 MVA is being met from
Damodar Valley Corporation. Power requirement of 40 MVA instead of 35 MVA
earlier proposed will be met from West Bengal State Electricity Distribution
Company Limited.
The
Committee deliberated on the issues of location of the project with specific
reference to the critically polluted area. The proponent could not provide the
exact location of the plant. The Committee also suggested to give presentation
as per the TORs prescribed by the Committee.
The Committee decided to defer the
project and suggested the project on the following for the re-consideration of
the project.
1. A
detailed map indicating the location of the proposed project and Haldia which
has been identified as critically polluted area.
2.
The presentation of
the project shall be as per the prescribed TORs.
11.2.9 Non-recovery type Coke Oven Plant (3,00,000 TPA) along with Captive
Power Plant (WHRB 8 MW) at Village Basboni, P.O. Ramkanali, P.S. Neturia,
District Purulia, West Bengal by M/s Metallite Coke and Coal Private Limited (EC).
The project
authorities and their consultant
M/s Envirotech East Pvt. Ltd., Kolkata gave a detailed presentation on the
salient features of the project and proposed
environmental protection measures to be undertaken as per Terms of References
(TORs) awarded during the 95th Meeting
of the Expert Appraisal Committee (Industry) held during 15th–17th
June, 2009 for preparation of EIA/EMP report . All the Coke Oven
Plants (>2,50,000 TPA) are listed at Sl. No. 4 (b) under Category ‘A’ in EIA
Notification, 2006 and are appraised at the Central level.
M/s Metallite Coke & Coal Pvt. Ltd. have proposed to set up a Non-recovery type Coke Oven
Plant of 3,00,000 TPA capacity along
with Captive Power Plant (WHRB 8 MW) at Village Basboni, P.O. Ramkanali, P.S.
Neturia, District Purulia, West Bengal.
Total land required for the proposed project will be
S. N. |
Products |
Phase-I |
Phase-II |
Total |
1. |
Coke |
60,000 TPA |
2,40,000 TPA |
3,00,000 TPA |
2 |
Power Plant (WHRB - 2 x 18 TPH) |
-- |
8 MW |
8 MW |
Coking Coal (3,90,000 TPA) will be imported
from China, Australia and other countries along with use of indigenous coal.
Carbonization of coal will be carried out in coke oven plant to produce Low ash
metallurgical hard coke. Coal from mines will be sent to coal handling plant
where it will be crushed and iron impurities will be removed by a magnetic
separator. This crushed coal will then be charged in the oven and subjected to
carbonization for 36 hours. During the carbonization, coal mass liberates CO,
which is burnt in air to maintain the temperature in the oven around 1200 OC.
The unburnt CO will be burnt at several points like primary and secondary
ducts, waste heat tunnel etc. The coke from the oven will then be subjected to
quenching. After quenching, coke will be transferred to the coke wharf. The coke mass from the wharf will be stacked
at the coke yard for sizing and screening.
High temperature flue gases produced during coking will be supplied to
WHRB for generation of steam to generate power.
There will be no emissions from production
process, as negative pressure technology is adopted in the proposed plant.
Adequate dust extraction/dust suppression systems will be installed at all
locations of dust generation. Water sprinkling system will be used to control
fugitive emissions during handling of coke and coal. A baffle plate dust
collector will be provided at Coke quenching tower. Dust extraction system will
be provided at coke screening & crusher house and coke storage bunker house.
Total water requirement is 29 m3/hr and will be met from ground
water and water supplied by Damodar Valley Corporation. No industrial effluent
will be discharged as the quenching water after sedimentation will be
re-circulated back into the system. Cooling tower blow down, boiler blow down
and DM plant effluent from the CPP will be used for coke quenching. Domestic
effluent after treateatment in Sewage
Treatment Plant will be used for the green belt development and dust
suppression. Total Power requirement of 5,450 KWH/day
will be met from the State Grid and in house power generation. Coke breeze will
be sold to cement and brick manufacturers. STP sludge will be used as manure
for green belt development. Green belt will be developed in 33 % area.
Public hearing/Public consultation meeting was conducted by the West Bengal Pollution Control Board on 23rd December, 2009. The
Committee deliberated upon the issues raised during the public
hearing including effective pollution control measures, addressing dust
deposition, zero discharge of effluent, appropriate stack height, green belt
development etc. and have satisfactorily been incorporated in the final EIA/EMP
report.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
9.
Efforts
shall be made to make use of rain water harvested. If needed, capacity of the
reservoir shall be enhanced to meet the maximum water requirement. Only balance
water requirement shall be met from other sources.
13.
All the commitments made to the public during the Public
Hearing / Public Consultation meeting held on 15th June, 2009 shall
be satisfactorily implemented and a
separate budget for implementing the same shall be allocated and information
submitted to the Ministry’s Regional Office at Bhubaneswar..
14.
At
least 5 % of the total cost of the project shall be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhubaneswar. Implementation of such program should be ensured accordingly in
a time bound manner.
16.
All the commitments made to the public during the Public Hearing /
Public Consultation meeting held on 23rd
December, 2009 should be satisfactorily implemented and a separate
budget for implementing the same should be allocated and information submitted
to the Ministry’s Regional Office at Bhubaneswar.
17.
The
company shall provide housing for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
11.2.10 Setting up of Proposed Aluminium Smelter (6.5 Lakh TPA)
and Captive Power Plant (1,500 MW) at Bidanbagh Unit, Mauja Bagra PS Jamuria,
Dist. Burdhwan, West Bengal by M/s Vedanta Aluminium Limited – Environmental
Clearance reg.
The project authorities and their consultant M/s Vimta Labs Ltd., Hyderabad gave a detailed presentation on the salient features of the project and proposed environmental protection measures to be undertaken as per Terms of References (TORs) awarded during the 82nd Meeting of the Expert Appraisal Committee (Industry) held during 10th –12th June, 2008 for preparation of EIA/EMP. The primary metallurgical processes are kept at S. No. 3(a) under Category ‘A’ in EIA Notification 2006 and appraised at central level.
M/s Vedanta Aluminium Limited proposed establishing an Aluminium Smelter of 6.5 Lakh Ton/Annum and a Captive Power Plant of 1,500 MW at Bidanbagh Unit, Mauja Bagra PS Jamuria, Dist. Burdhwan, West Bengal. Ultimate land requirement is 1,500 acres, 495 acres constituting the greenery. The cost of the project is Rs. 11,000 Crores.
Hall-Heroult process of electrolysis with state of the art 320/350 GP (II) technology of GAMI-China will be installed for electrolytic reduction of alumina using centre worked pre-baked cell technology at low voltage and high amperage. The reductant is the consumable carbon anode. The technology deploys multiple anodes in each cell, which are pre-baked in a separate facility and suspended by in the cell. The facilities planned for the proposed smelter are two pot lines of 320 KA, carbon plant, green anode plant, bake oven and rodding shop, cast house (ingots and rod causting facility) and auxiliaries consisting of rectifier compressor, substations, storage area etc. The captive power plant will use pulverized coal fired boilers. Raw material requirement is Coal (28,800 TPD), Alumina (13 LTPA), Petroleum coke (3.25 LTPA), Coal tar pitch (0.6 LTPA), Fuel oil (30,000 KLPA), Aluminium fluoride (15,000 TPA), Calcium fluoride (800 TPA) and Cryolite (1500 TPA).
ESPs will control the dust emission from CPP. The fume treatment plant will serve for alumina dry scrubbing and control of fluoride emissions. Bag filters will handle dust emission in crushing and grinding area and FTP with condensing system will address Coal Tar Pitch Volatile emissions and Fluoride. The total water requirement will be 5,000 m3/hr which will be sourced from Damodar Valley Corporation. Ash (11,520 TPD) generated will be reutilized to the maximum possible extent and balance will be disposed off in the ash pond resorting to High Concentration Slurry Disposal method. Spent Pot Lining (14,300 TPA) generated after five years will be sold to cement and steel plant and surplus SPL will be used as secured land fill. Dross (5,200 TPA) and used oil (13.5 kl/annum) will be recycled or sold. Used batteries (50 banks/year) will be sent back to suppliers/manufacturers. Coal (24300 TPD) will be used as fuel in the Power Plant which will be sourced from ECL. Fuel oil (57,000 KLPA) will be used in Bake Ovens and Power Plant. Emergency DG sets will be on stand by with silencer fitted stacks.
Public hearing/Public consultation meeting was conducted by the West Bengal Pollution Control Board on 9th September, 2009. The Committee deliberated upon the issues raised during the public hearing including effective pollution control measures, 33 % green belt development, coal mining area sanguine, health service, water availability, rain water harvesting, fly ash disposal, hazardous waste management etc. These have been satisfactorily attended to in the final EIA/EMP report. This is a major project of national importance involving substantial investment.
The Committee noted that there will be 7000 land oustees and about 270 acres of land has been acquired. The company represented that the land is fragmented, the average land holding being about 2 acres. The Committee deliberated on the issue of land acquisition, confirmation for water allocation, coal allocation and characteristics of imported coal etc. Regarding the coal requirement, the proponent informed that they have letter of Assurance from the West Bengal Government for coal allocation. The land in possession of the proponent is 270 acres, which is about 1/6 of the total area. Extent wise it is substantial. It would be unrealistic to expect an applicant to defray substantial cost and be in full possession of the entire area for a major project of this size and investment, approval of which has to await scrutiny and consideration by government and may not be presumed. Nevertheless, it is a moot point that there is satisfactory evidence of earnestness on the part of the proponent in securing land for the project. The importance of the project, scale of investment and employment, standing of the company, its track record, its portfolio of its existing, emerging or envisaged associated projects, the scheme for acquisition of land and rehabilitation, assurances of or memoranda signed with the government, etc.are relevant factors for the Committee to assess whether the land is in possessin of the proponent at this stage holds promise of the project fructifying. In this connection it was noted that a major Alumina project proposed by the proponent- which could be associated to the instant proposal- is also under consideration and a site visit by a Sub Committee of the EAC is t shortly take place.
The Committee proposed that a scheme for phased acquisition of land by the proponent with details of action being taken towards this end including resettlement/ rehabilitation and accompanied by due assurances may be called for from the proponent. The case may be reconsidered by the Committee subject to its satisfaction that the project is current for implementation. As of now no such conclusion may be drawn. Further, it was also desired that the company shall submit the information regarding supply of coal is from the running mine or from the new mines along with the status of environmental clearance of the coal mine.
11.2.11 Induction Furnace
(1,80,000 TPA, Ingots / Billets) and Rolling Mill (1,80,000 TPA, M.S.
Structures/ Bars) at Plot 49-A, Industrial Growth Centre (APIIC), Village
Thumakunta, Mandal Hindupur, District
Anantapur, Andhra Pradesh by M/s Sasa Metal
Private Limited Environmental Clearance reg.
The project authorities and their consultant Consafescience
(India)- Shri Datta Envirotech, Hyderabad gave a
detailed presentation on the salient features of the project and proposed environmental protection measures to be
undertaken as per Terms of References (TORs) awarded during the 5th
Meeting of
the Expert Appraisal Committee-1 (Industry) held during 24th –25th
November, 2009 for preparation of EIA/EMP. All the Induction Furnace and Rolling Mills are listed at Sl. No. 3(a) under Category ‘B’ but apprised
at the Central level due to location of the project within 10 km distance of
interstate boundary as per the general condition of EIA
Notification, 2006. Public
hearing was exempted since the project is located in notified
Industrial Area. PAs have submitted
a copy of the Gazette Notification issued by the Govt. of Andhra Pradesh vide
letter dated 4th March, 1995 indicating location of the project in notified
Industrial Growth Centre (APIIC) at Hindupur, Anantpur, A.P
M/s Sasa Metal Pvt. Ltd. have proposed for the Induction
Furnace (1,80,000 TPA, Ingots/Billets) and Rolling Mill (1,80,000 TPA, M.S.
Structures/Bars) at Plot No. 49-A, Industrial Growth Centre (APIIC), Viallge Thumakunta,
Hindupur, District Anantapur, Andhra Pradesh. Total project area is 5 acres.
No R & R is involved. No national park / wild life sanctuary /
reserve forest is located within 10 km radius of the project site. Rivers Penna
and Kumudarati flow at a distance of 3 & 6 km respectively. Distance of
proposed site from Andhra pradesh- Karnataka state border is 2.5 km. Total cost
of the project is Rs. 50.0 Crores. Rs. 5.0 Crores and Rs.50.0 Lakhs/annum
will be earmarked towards capital costs and recurring cost/annum for
environment pollution control measures. Following are the details of facilities
to be installed and products to be manufactured:
S.No. |
Name of the unit |
Product Name |
Capacity (TPA) |
1. |
Induction Furnace |
Ingots / Billets |
1,80,000 (2x25 TPC, 1x500 TPD) 4 crucibles with 2 in operating
mode and 2 in stand-by mode |
2. |
Rolling Mill |
M.S. Structures/Bars |
1,80,000 (1x500 TPD) |
Wet scrubber and bag filters will be provided
to control particulate matter within 100 mg/Nm3. Fume
extraction system with spark arrestor, bag filters, ID fans and stacks of
adequate height will be provided to induction furnace. SO2 will be
generated from the rolling mill due to the ‘S’ present in the furnace oil i.e LDO. Ventury
wet scrubber will be provided to Rolling mill. Total water requirement from
APIIC will be 48 m3/day.
There is no generation of waste water from the proposed units. The
water is continuously re-circulated in the cooling water circuits and will be
evaporated. No effluent will be discharged outside the premises and ‘Zero’
discharge will be adopted. Domestic water will be treated in septic tank
followed by soak pit.
Mill scales / crop cuts from the rolling mill will be sold
to M.S. Scrap dealers / resued in Indcution furnace. Induction furnace slag after metal recovery
will be used in land fill in low lying areas / sold to brick
manufacturers. Used oil and lubricant
will be disposed off to authorized recyclers. Green belt will be developed in
1.65 acres, out of total plant area of 5 acres. Total power requirement will be
23,000 KVA. D.G set (1,250 KVA) will be provided.
After detailed
deliberations, the Committee deferred the proposal and sought following additional information
for reconsideration of the project.
1. It was noted that the data generated for AAQ was erroneous which
needs to be rechecked
2. Details regarding seismicity of the area.
11.2.12 Integrated Steel Plant (0.3 MTPA):
Beneficiation Plant, Pelletization Plant, Sponge Iron Plant, Induction Furnace,
Rolling Mill and Captive Power Plant at Notified Industrial Estate, Gram
Hargarh, Tehsil Sihora, District Jabalpur, Madhya Pradesh by M/s. Euro Pratik Ispat Private Limited – Environmental
Clearance reg.
The project authorities and their consultant J.M.Environet Pvt. Ltd., Gurgaon gave a detailed
presentation on the salient features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (ToRs) awarded during the 93rd
Meeting of the Expert Appraisal Committe (Industry) held
during 14th – 16th April, 2009 for
preparation of EIA/EMP. All the Integrated steel plants and Captive
Power Plant (>50 MW) are listed at S.No. 3(a) under Category ‘A’ and
appraised at the Central level. Public hearing was
exempted since the project is located in notified Hargarh Industrial Area.
M/s Euro
Pratik Ispat Pvt. Ltd. have proposed for Integrated Steel Plant (0.3 MTPA)
comprising Beneficiation Plant, Pelletization Plant, Sponge Iron Plant,
Induction Furnace, Rolling Mill and Captive Power Plant at Notified Industrial
Estate, Gram Hargarh, Tehsil Sihora, District Jabalpur, Madhya Pradesh. No
national Park/wild life sanctuary is located within 10 km radius of
the project site. Hargarh RF (1.7 km NNW) and Dhanwahd RF (6 km NNE)
is located within 10 km radius of the project site. Total project area is
25 acres Total cost of the project is Rs. 740.0
Crores. Rs. 22 Crores and Rs. 11.30 Crores will be earmarked towards capital
cost and recurring cost for environmental pollution control measures. Following
are the details of the proposed plants:
S.No. |
Units |
Capacity |
1 |
Beneficiation & Pelletization Plant |
0.6 MTPA |
2 |
DRI Sponge Iron Unit (Coal based) |
4x350 TPD |
3 |
Induction Furnace |
4x25 MTPA |
4 |
Rolling Mill |
80 TPH |
5 |
Captive Power Plant WHRB
(4x35 TPH) AFBC
(1x150 TPH) |
60 MW 32MW |
Iron ore,
Coal, Laterite, Bentonite will be used as raw materials. Low
grade lateritic ore will be beneficiated by Magnetic separation, serial
launders and floation into high-grade ore with 67% Fe content in the
beneficiation plant. The high-grade ore fines with Benetonite will
be converted to green balls and baked to manufacture pellets in pelletization
plant. The pellets along with pulverized coal will be fed to DRI
kiln to reduce Fe2O3 into Fe. The sponge
iron will be fed to Induction furnace to make ingots / billets which will be
casted in rolling form of steel i.e. angles, channels, rods, TMT Bars, hot
rolled coils, cold rolled coils in rolling mill. Power will be generated in CPP
(12 MW coal and char based) and WHRB (48 MW) using waste gases.
Gaseous
emission will be controlled by installing air pollution control
equipments. Dust suppression will be done by water sprinkling to
control fugitive emissions due to transportation activities. Bag filters will
be provided to Crusher, coal pulverization section, additive grinding section,
bentonite hopper section, additive hopper section and return material hopper of
Iron ore beneficiation & Pelletization Plant. Multi cyclone will be
provided to Pelletization Grate and Pelletization cooler. In the Sponge Iron
plant, bag filters will be provided at coal crusher, coal crusher transfer
point, Iron ore screen, Iron ore ground, hopper, Stock house, Cooler discharge,
product house, loading point of Sponge Iron and char. Fume
extraction system with bag filters will be provided to Induction Furnace, LRF
and CCM. Bag filters will be provided to Rolling Mill. ESP will be provided to
WHRB and AFBC boiler of Power Plant. Bag filters will be provided to Coal
crushers and screens of Power Plant. Water sprinkling will be done along the
haul roads to control dust arising from vehicular movement.
Total
water requirement for the proposed project from Audyogik Kendra Vikas
Nigam, Jabalpur is 900 m3/day. STP will be installed for
the treatment of wastewater and the treated water will be used for dust
suppression, plantation etc. Blow down water will be used as make-up water for
Sponge Iron plant. Waste water generated from RO/DM plant will be fed back to
sponge iron kiln after neutralization. Filter press technology will be used to
recover water from solid waste in Beneficiation unit. Domestic wastewater will
be disposed off into the soak pit via septic tank. Zero discharge will be
maintained in the proposed plant.
Solid
waste generated from Iron ore beneficiation and Pelletization plant will be
used for filling up abandoned mines pit, red brick making and making other building
material like blocks etc. Char lumps generated from Sponge iron plant will be
partly sold to brick manufacturers or can be used in AFBC boiler and the rest
will be dumped in char dumping yard. Dolochar along with DSC discharge will be
dumped in char dumping yard. Induction furnace slag will be crushed to recover
metals and the fine slag will be used in civil construction or in brick making
and the balance slag will be dumped in char dumping yard. Mill scale from
Rolling mill will be sold to nearby cement plants. Scrap generated from Rolling
mill will be fed back to Induction Furnace. Fly ash generated from Power Plant
will be either sold to Cement plants or used for fly ash brick making. Bed ash
will be used on roads as a filling material.
Green
belt will be developed in 33% of the total plant area. Ear muffs/ear plugs will
be provided to workers working in high noise prone areas. Power requirement of
70 MW will be met from Captive Power Plant (60 MW) and State Electricity Board
(10 MW).
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
1.
On-line ambient air quality monitoring and continuous stack monitoring
facilities for all the stacks should be provided and sufficient air pollution
control devices viz. Electrostatic precipitator
(ESP), cyclones, bag filters etc. shall
be provided to keep the emission levels below 50 mg/Nm3 by installing energy efficient technology.
3.
Gaseous emission levels including secondary fugitive emissions
from all the sources should be controlled within the latest permissible limits
issued by the Ministry vide G.S.R. 414(E) dated 30th May, 2008 and
regularly monitored. Guidelines / Code of Practice issued by the CPCB should be
followed.
4.
Hot gases from DRI kiln shall be passed through Dust Settling
Chamber (DSC) to remove coarse solids and After Burning Chamber (ABC) to burn
CO completely and used in waste heat recovery boiler (WHRB). The gas then should be cleaned in ESP before
leaving out into the atmosphere through ID fan and stack.
6.
The
water consumption shall not exceed as per the standard prescribed for the steel
plants.
7.
All
the char from DRI plant shall be utilized in AFBC boiler of power plant and no
char should be disposed off anywhere else. AFBC boiler shall be installed
simultaneously along with the DRI plant to ensure full utilization of char from
the beginning.
8.
Proper utilization of fly ash shall be ensured as per Fly Ash
Notification, 1999 and subsequent amendment in 2003 and 2010. All the fly ash
should be provided to cement and brick manufacturers for further utilization
and ‘Memorandum of Understanding’ should be submitted to the Ministry’s
Regional Office at Bhopal
9.
As proposed, green belt should be developed in 33 % area.
10. All the
recommendations made in the Charter on Corporate Responsibility for Environment
Protection (CREP) for the Steel Plants should be implemented.
11. Prior permission from
the State Forest Department should be taken regarding likely impact of the
expansion of the proposed steel plant on the reserve forests. Measures should
be taken to prevent impact of particulate emissions / fugitive emissions, if
any from the proposed plant on the surrounding
reserve forests viz. Hargarh RF (1.7 km NNW) and Dhanwahd RF (6
km NNE) located within 10
km radius of the project site. Further, Conservation Plan for the
conservation of wild fauna in consultation with the State Forest Department
should be prepared and implemented.
12. At least
5 % of the total cost of the project should be earmarked towards the corporate
social responsibility and item-wise details along with time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at
Bhubaneswar. Implementation of such program should be ensured accordingly in a
time bound manner.
11.2.13 Expansion of
integrated cement plant clinker ( 0.8 to 1.0 MTPA), Cement ( 1.0 to 1.5 MTPA)
and Limestone (1.3 to 1.6 MTPA) at Ramapuram Village, Mellacheruvu Mandal,
Nalgonda District, Andhra Pradesh by
M/s
Rain Industries Limited (EC).
Project authorities didn’t attend the meeting and,
therefore, it was decided that proposal shalld be considered afresh whenever
requested by the PAs.
11.2.14 Integrated Steel Plant (2.5 MTPA) with
Captive Power Plant (559 MW) at Village Patrapalli & Kotmar, District
Raigarh, Chhattisgarh by M/s Visa Steel
Limited.- Reg. Environmental Clearance reg.
The project authorities and their consultant EMTRC Consultants Pvt.
Ltd., Delhi & Envirotechno Consultants Pvt. Ltd., Bhilai gave a detailed
presentation on the salient features of the project and proposed environmental protection measures to be
undertaken as per Terms of References (TORs) awarded during the 90th
Meeting of the Expert Appraisal Committee (Industry) held during 6th –8th
January, 2009 for preparation of EIA/EMP. The Committee prescribed the TORs and advised
the project proponent to submit the draft EIA report to the Chhattisgarh Enviornment Conservation
Board (CECB) for conducting public hearing. The final EIA report incorporating
the response to the issues raised during the public hearing shall be submitted
to the Ministry for obtaining environmental clearance. All the Integrated Steel
Plants are listed at Sl. No. 3 (a) under Primary Metallurgical Industries under
of EIA Notification, 2006 and appraised at Central level.
M/s
Visa Steel Ltd. have proposed for the Integrated Steel Plant (2.5 MTPA) alongwith
Captive Power Plant (559 MW) at Village Patrapalli & Kotmar, District Raigarh,
Chhattisgarh. Total project area is
S.N. |
Name of the unit |
Capacity |
1 |
Blast Furnace
(2x900 Cum) |
1.764 MTPA molten metal |
2 |
DRI Plant (8x500
TPD) |
1.2 MTPA Sponge Iron |
3 |
Iron ore
beneficiation and Pellet Plant (2x1.2 MTPA) |
2.4 MTPA Pellets |
4 |
Coal washery (2x2.5
MTPA) |
5.0 MTPA |
5 |
Sinter Plant (2x120
SQM) |
2.4 MTPA |
6 |
Non-recovery coke
oven |
0.8 MTPA |
7 |
Steel Melting
shop (EAF Furnace-2x150 t, LRF-2x150
t, Concast-2x6 Strand Billet Caster) |
2.5MTPA |
8 |
Rolling Mill (Bar
& Wire Rod Mill - 1.25 MTPA, Section Mill - 1.25 MTPA) |
2.5 MTPA |
9 |
Captive Power Plant
(WHRB-2x77 MW = 154 MW CFBC 3x135 MW =405 MW) |
559
MW |
10 |
Oxygen Plant (2x
500 TPD) |
1000 TPD |
Proposed product mix
will be as follows:
S.No. |
Product |
|
Total |
1. |
Bar & wire Rod
Mill product MS Billets TMT Bar 5 mm- Plain Round Bars RCS 40- Angles 50-100 |
4,00,000 t 3,00,000 t 3,00,000 t 2,50,000 t |
|
|
Total |
12,50,000 |
12,50,000 |
2 |
Section Mill
Products Heavy Beams >
350 to 600 |
2,00,000 t 2,00,000 t |
|
Iron ore from Orissa by rail, dolomite from Bilaspur through road,
limestone from Raigarh through from road and coal will be used as raw
materials. DR and MBF technology will be used. 16
Nos. of non- recovery type coke oven batteries will be installed to meet the
requirements of Met Coke. To promote
economic efficiency and minimize coke consumption, the pulverized coal
injection system will be used.
ESP,
bag filters will be provided to control particulate emission within 50 mg/Nm3. A de-sulphurization plant will be installed
for removal of sulphur from hot metal.
BF gas will be used in sinter plant after cleaning in gas cleaning plant
(GCP). Fugitive dust emission will be controlled using water sprinkling
systems, closed conveyors, bag filters etc.
Hot waste gases from DRI kiln will pass through DSC and ABC and then
cleaned in ESP before letting out into atmosphere through ID fan and
stack. Bag filter and tall chimney will
be provided to coke oven and by product plant.
ESP will be provided to sinter plant, pellet plant, DRI Plant, bag
filters, GCP, cast house and stock house will be provided to Blast Furnace
plant. Bag filter, gas cooler, chimney
will be provided to SMS.
Total
water requirement from River Sapnai will be 3,550 m3/hr. Effluent treatment plant (ETP) will be
installed for the treatment of wastewater. Sewage will be treated in STP. No treated effluent will be discharged. Treated liquid effluent will be recycled /
reused. Char and washery rejects will be utilized in AFBC power plants. Slag will be sold to crusher units and cement
manufacturers. Other solid waste will be
dumped in dump yard till any final use is found. The fly ash will be sold to the cement
plants. Bottom ash will be used for land
filling and road making. Steel scrap
will be used in BOF as coolant. BF slag
will be sold as by product. Flue dust
from different plants will be used in sinter plant. Spent oil and lubricants will be given to
authorized recyclers. Green
belt will be developed in 33% area. CPP (550 MW) will be installed. 154 MW power will be generated using WHRB;
405 MW power will be generated using CFBC boiler where char and washery rejects
will be used as fuel.
The public hearing
of the project was held on 10th October, 2009. The issues raised during the public hearing regarding include raw
material availability , cutting of trees, education to the local people, measures for pollution control, provision of
employment etc. have been addressed and incorporated in the final EIA/EMP
report.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of following
specific conditions along with other environmental conditions:
1. Efforts should be made to reduce RSPM levels
in the ambient air and a time bound action plan should be submitted. On-line
ambient air quality monitoring and continuous stack monitoring facilities for
all the stacks should be provided and sufficient air pollution control devices
viz. Electrostatic precipitator (ESP), gas cleaning plant, cyclone,
multi-cyclone, wet scrubber, bag
filters etc. should be provided to keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
2. As proposed, Electrostatic precipitator
(ESP) shall be provided to sinter plant, WHRB, CFBC, DRI and slag cement
plants; bag house to blast furnace and ESP & bag filters to by-product
recovery type of coke oven to control SPM levels within 50 mg/Nm3.
Fume extraction system with bag filters should be provided to electric arc
furnace and ladle furnace.
3. All the standards prescribed for the coke
oven plants shall be followed as per the latest guidelines. Naphthalene
scrubbing unit should be provided to remove residual naphthalene from coke oven
gas. Ammonia released in de-sulphurization section of coke oven plant shall be
catalytically cracked to Nitrogen and Hydrogen. BF top gas shall be cleaned in dust
catcher and gas cleaning plant (GCP) comprising of bag filters and used in
furnace of CSP, BF, EAF, sinter plant, lime & dolo plant. Bag filters with
adequate stack height shall be provided to lime and dolo plant. Proper and full
utilization of coke oven gases in power plant using heat recovery steam
generators should be ensured and no flue gases shall be discharged into the
air.
4. The National Ambient Air Quality Standards
issued by the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be followed.
5. Gaseous emission levels including secondary fugitive emissions from all the sources should be
controlled within the latest permissible limits issued by the Ministry and
regularly monitored. Guidelines/Code of Practice issued by the CPCB should be
followed. New standards for the sponge iron plant issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008 should be followed.
6. Hot gases from DRI kiln shall be passed
through Dust Settling Chamber (DSC) to remove coarse solids and After Burning
Chamber (ABC) to burn CO completely and used in waste heat recovery boiler
(WHRB). The gas then should
be cleaned in ESP before leaving out into the atmosphere through ID fan and
stack.
7. Vehicular pollution due to transportation
of raw material and finished product should
be controlled. Proper
arrangements should also be made to control dust emissions during loading and
unloading of the raw material and finished product.
8. Total water requirement from River Sapnai
shall not exceed 3,500 m3/hr. Efforts should further be made to use
maximum water from the rain water harvesting sources. As proposed, modified wet
quenching system should be provided to coke oven plant. Air cooled condensers
and closed circuit cooling system should be provided to reduce water
consumption and water requirement shall be modified accordingly. All the
effluent shall be treated and used for ash handling, dust suppression and green
belt development. No
effluent shall be discharged and ‘zero’ discharge should be adopted. Sanitary
sewage should be treated in septic tank followed by soak pit.
9. Effluent treatment plant (ETP) shall be
provided for the treatment of Phenolic effluent from coke oven plant and the
treated water should be used for sprinkling at coal stockyard. Clarifier,
sludge pond and filter press should be provided in raw water treatment plant.
DM plant water should be neutralized in neutralization pit and the treated
water should be used for ash handling. Process wastewater should be recycled /
reused in the plant. Cooling tower blow down should be reused in the plant for
dust suppression and slag granulation, pig casting machine etc. Provision of
separate drains for the process and storm water should be kept.
10. Efforts shall be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement should be
met from other sources.
11. Measures should be taken to prevent impact of
particulate emissions / fugitive emissions, if any from the proposed plant on
the surrounding reserve forests located within 10
km radius of the project site. Further, Conservation
Plan for the conservation of
wild fauna in consultation with the State Forest Department shall be prepared
and implemented. A separate fund shall be earmarked in this regard.
12. Regular
monitoring of influent and effluent surface, sub-surface and ground water
should be ensured and treated wastewater should meet the norms prescribed by
the State Pollution Control Board or described under the E(P) Act whichever are
more stringent. Leachate study for the effluent generated and analysis shall
also be regularly carried out and report submitted to the Ministry’s Regional
Office at Bhopal, CSPCB and CPCB.
13. All the
wastewater from the coke oven plant containing
cyanide, phenol and COD etc. should be properly treated in the BOD plant.
Continuous monitoring of Total Organic Compounds (TOC) should be done at the
outlet of ETP (BOD plant) and
recovery of products like tar, ammonia, naphthalene etc. should be ensured.
14. The water
consumption should not exceed 16 m3/Ton of Steel as per prescribed
standard.
15. All the
standards prescribed for the coke oven plants shall be followed as per the
latest guidelines. Proper and full utilization of coke oven gases in power
plant using heat recovery steam generators should be ensured and no flue gases
should be discharged into the air.
16. Iron ore
fines, process dust, and mill scales should be recycled to sinter plant to
produce sinter. Sludge and
slag from electric arc furnace (EAF) should also be recycled in the sinter
plant.
17. All the
coal fines, char from DRI plant and washery rejects should be utilized
in AFBC boiler of power plant and no char should be used for briquette making
or disposed off anywhere else. AFBC boiler should be installed simultaneously
along with the DRI plant to ensure full utilization of char from the
beginning. All the blast furnace (BF) slag should be granulated and used in
manufacturing Portland Slag Cement (PSC) in the proposed cement plant. Scrap
should be used in steel melting shop (SMS). EAF & SMS slag and kiln
accretions should be properly
utilized. All the other solid waste including broken
refractory mass should be
properly disposed off in environment-friendly manner. Tar sludge from coke oven
decanter, waste oil and oil sludge should be properly disposed as per Hazardous
Waste (Management & Handling) Rules, 1989 as subsequently amended.
18. All the
slag shall be used for land filling inside the plant or used as building
material only after passing through Toxic Chemical Leachability Potential
(TCLP) test. Toxic slag
should be disposed in secured landfill as per CPCB guidelines. Otherwise, hazardous
substances should be recovered from the slag and output waste and be disposed
in secured landfill as per CPCB guidelines.
19. Proper
utilization of fly ash should be ensured as per Fly Ash Notification, 1999 and
subsequent amendment in 2003. All the fly ash generated should be fully
utilized in manufacturing of Pozollona Portland Cement (PPC) and BF slag in
should be ensured.
20. Proper
handling, storage, utilization and disposal of all the solid waste shall be
ensured and regular report regarding toxic metal content in the waste material
and its composition, end use of solid/hazardous waste should be submitted to
the Ministry’s Regional Office at Bhopal,
CSPCB and CPCB.
21. A time
bound action plan should be submitted to reduce solid waste, its proper utilization
and disposal.
22. Risk and
Disaster Management Plan along with the mitigation measures should be prepared
and a copy submitted to the Ministry’s Regional Office at Bhopal, CSPCB and CPCB within 3 months
of issue of environment clearance letter.
23. As proposed, green belt should be developed in 33 %
area.
24. All the
recommendations made in the Charter on Corporate Responsibility for Environment
Protection (CREP) for the Steel Plants should be implemented.
25. At least
5 % of the total cost of the project should be earmarked towards the corporate
social responsibility and item-wise details along with time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at Bhopal. Implementation of such program
should be ensured accordingly in a time bound manner.
26. Rehabilitation
and Resettlement Plan for the
project affected population including tribals shall be implemented as per the
policy of the State Govt. in consultation with the State Govt. of Chhattisgarh.
Compensation paid in any case should not be less than the norms prescribed
under the National Resettlement and
Rehabilitation Policy, 2007.
Proposals for TORs
11.2.15 Ferro Alloy Plant (Submerged Arc Furnace (1 x 9.0 MVA);
38,854 TPA (Silico Manganese/ ferro manganese / ferro silicon (22,855TPA) and
High Carbon Ferro Chrome (15,999 TPA) at Mouza Birsingpur P.O & P.S
Barjora, District Bankura, West Bengal M/s Keyal Ferrotech Limited- (TOR)
The project authorities and their consultant Green
Oracle, Kolkata gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP. All
the Ferro Alloy Plants are listed at S.No. 3(a) under Primary Metallurgical
Industries under Category ‘A’ and appraised at the Central level.
M/s Keyal Ferrotech Ltd have proposed for the Ferro Alloy Plant (Submerged Arc Furnace (1 x 9.0 MVA); 38,854 TPA (Silico
Manganese/ ferro manganese / ferro silicon (22,855TPA) and High Carbon Ferro Chrome
(15,999 TPA) at Mauza Birsingpur P.O.
& P.S. Barjora, District Bankura, West Bengal. Total land acquired is 4.8
acres of which 1.584 acres is earmarked for green belt development. Beliator PF
and Gobindapur PF are located at a distance of 1.5 km and 9.5 km
respectively. River Damodar flows at a distance of 7 km. Total cost of the project is Rs.12.72
Crores.
Water requirement of 100 m3/d
will be met from the Block Development Office, Barjora. Closed re-circular
cooling water system will be provided. Cooling tower blow down will be
collected in a sump/guard pond and recycled / reused in the cooling tower
itself. The treated effluent will be
used for ash conditioning, dust suppression and green belt development. Service
water will be passed through oil separator to remove oil content in the
effluent. Domestic waste water will be treated in septic tank followed by
soak pit. Power requirement of 33 MW will be sourced from WBSEB. D.G. Sets (2x160 KVA) will also be installed.
High
efficiency bag filter/water cooled heat exchanger / spark arrestor / I.D. fan connected to 30 m stack will be provided
to control particulate emissions within 50 mg/Nm3. Dedusting system and water
sprinkling system will be provided to arrest fugitive emissions.
Solid / hazardous waste will be generated in the form of Ferro
Manganese slag (30,000 TPA) and will be used in manufacture of
Silico-Manganese. Silico-Manganese slag
(1,200 TPA) will be used for road construction and own land filling prupose. Chrome slag (3,099 TPA) will be disposed off
through common hazardous waste disposal facility of Ramkey at Mangalpur,
Raniganj, West Bengal. Waste / used / spent oil and used batteries will
be sold to authorized recyclers / re-processors.
The Committee prescribed the following TORs
for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should be submitted to the Ministry
for environment clearance only after acquiring total land. Necessary documents
indicating acquisition of land should be included.
4.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
5.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
6.
Location of national
parks / wildlife sanctuary / reserve forests within
7.
A list of industries
within 10 km radius of the plant area.
8.
Details and
classification of total land (identified and acquired) should be included.
9.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
10.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
11.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
12.
Mass balance for
the raw material and products should be included.
13.
Energy balance
data for all the components of ferro alloy plant should be incorporated.
14.
Design details of
Ferro Alloy Plant and manufacturing process details should be included.
15.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
16.
Ambient air
quality at 8 locations within the study area of
17.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
18.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
19.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
20.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
21.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
22.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
23.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
24.
Presence
of aquifer/aquifers within
25.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
26.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
27.
‘Permission’ for the drawl of 100 m3/day
ground water from bore wells should be included. Water balance data must be
provided.
28.
A
note on the impact of drawl of water on the nearby River during lean season.
29.
Action
plan for rainwater harvesting measures.
30.
Surface
water quality of nearby River (
31.
If
the site is within
32.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
33.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
34.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
35.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
36.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
37.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
38.
Commitment
that no Ferro chrome will be manufactured without prior approval of the Ministry.
39.
Acton
plan for the green belt development plan in 33 % area should be included.
40.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
41.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
42.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of evaluation
of health of workers by pre designed format, chest x ray, Audiometry,
Spirometry Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations and plan of monthly and yearly report of the
health status of workers with special reference to Occupational Health and
Safety.
43.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
44.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
45.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
46.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the West Bengal Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA
report. The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP and Public hearing reports.
11.2.16 Cement Grinding Unit (500 TPD=1.65 MTPA) at Dag no.
428-430, 421-424, 403, 405,407, patta no. 41,61,174,86,70,94,195,10,46,47
Village Sila, Tehsil Sila, Sundarigoopa, District Kamrup, Assam by M/s Lalita Minerals Private Limited - (TOR)
The project
authorities did not attend the meeting and there was no information in this
regard. The committee decided that the proposal may be placed before the
Committee as and when requested by the proponent.
11.2.17 Proposed Ferro Alloys Plant (Ferro Silicon – 15 TPD/
Silico Mangnese 30 TPD / Ferro Mangnese – 40 TPD) at Plot No. 5 & 6
Industrial Park, Village- Gollapuram, Mandal-Hindupur, Dist-Ananthapur, Andhra
Pradesh by M/s Sri Ramakrishna Ferro Alloys (India) Pvt. Ltd.- (TOR)
The project authorities and
their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken along with the
draft TORs for preparation of EIA/EMP. All the Ferro
Alloy Plants are listed at S. No. 3(a) under Primary Metallurgical Industries
under Category ‘A’ and appraised at the Central level.
M/s. Sri Ramakrishna
Ferro Alloys (India) Pvt. Ltd. have proposed for the ferroalloy plant (15 TPD
ferrosilicon/30 TPD silico manganese/40 TPD ferromanganese) at plot no. 5 and
6, Industrial Park, Gollapuram (V), Hindupur (M), Ananthapur (Dist), Andhra
Pradesh in an area of 17.79 acres. Green Belt will be developed in an area of
23,957 m2. No National parks/wildlife sanctuary/reserved forest is located
within 10 km radius. The nearest human habitation is Gollapuram village at a
distance of 0.8 km. The River Penna flows at a
distance of 2.5 km. The total cost of the project is 974.4 lakhs of
which Rs 25 Lakhs is for pollution
control measures. About 5% of the total cost of the project is earmarked
towards the corporate social responsibility.
Ferrosilicon/Ferromanganese
/ Silico manganese will be manufactured in Submerged Electric Arc Furnace
(SEAF) of 6000 KVA. The process involves blending of raw materials, charging
and smelting of raw materials in SEAF at 1600-1700 °C, tapping and cooling of
the molten materials, breaking and cleaning and packing of the product for
market selling quartz, coke/charcoal, M.S. Scrap, manganese ore, electrode
paste etc. will be used as raw materials.
The water requirement
of 24 m3/day will be met from the APIIC. The cooling water will be
recycled and boiler blow down will be utilized
for dust suppression and greenbelt development. Domestic waste water shall be treated
in septic tank and finally discharged into the soak-pit. No effluent will be
discharged to outside the factory premises. The total power requirement is 6500
KVA.
Air pollution
management will be by fume extraction through hood by induced draft fan and
treated in bag filters and finally treated gas will be discharged into the
atmosphere through the stacks. Fugitive emissions will be controlled by
sprinkling water at loading and unloading points and by provision of
non-leaking of pipe connections, valves, fan, compressor etc. The slag
generated from the production process would be sold to cast iron foundries for
further utilization. Rejects generated during the cleaning of the product will
be recycled back into the production process. Dust from the bag filters will be
sold to brick/cement manufacturers. Waste oil and used batteries would be sold to authorized recyclers/reprocessors.
The Committee
prescribed the following TORs for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should be submitted to the Ministry
for environment clearance only after acquiring total land. Necessary documents
indicating acquisition of land should be included.
4.
A copy of Gazette
Notification showing that the unit is
located in the Notified Industrial Area.
5.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
6.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
7.
Location of
national parks / wildlife sanctuary / reserve forests within
8.
A list of
industries within 10 km radius of the plant area.
9.
Details and classification
of total land (identified and acquired) should be included.
10.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
11.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
12.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
13.
Mass balance for
the raw material and products should be included.
14.
Energy balance
data for all the components of ferro alloy plant should be incorporated.
15.
Design details of
Ferro Alloy Plant and manufacturing process details should be included.
16.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
17.
Ambient air quality
at 8 locations within the study area of
18.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
19.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
20.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
21.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
22.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
23.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
24.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
25.
Presence
of aquifer/aquifers within
26.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
27.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
28.
‘Permission’ for the drawl of 24 m3/day
from APIIC . Water balance data must be provided.
29.
A
note on the impact of drawl of water on the nearby River during lean season.
30.
Action
plan for rainwater harvesting measures.
31.
Surface
water quality of nearby River (
32.
If
the site is within
33.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
34.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
35.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
36.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
37.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
38.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
39.
Commitment
that no Ferro chrome will be manufactured without prior approval of the
Ministry.
40.
Acton
plan for the green belt development plan in 33 % area should be included.
41.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
42.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
43.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
44.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
45.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
46.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The letter/application
for environmental clearance should quote the MOEF file No. and also attach a
copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The final EIA report shall be
submitted to the Ministry for obtaining environmental clearance. It is noted that no public
hearing/consultation is
required due to project being located in notified industrial area as per Section (iii), Stage (3), Para (i)(b)
of EIA Notification 2006.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP.
11.2.18 Ferro Alloy Plant (2x3.6 MVA & 2x6 MVA, SAF) and
Induction Furnace at Sy. No. 218, 219,
220 & 222, Village Chinnamandadi, Mandal Peddamandadi, District
Mahabubnagar, Andhra Pradesh by M/s SMTC Power & Industries Private
Limited - (TOR)
The project
authorities and their consultant
Sri Sai Manasa Nature Tech Pvt. Ltd.
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken along with the
draft TORs for preparation of EIA/EMP. All the Ferro
Alloy Plants are listed at S.N. 3(a) under Primary Metallurgical Industries
under Category ‘A’ and appraised at the Central level.
M/s SMTC Power & Industries Pvt.
Ltd. have proposed for the Ferro Alloy Plant (2x3.6 MVA & 2x6
MVA,SAF) and Induction Furnace at Sy. No. 218, 219, 220 & 222, Village Chinnamandadi, Mandal Peddamandadi, District
Mahabubnagar, Andhra Pradesh. It is proposed to manufacture 20,000 TPA of Ferro
Alloys (10,000 TPA of ferro manganese and 10,000 TPA of Silico Mangnese), 3,000
TPA of Pig Iron and 20, 000 of Steel.
The proponent informed the Committee
that they were awarded ‘TORs’ vide letter No.J-11011/541/2009-IA-II(I)
dated 26th October, 2009 but are forced to change location due to
local politics from Industrial Park, Gooty, APIIC, Ananthapur District, Andhra
Pradesh, to Sy No. 218, 219, 220 & 222,
Chinnamandadi (V), Peddamendadi (M), Mahabubnagar, Andhra Pradesh. No
ecological sensitive areas are located within 15 km. Village Chinnamandadi is located at 2 km from
the project site. Total land acquired is
30 acres. Total cost of the project is
Rs.30 Crores.
The main raw
materials for Ferro alloys plant are Manganese Ore, Coal, Coke, Dolomite,
Quartz and Carbon paste. Ferro Alloys will be
manufactured in electric arc furnace by smelting ore, coke, coal and
briquettes. Pulse jet bag filters will be provided to control dust
emissions. Stacks (30 m) will be
provided to furnace as per CPCB guidelines. Total ground water requirement
from bore wells will be 210 m3/day.
Liquid
effluents will be treated in effluent treatment plant (ETP). Cooling
tower blow down will be recycled / reused for cooling. The treated effluent
will be used for dust suppression and green belt development. Service water
will be passed through oil separator to remove oil content in the
effluent. Domestic effluent (10 KLD) will be treated in septic tank followed
by soak pit. No effluent will be discharged outside the premises and
‘Zero’ discharge will be adopted.
Slag (50
TPD) and fly ash from bag filters (14.03 TPD) will be sold to brick
manufacturers. Furnace dust will be reused for sinter making. Slag will be disposed to slag cement
manufacturing plants. Waste / used
/ spent oil and used batteries will be sold to authorized recyclers /
re-processors.
The Committee decided
to prescribe the same TORs as were communicated
vide Ministry’s letter no. .J-11011/541/2009-IA-II(I)
dated 26th October, 2009 for undertaking detailed EIA /EMP study. The
proponent were advised that the draft EIA/EMP report shall be submitted to the
Andhra Pradesj Pollution Control Board for public hearing. The issues emerged
and response to the issues shall be incorporated in the EIA report. The final
EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP and Public hearing reports.
11.2.19 Expansion of Steel Plant by Installing Sponge Iron Plant
(3x100 TPD=1,08,000 TPA) along with Captive Power Plant (12 MW) at Paiki
Village, Marar, District Ramgarh, Jharkhand by M/s. Radha Casting & Metaliks (P) Ltd. - (TOR)
The project
authorities and their consultant
Consafe Science (India) - Shri Datta Envirotech, Hyderabad gave a detailed
presentation on the salient features of the project and proposed environmental
protection measures to be undertaken along with the draft TORs for preparation
of EIA/EMP. All the Sponge Iron Plants (more than 200
TPD) are listed at S.No. 3(a) under Primary Metallurgical Industries under
Category ‘A’ and appraised at the Central level.
M/s Radha Casting & Metalik (P) Ltd. have proposed for the expansion of Steel Plant by installing Sponge
Iron Plant (3x100 TPD = 1,08,000 TPA) along with Captive Power Plant (12 NW) at
Paiki Village, Marar, District Ramgarh, Jharkhand. Environment clearance for the existing plant
was accorded vide MoEF’s letter No.J-11011/507/2009 dated 23rd
December, 2009. Public hearing meeting
was held on 30th July, 2009.
PAs have mentioned that sponge iron plant (3x100 TPD) with CPP (12 MW)
is proposed due to shortage of raw material i.e. sponge iron for the existing
induction furnace. Total project area
is 22 acres and expansion will be carried out in the same premises. The green belt will be developed 7.26 acres
(33%) of 22 acres. River Damodar flows
at a distance of 1.5 km. Total cost of
the project is Rs.84 Crores.
Following
are the details of the existing and proposed facilities and products to be
manufactured:
S.No. |
Facilities |
Products |
A. |
EXISTING |
|
1. |
Mini Blast Furnace |
15,000 TPA |
2. |
Induction Furnace |
15,000 TPA |
3. |
Submerged Arc Furnace |
9,000 TPA |
4. |
Cement Grinding Unit |
18,000 TPA |
5. |
Re-Rolling Mill |
18,000 TPA |
B. |
PROPOSED |
|
1. |
Sponge Iron (100x3 kilns) |
1,08,000 TPA |
2. |
Captive Power Plant |
12 MW |
Iron ore
(1,83,600 TPA), coal (15,120 TPA) and lime stone (5,400 TPA) will be used as
raw materials. The rotary kilns will be provided for reduction of iron ore into
sponge iron using non-coking coal as reductant and heated up to 1000 0C
to 1050 0C to reduce iron oxide of the ore to metallic iron. The reduced material from the kiln will be
cooled in rotary cooler. Magnetic spray
iron will be used for steel making in the existing unit and non-magnetic char
will be used for power generation through FBC boiler. Atmospheric Fluidized Bed
Combustion (AFBC, 6 MW) and Waste Heat Recovery Boiler (WHRB) (6 MW) will be
installed to make use of waste gases from DRI kiln and char. Total power requirement
will be 12 MW and sourced from captive power plant (12 MW).
Electrostatic
precipitator (ESP) will be provided to Sponge Iron Plant, WHRB & AFBC power
plant to control SPM within 50 mg/Nm3. Base line data was collected by the PA for
the existing plant w.e.f. July, 2008 to May, 2009 and data submitted indicated
SPM (12.1 – 48.6 mg/Nm3), RSPM (30.1 -35.6 mg/m3), SO2
(8.8 – 16.0 mg/m3) and NOx (10.2-15.7 mg/m3) and are within the permissible limits as per
notification dated 16th November, 2009. Hot gases for the rotary kiln will be passed
through dust settling chamber after burning chamber and then led to waste heat
recovery boiler (WHRB) to generate steam for power generation. The gas will be cleaned in ESP before letting
out into the atmosphere through ID fans and stack (75m). De-dusting system will
be provided to control dust from various material transfer points. Dust extraction system with bag filters will
be provided to material handling points, raw material storage, cover discharge
product area. All conveyor belt will be
covered with G.I. Sheet. Water
sprinkling will be provided for dust suppression during unloading.
Total ground
water requirement from bore wells will be 280 m3/day. Heat exchangers will be provided for
cooling. Closed-circuit cooling system
will be provided and all the cooler water will be re-circulated. Acidic and alkaline effluent from cation and
anion units of DM Plant will be neutralized in neutralization tank.
Boiler blow down will be neutralized in the neutralization tank before mixing
with other effluent streams. After neutralization, these two effluents
will be mixed with cooling tower blow down in a Central Monitoring Basin. The
treated effluent will be used for ash conditioning, dust suppression and green
belt development. Oil and grease will
be separated using oil separators.
Service water will be passed through oil separator to remove oil content
in the effluent. Domestic effluent will be treated in septic tank
followed by soak pit. No effluent will be discharged outside the premises
and ‘Zero’ discharge will be adopted. The char (36 TPD) generated from the DRI
plant will be utilized as fuel in the AFBC boiler. Accretion slag will be used in road
construction. Ash from FBC and WHRB
boiler (45 TPD) and dust from bag filter will be given to brick/cement
manufacturers. Waste / used / spent
oil and used batteries will be sold to authorized recyclers / re-processors. D.G. set will be kept in separate
closed room with acoustic enclosures.
The Committee
prescribed the following TORs for undertaking detailed EIA study:
1.
Executive summary of the project.
2.
Compliance to the environmental clearance stipulated in the environmental
clearance accorded by the Ministry for the existing plant.
3.
Proposal should be submitted to the Ministry for environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
4.
A map indicating distance between project site and critically/severely
polluted area and a certificate from the CPCB/SPCB certifying the same.
5.
A site location map on Indian map
of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet
with at least next 10 Kms of terrains i.e. circle of 10 kms and further 10 kms
on A3/A2 sheets with proper longitude/latitude/heights with min. 100/200 m.
contours should be included. 3-D view i.e. DEM (Digital Elevation Model) for
the area in 10 km radius from the proposal site. A photograph of the site
should also be included.
6.
Present land use should be prepared based on satellite imagery. High-resolution satellite image data
having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened
etc. for the 10 Km radius area from proposed site.
The same should be used for land used/land-cover mapping of the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location of national parks / wildlife sanctuary /
reserve forests within 10 km. radius should specifically be mentioned. A map
showing landuse/landcover,
reserved forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km
of the project site.
9.
Project site layout plan showing raw materials,
fly ash and other storage plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing
through the project site should be included.
10.
Coordinates
of the plant site as well as ash pond with topo sheet co-ordinates of the plant
site as well as ash pond with topo sheet should also be included.
11.
Details and classification of total land
(identified and acquired) should be included.
12.
Rehabilitation & Resettlement (R & R) should be as per policy of the
State Govt. and a detailed action plan should be included.
13.
Permission from the tribals, if tribal land has also to be acquired
alongwith details of the compensation plan.
14.
A list of industries containing name and type
in 10 km radius should be incorporated.
15.
List of raw
material
required, analysis of all the raw materials and source alongwith mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
16.
Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS location
of source of raw material) i.e. ores, minerals, rock, soil, coal, iron,
dolomite quartz etc. using high definition and precision instruments mentioning
their detection range and methodology such Digital Analyzers, AAS with Graphite
furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per
I30-10500 and WHO norms. These analysis should include trace element and metal
studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be included..
17.
Petrography,
grain size analysis and Major element analysis of raw material and soil from project site
and raw material should be done on the same parameters along with analysis for SiO2, Al2O3, MgO,
MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
18.
If the rocks, ores, raw material has trace elements their petrography, ore microscopy, XRD, elemental mapping EPMA, XRF is
required to quantify the amount present in it and hence future risk involved
while using it and management plan.
19.
Action plan for excavation and muck disposal during construction phase.
20.
Studies for fly ash, muck, slurry, sludge material disposal and solid
waste generated, if the raw materials used has trace elements and a management plan should also be included.
21.
Manufacturing
process details
for all the plants should be included.
22.
Mass balance for the raw material and
products should be included.
23.
Energy balance
data for all
the components of steel plant including
proposed power plant should be incorporated.
24.
Site-specific micro-meteorological data using temperature,
relative humidity, hourly wind speed and direction and rainfall should be
collected.
25.
Data generated in the last
three years i.e. air, water, raw material
properties and analysis (major, trace and heavy metals),
ground water table, seismic history, flood hazard history etc.
26.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
27.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
28.
The suspended particulate matter present in the
ambient air must be analyzed for the presence of poly-aromatic hydrocarbons
(PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
29.
Determination of atmospheric inversion level at
the project site and assessment of ground level concentration of pollutants
from the stack emission based on site-specific meteorological features.
30.
Air quality modelling for steel plant and cement grinding unit for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
31.
AAQ
monitoring as per the National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
32.
Ambient air quality monitoring modeling alongwith cumulative impact should be
included for the day (24 hrs) for maximum GLC alongwith following :
i)
Emissions (g/second) with and without the air pollution control
measures
ii)
Meteorological inputs (wind speed, m/s), wind direction,
ambient air temperature, cloud cover, relative humidity & mixing height) on
hourly basis
iii)
Model
input options for terrain, plume rise, deposition etc.
iv)
Print-out
of model input and output on hourly and daily average basis
v)
A
graph of daily averaged concentration (MGLC scenario) with downwind distance at
every 500 m interval covering the exact location of GLC.
vi)
Details
of air pollution control methods used with percentage efficiency that are used
for emission rate estimation with respect to each pollutant
vii)
Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii)
No.
I-VII are to be repeated for fugitive emissions and any other source type
relevant and used for industry
ix)
Graphs
of monthly average daily concentration with down-wind distance
x)
Specify
when and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi)
Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
33.
A plan for the utilization of
waste/fuel gases
in the WHRB for generating power have to be set out.
34.
Impact of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided. The alternate method of raw
material and end product transportation should also be studied and details
included.
35.
One
season data for gaseous emissions other than monsoon season is
necessary.
36.
An action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
37.
Presence of aquifer(s) within 1 km of the project boundaries and
management plan for recharging the aquifer should be included.
38.
Source of surface/ground water level, site (GPS), cation, anion (Ion
Chromatograph), metal trace element (as above) chemical analysis for water to
be used. If surface water is used from river, rainfall, discharge rate,
quantity, drainage and distance from project site should also be included. Information regarding surface hydrology
and water regime should be included.
39.
Ground water analysis with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and
volume of aquifer and its management.
40.
Ground
water modelling showing the pathways of the pollutants should be included
41.
Column
leachate study for all types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
42.
Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the
ground water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is necessary, if
source of water is bore well.
43.
Permission for the drawl
of 280 m3/day
ground water from bore well from the SGWB/CGWA or concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
44.
A note on the impact of drawl of water on the nearby River during lean
season.
45.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
46.
If the site is within 10 km radius of any major river, Flood Hazard
Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the peak
and lean river discharge as well as flood occurrence frequency.
47.
A note on treatment of wastewater from different plants, recycle and
reuse for different purposes should be included.
48.
Provision of traps and treatment
plants are to
be made, if water is getting mixed with oil, grease and cleaning agents.
49.
If the water is mixed with solid
particulates,
proposal for sediment pond before further transport should be included. The
sediment pond capacity should be 100 times the transport capacity.
50.
Wastewater
characteristics
(heavy metals, anions and cations, trace metals, PAH) from washed /
beneficiated plants / washery or any other source should be included.
51.
The pathways for pollution via seepages,
evaporation, residual remains are to be studied for surface water (drainage,
rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans.
52.
Ground water
monitoring
minimum at 8 locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
53.
Geotechnical data by a bore hole of upto 40
mts. in every One sq. km area such as ground water level, SPTN values, soil
fineness, geology, shear wave velocity etc. for liquefaction studies and to
assess future Seismic Hazard and Earthquake Risk Management in the area.
54.
Action plan for solid/hazardous
waste
generation, storage, utilization and disposal particularly slag from all the
sources, char and fly ash. Copies of MOU regarding
utilization of ash should also be included.
55.
Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
56.
A note on the treatment, storage and disposal of all type of slag should be
included. Identification and details of land to be used for SMS slag disposal should be included.
Details of secured land fill as per CPCB guidelines should also be included.
57.
End
use of solid waste and its composition should be covered.
Toxic metal content in the waste material and its composition should
also be incorporated particularly of slag.
58.
All stock piles will have to be on top of a stable
liner to avoid leaching of materials to ground water.
59.
Acton plan for the green belt development plan in 33 % area i.e. land with not less than 1,500 trees
per ha. giving details of species, width of plantation, planning schedule etc. should be
included. The green belt should be around the project boundary and a scheme for
greening of the travelling roads should also be incorporated. All rooftops/terraces
should have some green cover.
60.
Detailed description of the flora and fauna (terrestrial
and aquatic) should be given with special reference to rare, endemic and
endangered species.
61.
At least 5 % of the total cost of the project
should be earmarked towards the corporate social responsibility and item-wise
details alongwith time bound action plan should be included. Socio-economic development
activities need to be elaborated upon.
62.
Disaster
Management Plan including risk assessment and damage control needs to be addressed and
included.
63.
Occupational
health:
a) Details of existing
Occupational & Safety Hazards. What are the exposure levels of above
mentioned hazards and whether they are within Permissible Exposure level (PEL).
If these are not within PEL, what measures the company has adopted to keep them
within PEL so that health of the workers can be preserved,
b) Details of exposure
specific health status evaluation of worker.
If the workers’ health is being evaluated by pre designed format, chest
x rays, Audiometry, Spirometry, Vision testing
(Far & Near vision, colour vision and any other ocular defect) ECG, during pre placement and periodical examinations
give the details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual
report of heath status of workers with special reference to Occupational Health and Safety.
64.
Details
regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
65.
Impact
of the project on local infrastructure of the area such as road network and
whether any additional infrastructure need to be constructed and the agency
responsible for the same with time frame.
66.
Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for
environmental pollution control measures should be included.
67.
Plan for the implementation of the recommendations
made for the steel plants in
the CREP guidelines must be prepared.
68.
A note on identification and implementation of
Carbon Credit project should be included.
69.
Public
hearing issues raised and commitments made by the project proponent on the
same should be included separately in EIA/EMP Report in the form of tabular
chart with financial budget for complying with the commitments made.
70.
Any litigation pending against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof
should also be included.
In addition to the above, information on the following may also be
incorporated in the EIA report.
1. Is the project intended to
have CDM-intent?
(i) If not, then why?
(ii) If yes, then
(a)
Has PIN (Project Idea Note) {or PCN (Project
Concept Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(b)
If not, then by when is that expected?
(c)
Has PDD (Project Design Document) been prepared?
(d)
What is the ‘Carbon intensity’ from your
electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
(e)
Amount of CO2 in Tons/year expected to
be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding 1(i) above,
data on (d)
& (e) above to be worked out and reported.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to the Jharkhand State Pollution Control Board for
public hearing. The issues emerged and response to the issues shall be
incorporated in the EIA report. The final EIA report shall be submitted to the
Ministry for obtaining environmental clearance. Further it is noted that the
unit is located at Ramgarh which has been identified as severely polluted area.
Therefore, comments from the SPCB regarding impact of the plant on the AAQ
shall be obtained.
The TORs prescribed shall be valid
for a period of two years for submission of the EIA/EMP reports.
11.2.20 Ferro Alloys Plant (Fe-Mn 30, 000 MTPA & Si-Mn 75, 000 MTPA) at Khasra No. 458,
Nandini Mines, P.O. Ahiwara District Durg, Chhattisgarh by M/s Sail & Moil Ferro Alloys Pvt. Ltd
(SMFAPL). (TOR)
The project authorities and their consultant Envision, Surat gave a detailed
presentation on the salient features of the project and proposed environmental
protection measures to be undertaken along with the draft TORs for preparation
of EIA/EMP. All the Ferro Alloy Plants are listed at
S.No. 3(a) under Primary Metallurgical Industries under Category ‘A’ and
appraised at the Central level.
M/s. Sail & Moil Ferro Alloys Pvt.
Ltd. (SMFAPL) have proposed for the
Ferro Alloys Plant (Fe-Mn 30,000 MTPA & Si-Mn 75,000 MTPA) at Khasra
No.458, District Durg, Chhattisgarh. Total
private land is 104 acres is already acquired.
Ahiwara town is at 3 km. Bhilai
city is at 23 km. No litigation or court
case is in pending against the project and / or land where the project is to be
set up. River Shivnath flows at a
distance of 7 km. Proposed project will
be located in Seismic Zone III and earth quake resistance structure will be
provided. Cost
of the proposed project would be Rs.
39,228.0 lakhs. Total capital cost for environmental pollution control
measures would be Rs. 1529.0 lakhs
and recurring cost per annum would be Rs.
350 lakhs.
Following are the details
of facilities to be provided and products to be manufactured:
S.No. |
Facility |
Plant Configuration |
Product |
Production capacity |
1. |
Submerge Arc Furnace |
16.5 MVA x 1 |
Ferro-Manganese |
30,000 MTPA |
2. |
Submerge Arc Furnace |
27.0 MVA x 2 |
Silico-Manganese |
75,000 MTPA |
TOTAL PRODUCTION OF FERRO ALLOYS |
1,05,000 MTPA |
Mn ore (2,26,000 TPA), Iron ore (2,000 TPA),
Dolomite (19,000 TPA), Coke (50,500 TPA), Coal 36,000 TPA), Carbon electrode
paste (2,400 TPA), Fe-Mn slag (29,000 TPA), quartz (16,300 TPA), will be
used as raw materials. All the raw
materials except Manganese ore will be transported by road and Manganese ore
will be transported by existing railway. Power requirement of 220 KVA
will be sourced from CSEB. The charged material for manufacturing Fe-Mn &
Si-Mn will be continuously reduced by carbon reductants. Electrode will also be deeply submerged into
furnace hearth. Liquid ferro alloy and
slag will be tapped periodically. Ferro
alloys will be casted into casting bed.
Casted ferro alloy will be cooled, cleaned for any slag sticking to it
and then transferred to product storage area where it will be broken, screened
and stacked for dispatch.
The smoke and fumes from the ore furnace will
be controlled by suction hood ducts and pulse jet bag filters before
discharging into the atmosphere through a stack of adequate height. Dual fluid
based dust suppression system will be provided at all the material transfer
points. Dust extraction and dust
suppression system will be provided to screen house and raw material handling
area. Total water requirement of 70 m3/hr will be met from Nandini Mine
Pit. The ground water from bore wells or Tandula Canal will be used in
emergency and prior permission will be obtained. The treated effluent will be
used for ash conditioning, dust suppression and green belt development. Service
water will be passed through oil separator to remove oil content in the
effluent. Domestic effluent will be treated in septic tank followed by
soak pit and used for green belt development.
No industrial waste water will be discharged outside the premises and
‘Zero’ discharge will be adopted.
Fe-Mn slag will
be reused in manufacture of Si-Mn. Si-Mn slag will be used for leveling,
construction or dumped at a slag yard.
Dust collected from bag filters will be used in fly ash brick
manufacturing. The fines collected from
Pollution control equipment will be reused in raw material processing area (i.e
briquetting plant) and mixed with the ore to be briquetted and charged in the
furnace. Waste / used spent oil and used
batteries will be sold to authorized recyclers / re-processors. Acoustic,
enclosures and silencers will be provided. About 34.32 acre of area i.e. 33 % of total
plant area shall be developed as green belt.
The Committee
prescribed the following TORs for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should be submitted to the Ministry
for environment clearance only after acquiring total land. Necessary documents
indicating acquisition of land should be included.
4.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
5.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened
etc. for the 10Km radius area from proposed site. The same should be used for
land used/land-cover mapping of the area.
6.
Location of
national parks / wildlife sanctuary / reserve forests within
7.
A list of
industries within 10 km radius of the plant area.
8.
Details and
classification of total land (identified and acquired) should be included.
9.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
10.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
11.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
12.
Mass balance for
the raw material and products should be included.
13.
Energy balance
data for all the components of ferro alloy plant should be incorporated.
14.
Design details of
Ferro Alloy Plant and manufacturing process details should be included.
15.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
16.
Ambient air
quality at 8 locations within the study area of
17.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
18.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
19.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
20.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
21.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
22.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
23.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
24.
Presence
of aquifer/aquifers within
25.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
26.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
27.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
28.
A
note on the impact of drawl of water on the nearby River during lean season.
29.
Action
plan for rainwater harvesting measures.
30.
Surface
water quality of nearby River (
31.
If
the site is within
32.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
33.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
34.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
35.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
36.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
37.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
38.
Commitment
that no Ferro chrome will be manufactured without prior approval of the
Ministry.
39.
Acton
plan for the green belt development plan in 33 % area should be included.
40.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
41.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
42.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
43.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
44.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
45.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
46.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the Chhattisgarh Environment Conservation Board for public hearing. The issues emerged and
response to the issues shall be incorporated in the EIA report. The final EIA
report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP and Public hearing reports.
11.2.21 Expansion of Cement Plant (60 TPD) to 1550 TPD) at Mouza
Gopinathpur, J.L. No. 85, Plot No. 286 (P) to 291 (P) 1667 (P), 1671 (P), 1673
to 1685, 1689, 1690 (P), 1693 (P) to 1699 (P), 1702 (P), Nasser Avenue,
Durgapur, District Burdwan in West Bengal
by M/S Janardan Cement Co(Pvt)
Ltd . (TOR)
The project authorities and their consultant gave a detailed presentation on
the salient features of the project and proposed environmental protection
measures to be undertaken along with the draft TORs for preparation of EIA/EMP.
All the cement plants (more than 1.0 MTPA) are listed
at S.N. 3(b) under Category ‘A’ and appraised at the Central level.
M/s
Janardan Cement Co (P) Ltd. have proposed for the expansion of Cement Plant (60
TPD to 550 TPD) at Mouza, Gopinathpur, J.L.No.85, Plot No.286 (P) to 291 (P),
1667 (P), 1671 (P), 1673 to 1685, 1689, 1690 (P), 1693 (P) to 1699 (P), 1702
(P), Nasser Avenue, Durgapur, District Burdwan, West Bengal. Total project area is 3.0 acres. Land is allotted by Asansol Durgapur
Development Authority (ADDA) vide letter dated 2nd April, 1995. ‘No objection Certificate’ has been granted
for 60 TPD Portland and slag cement grinding unit in the existing campus vide
WBPCB letter No.245/325/WPB-NOC/96-97 dated 19.1.1998. Total cost of the project is Rs. 16.00
Crores.
Clinker (66,000 TPA), Slag (94,200 TPA) and Gypsum (4,800
TPA) are the raw materials that would be required. Power (16 KWh) will be supplied by
Durgapur Power Ltd. The manufacturing process is fully enclosed, followed by
bag filter except only at lodging / unloding of raw materials. Water sprinkling
would be adopted for suppuration of the dust
and
for coal fired drier, the particulate emission will be controlled by cyclone separator & wet scrubber &
discharged through 30 m stack as per CPCB norms.
No
process water will be required. Make up water
requirement for cooling, domestic use and green belt will be 6 m3/day.
The water requirement will be met from
Durgapur Projects Limited. All the cooling water will be recycled. The treated
effluent will be used in the process itself for dust suppression and green belt
development. Service water will be passed through oil separator to remove oil
content in the effluent. Domestic effluent will be treated in septic tank
followed by soak pit. No effluent will be discharged outside the premises
and ‘Zero’ discharge will be adopted. All the dust from air pollution
control devices will be recycled / reused in the process. Waste / used / spent oil and used
batteries will be sold to authorized recyclers / re-processors.
.
The Committee prescribed the following TORs
for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
A copy of Gazette Notification that the unit is located in the Notified
industrial area.
3.
Compliance to the conditions stipulated for existing capacity in the
environmental clearance or NOC obtained from the SPCB.
4.
Photographs of plant area.
5.
Proposal should
be submitted to the Ministry for environment clearance only after acquiring
total land. Necessary documents indicating acquisition of land should be
included.
6.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
7.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
8.
Location of
national parks / wildlife sanctuary / reserve forests within
9.
A list of
industries within 10 km radius of the plant area.
10.
Details and
classification of total land (identified and acquired) should be included.
11.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
12.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
13.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
14.
Mass balance for
the raw material and products should be included.
15.
Energy balance
data for all the components of Cement plant should be incorporated.
16.
Design details of
Cement Plant and manufacturing process
details should be included.
17.
Mineralogical
composition of the dust along with percentage of silica fractions in the dust
particle and particle size analysis shall be carried out. Further, personnel
exposure monitoring for dust shall be carried out for the workers.
18.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
19.
Ambient air
quality at 8 locations within the study area of
20.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
21.
Air
quality modeling for cement plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
22.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
23.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
24.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
25.
Presence
of aquifer/aquifers within
26.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
27.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
28.
‘Permission’ for the drawl of 6 m3/day.
Water balance data must be provided.
29.
A
note on the impact of drawl of water on the nearby River during lean season.
30.
Action
plan for rainwater harvesting measures.
31.
Surface
water quality of nearby River (
32.
If
the site is within
33.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
34.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
35.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
36.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
37.
Acton
plan for the green belt development plan in 33 % area should be included.
38.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
39.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
40.
Occupational
health:
a) Details of existing
Occupational & Safety Hazards. What are the exposure levels of above
mentioned hazards and whether they are within Permissible Exposure level (PEL).
If these are not within PEL, what measures the company has adopted to keep them
within PEL so that health of the workers can be preserved,
b) Details of exposure
specific health status evaluation of worker.
If the workers’ health is being evaluated by pre designed format, chest
x rays, Audiometry, Spirometry, Vision testing (Far & Near vision, colour
vision and any other ocular defect) ECG, during pre placement and periodical
examinations give the details of the same. Details regarding last month
analyzed data of abovementioned parameters as per age, sex, duration of
exposure and department wise.
c) Annual report of
heath status of workers with special reference to Occupational
Health and Safety.
41.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
42.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
43.
Compliance
to the recommendations made in the CREP Guidelines.
44.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The final EIA report shall be
submitted to the Ministry for obtaining environmental clearance. It is noted that no public
hearing/consultation is
required due to project being located in notified industrial area as per Section (iii), Stage (3), Para
(i)(b) of EIA Notification 2006.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP.
11.2.22 Ferro Alloys Plant (1 x 9 MVA, SAF; 38, 854 TPA; Fe-Cr=
15,999 TPA & Fe-Mn/ Fe-Si/Si-Mn= 22,855 TPA) at Mouza Birsingpur, P.O.
& P.S. Barjora, District Bankura in West Bengal by
M/s Mortex Smelters Private Limited-
(TOR)
The
project authorities and their consultant Green
Oracle, Kolkata gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP. All
the Ferro Alloy Plants are listed at S.No. 3(a) under Primary Metallurgical
Industries under Category ‘A’ and appraised at the Central level.
M/s
Mortex Smelters Pvt. Ltd. have proposed for the
Ferro Alloy Plant (1x9 MVA,SAF; 38,854 TPA; Fe-Cr= 15,999 TPA &
Fe-Mn/Fe- Si/Si-Mn = 22,855 TPA) at Mouza Birsingpur, P.O. & P.S. Barjora,
District Bankura, West Bengal. Total
project area is 4.8 acres. Beliator PF
(1.5 km) and Gobindpur PF (9 km) are located within 10 km radius. River Damodar
flows at a distance of 7 km. Durgapur
town is at 15 km from the project site.
Total cost of the project is Rs.12.34 crores.
Chrome
ore (18,750 TPA), Chrome ore lumps (7,500 TPA), coke (1,875 TPA), dolomite
(15 TPA)/ quartzite (1,950 TPA) for manufacturing ferro chrome and Mn ore
(36,000 TPA), Mn slag (12,000 TPA), coke breeze (12,800 TPA), steel turnings
(2,000 TPA) and dolomite (5,400 TPA) will be used as raw materials. Ferro Alloy
will be manufactured using smelting process.
Charge material will be charged according to the type of ferro alloy to
be manufactured. The metal and slag will
be tapped separately from the furnace every two hours. The metal will be transferred to ladle and
then casted in casting machine. For ferro
chrome manufacturing, chromite ore, and coke with flux like quartzite and magnesite will be
used. Molten ferro chrome and slag will
be tapped separately. Molten metal will
be casted in the casting machine into ingots. Power (12 MW) will be
sourced from WBSEB. D.G. sets (2x160
KVA) will also be installed for emergency use during power failure.
High-efficiency off line clearing bag filters / water
cooled heat exchanger / spark arrestor / ID fans and 30 m steel will be
provided to control emissions within 50 mg/Nm3. Fugitive dust will be controlled by water
sprinkling system. Total ground water requirement from bore wells will be
100 m3/day. Closed
re-circulation cooling water system will be installed. Cooling tower blow down
will be collected in a guard pond and recycled / reused for dust suppression
and green belt development. Service water will be passed through oil separator
to remove oil content in the effluent. Domestic effluent will be treated
in septic tank followed by soak pit. Treated effluent will be discharged
to HAD drain and ‘Zero’ discharge will be adopted. Silico-Manganese (1,200 TPA)
slag will be used for road construction and low land filling inside the plant. Dust from APCS will be used in making fly ash
bucks. The slag will be granulated and
used in civil engineering.
Ferro-Manganese slag (34,000 TPA) will be used to manufacture
Silico-Manganese. Ferro chrome slag
(3,099 TPA) will be treated and disposed off to common hazardous disposal
facility of Ramkey at Mangalpur, Raniganj, West Bengal. Waste / used spent
oil and used batteries will be sold to authorized recyclers / re-processors.
The Committee
prescribed the following TORs for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should be submitted to the Ministry
for environment clearance only after acquiring total land. Necessary documents
indicating acquisition of land should be included.
4.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
5.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
6.
Location of
national parks / wildlife sanctuary / reserve forests within
7.
A list of
industries within 10 km radius of the plant area.
8.
Details and
classification of total land (identified and acquired) should be included.
9.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
10.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
11.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
12.
Mass balance for
the raw material and products should be included.
13.
Energy balance
data for all the components of ferro alloy plant should be incorporated.
14.
Design details of
Ferro Alloy Plant and manufacturing process details should be included.
15.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
16.
Ambient air
quality at 8 locations within the study area of
17.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
18.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
19.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
20.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
21.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
22.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
23.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
24.
Presence
of aquifer/aquifers within
25.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
26.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
27.
‘Permission’ for the drawl of 100 m3/day
ground water from bore wells should be included. Water balance data must be
provided.
28.
A
note on the impact of drawl of water on the nearby River during lean season.
29.
Action
plan for rainwater harvesting measures.
30.
Surface
water quality of nearby River (
31.
If
the site is within
32.
Pretreatment
of raw water, treatment plant for waste water should be described in detail. Design
specifications may be included.
33.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
34.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
35.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
36.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
37.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
38.
Commitment
that no Ferro chrome will be manufactured without prior approval of the
Ministry.
39.
Acton
plan for the green belt development plan in 33 % area should be included.
40.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
41.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
42.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
43.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
44.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
45.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
46.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the West Bengal Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA
report. The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP and Public hearing reports.
11.2.23 Low Ash Hard Coke (12, 000 TPA), Coal Washery Unit (1,
000 TPA) at village Harvey, P.O. Karma, District Ramgarh, Jharkhand by M/s Ma Chhinamastika Sponge Iron Ltd. (TOR)
The project authorities gave a detailed
presentation on the salient features of the project and proposed environmental
protection measures to be undertaken along with the draft TORs for preparation
of EIA/EMP. The Coke oven plants with capacity
<25,000 TPA does not require Environmental Clearance and Coal washeries with
capacity <1 million ton/annum throughput of coal are listed at S.No. 4(b)
under Category ‘B’ & being appraised at the Central level due to
non-existence of the SEIAA / SEAC in Jharkhand.
Ma
Chhinamastika Sponge Iron Limited have
proposed for the Low Ash Hard Coke (10,000 TPA) and
Coal Washery Unit (12,000 TPA) at Village
Harvey, P.O. Karma, District Ramgarh, Jharkhand. The capacity of the washery
will be 20,000 TPA of raw coal. Total project area is 1.56 ha. River Damodar flows at a distance of 7.5
km. No ecological sensitive areas are
located within 15 km. Ramgarh, a densely
populated area is at a distance of 11 km. Total cost of the project is Rs. 4
Crores.
Coal
washery will receive coal of required grade and quality from coal mines of
C.C.L, Kuju area. The coal washery will
produce clean coal (12,000 TPA) with an ash content of 24-32% and used for
making hard coke (10,000 TPA). Diesel (0.2 KLD) will be used as fuel.
Crushing, screening, deshaling in improved type of jig to produce floats and
sinks, de-sliming, washing, de-pulping, slurry collection, slurry thickening,
thickening of tailings of spirals, collection of jig rejects and slime pond material for further dumping in
dumping yard etc are carried out in the coal washery. Hard coke plant will
consists of 12 ovens with one chimney (40 m). The washed coal will be fed in
the ovens for making hard coke. Crushed
coal will be preheated in ovens and then charged at 100 0C to coke
ovens for carbonization. All the tarry
matter generated during carbonization will be completely burnt inside the ovens
only.
Gaseous
emissions will be generated from carbonization plant and released through stack
(40 m). No air emissions will be
generated from coal washery. A wet
scrubber system will be provided to coke oven plant and scrubber water will be
used for cooling after proper treatment. Dust suppression and dust extraction
system will be provided in raw material handling area. Water spraying will be done in coal
receiving, transfer, reclaim coal belt, conveyor etc. to suppress dust.
Total ground
water requirement from bore wells will be 30 m3/day. Water quenching will be adopted and all the
water will be recycled and reused for quenching. Heavy Media (H.M.) cyclone
will be provided for beneficiation of de-shelled coal to improve quality of
coal. Sprinkler will be provided to
upgrade the finer. Belt from filter will
be provided to dewater slimes. The
treated effluent will be used for ash conditioning, dust suppression and green
belt development. Fine coal thickener, tailing thickener over flow water
and filtrate from continuous press belt filter will be collected in the slime/slurry
ponds to settle solid particles and clarified water will be circulated back
into the process. Flocculants will be used in thickeners and belt press
filter. Service water will be passed
through oil separator to remove oil content in the effluent. Domestic
effluent will be treated in septic tank followed by soak pit. Sewage will
be treated in oxidation pond and sludge digestion tank. No effluent will be discharged outside the
premises and ‘Zero’ discharge will be adopted.
Rejects
from coal washery and slurry pond will be disposed off in dumping area. The solids from the slurry ponds will be
recovered by back hoe excavator and mixed with rejects / power coal.
Sponge iron grade washed coal will be used in the Sponge irons plant and
power grade washed coal will be used in Power Plant. Waste / used / spent oil and used
batteries will be sold to authorized recyclers / re-processors. Noise pollution
control measures would be implemented for the noise generated due to crushing
of coal, operation of coal handling plant, operation of D.G. Sets &
construction of equipments.
The Committee categorized the project as B2
category and the project was exempted from public hearing as there will be zero
discharge and the clompany has suggested adequate protection measures to
control the pollution. The committee prescribed the following TORs for
undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should be submitted to the Ministry
for environment clearance only after acquiring total land. Necessary documents
indicating acquisition of land should be included.
4.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
5.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
6.
Location of
national parks / wildlife sanctuary / reserve forests within
7.
A list of
industries within 10 km radius of the plant area.
8.
Details and
classification of total land (identified and acquired) should be included.
9.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
10.
List of raw
material required and source along with mode of transportation should be included.
All the trucks for raw material and finished product transportation must be
“Environmentally Compliant”.
11.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
12.
Mass balance for
the raw material and products should be included.
13.
Design details of
the coke oven plant and manufacturing process details should be included.
14.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
15.
Ambient air
quality at 8 locations within the study area of
16.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
17.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
18.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
19.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
20.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
21.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
22.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
23.
Presence
of aquifer/aquifers within
24.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
25.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
26.
‘Permission’ for the drawl of water. Water
balance data must be provided.
27.
A
note on the impact of drawl of water on the nearby River during lean season.
28.
Action
plan for rainwater harvesting measures.
29.
Surface
water quality of nearby River (
30.
If
the site is within
31.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
32.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
33.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly coal middlings.
34.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
35.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
36.
Acton
plan for the green belt development plan in 33 % area should be included.
37.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
38.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
39.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
40.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
41.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
42.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(ix)
All documents should
be properly indexed, page numbered.
(x)
Period/date of data
collection should be clearly indicated.
(xi)
Authenticated English
translation of all material provided in Regional languages.
(xii)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(xiii) The copy of the letter received from the Ministry should be also
attached as an annexure to the final EIA-EMP Report.
(xiv)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(xv)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(xvi)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The final EIA report shall be
submitted to the Ministry for obtaining environmental clearance. Public hearing
in jthis case has been exempted as the the project has been categorized as B2.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP reports.
11.2.24 Ferro Alloys Plant (2x4.5 MVA, Submerged Electro Arc
Furnace for production of 16,500 TPA of Ferro Manganese / Silico Manganese /
Ferro Chrome / Ferro Silica) at Village and Mandal Kasim Kota, District
Visakhapatnam in Andhra Pradesh by M/s
Sarojini Ferro Alloys Private Limited- (TOR)
The project authorities
and their consultant
Sri Sai Manasa Nature Tech Pvt. Ltd. gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft TORs for preparation of EIA/EMP. All the Ferro Alloy Plants are listed at S.No. 3(a) under
Primary Metallurgical Industry under Category ‘A’ and appraised at the Central
level.
M/s Sarojini Ferro Alloys Pvt. Ltd. have
proposed for the Ferro Alloys Plant (2x4.5 MVA, Submerged Electro Arc Furnace) for
production of 16,500 TPA of Ferro Alloys at Village and Mandal Kasim Kota,
District Visakhapatnam, Andhra Pradesh.
Total land area acquired is 3.5 acres of which 2.3 acres has been
earmarked for green belt. Kasimkata village is at 2 km. Total cost of the
project is Rs. 18.0 Crores.
Mn ore, pearl coke, coal, dolomite,
electrode paste for fe-Mn; Mn ore, Fe-Mn slag, pearl coke, coal, dolomite,
electrode paste for Si-Mn and dry Cr. fines, Cr Ore, lam coke, coal quartz,
Magnasite and electrode paste for Fe-Cr and quartz, mill scale, Charcoal, Ms
rounds, casting sheets for Ferro slicon will be used as raw materials. Ferro
alloy will be manufactured using electro thermic process in submerged ore
furnaces. The molten metal and slag will be trapped at regular intervals from
fixed tap holes and collected in pans / moulds.
After solidification of the metal, the same is broken into required
sizes and delivered to the containers. Power (164 KVA) will be sourced from AP
TRANSCO. HSD (200 L/day) will be used as
fuel.
Furnace
emission will be controlled by effective stack height and installation of Pulse
jet bag filters. The furnace will be covered by a hood to collect the fugitive
emissions and transferred to chimney to suck the smoke and discharged filtered
smoke to the chimney. Water spraying will be done at material handling areas to
control fugitive emissions. Total ground water requirement from bore wells
will be 50 m3/day. Treated water from cooling towers will be
recycled and reused. The treated
effluent will be used for ash conditioning, dust suppression and green belt
development. Service water will be passed through oil separator to remove oil
content in the effluent. Domestic effluent will be treated in septic tank
followed by soak pit. No effluent will be discharged outside the premises
and ‘Zero’ discharge will be adopted. Slag will be used in construction waster
and filling low lying areas. Bag filter
will be sent to fly ash brick manufacturing units. Ferro-Manganese slag will be
used as a raw material for Silico-Manganese products. Silico-Manganese slag (1500 TPM) will be used
for leveling, road construction etc.
Waste / used spent oil and used batteries will be sold to
authorized recyclers / re-processors.
The Committee
prescribed the following TORs for undertaking detailed EIA /EMP study:
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
Proposal should
be submitted to the Ministry for environment clearance only after acquiring
total land. Necessary documents indicating acquisition of land should be
included.
4.
A site location
map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on
an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in
5.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
6.
Location of
national parks / wildlife sanctuary / reserve forests within
7.
A list of
industries within 10 km radius of the plant area.
8.
Details and
classification of total land (identified and acquired) should be included.
9.
Project site
layout plan showing raw materials and other storage plans, bore well or water
storage, aquifers (within
10.
List of raw
material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
11.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
12.
Mass balance for
the raw material and products should be included.
13.
Energy balance
data for all the components of ferro alloy plant should be incorporated.
14.
Design details of
Ferro Alloy Plant and manufacturing process details should be included.
15.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
16.
Ambient air
quality at 8 locations within the study area of
17.
The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
18.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
19.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
20.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
21.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
22.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
23.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
24.
Presence
of aquifer/aquifers within
25.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
26.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
27.
‘Permission’ for the drawl of 50 m3/day
ground water from bore wells should be included. Water balance data must be
provided.
28.
A
note on the impact of drawl of water on the nearby River during lean season.
29.
Action
plan for rainwater harvesting measures.
30.
Surface
water quality of nearby River (
31.
If
the site is within
32.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
33.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
34.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
35.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
36.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
37.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
38.
Commitment
that no Ferro chrome will be manufactured without prior approval of the
Ministry.
39.
Acton
plan for the green belt development plan in 33 % area should be included.
40.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
41.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
42.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
43.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
44.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
45.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
46.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the letter
received from the Ministry should be also attached as an annexure to the final
EIA-EMP Report.
(vi)
The index of the
final EIA-EMP report must indicate the specific chapter and page no. of the
EIA-EMP Report
(vii)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
(viii)
The
consultants involved in the preparation of EIA/EMP report after accreditation
with Quality Council of India (QCl) / National Accreditation Board of Education
and Training (NABET) would need to include a certificate in this regard in the
EIA/EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the Andhra Pradesh Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA
report. The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP and Public hearing reports.
11.2.25 Expansion of Integrated Cement Project (Clinker from 2.4
MTPA to 2.9 MTPA, Cement 3.6 MTPA), Limestone Mine (RAS - I (
The project authorities and
their consultant
J. M. Environet Pvt Ltd, Gurgaon gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken along with the draft TORs for preparation of EIA/EMP. All the cement plants (more than 1.0 MTPA) are listed at
S.No. 3(b) under Category ‘A’ and appraised at the Central level.
M/s
Ambuja Cement Limited have proposed for Expansion of Integrated Cement
Project (Clinker from 2.4 MTPA to 2.9 MTPA, Cement 3.6 MTPA), Limestone Mine
(RAS - I (
Method of mining will be opencast
involving drilling and blasting. The total geological limestone reserves and
mineable reserves are 79.65 MT and 54.62 MT respectively. The life of the mine
is 196 years. Mine will not intercept ground water table at any stage of mine
activity. Water requirement of 2400 m3/d will be obtained from the ground water
source. The company has obtained permission from CGWA for drawl of 2400 m3 of
ground water vide letter no. 21-4(4)/WR/CGWA/2005 -1188 dated 15.10.2008. Bag
filters would be installed to control the particulate emissions from the
screening and crusher plant, raw mill, kiln, coal mill, packaging plant and ESP
will be installed for the cement grinding unit, clinker cooler and power
plants.
The Expert Appraisal Committee (Industry)
recommended the proposal for the preparation of revised EIA/EMP as per the
following TORs:
TORs for Cement Plant:
1.
Executive summary of the project.
2.
Compliance to the conditions stipulated in
the environmental clearance for the existing cement plant and limestone mine.
3.
Photograph of Plant area.
4.
The earlier questionnaire for cement,
captive power plant and mining sectors should be submitted while submitting
EIA/EMP.
5.
A site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
6.
Present land use should be prepared based on satellite imagery.
High-resolution satellite image data having 1m-5m spatial resolution like
quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10Km radius area from
proposed site. The same should be used for land used/land-cover mapping of the
area.
7.
Location of national parks / wildlife sanctuary / reserve forests
within
8.
Project site layout plan showing raw materials, fly ash and other
storage plans, bore well or water storage, aquifers (within
9.
Details and classification of total land (identified and acquired)
should be included.
10.
Proposal should be submitted to the Ministry for environment clearance
only after acquiring total land. Necessary documents indicating acquisition of
land should be included.
11.
A list of industries containing name and type in 10 km radius should be
incorporated.
12.
List of raw material required and source alongwith mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
13.
Petrological and Chemical analysis and other chemical properties of raw
materials used (with GPS location of source of raw material) i.e. ores,
minerals, rock, soil, coal, iron, dolomite quartz etc. using high definition
and precision instruments mentioning their detection range and methodology such
Digital Analyzers, AAS with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD,
Nano studies or at least as per I30-10500 and WHO norms. These analysis should
include trace element and metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se,
S etc. Presence of radioactive elements (U, Th etc.).
14.
Petrography, grain size analysis and Major element analysis of raw
material and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
15.
If the rocks, ores, raw material has trace elements their petrography,
ore microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the
amount present in it and hence future risk involved while using it and
management plan.
16.
Quantification & Characteristic of solid/hazardous waste and its
action plan for management may be included.
17.
Manufacturing process details for all the cement plant, captive power
plant and mine should be included.
18.
Possibility of installation of WHRB will be explored and details
included
19.
Mass balance for the raw material and products should be included.
20.
Site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall should be collected.
21.
A write up on use of high calorific hazardous wastes from all the
sources in kiln and commitment regarding use of hazardous waste should be
included.
22.
Ambient air quality at 8 locations within the study area of
23.
The suspended particulate matter present in the ambient air must be
analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene
soluble fraction. Chemical characterization of RSPM and incorporating of RSPM
data.
24.
Determination of atmospheric inversion level at the project site and
assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
25.
Air quality modelling for all the plants proposed including mine for
specific pollutants needs to be done. APCS for the control of emissions within 50 mg/Nm3 should be included.
26.
Ambient Air
Quality as per National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
27.
Air Quality
Impact Prediction modeling based on ISCST -3
or the latest models may be included.
28. Impact of the transport of
the raw materials and end products on the surrounding environment should be
assessed and provided.
29. Presence of aquifer(s)
within
30. Ground and surface water
to be analyzed from the project impact area as per ISO 10,500.
31. Ground water analysis with
bore well data, litho-logs, drawdown and recovery tests to quantify the area
and volume of aquifer and its management.
32. Action plan for rainwater harvesting measures at plant
site should be submitted to harvest rainwater from the roof tops and storm
water drains to recharge the ground water and also to use for the various
activities at the project site to conserve fresh water and reduce the water
requirement from other sources. Rain
water harvesting and groundwater recharge structures may also be constructed
outside the plant premises in consultation with local Gram Panchayat and
Village Heads to augment the ground water level. Incorporation of water harvesting plan for
the project is necessary, if source of water is bore well.
33. Permission for the drawl of water from
the concerned authority and water balance data including quantity of effluent
generated, recycled and reused and discharged is to be provided. Methods
adopted/to be adopted for the water conservation should be included.
34. A note on the
impact of drawl of water on the nearby River during lean season.
35. Surface water
quality of nearby River (
36. If the site is
within
37. A note on treatment of
wastewater from different plants, recycle and reuse for different purposes
should be included.
38. If the water is mixed with
solid particulates, proposal for sediment pond before further transport should
be included. The sediment pond capacity should be 100 times the transport
capacity.
39. Ground water monitoring
minimum at 8 locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
40. Action plan for
solid/hazardous waste generation, storage, utilization and disposal. A note on
the treatment, storage and disposal of all type of solid waste should be
included. End use of solid waste viz. fly ash etc.
and its composition should be covered.
41. Acton plan for
the green belt development plan in 33 % area should be included.
42. A scheme for
rainwater harvesting have to be put in place. Incorporation of water harvesting
plan for the project is necessary, if source of water is bore well. Efforts should be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement should be
met from other sources.
43. Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special
reference to rare, endemic and endangered species.
44. Acton plan for the green belt development plan in 33 % area should be included.
The green belt should be around the project boundary and a scheme for greening
of the traveling roads should also be incorporated. All rooftops/terraces
should have some green cover.
45. Detailed description of
the flora and fauna (terrestrial and aquatic)
should be given with special reference to rare, endemic and endangered species.
46. At least 5 % of the total
cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities
need to be elaborated upon.
47. Disaster Management Plan including risk assessment and damage control needs
to be addressed and included.
48. Occupational health:
a) Details of existing
Occupational & Safety Hazards. What are the exposure levels of above
mentioned hazards and whether they are within Permissible Exposure level (PEL).
If these are not within PEL, what measures the company has adopted to keep them
within PEL so that health of the workers can be preserved,
b) Details of exposure
specific health status evaluation of worker.
If the workers’ health is being evaluated by pre designed format, chest
x rays, Audiometry, Spirometry, Vision testing (Far & Near vision, colour
vision and any other ocular defect) ECG, during pre placement and periodical
examinations give the details of the same. Details regarding last month
analyzed data of abovementioned parameters as per age, sex, duration of
exposure and department wise.
c)
Annual
report of heath status of workers with special reference to Occupational Health and Safety.
49. Plan for the
implementation of the recommendations made for the cement plant in the CREP
guidelines must be prepared.
50. At least 5 % of the total
cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
prepared and incorporated.
51. Total capital cost and recurring
cost/annum for environmental pollution control measures.
52. Public hearing issues
raised and commitments made by the project proponent on the same should be
included separately in EIA/EMP Report in the form of tabular chart.
53. Any litigation pending against
the project and / or any direction / order passed by any Court of Law against
the project, if so, details thereof.
TORs for Mines:
1.
The proposal for
mining will be considered only if Mining Plan and Mining lease approval from
the IBM and State Govt. is included in the final EIA/EMP.
2.
The study area should comprise of
3.
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features.
4.
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases.
5.
Location of National Parks, Sanctuaries, Biosphere Reserves, Reserve
Forest, Wildlife corridors, within
6. A detailed biological
study for the study area [core zone and buffer zone (
7. Impact of change of land
use particularly agriculture land and gaucher / grazing land, if any.
8.
Number of land oustees and mode of compensation.
9.
Collection of one season (non-monsoon) primary baseline data on ambient
air quality, water quality, noise level, soil and flora and fauna. Site-specific meteorological data should also
be collected. The location of the
monitoring stations should be justified.
10.
Air quality modeling should be carried out for prediction of impact of
the project on the air quality of the area. It should also take into account
the impact of cement plant, captive power plant, lime stone mine and movement
of vehicles for transportation of mineral. The details of the model used and
input parameters used for modeling should be provided. The air quality contours
may be shown on a location map clearly indicating the location of the site,
location of sensitive receptors, if any and the habitation. The wind roses
showing pre-dominant wind direction may also be indicated on the map.
11.
The water requirement for the project, its availability and source to
be furnished. A detailed water balance should also be provided. Fresh water requirement for the project
should also be indicated.
12.
Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
13.
Necessary clearance water drawl from the Competent Authority.
14.
Details of water conservation measures proposed to be adopted in the
project.
15.
Impact of the project on the water quality both surface and groundwater
should be assessed and necessary safeguard measures, if any required should be
provided.
16.
Details of rainwater harvesting proposed, if any, in the project area
to be provided.
17.
Information on site elevation, working depth, groundwater table should
be provided both in AMSL and BGL. A
schematic diagram may also be provided for the same. In case the working will intersect
groundwater table, a detailed hydro-geological study should be undertaken and
report furnished.
18.
Quantity of solid waste generation to be estimated and details for its
disposal and management be provided.
19.
The reclamation plan, post mine land use and progressive greenbelt
development plan should be prepared in tabular form (prescribed format) and
submitted.
20. Impact on local transport
infrastructure due to the project. Projected increase in truck traffic as a
result of the project in the present road network (including those outside the
project area) and whether it is capable of handling the increased load. Arrangement for improving the infrastructure,
if contemplated including action to be taken by other agencies such as State
Government, if any, should be covered.
21.
Details of the infrastructure facilities to
be provided for the mine workers.
22.
Conceptual post mine land use and Reclamation and Rehabilitation of
mined out area (with plans and with adequate number of sections).
23.
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation clearly indicating the area to be covered under plantation and
the species to be planted. The details of plantation already done should be
given.
24.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
25.
Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital
cost and recurring cost/annum for environmental pollution control measures should be included.
26.
Measures of socio-economic influence to the local community proposed to
be provided by project proponent. As far
as possible, quantitative dimension to be given.
27.
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, besides other
impacts of the projects should be provided.
28.
At least 5 % of
the total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
29.
Public hearing
issues raised and commitments made by the project proponent on the same should
be included separately in EIA/EMP Report in the form of tabular chart with
financial budget for complying with the commitments made.
30.
Any litigation pending against
the project
and/or any direction/order passed by any Court of Law against the project, if
so, details thereof should also be included.
The
following general points should be noted:
(i)
All documents should
be properly indexed, page numbered.
(ii)
Period/date of data
collection should be clearly indicated.
(iii)
Authenticated English
translation of all material provided in Regional languages.
(iv)
The
letter/application for environmental clearance should quote the MOEF file No.
and also attach a copy of the letter.
(v)
The copy of the
letter received from the Ministry should be also attached as an annexure to the
final EIA-EMP Report.
(vi)
While
preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I)
dated 4th August, 2009, which are available on the website of this Ministry
should also be followed.
4. The Expert Committee (Industry) decided
that the proponent may be communicated the above ‘TORs’ for the preparation of
EIA/EMP for the cement plant, captive mine and captive power plant. As soon as the draft EIA/EMP report is
prepared, the same may be submitted by the PAs to the Rajasthan State Pollution Control Board
for conducting public hearing as per EIA Notification, 2006. On
finalization of EIA/EMP prepared as per TORs addressing all concerns set out in
EIA/EMP should be submitted to the MOEF for prior
environmental clearance.
5. The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP & public hearing reports.
11.2.26 Proposed Integrated Steel Plant at Village Halvarthi, Taluk
& District Koppal in Karnataka by M/s Gallantt Metal Limited - (TOR)
The project authorities and their consultant Metamorphosis, Bangalore gave a
detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken along with the draft TORs
for preparation of EIA/EMP. All the Steel Plants are listed at S.N. 3(b) under Category ‘A’ and appraised
at the Central level.
M/s Gallantt Metal
Limited have proposed for Integrated Steel Plant at Village Halvarthi, Taluk
& District Koppal in Karnataka. The
total land available at the present plant site is about 93.00 acres which is a
private land. The land has been acquired. There is no national forest/wildlife
sanctuary/biosphere reserves located within 10 km radius of the project site.
The total cost of the project is Rs.
255.20 Crores. PAs have also confirmed that no
litigation/court case is in pending against the project.
Products along with its capacity to be
manufactured are as follows:
S.
No. |
Product |
Capacity |
1 |
Sponge Iron (DRI Kiln) |
99,000
MTPA |
2 |
Sponge Iron (Tunnel Kiln) |
1,48,500
MTPA |
3 |
Beneficiation (Iron Ore Fines) |
3,00,000 TPA |
4 |
Steel Melt Shop (SMS) |
1,07,800 TPA |
5 |
Rolling Mill (TMT) |
1,04,000 TPA |
6 |
CPP (From Waste heat, Coal and Dolachar),
with Air Cooled Condenser |
12 MW-AFBC 6 MW -WHRB |
The production of
sponge iron involves reduction of iron ore /pellets with solid carbonaceous
material (coal/coke/lignite) in a rotary kiln at high temperature, cooling to
room temperature in the rotary cooler with indirect water cooling system,
screening and magnetic separation of the
product. Sponge iron being magnetic gets attracted and separated from the
non-magnetic char. The product handling area will be provided with cyclone
separator in series with the bag filter. All the waste gas from the sponge iron
kiln will be utilized in West Heat Recovery Boiler in Captive Power Plant which
will generate 30 TPH of steam. Char produced by DRI kiln will have an outlet as
fuel to AFBC boiler. Coal and Char will be fired as a base fuel to AFBC boiler
for steam generation. To control the particulate emissions from the DRI plant
and Captive Power Plant electrostatic
precipitator and Bag filters will be installed. Cyclones and wet scrubbers will
be installed to control the emissions from the steel melting shop, rolling mill
and beneficiation plant.
PAs mentioned that the water requirement will be 950 m3/d and
will be source from the bore wells located at the project site. Water re-circulating system has been proposed and reuse
of return water. The company will install Air Cooled Condenser for its proposed
power project. Domestic effluent will be
treated in septic tank followed by soak pit. No effluent will be
discharged outside the premises and ‘Zero’ discharge will be adopted.
It was noted that the
solid waste generated will be mostly tailing, flyash and Slag. Domestic waste
and sludge from STP. Tailing and fly ash
will be utilized for in-house brick manufacturing and will be sold to the cement plants. Slag will be utilized
for strengthening of internal roads and sold to cement plants. Biodegradable
waste from canteen and sludge from sewage treatment plant will be composted and
utilized for green belt in the plant
premises.
It was mentioned that total power requirement
of 18 MW will be source from captive
power plant and also from the stand by
DG sets.
The Committee
prescribed the following TORs for undertaking detailed EIA study:
1.
Executive summery of the project
2.
Photographs of the plant area.
3.
A copy of the mutual agreement for land acquisition signed with land
outstees.
4.
A map indicating distance between project site and critically/severely
polluted area and a certificate from the CPCB/SPCB certifying the same.
5.
A site location map on Indian map
of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet
with at least next 10 Kms of terrains i.e. circle of 10 kms and further 10 kms
on A3/A2 sheets with proper longitude/latitude/heights with min. 100/200 m.
contours should be included. 3-D view i.e. DEM (Digital Elevation Model) for
the area in 10 km radius from the proposal site. A photograph of the site
should also be included.
6.
Present land use should be prepared based on satellite imagery. High-resolution satellite image data
having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened
etc. for the 10 Km radius area from proposed site.
The same should be used for land used/land-cover mapping of the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location of national parks / wildlife sanctuary /
reserve forests within 10 km. radius should specifically be mentioned. A map
showing landuse/landcover,
reserved forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km
of the project site.
9.
Project site layout plan showing raw materials,
fly ash and other storage plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing
through the project site should be included.
10.
Coordinates
of the plant site as well as ash pond with topo sheet co-ordinates of the plant
site as well as ash pond with topo sheet should also be included.
11.
Details and classification of total land
(identified and acquired) should be included.
12.
Rehabilitation & Resettlement (R & R) should be as per policy of the
State Govt. and a detailed action plan should be included.
13.
Permission from the tribals, if tribal land has also to be acquired
alongwith details of the compensation plan.
14.
Permission and approval for the
use of forest land, if any, and recommendations of the State Forest Department regarding impact of
proposed expansion on the surrounding reserve
forests viz. Barkagaon
RF (9 Km, W), Jorakath RF (9 km, S), Gurua PF (4 km, E), Gali R.F. (9 km, S)
should be included.
15.
A list of industries containing name and type
in 25 km radius should be incorporated.
16.