MINUTES FOR 10th
MEETING OF THE RECONSTITUTED EXPERT APPRAISAL COMMITTEE (INDUSTRY-1) HELD
DURING 17th–18th May, 2010
VENUE:Tagore Hall, SCOPE
CONVENTION CENTRE, Institutional Area, Lodhi Road, New Delhi
1.0 Opening Remarks of
the Chairman
2.0 Minutes of 9th
Meeting of the Expert Appraisal Committee (Industry-1) held during 7th–8th
April, 2010 were confirmed.
3.0
Consideration of the Projects
17th May, 2010
4.0 New Proposals :
4.1
Expansion of Steel Plant [Sinter
(2,62,000 TPA), Mini Blast Furnace, Steel (2,50,000 TPA), Rolling mill
(2,25,000 TPA)] and Captive Power Plant (16 MW) at Village Barahamusa, Taluk
Bonai, District Sundergarh, Orissa by M/s Surendra Mining Industries (P) Ltd. (EC)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Draft Terms
of References (TORs) awarded during the
88th Meeting of the Expert Appraisal Committee (Industry) held
during 11th -12th December, 2008 for preparation
of EIA/EMP. All the primary
metallurgical industries are kept under S. N. 3 (a) of EIA Notification, 2006
and will be appraised at Central level.
Additionally, PAs informed to the Committee that M/s Surendra Mining Industries (P) Ltd. has proposed to expand its steel plant at Village Barahamusa,
Taluk Bonai, District Sundargarh, Orissa. Existing DRI plant was installed in
2006. Total land required for the proposed expansion will be 200 acres, of
which 130 acres is already acquired and 70 acres is under acquisition. Amruhi
RF, Rakshi RF, Burha Pahar RF, Pangoli RF are located at 7-8 km from the
project site. No national parks/wildlife sanctuary is located within 10 km. During
presentation, PAs have submitted a copy of letter from DFO, Bonai Division, State Forest Department issued vide letter
no. 2098/6F dated 15th April, 2009 indicating that there may be some
impact on the surrounding reserve forests due to expansion of the project.
River Baitarani is situated at a distance of 1.5 kms from the plant site in
east direction. Total cost of the proposed expansion will be Rs. 645.53 Crores
is enhanced to Rs. 647.54 Crores. Rs. 33.60 Crores and Rs. 0.40 Crores will be
earmarked towards total capital cost and recurring cost/annum for environmental
pollution control measures instead of Rs. 34.00 Crores and Rs. 0.80 Crores
proposed earlier. Following
will be the existing and proposed facilities from the proposed plant:
Units |
Existing Capacity (TPA) |
Proposed Capacity (TPA) |
Total Capacity (TPA) |
DRI (2x100 TPD) |
62,000 |
-- |
62,000/60,000 |
Sinter (1x28 m2) |
-- |
2, 62,000 |
2,62,000/2,68,000/3,00,000 |
Mini Blast Furnace (200 m3) |
-- |
2,24,000 |
2,24,000/22,24,000/2,31,000 |
SMS (IF-2x15 T, EAF-1x25/30T, LRF-2x30T, Concast-1x3
Strand) |
-- |
2,50,000 |
2,50,000/2,40,000 |
Rolling Mill |
-- |
2,25,000 |
2,25,000/2,10,000 |
Captive Power Plant
WHRB-2x12 t
FBC-1x 40 tph BF
Gas fired Boiler- 1x25 tph |
-- |
16 MW |
16 MW |
However,
during presentation, PAs informed that following will
be the configuration of existing and proposed facilities from the proposed
plant:
Units |
Existing Capacity (TPA) |
Proposed Capacity (TPA) |
Total Capacity (TPA) |
DRI (2x100 TPD) |
62,000 |
-- |
62,000 |
Sinter (1x28 m2) |
-- |
2,62,000 |
2,62,000 |
Mini Blast Furnace (200 m3) |
-- |
2,24,000 |
2,24,000 |
SMS (IF-2x15 T, EAF-1x30T, LRF-2x30T,
Concast-1x3 Strand) |
-- |
2,50,000 |
2,50,000 |
Rolling Mill |
-- |
2,10,000 |
2,10,000 |
Captive Power Plant
WHRB-2x12 t
AFBC-1x 40 tph
BF Gas fired Boiler- 1x25 tph |
-- |
16 MW |
16 MW |
Coal washery |
|
100 TPH |
100 TPH |
As per EIA/EMP report, additional unit
i.e. SAF (Ferro Alloy, 25,000 TPA) and coal washery / beneficiation unit was
proposed. During presentation, PAs have confirmed that no submerged arc furnace
(SAF) will be installed to manufacture ferro alloy and only coal washery (100
TPH) will be added.
Raw
materials required for the proposed expansion will be
Iron ore (DR grade, 1,01,000 TPA; BF grade, 1,02,000 TPA; Sinter grade,
2,49,200 TPA), Limestone (52,500 TPA), Dolomite (51,430 TPA), Non-coking Coal
(1,06,000 TPA), BF Coke (1,37,000 TPA), Mn Ore (4,480 TPA), Quartzite (6,700
TPA), Coke Fines (9,000 TPA), Burnt Dolo (6,000 TPA), Ferro alloy (increased
from 48,000 TPA to 82,407 TPA), Sponge Iron (increased from 78,000 TPA to
97,863 TPA) and Pet coke (7,200 TPA). PAs
informed that source of coke will be decided later on.
Sinter
manufacture process will involve crushing of flux and fuel, mixing of
constituents, nodulising, ignition of Sinter mix using BF gas in the hearth
followed by cooling and screening. In
the blast furnace, the solid burden charged will be smelted by the hot blast
and the hot metal will be tapped through an iron notch into ladle and slag
through slag notch. For casting the hot metal into cold pigs, a single strand
Pig Casting Machine will be installed. Hot metal, scrap and DRI will be melted
in Electric Arc Furnace. Scrap and cold pig will be charged and melted in the
Induction Furnace. After melting of the charge, DRI fines mash will be
continuously charged with small amount of coke dust/pet coke till the furnace
is full with molten metal. Slag is continuously scooped out. The molten metal
from both EAF and IF will be tapped into a ladle and taken to LRF for refining
and subsequently to the Continuous Casting Machine for casting the billet.
Captive power plant will comprise of a waste heat boiler, fluidized bed
combustion boiler and BF gas fired boiler.
Ambient
air quality monitoring was carried out at 8 locations during December, 2008–February,
2009 and submitted data indicated the levels of SPM (75 – 125 ug/m3),
RSPM (34–53 ug/m3), SO2 (8-15 ug/m3) and NOx
(9-29 ug/m3). The submitted data indicated incremental SPM
(18.505 µg/m3), SO2 (48.474 µg/m3) and NOX
(12.825 µg/m3) which are within the permissible limit.
Dust
extraction system comprising of suction hood, duct work, ESP, fans and stack
will be provided to DR waste heat boiler, Sinter Plant, Blast Furnace, Steel
Melt Shop (SMS), DRI screening plant, Ore screening & Coal crushing plant
etc. BF will be provided with dust
catcher followed by a two-stage venturi system for final cleaning. Flue gases
from DRI plant will be passed through After Burning Chamber (ABC) and then
subsequently taken to unfired furnace chamber, super heater, convective
evaporator and economizer before being discharged to atmosphere through ESP and
chimney. Flue gases from FBC will pass over heat transfer surfaces to ESP and
then finally vented to atmosphere through a chimney by ID fans. Dust
suppression system will be provided at different conveyor transfer points in
raw material handling area. Dust extraction system comprising of suction hood,
duct, bag filter, fan, stack will be provided to ore screening section.
During
presentation, PAs have clarified that total water requirement for proposed unit
from the River Brahmani will be 360 m3/hr and water requirement for
existing unit is 30 m3/hr and permission for the drawl of water is
obtained from Water Resource Department, Govt. of Orissa. PAs have also obtained NOC for drawl of 364 m3/day
ground water from Central Ground Water Board vide letter no. 21-4(35)/SER/CGWA/
2008/88 dated 1st May, 2008. ‘Zero’ discharge will be adopted.
Underflow sludge from clarifloculaters will be collected and will be pumped to
sludge pond. Regeneration waste from water treatment plant will be neutralized
before discharge from the plant. Blow down water will be reused in the plant.
Oil & Grease will be removed from the contaminated water. Rain water
harvesting structure will be installed.
Currently,
char generated from DRI kiln is being sold to different customers. However, after expansion, the char or coal
fines will be reused in FBB boiler for power generation. Coal fines generated
during crushing will partly be sold and rest will be dumped in separate area.
Accretion and lumpy waste will be sent for landfill. Fly ash from AFBC and WHRB
will be used in cement manufacture, brick making and road making. Bottom ash
from AFBC will be used in brick and road making. BF Slag will be for slag cement production.
Dedusting dust from blast furnace, SMS, sinter plant will be used in sinter
making. SMS slag will be used for road making. Mill scale from rolling mill
will be recycled to SMS. Dust collected from ESP and bag filters will be transported
to nearby technological material handling system. Used oil generated will be
burnt alongwith coal. Slag from SAF will be used as ballast for road making. A
copy of letter dated 15.04.2010 issued by M/s Arpita Enterprises, M/s Sanjay
Concrete Pipe & Products and Utkal Plaster Pvt. Ltd indicating requirement of 17,000 MTPA of fly
ash and bottom ash for their fly ash brick plant.
PAs confirmed that green belt will be
developed in 27.11 ha (33%) out of total 80.94 ha. Acoustic enclosures,
silencers, selection of low noise equipment, isolation of noisy equipment from
working personnel. Ear muffs/plugs will be provided to employees working in
high noise zones. Maximum power
requirement (46 MW) will be met from Captive Power Plant (16 MW) and public supply
(30 MW). High Speed Diesel will be used as fuel. Light diesel oil (LDO) will be used as fuel
for start-up of kilns. 23,000 TPA of Oxygen will be used in Billet production.
Nitrogen will be used in liquid steel for rinsing purpose. Acetylene will be
required in rolling mill, SMS and BF for cutting/autogeneous needs. LPG will be
used in Sinter plant for upgrading fuel value of BF gas and also for enriching
of blast air to BF.
Public hearing/Public
consultation meeting was conducted by the Orissa Pollution Control Board on 6th November, 2009. The Committee deliberated upon
the issues raised during the public
hearing including local employment, drinking water supply, pollution control
measures, development activities, solid waste etc. and have satisfactorily been
incorporated in the final EIA/EMP report.
After detailed
deliberations, the Committee has recommended the proposal for environmental
clearance subject to stipulation of following specific conditions alongwith
other environmental conditions :
1.
Compliance
to all the specific and general conditions stipulated for the existing plant(s)
by the Central/State Govt. should be ensured and regular reports submitted to
the Ministry and its Regional Office at Bhuvaneswar.
2.
Adequate air pollution control devices
viz. Electrostatic precipitator (ESP), gas cleaning plant, dust catcher,
ventury scrubber, bag filters etc. should
be provided to keep the emission levels below 50 mg/Nm3 and by
installing energy efficient technology.
4.
Gaseous emission levels including
secondary fugitive emissions
from all the sources should be controlled as per Ministry
vide G.S.R. 414(E) dated 30th May, 2008 within
the latest permissible limits issued by the Ministry and regularly monitored.
Guidelines / Code of Practice issued by the CPCB should be followed.
5.
Hot gases from DRI
kiln should be passed through Dust Settling Chamber (DSC) to remove coarse
solids and After Burning Chamber (ABC) to burn CO completely and used in waste
heat recovery boiler (WHRB). The gas
then should be cleaned in ESP before leaving out into the atmosphere through ID
fan and stack.
6.
Total water requirement from the
River Brahmani should not exceed 360 m3/hr as per the permission
accorded by the Central Ground Water Board vide letter no. 21-4(35)/SER/CGWA/
2008/88 dated 1st May, 2008.
7.
The water consumption should not exceed as
per the standards prescribed for the steel plants.
8.
All the char from DRI plant should be utilized in AFBC boiler of power
plant and no char should be disposed off anywhere else. AFBC boiler should be
installed simultaneously alongwith the DRI plant to ensure full utilization of
char from the beginning. All the blast furnace (BF) slag should be
granulated and provided to cement manufacturers for further utilization. Mill scale from rolling mill should be recycled to SMS
only.
9.
Proper utilization of fly ash should be ensured as per Fly Ash
Notification, 1999 and subsequent amendment in 2003 and 2010.
10.
All the recommendations made in
the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Plants should be
implemented.
11.
Prior permission from the State Forest Department should be
taken regarding likely impact of the expansion of the proposed steel plant on
the reserve forests. Measures should be taken to prevent impact of particulate
emissions / fugitive emissions, if any from the proposed plant on the surrounding
reserve forests viz. Amruhi RF, Rakshi RF, Burha Pahar RF, Pangoli RF located
within 10 km radius of the project. Further, Conservation Plan for the conservation of wild fauna in
consultation with the State Forest Department should be prepared and implemented.
12.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 6th
November, 2009 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bhuvaneswar..
13.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhuvaneswar. Implementation of such
program should be ensured accordingly in a time bound manner.
4.2
Mini Integrated Steel Plant alongwith Captive Power
Plant (8 MW) at Khatian No. 90, Village
Marhand, P. O. Lila Nagar, District Hazaribag, Jharkhand by M/s Jharkhand Sales
Agencies Pvt. Ltd. (EC)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Draft Terms
of References (TORs) awarded during the
90th Meeting of the Expert Appraisal Committee (Industry) held
during 6th-8th January, 2009 for preparation of
EIA/EMP. All the primary metallurgical
industries are kept under S. N. 3 (a) of EIA Notification, 2006 and will be
appraised at Central level.
Additionally, PAs informed to the Committee that M/s Jharkhand Sales Agencies Pvt. Ltd. has
proposed to set up a Mini Integrated Steel Plant alongwith Captive Power Plant
(8 MW) at Khatian No. 90, Village Marhand, P. O. Lila Nagar, District
Hazaribag, Jharkhand. Total land required will be 15 acres. Hazaribag is 10
km away from the project site. No national park and wild life sanctuary is
located within 10 km radius of the project site. Barkagaon Reserve Forest and Jorakath Reserve Forest is located at
9 Km. Total cost of the proposed project
will be Rs. 10529.81 Lakhs. Rs. 431.00 Lakhs and Rs. 117.95 Lakhs
are earmarked towards capital costs and recurring cost for pollution control
measures. Following facilities will be
the installed in the proposed plant:
Plant |
Capacity (TPA) |
Sponge Iron |
60,000 (2x100 TPD) |
Induction Furnace with Concast
plant |
33,900 (1x12 TPD) |
Captive Power Plant WHRB AFBC |
8 MW (4MW) (4 MW) |
Raw
materials required for the proposed project will be Iron ore, Limestone, Coal,
Coal char, Sponge Iron, Scrap & Pig Iron.
Iron ore
and coal will be charged into a rotary kiln in requisite proportion alongwith
dolomite at 950-1050oC. Melting scrap and cast Iron alongwith
sponge iron will be charged into an Induction Furnace at 1600oC and
then additives like Ferro alloys and Aluminium ingots will be added. Molten
metal will be transferred to an Ingot mould and the final ingots will be taken
out from the mould. Power will be generated using AFBC
technology and WHRB technology.
The former burns coal in fluidized bed of inert material while the latter will
utilize the waste heat from the flue gases.
Ambient
air quality monitoring was carried out at 8 locations during December,
2008–February, 2009 and submitted data indicated the average value of SPM
(119.48–327.19 ug/m3), RSPM (46–101.91 ug/m3), SO2 (9.99-26.57
ug/m3) and NOx (9.13–18.62 ug/m3). The
submitted data indicated the incremental value of SPM (26.388 µg/m3),
NOx (26.388 µg/m3) and SO2 (17.592 µg/m3)
which are within the permissible limit except RSPM.
ESPs with fabric filters and cyclones will be
provided to AFBC boiler and WHRB to control particulate emissions
within 100 mg/m3 but committee asked to control particulate
emissions within 50 mg/m3. Flue gases from furnace will be passed
through ESP and dust collectors for dust control. Dust extraction system will be installed in raw material handling
area and dust suppression system in material yard will also be provided. Bag filters will be provided to
Induction Furnace. Fume extraction system attached with multi-cyclone air
pollution control system or bag filter will be installed at product house,
intermediate bin, cooler discharge circuit, stock house, coal circuit and coal
injector area to curb spreading of dust. Arrangements for water spraying at all
the dusty places in the premises and during loading, unloading process. In
billets plant, fume extraction system with appropriate air pollution control
device will be installed to control the emissions from the process and fugitive
emissions at furnace. All de-dusting unit will be connected to stack height of
30 m.
Total water requirement (400 KLD) will be
met from bore well instead of bore well / river proposed earlier
and an application seeking permission is submitted to District level Ground
Water Resources Development Authority. Effluent from the plant and Domestic
effluent after treatment in septic tank will be recycled. No industrial
effluent will be generated. Fly ash will
be used for brick manufacturing. Surface water quality results reveal high BOD
level (86.23 mg/l), oil and grease and presence of coliform. DO level of river
is not monitored. Rain water harvesting
structure will be constructed.
Coal char will be used for power
generation. Iron ore and Coke fines will be sold to pellet manufacturing
company. Induction furnace slag and
dust from Pollution Control System will be used for land filling.
Green
belt will be developed in 5 acres
(33%). Low noise generating
equipments with vibration isolators will be installed. Ear muffs/ear plugs will
be provided to workers in noise prone areas. Acoustic enclosures will be
provided to DG sets. Regular lubrication and maintenance will be done to reduce
noise generation. Power requirement (25 MW reduced to 7.5 MW) will be met
from Jharkhand State Electricity Board.DG set (2 x 500 KVA). Fuel oil will be used as fuel for start-up of
kilns.
Public
hearing/Public consultation meeting was conducted by the Jharkhand State Pollution Control Board
on 30th August, 2009.
The main issues raised in the public
hearing meeting included water supply arrangement, employment, waste
management, air pollution etc. and have been satisfactorily included in the
EIA/EMP.
After detailed
deliberations, the Committee has recommended the proposal for environmental
clearance subject to stipulation of following specific conditions alongwith
other environmental conditions :
1.
On-line ambient air quality
monitoring and continuous stack monitoring facilities for all the stacks should
be provided and sufficient air pollution control devices viz. Electrostatic
precipitator (ESP), cyclones, bag filters etc. should be provided to keep the
emission levels below 50 mg/Nm3 by installing energy efficient
technology.
3.
Gaseous emission levels including secondary fugitive emissions
from all the sources should be controlled within the latest permissible limits
issued by the Ministry Ministry vide
G.S.R. 414(E) dated 30th May, 2008 and regularly monitored.
Guidelines / Code of Practice issued by the CPCB should be followed.
4.
Hot gases from DRI kiln should be passed
through Dust Settling Chamber (DSC) to remove coarse solids and After Burning
Chamber (ABC) to burn CO completely and used in waste heat recovery boiler
(WHRB). The gas then should be cleaned
in ESP before leaving out into the atmosphere through ID fan and stack.
5.
Prior ‘Permission’ for the drawl of 400 m3/day ground water from
the SGWB/CGWA should be obtained.
7.
The
water consumption should not exceed as per the standard prescribed for the
steel plants.
8.
All
the char from DRI plant should
be utilized in AFBC boiler of power plant and no char should be disposed off
anywhere else. AFBC boiler should be installed simultaneously alongwith the DRI
plant to ensure full utilization of char from the beginning. All the SMS slag should be properly utilized.
9. Proper utilization of fly ash should be ensured as per Fly Ash
Notification, 1999 and subsequent amendment in 2003 and 2010. All the fly ash
should be provided to cement and brick manufacturers for further utilization
and ‘Memorandum of Understanding’ should be submitted to the Ministry’s
Regional Office at Bhuvaneswar
10.
As proposed, green belt should be developed in 33 % area.
11. All the
recommendations made in the Charter on Corporate Responsibility for Environment
Protection (CREP) for the Steel
Plants should be implemented.
12.
Prior
permission from the State Forest
Department should be taken regarding likely impact of the expansion of
the proposed steel plant on the reserve forests. Measures should be taken to
prevent impact of particulate emissions / fugitive emissions, if any from the proposed
plant on the surrounding reserve forests viz.
Barkagaon & Jorakath RFs located within 10 km radius of the project.
Further, Conservation Plan for
the conservation of wild fauna in consultation with the State Forest Department
should be prepared and implemented.
13. All
the commitments made to the public during the Public Hearing / Public
Consultation meeting held on 30th August, 2009 should be
satisfactorily implemented and a
separate budget for implementing the same should be allocated and information
submitted to the Ministry’s Regional Office at Bhuvaneswar.
14.
At least 5 % of the total cost of the
project should be earmarked towards the corporate social responsibility and
item-wise details alongwith time bound action plan should be prepared and submitted to the Ministry’s Regional Office at Bhuvaneswar. Implementation of such program should
be ensured accordingly in a time bound
manner.
4.3
Sponge Iron (60,000 TPA), Pig Iron Plant
(36,000 TPA and Captive Power Plant (8 MW) at Village Bhumri (Juri), P. O.
Hata, District East Singhbum, Jharkhand by M/s Shah Sponge and Power Ltd. (EC)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Draft Terms
of References (TORs) awarded during the
76th Meeting of the Expert Appraisal Committee (Industry) held
during 26th-28th, 2009 for preparation of
EIA/EMP. All the primary metallurgical
industries are kept under S. N. 3 (a) of EIA Notification, 2006 and will be
appraised at Central level.
Additionally, PAs informed to the Committee that M/s Shah Sponge & Power Pvt. Ltd.
proposed to set up Steel Plant [Sponge
Iron (60,000 TPA) and Pig Iron (36,000 TPA) and Captive Power Plant (8 MW)]
at Bhumri, Singhbhum East,
Jharkhand. PAs also confirmed that critically/severely polluted area from the
project site is about 18 km. Total land
required for the plant is 33 Acres.
Total cost of project is enhanced from
Rs. 46.14 Crores to Rs. 80.17 Crores. Dholadih P.F., Morchgora Kudada P.F., Nundup P.F., Jojodih P.F., and
Tiring P.F. are situated within 15 Km periphery of the plant. Gara River
(3.5 Km, SE) and Bhangabanga nadi (7 Km, NW) are located. Orissa state boundary
is also within 15 Km periphery of the plant. The products and production
capacity of the plant will be Sponge Iron (60,000 TPA) and Pig Iron
(36,000TPA). Capacity of captive power plant [ WHRB (4 MW) and AFBC(4 MW)] will
be 8 MW.
The
coal based rotary kiln-DRI process
will be used for production of sponge iron and Mini blast furnace technology
will be used for production of Pig iron. Iron ore (96,000TPA), Non-coking coal
(78,000 TPA) and Dolomite/Limestone will be required as raw materials for
Sponge Iron plant. Iron ore, coke, Dolomite, Limestone, Dolomite, Manganese and
Quartzite will be required as raw materials for Pig iron (Blast Furnace).
Ambient
air quality monitoring was carried out at 8 locations during March – May, 2008
and submitted data indicated the levels of SPM (120.99–209.19 ug/m3),
RSPM (41.78–90.14 ug/m3), SO2 (10.86-32.87 ug/m3)
and NOx (10.60–31.67 ug/m3). The submitted data indicated
the incremental SPM (0.539 µg/m3), SO2 (0.3899
µg/m3) and NOX (0.35274 µg/m3), which
are within the permissible limit.
The sponge iron and pig iron manufacturing
processes are mainly air polluting in nature. The dust emissions will be
generated from the rotary kiln stack and will be controlled by installing
Electrostatic Precipitator (ESP) with stack height (40 m) to keep the particulate
emission below 50 mg/Nm3.
Fume extraction system attached with multcyclone air pollution control system
or bag filter (house) system will be provided to Product house, Intermediate
Bin, Cooler Discharge Circuit, Stock House, Coal Circuit, Coal Injector Area to
curb the spreading of dust into atmosphere. Emissions from the mini blast furnace will be controlled
by providing dust catcher, cyclone separator and 6 nos. of bag filters. The
clean gas from the bag filters will be used as fuel in the BF stoves. Water
sprinkling will be done in loading/stocking area.
Total
ground water requirement will be 1,020
m3/day and permission
for drawl of 3600 m3/day has been obtained from Central
Ground Water Authority, Ministry of Water Resources vide letter no.
SSPL/GW/01/08-09 dated 8th November 2008. Ground water will be
required for the cooling and domestic purposes. No industrial waste water will
be generated. Surface water quality monitoring data revealed high BOD
(71.57–122.59 mg/l) and presence of coliform (96.95–125.53). Rain water
harvesting structure will be installed.
Dolochar will be burnt in AFBC boiler for power generation as
mixed fuel. Fly Ash will be used
as fly ash brick or cement plants. Dust
from WHRB will be sent to landfill. Dust from bag filter will be used for land filling and partly in
power plant. Accretions will be
used for road making. Fly ash
from AFBC boiler will be used in cement
plant. Bottom ash from power plant will be used as coarse aggregate for
fly ash brick/ for land filling. Slag
generated from the pig iron plant will be granulated and sold to cement plants.
Green belt will be developed in 11.20 acres out of
33.0 acres. Power requirement from JSEB for the proposed unit will be 1400
KVA. DG sets (250 KVA) will be installed for power backup. The power
requirement will be 1750 KVA for sponge iron plant and 500 KVA for pig iron
plant. DG sets (2x750 KVA and 500 KVA) will be installed for emergency
purposes. LDO/HSD will be required for preheating of stoves and DG sets.
Quantities are not given.
The
Committee deliberated upon the issues raised during the Public Hearing / Public
Consultation meeting conducted by the Jharkhand
Pollution Control Board on 14th
March, 2009. The main issues raised in the public hearing were water pollution,
air pollution control measures, dust suppression of road by water sprinkling,
Control of noise pollution, plantation, social improvement etc.
After detailed
deliberations, the Committee has recommended the proposal for environmental
clearance subject to stipulation of following specific conditions alongwith
other environmental conditions :
1.
Electrostatic precipitator (ESP),
dust catcher, cyclone separators, bag
filters etc. should be provided to keep the emission levels below 50
mg/Nm3 by installing energy efficient technology.
3.
Secondary fugitive emissions from all the sources should be
controlled within the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008 and regularly monitored. Guidelines/Code of Practice issued by the
CPCB should be followed.
4.
Hot
gases from DRI kiln should be passed through Dust Settling Chamber (DSC) to
remove coarse solids and After Burning Chamber (ABC) to burn CO completely and
used in waste heat recovery boiler (WHRB). The gas then should be cleaned in
ESP before leaving out into the atmosphere through ID fan and stack.
5.
Total ground water requirement
should not exceed 1,020 m3/day
although permission for the
drawl of 3,600 m3/day ground water is obtained from Central
Ground Water Authority, Ministry of Water Resources vide letter no.
SSPL/GW/01/08-09 dated 8th November 2008.
7.
‘Zero’ effluent discharge should
be strictly followed and no wastewater should be discharged outside the
premises.
8.
The water consumption should not
exceed as per prescribed standards for the steel plants.
9.
All the char from DRI plant should be utilized in AFBC boiler of power
plant and no char should be disposed off anywhere else. AFBC boiler should be
installed simultaneously alongwith the DRI plant to ensure full utilization of
char from the beginning. All the blast furnace (BF) slag should be
granulated and provided to cement manufacturers for further utilization. Accretions should also be properly
utilized.
10.
Proper utilization of fly ash should be ensured as per Fly Ash
Notification, 1999 and subsequent amendment in 2003 and 2010. All the fly ash
should be provided to cement and brick manufacturers for further utilization
and ‘Memorandum of Understanding’ should be submitted to the Ministry’s
Regional Office at Bhuvaneswar.
11.
All the recommendations made in
the Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Plants should be
implemented.
12.
Prior permission from the State Forest Department should be
taken regarding likely impact of the expansion of the proposed steel plant on
the reserve forests. Measures should be taken to prevent impact of particulate
emissions / fugitive emissions, if any from the proposed plant on the
surrounding reserve forests viz. Dholadih
P.F., Morchgora Kudada P.F., Nundup P.F., Jojodih P.F., and Tiring P.F. located
within 10 km radius of the project. Further, Conservation Plan for the conservation of wild fauna in
consultation with the State Forest Department should be prepared and
implemented.
13.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 14th March, 2009 should be
satisfactorily implemented and a
separate budget for implementing the same should be allocated and information
submitted to the Ministry’s Regional Office at Bhuvaneswar..
14.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhuvaneswar. Implementation of such program should be ensured accordingly in
a time bound manner.
4.4
Ferro Alloy Plant
(1x9 MVA SAF) at Survey Nos. 104-108, 267 and Dag No. 730, 842, 845, 857,
859-879, 881, 883-917, 921, 923, 925-933, 938, 939, 967, 969, 970, 972, 1241,
1242, 1245, Mouza Basdebpur (North), P.S. Barjora, District Bankura, West
Bengal by M/s Metsil Exports Private
Limited (EC)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Draft Terms
of References (TORs) awarded during the
1st Meeting of the Expert Appraisal Committee (Industry) held during
20-21st August, 2009 for preparation of EIA/EMP. All the ferro alloy plants have been kept at
S.N. 3(a) under primary metallurgical industry under category ‘A’ and appraised
at Central level.
Additionally, PAs informed to the Committee that M/s
Metsil Exports Private Limited have proposed to set up a Ferro Alloy Plant (1x9 MVA SAF) at Survey
Nos. 104-108, 267 and Dag No. 730, 842, 845, 857, 859-879, 881, 883-917, 921, 923, 925-933, 938, 939, 967, 969, 970, 972, 1241, 1242, 1245, Mouza
Basdebpur (North), P.S. Barjora, District Bankura, West Bengal. Total land acquired is 15 acres. Out of 15 acres, 13.78 acres of land is acquired. PAs clarified that Durgapur critically
polluted area is about 16 km and not covered under critically/severely polluted
area. Permission
from the Gram Sabha Panchyat is obtained vide letter dated 16th
July, 2009. No R & R is involved. No
national park/wild life sanctuary/reserve forest is located within 10 km radius
of the proposed project site. River Damodar flows at a distance of 5 km from
the proposed site. Total cost of the proposed expansion is Rs. 1721.00
Lakhs. Rs. 0.80 Crores and Rs. 0.10
Crores will be earmarked towards total capital cost and recurring cost/annum
for environmental pollution control measures. Following are the details of
facilities to be installed and products to be manufactured:
S. N. |
Facility |
Capacity |
Product |
Production capacity |
1 |
Submerged Arc Furnace |
1x9 MVA |
Ferro Manganese |
22,600 TPA |
Silico Manganese |
17,400 TPA |
|||
Ferro Silicon |
7,600 TPA |
Submerged arc furnace (SAF) will be
used for manufacture of ferro alloys. The molten metal and slag will be tapped
at regular time intervals into a ladle or onto cast iron pans. The slag will be
overflowed to another ladle or in casting pans.
Manganese ore (89,560 TPA), coke breeze (25,400 TPA), quartz (25,086
TPA), iron scrap (2,660 TPA), charcoal (9,500 TPA) and dolomite (4,785 TPA)
will be used as basic raw materials for Ferro alloy production.
Ambient air quality monitoring was carried out at 8
locations during October, 2009–December, 2009 and submitted data indicated the
average value of SPM (121–228 ug/m3), RSPM (32–3 ug/m3),
SO2 (4-12 ug/m3) and NOx (19–46 ug/m3). The
submitted data indicated the incremental value of SPM (12 µg/m3)
which are within the permissible limit. Cyclone-cum-bag filters will be provided to SAF. Dry fog dust suppression system will
be provided at crushers, screens, transfer points of raw material handling
yard, loading and unloading points to control fugitive emissions.
Total water requirement is
reduced from 40 KLD to 20 KLD and supplied
by Barjora Panchayat Samity instead of surface water/bore well earlier
proposed. Bag filter dust will be
recycled in the process. During presentation, PAs have informed that plant will
be based on zero discharge concept. Rain
water harvesting structure will be constructed.
Ferro-Manganese slag will be utilized in Silico-Manganese production. Silico-Manganese slag will be utilized in land/area/ road development. Bag filter dust will be
recycled in the process.
Green
belt will be developed in 4.9 acres,
out of total plant area of 15 acres. Acoustic enclosures will be
provided to noise generating equipment. Ear plugs/ear muffs will be provided to
personnel working in high noise prone areas. Total power requirement (9.3 MVA) will be met from West Bengal
State Electricity Distribution Company Limited (WBSEDCL). DG set (1x100 kVA) will be installed to meet the
emergency power requirement. Diesel (24 LPH) will be used as fuel in DG sets.
The
Committee deliberated upon the issues raised during the Public Hearing / Public
Consultation meeting conducted by the West
Bengal Pollution Control Board on
30th November, 2009. The main issues raised in the public
hearing meeting included employment pollution control measures, agriculture
development, CSR etc.
After
detailed deliberations, the Committee recommended the project for environmental
clearance subject to following specific conditions :
14.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 30th
Nov ember, 2009 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bhuvaneswar.
15.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhuvaneswar. Implementation of such program should be ensured accordingly in
a time bound manner.
4.5
Ferro Alloy Plant
(1x9 MVA SAF) at Survey Nos. 104-108, 267 and Dag No. 857, 932-934, 936-956,
961, 964-970, 1033-1066-1076, 1077, 1080-1086, 1172, 1173, Mouza Basudebpur
(North), P.S. Barjora, District Bankura, West Bengal by M/s Shree Ambey Ispat Pvt Ltd. (EC)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Draft Terms
of References (TORs) awarded during the
1st Meeting of the Expert Appraisal Committee (Industry) held during
20th-21st July, 2009 for preparation of EIA/EMP. All the ferro alloy plants have been kept at
S.N. 3(a) under primary metallurgical industry under category ‘A’ and appraised
at Central level.
Additionally, PAs informed to the Committee that M/s Shree
Ambey Ispat Pvt Ltd. have
proposed to set up a Ferro Alloy Plant
(1x9 MVA SAF) at Survey Nos. 104-108, 267 and Dag No. 857, 932-934,
936-956, 961, 964-970, 1033-1066-1076, 1077, 1080-1086, 1172, 1173, Mouza Basudebpur (North), P.S. Barjora,
District Bankura, West Bengal. Total land acquired is 15 acres. No R & R is involved. No national
park/wild life sanctuary/reserve forest is located within 10 km radius of the
proposed project site. During
presentation, PAs confirmed that Durgapur critically polluted area is 16 km
from the proposed project site and not covered under critically/severely
polluted area. River Damodar flows at a distance of 5 km from the proposed
site. Total cost of the proposed expansion is Rs. 1,721.00 Lakhs. Rs. 0.80
Crores and Rs. 0.10 Crores will be earmarked towards total capital cost
and recurring cost/annum for environmental pollution control measures.
Following are the details of facilities to be installed and the corresponding
products:
S.N. |
Facility |
Capacity |
Product |
Production capacity |
1 |
Submerged Arc Furnace |
1x9 MVA |
Ferro Manganese |
22,600 TPA |
Silico Manganese |
17,400 TPA |
|||
Ferro Silicon |
7,600 TPA |
Submerged
arc furnace (SAF) will be used for
manufacture of ferro alloys. The molten metal and slag will be tapped at
regular time intervals into a ladle or onto cast iron pans. The slag will be
overflowed to another ladle or in casting pans. Manganese ore, Coke
breeze, Quartz, Iron scrap, Charcoal and Dolomite will be used as basic raw
materials for Ferro alloy production.
Ambient air quality monitoring was
carried out at 8 locations during October, 2009–December, 2009 and submitted
data indicated the average value of SPM (121–228 ug/m3), RSPM (32–73
ug/m3), SO2 (4-12 ug/m3) and NOx (19–46 ug/m3).
The submitted data indicated the incremental value of SPM (12 µg/m3),
which is within the permissible limit. However, incremental value for RSPM, SO2
and NOX is not estimated.
Cyclone-cum-bag filters will be provided
to SAF. Dry fog dust suppression system will be provided at crushers, screens,
transfer points of raw material handling yard, loading and unloading
points to control fugitive emissions.
Total water requirement is reduced
from 40 KLD to 20 KLD and will
be supplied by Barjora Panchayat Samity instead of surface water / bore well
earlier proposed. Domestic wastewater
will be used for dust suppression and greenbelt development.
Bag
filter dust will be recycled in the
process. Ferro Manganese slag
will be utilized in Silico-Manganese production. Silico-Manganese slag will be utilized in land/area/road
development.
Green
belt will be developed in 4.9 acres,
out of total plant area of 15 acres. Acoustic enclosures will be
provided to noise generating equipment. Ear plugs/ear muffs will be provided to
personnel working in high noise prone areas. Total power requirement of 9.3 MVA will be met from West Bengal
State Electricity Distribution Company Limited (WBSEDCL). DG set (1x100 kVA) will be installed to meet the
emergency power requirement. Diesel (24 LPH) will be used as fuel in DG sets.
PAs have informed during presentation that total amount of Rs. 17.20 Lakhs is
earmarked for CSR.
The
Committee deliberated upon the issues raised during the Public Hearing / Public
Consultation meeting conducted by the West
Bengal Pollution Control Board on
30th November, 2009. The main issues raised in the public
hearing meeting were local development, pollution control, ground water
depletion etc.
After
detailed deliberations, the Committee recommended the project for environmental
clearance subject to following specific conditions :
14.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 30th
Nov ember, 2009 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bhuvaneswar.
15.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details alongwith time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhuvaneswar. Implementation of such program should be ensured accordingly in
a time bound manner.
4.6
Steel Plant (Induction Furnace
(2x12 T), Steel Melting Shop with Continuous Casting Machine and Re-rolling
Mill (80,000 TPA) at Plot No. 17, Village Chittornatham, Panchayat
Eguvarpalayam, Taluk Gummidipoondi, District Thiruvallur, Tamil Nadu by M/s
Shree Sai Hanuman Smelters (P) Ltd (TORs)
Project authorities didn’t attend the meeting and,
therefore, it was decided that proposal should be considered afresh whenever
requested by the PAs.
4.7
Steel Plant (Sponge Iron 96,000
TPA; Billets 44,800 TPA, Rolled Products (42,240 TPA) alongwith Captive Power
Plant (12 MW) at Plot Nos. 436, 519, 520, Village Marhand, P.S. Katkamsandi,
Hazaribagh, Jharkhand by M/s Narsimha Iron and Steel Pvt. Ltd. (TORs)
The project authorities and their consultant gave a detailed presentation on
the salient features of the project and proposed environmental protection
measures to be undertaken alongwith the draft
Term of References for the preparation of EIA/EMP. All the Steel Plants
and Thermal Power Plants are listed at S.N. 3(a) under Primary Metallurgical
Industries and 1(d) respectively under Category ‘A’ and appraised at the
Central level.
M/s Narsimha Iron and
Steel Pvt. Ltd. have proposed for the Steel Plant (Sponge Iron 96,000 TPA;
Billets 44,800 TPA, Rolled Products (42,240 TPA) alongwith Captive Power Plant
(12 MW) at Plot Nos. 436, 519, 520,
Village Marhand, P.S. Katkamsandi, Hazaribagh, Jharkhand. PAs have confirmed that proposed project is
not located within 10 km of critically polluted area and Ramgarh is about 40-45
km. No national park/wildlife sanctuary
is located within 10 km. Total project area acquired is 22.35 acres. Nearest town
is Hazaribagh at 7 km. No litigation or
court case is in pending against the project and/or land. Barkagaon
RF (9 Km, W), Jorakath RF (9 km, S), Gurua PF (4 km, E), Gali R.F. (9 km, S)
are located within 10 km radius of the project.
Kunur Nadi is at 3 km. Total cost
of the project is Rs. 116.35
Crores. Rs 3.653 Crores and Rs. 0.83 Crores instead of Rs 10.10 Crores and Rs. 3.20 Crores
are earmarked towards capital cost and recurring cost/annum for environment
pollution control measures. Following
will be manufactured:
S.N. |
Products |
Capacity (TPA) |
1. |
Sponge Iron |
96,000 |
2. |
Billets |
44,800 |
3. |
Rolled Products |
42,240 |
4. |
Captive Power Plant |
12 MW |
|
WHRB |
6 MW |
|
AFBC |
6 MW |
Following facilities will be
installed:
S.N. |
Products |
Capacity |
1. |
Sponge Iron |
3x100 TPD |
2. |
Steel Melting |
2x7 MT |
3. |
Power Plant |
12 MW |
4. |
Rolling Mill |
12 TPH (132 TPD) |
Iron ore, coal, dolomite for sponge iron plant, sponge iron,
scrap, ferro alloy, billets for rolling mills, char, coal & fines for power
plant will be used as raw materials.
Sponge Iron will be
manufactured in coal based Direct Reduction (DR) kilns. Billets
will be manufactured by melting in Induction furnace and casting in continuous
casting machine. Rolled products
will be manufactured in reheating furnace land coal fired rolling mill. Waste heat recovery boiler (WHRB) and AFBC
boiler will be installed.
Electrostatic precipitator (ESP) will be provided to DRI kiln and AFBC boiler to control
particulate emissions within 50 mg/Nm3.
Bag filters will be installed to
control emissions from induction
furnace and rolling mill. Flue gases for DRI plant will be utilized in
Waste heat recovery boiler (WHRB) and passed through ESP and then into
atmosphere through ID fans and chimney.
Hot gases for DRI plant will pass through dust settling chamber (DSC) and after burning chamber (ABC), WHRB and
stack. Fume extraction system with ID
fan will be provided to IF. Dust suppression (chemical and dry fog type)
will be provided to control emissions.
Bag filters will be provided to material handling areas, coal handling
areas, crusher, stock house, cooler discharge area, screening area etc.
Total ground water requirement from bore
wells will be 1,380 m3/day.
Closed loop system will be adopted so that no effluent is discharged from the
proposed plants. Only make up water will be fed into the plant. Acidic and
alkaline effluent from cation and anion units of DM Plant will be neutralized
in neutralization tank. Boiler blow down will be neutralized in the
neutralization tank before mixing with other effluent streams. After
neutralization, these two effluents will be mixed with cooling tower blow down
in a guard pond. The treated effluent will be used for ash conditioning, dust
suppression and green belt development. Service water will be passed through
oil separator to remove
oil content in the effluent. Domestic effluent will be treated in septic
tank followed by soak pit. No
effluent will be discharged outside the premises and ‘Zero’ discharge will be
adopted. Rain water harvesting structure will be constructed.
Char from DRI process will be used in AFBC
boiler as fuel. Dust from air pollution control devices (APCD) will be partly used in the plant and partly for land and/or
abandoned mines filling slag from
Induction Furnace will be used for road making and land filling. Bottom
ash will be used for low land filling. Fly ash from AFBC power
plant will be sold to fly ash brick manufacturers and cement grinding
units. Waste oil and used batteries will be sold to authorized
recyclers/re-processors.
Out of 22.35 acres, green belt will be developed in 8 acres.
Power requirement will be 11 MW and sourced from captive power plant (12
MW). DG sets (2x1000 KVA) will be
installed.
After deliberating on the facts presented before the Expert Appraisal
Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1.
Proposal should be
submitted to the Ministry for environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
2.
A map indicating
distance between project site and critically/severely polluted area and a
certificate from the CPCB/SPCB certifying the same.
3.
A site location map
on Indian
map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e.
circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
4.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image data having 1m-5m spatial
resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km
radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
5.
Topography of the area should be
given clearly indicating whether the site requires any filling. If so, details
of filling, quantity of fill material required, its source, transportation etc.
should be given.
6.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover,
reserved forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
7.
Project
site layout plan showing raw materials, fly ash and other storage plans, bore
well or water storage, aquifers (within 1 km.) dumping,
waste disposal, green areas, water bodies, rivers/drainage passing through the project site should be
included.
8.
Coordinates of the plant site as
well as ash pond with topo sheet co-ordinates of the plant site as well as ash
pond with topo sheet should also be included.
9.
Details
and classification of total land (identified and acquired) should be included.
10. Rehabilitation & Resettlement (R
& R) should be as per policy of the State Govt. and a detailed action plan should be
included.
11. Permission from the tribals, if tribal land has also to be acquired
alongwith details of the compensation plan.
12. Permission and approval for the use of forest land, if any, and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests viz. Barkagaon RF (9 Km, W),
Jorakath RF (9 km, S), Gurua PF (4 km, E), Gali R.F. (9 km, S) should be
included.
13. A list of industries
containing name and type in 25 km radius should be incorporated.
14. Residential colony should be located in upwind direction.
15. List of
raw material required, analysis of all
the raw materials and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
16. Petrological
and Chemical analysis and other
chemical properties of raw materials used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be
included..
17.
Petrography, grain size analysis and Major element analysis of raw material
and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
18. If the rocks, ores, raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
19. Action plan for excavation and muck disposal during construction phase.
20. Studies for fly ash, muck, slurry, sludge material disposal and solid
waste generated, if the raw materials used has trace elements and a management plan should also be
included.
21. Manufacturing
process details for all the plants
should be included.
22. Mass
balance for the raw material and
products should be included.
23. Energy
balance data for all the components of steel
plant including proposed power plant
should be incorporated.
24. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and
direction and rainfall should be collected.
25. Data generated in the last three
years i.e. air,
water, raw material properties and analysis (major, trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
26.
One season site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall and AAQ data (except monsoon) should be
collected. The monitoring stations should take into account the pre-dominant
wind direction, population zone and sensitive receptors including reserved
forests.
27. Ambient
air quality at 8 locations within the
study area of 10 km., aerial coverage from project site with one AAQMS in
downwind direction should be carried out.
28. The suspended particulate matter present in the
ambient air must be analyzed for the presence of poly-aromatic hydrocarbons
(PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating
of RSPM data.
29. Determination of atmospheric inversion level at the
project site and assessment of ground level concentration of pollutants from
the stack emission based on site-specific meteorological features.
30. Air quality modelling
for steel plant for specific pollutants
needs to be done. APCS for the control
of emissions from the kiln and WHRB should also be included to control
emissions within 50 mg/Nm3.
31. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
32. Ambient air quality monitoring
modeling alongwith cumulative impact
should be included for the day (24 hrs) for maximum GLC alongwith following :
i)
Emissions (g/second) with and without the air pollution control
measures
ii)
Meteorological inputs (wind speed, m/s), wind direction,
ambient air temperature, cloud cover, relative humidity & mixing height) on
hourly basis
iii)
Model
input options for terrain, plume rise, deposition etc.
iv)
Print-out
of model input and output on hourly and daily average basis
v)
A
graph of daily averaged concentration (MGLC scenario) with downwind distance at
every 500 m interval covering the exact location of GLC.
vi)
Details
of air pollution control methods used with percentage efficiency that are used
for emission rate estimation with respect to each pollutant
vii)
Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii)
No.
I-VII are to be repeated for fugitive emissions and any other source type
relevant and used for industry
ix)
Graphs
of monthly average daily concentration with down-wind distance
x)
Specify
when and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi)
Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
33. A plan for the utilization of waste/fuel gases in the WHRB for
generating power have to be set out.
34. Impact of the transport
of the raw materials and end products
on the surrounding environment should be assessed and provided. The alternate
method of raw material and end product transportation should also be studied
and details included.
35. One
season data for gaseous emissions other
than monsoon season is necessary.
36. An action plan to control and monitor secondary
fugitive emissions from all the sources
as per the latest permissible limits issued by the Ministry vide G.S.R. 414(E)
dated 30th May, 2008.
37. Presence of aquifer(s)
within 1 km of the project boundaries
and management plan for recharging the aquifer should be included.
38. Source of surface/ground water
level, site (GPS), cation, anion (Ion
Chromatograph), metal trace element (as above) chemical analysis for water to
be used. If surface water is used from river, rainfall, discharge rate,
quantity, drainage and distance from project site should also be included.
Information regarding surface hydrology and water regime should be included.
39. Ground water analysis with bore well
data, litho-logs,
drawdown and recovery tests to quantify the area and volume of aquifer and its management.
40. Ground
water modelling showing the pathways of
the pollutants should be included
41.
Column leachate study for all
types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
42.
Action plan for rainwater
harvesting measures at plant site should be submitted to harvest rainwater from
the roof tops and storm water drains to recharge the ground water and also to
use for the various activities at the project site to conserve fresh water and
reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water
harvesting plan for the project is necessary, if source of water is bore well.
43. Permission for the drawl of 1,380 m3/day
ground water from bore well from the
SGWB/CGWA or concerned authority and water balance data including quantity of
effluent generated, recycled and reused and discharged is to be provided.
Methods adopted/to be adopted for the water conservation should be included.
44. A note on the impact of
drawl of water on the nearby River
during lean season.
45. Surface
water quality of nearby River (60 m
upstream and downstream) and other surface drains at eight locations must be
ascertained.
46. If the site is within 10 km
radius of any major river, Flood Hazard
Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the peak
and lean river discharge as well as flood occurrence frequency.
47. A note on treatment of wastewater
from different plants, recycle and
reuse for different purposes should be included.
48. Provision of traps and treatment plants are to be made, if water is getting mixed with oil, grease and cleaning agents.
49. If the water
is mixed with solid particulates,
proposal for sediment pond before further transport should be included. The
sediment pond capacity should be 100 times the transport capacity.
50. Wastewater
characteristics (heavy metals, anions
and cations, trace metals, PAH) from washed / beneficiated plants / washery or
any other source should be included.
51. The pathways
for pollution via seepages,
evaporation, residual remains are to be studied for surface water (drainage,
rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans.
52. Ground
water monitoring minimum at 8 locations
and near solid waste dump zone, Geological features and Geo-hydrological status
of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
53. Geotechnical
data by a bore hole of upto 40 mts. in
every One sq. km area such as ground water level, SPTN values, soil fineness,
geology, shear wave velocity etc. for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk Management in the area.
54. Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly slag from all
the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
55. Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
56. A note on the treatment, storage and disposal of all
type of slag should be included.
Identification and details of land to be used for SMS slag disposal should be included. Details of
secured land fill as per CPCB guidelines should also be included.
57. End
use of solid waste and its composition
should be covered. Toxic metal content
in the waste material and its composition should also be incorporated
particularly of slag.
58. All stock piles will have to be on top of a stable
liner to avoid leaching of materials to ground water.
59. Acton plan for the green
belt development plan in 33 % area i.e.
land with not less than 1,500 trees per ha. giving details of species, width of
plantation, planning schedule etc. should
be included. The green belt should be around the project boundary and a scheme
for greening of the travelling roads should also be incorporated. All rooftops/terraces
should have some green cover.
60. Detailed description of the flora and
fauna (terrestrial and aquatic) should
be given with special reference to rare, endemic and endangered species.
61. At least 5 % of the total cost of the project should
be earmarked towards the corporate social responsibility and item-wise details
alongwith time bound action plan should be included. Socio-economic development activities need to be elaborated
upon.
62. Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
63. Occupational
health of the workers needs
elaboration. Health effects of other metals used and health hazard plans based
on monthly correlation of these metal related diseases and people affected and
mitigation plans; Arsenicosis Management Plan, if Arsenic is present in ore,
rock, coal, fly ash, water and action plan for protecting the workers against
hazardous chemicals such as Sulphuric acid, pesticides, solvents etc. should be
included
64. Occupational
health of the workers needs elaboration
including evaluation of noise, heat, illumination, dust, any other chemicals,
metals being suspected in environment and going into body of workers either
through inhalation, ingestion or through skin absorption and steps taken to
avoid musculo-skeletal disorders (MSD), backache, pain in minor and major
joints, fatigue etc. Occupational hazards specific
pre-placement and periodical monitoring and periodical monitoring should be
carried out. The detailed plan to carry out above mentioned activity should be
mentioned.
65.
Details regarding infrastructure
facilities such as sanitation, fuel, restroom etc. to be provided to the labour
force during construction as well as to the casual workers including truck
drivers during operation phase.
66.
Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure need to be constructed and the agency responsible for the same
with time frame.
67. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for environmental pollution control measures should be included.
68. Plan for the implementation of the recommendations
made for the steel plants in the CREP
guidelines must be prepared.
69. A note on identification and implementation of
Carbon Credit project should be included.
70. Public
hearing issues raised and commitments
made by the project proponent on the same should be included separately in
EIA/EMP Report in the form of tabular chart with financial budget for complying
with the commitments made.
71. Any litigation
pending against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof should also be included.
In addition to the above, information on the
following may also be incorporated in the EIA report.
1. Is the
project intended to have CDM-intent?
(i) If not, then why?
(ii) If yes, then
(a) Has PIN (Project Idea Note) {or PCN (Project
Concept Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(b) If not, then by when is that expected?
(c) Has PDD (Project Design Document) been prepared?
(d) What is the ‘Carbon intensity’ from your
electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
(e) Amount of CO2 in Tons/year expected to be
reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding
1(i) above, data on (d) & (e) above to be worked out and
reported.
The Expert Appraisal Committee
(Industry-1) decided that PAs may be communicated the above ‘TORs’ for the
preparation of EIA/EMP. As soon as the
draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in
Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted
by the PAs to the Jharkhand Pollution Control Board (JPCB) for
conducting public hearing as per EIA Notification, 2006. On finalization of
EIA/EMP prepared as per TORs addressing all concerns raised during public
hearing/consultation in EIA/EMP should be submitted to the MOEF for prior
environmental clearance.
4.8
Expansion
of Steel Plant by installing Sponge Iron Plant (60,000 TPA) alongwith Captive
Power Plant (8 MW; WHRB 4 MW & AFBC 4 MW) at Village Salarapentha, Post
Mahadeijoda, District Keonjhar, Orissa by M/s BRM Hi-Tech Steels (P) Ltd (TORs)
The project authorities and their
consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Steel Plant including Sponge Iron Plants (200 TPD
& above) are listed at S.N. 3(a) under Primary Metallurgy Industry under
Category ‘A’ and appraised at the Central level.
M/s BRM Hi-Tech Steels (P) Ltd. have proposed for the
expansion of Steel Plant by installing Sponge Iron Plant (60,000 TPA) alongwith
Captive Power Plant (8 MW; WHRB 4 MW & AFBC 4 MW) at Village Salarapentha,
Post Mahadeijoda, District Keonjhar, Orissa. Total project area available for
the existing plant is 33 acres which is adequate for the proposed expansion
also. Existing plant is located in 5.25 acres. PAs informed that 12 reserve forests are
located within 10 km. Total cost of the
project is Rs. 48.19 Crores. Rs.
2.20 Crores and Rs. 25.00 Lakhs/annum are earmarked towards central cost and
recurring cost/annum for environment pollution control measures. ‘Consent to Establish’ the existing plant is obtained for the
existing plant from Orissa Pollution Control Board vide letters dated 24th
April, 2006, 11th January, 2007 and 11th May, 2007. Following
are the details of existing and proposed facilities to be installed and
products to be manufactured:
Units |
Products |
Existing |
Proposed |
Total |
Iron Ore Crusher |
Calibrated Iron Ore |
85
TPH (1,44,000
TPA) |
- |
1,44,000
TPA |
DRI Plant |
Sponge Iron |
- |
2
x 100 TPD (60,000
TPA) |
2x100
TPD (60,000
TPD) |
SMS / Induction Furnace |
Liquid Steel / MS Ingots |
(4
T/1.8 MW) 14,
400 TPA |
- |
(4
T/1.8 MW) 14,
400 TPA |
Rolling Mill |
Rolled Products |
30,000
TPA |
- |
30,000
TPA |
Power Plant WHRB AFBC TG |
Power |
- |
2x10
TPH (4
MW) 1x20
TPH (4 MW) 1x8
MW |
8
MW |
Iron
ore for DRI making will be obtained from existing ore crusher. Non-coking coal, Si-Mn, coal fines, met coke,
scrap and dolomite will be used as raw materials. Waste char will be used in AFBC boiler.
Sponge
iron will be produced by reducing iron ore in the solid state at a temperature
of 900-10500C by using a reductant e.g. CO or H2. Char
(10,000 TPA) alongwith coal (13,500 TPA) will be utilized in AFBC boiler. Off gases from the DRI kiln will be used
in WHRB plant to generate power. Out of
60,000 TPA sponge iron produced, 13,100 TPA will be utilized in making steel
ingots in the existing SMS. The existing
rolling mill will use the steel ingots to produce 30,000 TPA TMT rods.
Ambient air quality data for SPM, SO2
NOx and RPM is collected at 12 locations but period of data collection is
not mentioned. The committee has asked PAs to collect base line data after the
award of TORs and didn’t accept data already collected. Hot gases from the DRI
kiln will pass through dust settling chamber (DSC) and after burning chamber
(ABC) and then to waste heat recovery boiler (WHRB) and then to electrostatic
precipitator (ESP) for cleaning. The clean gas will be released to the
atmosphere through stacks. Fume extraction system with bag filters will be
provided to Steel Making Shop (Induction furnace). Bag filters will be provided
to cooler discharge end, product processing areas, coal crushing and handling
areas and raw material handling areas like transfer points, junction houses
etc. to control particulate emissions. The fuel gas after passing through ESP
will be discharged through stacks of adequate height. Dry fog dust
suppression/water sprinkling system will be provided to raw material handling
and storage areas. Dust extraction
system will also be provided to control fugitive emissions.
Total ground
water requirement from bore wells after expansion will be 1,385 m3/day
including 70 m3/day for the existing plant. Cooling water will be completely
recycled. Effluent from cooling blow
down, boiler blow down soft water rejuvenation will be properly treated. Acidic
and alkaline effluent from cation and anion units of DM Plant will be
neutralized in neutralization tank. Boiler blow down will be neutralized
in the neutralization tank before mixing with other effluent streams.
After neutralization, these two effluents will be
mixed with cooling tower blow down in a Central Monitoring Basin. The treated
effluent will be used for ash moistening, dust suppression and green belt
development. Service water will be passed through oil separator to remove oil
content in the effluent. Domestic effluent will be treated in septic tank
followed by soak pit. No effluent will be discharged outside the premises
and ‘Zero’ discharge will be adopted.
Fly ash will be kept in ash mound and subsequently used
fly ash brick making. SMS slag will be
used for road making. Bottom ash will be used for low land filling and ash
brick manufacturing. Char alongwith coal fines will be used in AFBC boiler.
Accretion slag will be used for road making and for filling of low lying areas.
Scrap from SMS and rolling mill will be reused in SMS. Used oil will be sold to authorized
reprocessors.
Out of 33 acres, 11 acres (33%)
is allocated for the green belt development. Total power requirement (5.6 MW) will be met from captive generation
(8 MW). Char (10,000 TPA) and HSD (20 KLPA) will be used as fuel.
After deliberating on the facts presented before the
Expert Appraisal Committee (Industry), the committee recommended the proposal
for the preparation of EIA/EMP as per the following TORs:
1. Proposal should be submitted to the Ministry for
environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
2. A map indicating distance between project site and
critically/severely polluted area and a certificate from the CPCB/SPCB
certifying the same.
3. A site location map on Indian
map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e.
circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
4. Present land use should be prepared based on satellite
imagery. High-resolution satellite
image data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10 Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
5.
Topography of the area should be
given clearly indicating whether the site requires any filling. If so, details
of filling, quantity of fill material required, its source, transportation etc.
should be given.
6. Location of national parks / wildlife sanctuary /
reserve forests within 10 km. radius should specifically be mentioned. A map
showing landuse/landcover, reserved forests, wildlife sanctuaries,
national parks, tiger reserve etc in 10
km of the project site.
7. Project site layout plan showing raw materials, fly
ash and other storage plans, bore well or water storage, aquifers
(within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the
project site should be included.
8.
Coordinates of the plant site as
well as ash pond with topo sheet co-ordinates of the plant site as well as ash
pond with topo sheet should also be included.
9. Details and classification of total land (identified
and acquired) should be included.
10. Rehabilitation & Resettlement (R
& R) should be as per policy of the
State Govt. and a detailed action plan should be included.
11. Permission from the tribals, if tribal land has also
to be acquired alongwith details of the compensation plan.
12. Permission and approval
for the use of forest land, if any, and
recommendations of the State Forest Department regarding impact of proposed
expansion on the surrounding twelve (12) reserve forests, if applicable, should be included.
13. A list of industries containing name and type in 25 km radius
should be incorporated.
14. Residential colony should be located in upwind
direction.
15. List
of raw material required, analysis of
all the raw materials and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
16. Petrological
and Chemical analysis and other
chemical properties of raw materials used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be
included..
17.
Petrography, grain size analysis and Major element analysis of raw material
and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
18. If the rocks, ores, raw material has trace
elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
19. Action plan for excavation and muck disposal during
construction phase.
20. Studies for fly ash, muck, slurry, sludge material
disposal and solid waste generated, if the raw materials used has trace
elements and a management plan should
also be included.
21. Manufacturing
process details for all the plants
should be included.
22. Mass
balance for the raw material and
products should be included.
23. Energy
balance data for all the components of steel
plant including proposed power plant
should be incorporated.
24. Site-specific
micro-meteorological data
using temperature, relative humidity, hourly wind speed and direction and
rainfall should be collected.
25. Data on existing ambient air, stack emission, fugitive
emissions data; water requirement and water balance cycle; generation,
re-utilization and disposal of solid/ hazardous waste for the existing plant
and predicted increase in pollution load (GLCs) due to proposed expansion
should be incorporated.
26. All the environment clearances accorded by the
Ministry, Consent to Establish and Operate and point-wise compliance to the specific
and general conditions stipulated in
the environmental clearance and Consent to Establish and Operate for all the
existing plants.
27. Data generated in the last three years i.e. air,
water, raw material properties and analysis (major, trace and heavy metals),
ground water table, seismic history, flood hazard history etc.
28.
One season site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall and AAQ data (except monsoon and after the
award of TORs) should be collected. The monitoring stations should take into
account the pre-dominant wind direction, population zone and sensitive
receptors including reserved forests.
29. Ambient
air quality at 8 locations within the
study area of 10 km., aerial coverage from project site with one AAQMS in
downwind direction should be carried out.
30. The suspended particulate matter present in the
ambient air must be analyzed for the presence of poly-aromatic hydrocarbons
(PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and
incorporating of RSPM data.
31. Determination of atmospheric inversion level at the
project site and assessment of ground level concentration of pollutants from
the stack emission based on site-specific meteorological features.
32. Air quality modelling
for steel plant for specific pollutants
needs to be done. APCS for the control
of emissions from the kiln and WHRB should also be included to control
emissions within 50 mg/Nm3.
33. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
34. Ambient air quality monitoring
modeling alongwith cumulative impact
should be included for the day (24 hrs) for maximum GLC alongwith following :
i)
Emissions (g/second) with and without the air pollution control
measures
ii)
Meteorological inputs (wind speed, m/s), wind direction, ambient
air temperature, cloud cover, relative humidity & mixing height) on hourly
basis
iii)
Model input options for terrain, plume rise, deposition etc.
iv)
Print-out of model input and output on hourly and daily average
basis
v)
A graph of daily averaged concentration (MGLC scenario) with
downwind distance at every 500 m interval covering the exact location of GLC.
vi)
Details of air pollution control methods used with percentage
efficiency that are used for emission rate estimation with respect to each
pollutant
vii)
Applicable air quality standards as per LULC covered in the study
area and % contribution of the proposed plant to the applicable Air quality
standard. In case of expansion project, the contribution should be inclusive of
both existing and expanded capacity.
viii)
No. I-VII are to be repeated for fugitive emissions and any other
source type relevant and used for industry
ix)
Graphs of monthly average daily concentration with down-wind
distance
x)
Specify when and where the ambient air quality standards are
exceeded either due to the proposed plant alone or when the plant contribution
is added to the background air quality.
xi)
Fugitive dust protection or dust reduction technology for workers
within 30 m of the plant active areas.
35. A plan for the utilization
of waste/fuel gases in the WHRB for
generating power have to be set out.
36. Impact of the transport
of the raw materials and end products
on the surrounding environment should be assessed and provided. The alternate
method of raw material and end product transportation should also be studied
and details included.
37. One
season data for gaseous emissions other
than monsoon season is necessary.
38. An action plan to control and monitor secondary
fugitive emissions from all the sources
as per the latest permissible limits issued by the Ministry vide G.S.R. 414(E)
dated 30th May, 2008.
39. Presence of aquifer(s)
within 1 km of the project boundaries
and management plan for recharging the aquifer should be included.
40. Source of surface/ground water
level, site (GPS), cation, anion (Ion
Chromatograph), metal trace element (as above) chemical analysis for water to
be used. If surface water is used from river, rainfall, discharge rate, quantity,
drainage and distance from project site should also be included.
Information regarding surface hydrology and water regime should be included.
41. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume of aquifer and its management.
42. Ground
water modeling showing the pathways of
the pollutants should be included
43.
Column leachate study for all
types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
44.
Action plan for rainwater
harvesting measures at plant site should be submitted to harvest rainwater from
the roof tops and storm water drains to recharge the ground water and also to
use for the various activities at the project site to conserve fresh water and
reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water
harvesting plan for the project is necessary, if source of water is bore well.
45. Permission for the drawl of 1,385 m3/day
ground water from bore well from the
SGWB/CGWA or concerned authority and water balance data including quantity of
effluent generated, recycled and reused and discharged is to be provided.
Methods adopted/to be adopted for the water conservation should be included.
46. A note on the impact of
drawl of water on the nearby River
during lean season.
47. Surface
water quality of nearby River (60 m
upstream and downstream) and other surface drains at eight locations must be
ascertained.
48. If the site is within 10 km
radius of any major river, Flood Hazard
Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the peak
and lean river discharge as well as flood occurrence frequency.
49. A note on treatment of wastewater
from different plants, recycle and
reuse for different purposes should be included.
50. Provision of traps and treatment
plants are to be made, if water is
getting mixed with oil, grease and cleaning agents.
51. If the water is mixed with solid
particulates, proposal for sediment
pond before further transport should be included. The sediment pond capacity
should be 100 times the transport capacity.
52. Wastewater
characteristics (heavy metals, anions
and cations, trace metals, PAH) from washed / beneficiated plants / washery or
any other source should be included.
53. The pathways for pollution via seepages, evaporation, residual remains
are to be studied for surface water (drainage, rivers, ponds, lakes),
sub-surface and ground water with a monitoring and management plans.
54. Ground
water monitoring minimum at 8 locations
and near solid waste dump zone, Geological features and Geo-hydrological status
of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
55. Geotechnical
data by a bore hole of upto 40 mts. in
every One sq. km area such as ground water level, SPTN values, soil fineness,
geology, shear wave velocity etc. for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk Management in the area.
56. Action plan for solid/hazardous
waste generation, storage, utilization
and disposal particularly slag from all the sources, char and fly ash. Copies
of MOU regarding utilization of ash should also be included. Commitment that no char will be disposed off
anywhere bu used in AFBC boiler only.
57. Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
58. A note on the treatment, storage and disposal of all
type of slag should be included.
Identification and details of land to be used for SMS slag disposal should be included. Details of
secured land fill as per CPCB guidelines should also be included.
59. End
use of solid waste and its composition
should be covered. Toxic metal content
in the waste material and its composition should also be incorporated
particularly of slag.
60. All stock piles will have to be on top of a stable
liner to avoid leaching of materials to ground water.
61. Acton plan for the green
belt development plan in 33 % area i.e.
land with not less than 1,500 trees per ha. giving details of species, width of
plantation, planning schedule etc. should
be included. The green belt should be around the project boundary and a scheme
for greening of the travelling roads should also be incorporated. All
rooftops/terraces should have some green cover.
62. Detailed description of the flora and
fauna (terrestrial and aquatic) should
be given with special reference to rare, endemic and endangered species.
63. At least 5 % of the total cost of the project should
be earmarked towards the corporate social responsibility and item-wise details
alongwith time bound action plan should be included. Socio-economic development activities need to be elaborated
upon.
64. Disaster
Management Plan including risk assessment and damage control needs to be addressed and included.
65. Occupational
health of the workers needs
elaboration. Health effects of other metals used and health hazard plans based
on monthly correlation of these metal related diseases and people affected and
mitigation plans; Arsenicosis Management Plan, if Arsenic is present in ore,
rock, coal, fly ash, water and action plan for protecting the workers against hazardous
chemicals such as Sulphuric acid, pesticides, solvents etc. should be included
66. Occupational
health of the workers needs elaboration
including evaluation of noise, heat, illumination, dust, any other chemicals,
metals being suspected in environment and going into body of workers either
through inhalation, ingestion or through skin absorption and steps taken to
avoid musculo-skeletal disorders (MSD), backache, pain in minor and major
joints, fatigue etc. Occupational hazards specific pre-placement and periodical
monitoring and periodical monitoring should be carried out. The detailed plan
to carry out above mentioned activity should be mentioned.
67.
Details regarding infrastructure
facilities such as sanitation, fuel, restroom etc. to be provided to the labour
force during construction as well as to the casual workers including truck
drivers during operation phase.
68.
Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure need to be constructed and the agency responsible for the same
with time frame.
69. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for environmental pollution control measures should be included.
70. Plan for the implementation of the recommendations
made for the steel plants in the CREP
guidelines must be prepared.
71. A note on identification and implementation of
Carbon Credit project should be included.
72. Public
hearing issues raised and commitments
made by the project proponent on the same should be included separately in
EIA/EMP Report in the form of tabular chart with financial budget for complying
with the commitments made.
73. Any litigation
pending against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof should also be included.
In addition to the above, information on the
following may also be incorporated in the EIA report.
1. Is the project intended to have
CDM-intent?
(i) If not, then why?
(ii) If yes, then
(f) Has PIN (Project Idea Note) {or PCN (Project Concept
Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(g) If not, then by when is that expected?
(h) Has PDD (Project Design Document) been prepared?
(i)
What is the ‘Carbon intensity’
from your electricity generation projected (i.e. CO2 Tons/MWH or
Kg/KWH)
(j)
Amount of CO2 in Tons/year
expected to be reduced from the baseline data available on the CEA’s
web-site (www.cea.nic.in)
2. Notwithstanding
1(i) above, data on (d) & (e) above to be worked out and reported.
The Expert Appraisal Committee
(Industry-1) decided that PAs may be communicated the above ‘TORs’ for the
preparation of EIA/EMP. As soon as the
draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in
Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted
by the PAs to the Orissa Pollution
Control Board (OPCB) for conducting public hearing as per EIA
Notification, 2006. On finalization of EIA/EMP prepared as per TORs addressing
all concerns raised during public hearing/consultation in EIA/EMP should be
submitted to the MOEF for prior environmental clearance.
4.9
Expansion of Steel Plant (DRI, IF, CPP) and
installation of Coal Washery,
Beneficiation and Pelletisation Plant, Rolling Mill & Electric Arc Furnace
at Mouza Nabagram, Uttarah, Manpura, Post Digha, P.S. Nituria, District Purulia,
West Bengal by M/s Ispat Damodar Ltd. (TORs)
PAs vide letter no. IDL/ME&F/04/09-10 dated 15th
April, 2009 informed that they are
withdrawing their application due to some changes in the project. Since Project
authorities didn’t attend the meeting, it was decided that proposal should be
considered afresh whenever requested by the PAs.
4.10
Integrated Steel Plant at Mouza Kaliyam,
Gudrashol, Chatradoba, Taluk Chekulia East, District Singhbhum, Jharkhand by
M/s Eurasia Metaliks Limited. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Steel Plants are listed at S.N. 3(a) under Primary
Metallurgy Industries under Category ‘A’ and appraised at the Central level.
M/s Eurasia Metaliks Limited have proposed for
the Integrated Steel Plant at Mouza
Kaliyam, Gudrashol, Chatradoba, District Singhbhum, Jharkhand. Total
land acquired is 205.67 acre. PAs
informed that Railway line is at 300 m. No national park/wildlife
sanctuary/reserve forest is located within 10 km. Nearest town is at 6.8 km. Subernarekha River is at 7.9 km. Kaliyam Village is at 1.2 km. Total cost of the project is Rs. 685.00 Crores. PAs have also
confirmed that no litigation/court case is in pending against the project.
Following will be manufactured:
S.N. |
Products |
Proposed
Capacity (TPA) |
1. |
Sponge Iron |
4,20,000 |
2. |
Steel Billets from Induction
Furnace |
2,60,000 |
3. |
Power (WHRB + AFBC) |
40 MW |
4. |
Coal Washery |
0.8
Million TPA (8,00,000) |
5. |
Iron Ore Beneficiation &
Pelletisation |
0.8
Million TPA (8,00,000) |
6. |
Rolling Mill |
0.4
Million TPA (4,00,000) |
7. |
EAF |
1,44,000 |
Following facilities will
be installed:
S.N. |
Products |
Proposed
Capacity (TPA) |
1. |
Sponge Iron Kilns |
4x350
TPD |
2. |
Induction Furnace |
4x30
TPH |
3. |
WHRB |
1x28
TPH |
4. |
FBC |
1x100
TPH |
5. |
EAF |
1x60
TPH |
Iron ore, coal, bentonite and lime stone will be raw material for iron ore
beneficiation pellet plant. Iron ore,
coal and dolomite will be raw material for sponge iron plant will be used as
raw materials
Run-of-Mine coal (300 / 250-0 mm) will be crushed in crusher to –60 mm, to
secondary vibrating screen (SVS-1) to screen -20 mm, to secondary vibrating
screen (SVS-2) to separate - mm. The
washed coal will have 26-28% ash content. Iron ore beneficiation and pelletization will involve grinding,
drying, de-watering, boiling and induration followed by screening and handling.
Sponge iron will be manufactured
using coal as reductant through DRO process. Steel mainly will be manufactured
through IF-CCM-RM route. The steel
formed will be molded into billets and
rolled products by carting mills and rolling mills. Steel and scrap will be melted in IF, passed
through LF for further refining and cast as ingots. Reheating is done in
reheating furnace alongwith billets and rolled to rolled products. WHRB and AFBC boiler will be installed
to generate power (40 MW).
PAs informed that existing ambient air quality for SPM (117 ug/m3),
RSPM (33 ug/m3), SO2
(7 ug/m3) and NOx (8 ug/m3)
is within permissible limits. Adequate
air pollution control equipments will be installed to control particulate
matter. ESP will be provided to DRI kiln and AFBC boiler. Hot gases from
iron plant will be passed through dust settling chamber (DSC) after burning chamber (ABC), WHRB, ESP,
ID fan and chimney to control gaseous emissions within 100 mg/Nm3 but
committee insisted for 50 mg/Nm3.
Bag filters will be provided to
pellet plant induction and ladle furnace. ESP will be provided to AFBC boiler and iron ore beneficiation
plant also. Fugitive dust will be collected by bag filters at transfer points
and by water sprinkling on the roads within the premises. In coal washery, dust
suppression amongst with water spraying will be made at the ROM coal unloading
points at receiving hopper. Dust
extraction arrangement will be provided at coal reclamation points,
transfer points and screens. Water spraying arrangement will be provided at ROM
coal unloading at the top and reclamation points at the bottom of receiving
hopper, Dry screening points, Belt conveyer transfer points, ROM coal crushing
point, crushed raw coal storage point and crushed raw coal reclamation points.
ESP, bag filter, dust suppression system and chimney will be provided to iron
ore beneficiation. Bag filter will be provided to coal washery and pellet
plant. Bag filter, gas coolers and chimney will be provided to steel melting
shop.
Total water
requirement from Suvarnarekha River
will be 2,200 m3/day. Rejects/middling
dewatering screen continuing coal finer (-1 mm) will be collected in slurry
pump and pumped to dewatering
hydro-cyclone for re-circulate process water (closed circuit system) Jig
washing will be adopted. Process slurry will be treated in cyclones, radial
thickness and slurry ponds etc. Acidic
and alkaline effluent from cation and anion units of DM Plant will be treated
in effluent treatment plant ETP). After neutralization, these two
effluents will be mixed with cooling tower blow down in a guard pond. The
treated effluent will be used for coal yard, sprinkling, coal washery, dust
suppression and green belt development. Service water will be passed through
oil separator to remove oil content in the effluent. Domestic effluent
will be treated in septic tank followed by soak pit. No effluent will be
discharged outside the premises and ‘Zero’
discharge will be adopted.
Dust from ESP and
bag filters (95 TPD) will be reused in respective process operation/sent
to brick manufacturing. Mill scales will be sent to pellet plant. Char
will be used in AFBC boiler. Iron ore fines will be sent to pelletization plant. ETP sludge will be sold to brick
manufacturers. Slag will be sold
to cement manufacturers. Ash
from boiler will be sold to cement plants/brick manufacturers. Waste/used/spent
oil and used batteries will be sold to authorized recyclers/re-processors.
Out of
205.67 acres, green belt will be developed in 70 acres (33 %). Rubber padding will be provided in the vibrating
screens, crushers etc. to reduce noise level. Enclosures will be
provided to Jig compressor. Power will
be sourced from JSEB and captive power plant (40 MW). DG sets (4x1000 KVA & 4x500 KVA) are
proposed.
After deliberating on the facts presented before the
Expert Appraisal Committee (Industry), the committee recommended the proposal
for the preparation of EIA/EMP as per the following TORs:
1. Proposal should be submitted to the Ministry for
environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
2. Clearance from the Railway Department should be
obtained and enclosed in the EIA/EMP report.
3. A map indicating distance between project site and
critically polluted area and a certificate from the CPCB/SPCB certifying the
same.
4. A site location map on Indian
map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e.
circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
5. Present land use should be prepared based on satellite
imagery. High-resolution satellite
image data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10 Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
6.
Topography of the area should be
given clearly indicating whether the site requires any filling. If so, details
of filling, quantity of fill material required, its source, transportation etc.
should be given.
7. Location of national parks/wildlife
sanctuary/reserve forests within 10 km. radius should specifically be
mentioned. A map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
8. Project site layout plan showing raw materials, fly
ash and other storage plans, bore well or water storage, aquifers
(within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the
project site should be included.
9.
Coordinates of the plant site as
well as ash pond with topo sheet co-ordinates of the plant site as well as ash
pond with topo sheet should also be included.
10. Details and classification of total land (identified
and acquired) should be included.
11. Rehabilitation & Resettlement (R
& R) should be as per policy of the
State Govt. and a detailed action plan should be included.
12. Permission from the tribals, if tribal land has also
to be acquired alongwith details of the compensation plan.
13. Permission and approval
for the use of forest land, if any, and
recommendations of the State Forest Department regarding impact of proposed
expansion on the surrounding reserve forests, if applicable, should be included.
14. A list of industries containing name and type in 25 km radius
should be incorporated.
15. Residential colony should be located in upwind
direction.
16. List
of raw material required, analysis of
all the raw materials and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
17. Petrological
and Chemical analysis and other
chemical properties of raw materials used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO norms.
These analysis should include trace element and metal studies like Cr (vi) Ni,
Fe, As, Pb, Zn, Hg, Se, S etc. Presence of radioactive elements (U,
Th etc.), if applicable, should also be included..
18. Petrography,
grain size analysis and Major element
analysis of raw material and soil from project site and raw material should be
done on the same parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
19. If the rocks, ores, raw material has trace
elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
20. Action plan for excavation and muck disposal during
construction phase.
21. Studies for fly ash, muck, slurry, sludge material
disposal and solid waste generated, if the raw materials used has trace
elements and a management plan should
also be included.
22. Manufacturing
process details for all the plants
should be included.
23. Mass
balance for the raw material and
products should be included.
24. Energy
balance data for all the components of steel
plant including proposed power plant
should be incorporated.
25. Data generated in the last three years i.e. air,
water, raw material properties and analysis (major, trace and heavy metals),
ground water table, seismic history, flood hazard history etc.
26. One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
27. Ambient
air quality at 8 locations within the
study area of 10 km., aerial coverage from project site with one AAQMS in
downwind direction should be carried out.
28. The suspended particulate matter present in the
ambient air must be analyzed for the presence of poly-aromatic hydrocarbons
(PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and
incorporating of RSPM data.
29. Determination of atmospheric inversion level at the
project site and assessment of ground level concentration of pollutants from
the stack emission based on site-specific meteorological features.
30. Air quality modelling
for steel plant for specific pollutants
needs to be done. APCS for the control
of emissions from the kiln and WHRB should also be included to control
emissions within 50 mg/Nm3.
31. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
32. Ambient air quality monitoring
modelling alongwith cumulative impact
should be included for the day (24 hrs) for maximum GLC alongwith following :
i)
Emissions (g/second) with and without the air pollution control
measures
ii)
Meteorological inputs (wind speed, m/s), wind direction, ambient
air temperature, cloud cover, relative humidity & mixing height) on hourly
basis
iii)
Model input options for terrain, plume rise, deposition etc.
iv)
Print-out of model input and output on hourly and daily average
basis
v)
A graph of daily averaged concentration (MGLC scenario) with
downwind distance at every 500 m interval covering the exact location of GLC.
vi)
Details of air pollution control methods used with percentage
efficiency that are used for emission rate estimation with respect to each
pollutant
vii)
Applicable air quality standards as per LULC covered in the study
area and % contribution of the proposed plant to the applicable Air quality standard.
In case of expansion project, the contribution should be inclusive of both
existing and expanded capacity.
viii)
No. I-VII are to be repeated for fugitive emissions and any other
source type relevant and used for industry
ix)
Graphs of monthly average daily concentration with down-wind
distance
x)
Specify when and where the ambient air quality standards are
exceeded either due to the proposed plant alone or when the plant contribution
is added to the background air quality.
xi)
Fugitive dust protection or dust reduction technology for workers
within 30 m of the plant active areas.
33. A plan for the utilization
of waste/fuel gases in the WHRB for
generating power have to be set out.
34. Impact of the transport
of the raw materials and end products
on the surrounding environment should be assessed and provided. The alternate
method of raw material and end product transportation should also be studied
and details included.
35. One
season data for gaseous emissions other
than monsoon season is necessary.
36. An action plan to control and monitor secondary
fugitive emissions from all the sources
as per the latest permissible limits issued by the Ministry vide G.S.R. 414(E)
dated 30th May, 2008.
37. Presence of aquifer(s)
within 1 km of the project boundaries
and management plan for recharging the aquifer should be included.
38. Source of surface/ground water
level, site (GPS), cation, anion (Ion
Chromatograph), metal trace element (as above) chemical analysis for water to
be used. If surface water is used from river, rainfall, discharge rate, quantity,
drainage and distance from project site should also be included.
Information regarding surface hydrology and water regime should be included.
39. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume of aquifer and its management.
40. Ground
water modelling showing the pathways of
the pollutants should be included
41.
Column leachate study for all
types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
42.
Action plan for rainwater
harvesting measures at plant site should be submitted to harvest rainwater from
the roof tops and storm water drains to recharge the ground water and also to
use for the various activities at the project site to conserve fresh water and
reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water
harvesting plan for the project is necessary, if source of water is bore well.
43. Permission for the drawl of 2,200 m3/day
water from Suvarnarekha River from the
SGWB/CGWA or concerned authority and water balance data including quantity of
effluent generated, recycled and reused and discharged is to be provided.
Methods adopted/to be adopted for the water conservation should be included.
44. A note on the impact of
drawl of water on the nearby River
during lean season.
45. Surface
water quality of nearby River (60 m
upstream and downstream) and other surface drains at eight locations must be
ascertained.
46. If the site is within 10 km
radius of any major river, Flood Hazard
Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the peak
and lean river discharge as well as flood occurrence frequency.
47. A note on treatment of wastewater
from different plants, recycle and
reuse for different purposes should be included.
48. Provision of traps and treatment
plants are to be made, if water is
getting mixed with oil, grease and cleaning agents.
49. If the water is mixed with solid
particulates, proposal for sediment
pond before further transport should be included. The sediment pond capacity
should be 100 times the transport capacity.
50. Wastewater
characteristics (heavy metals, anions
and cations, trace metals, PAH) from washed / beneficiated plants / washery or
any other source should be included.
51. The pathways for pollution via seepages, evaporation, residual remains
are to be studied for surface water (drainage, rivers, ponds, lakes),
sub-surface and ground water with a monitoring and management plans.
52. Ground
water monitoring minimum at 8 locations
and near solid waste dump zone, Geological features and Geo-hydrological status
of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
53. Geotechnical
data by a bore hole of upto 40 mts. in
every One sq. km area such as ground water level, SPTN values, soil fineness,
geology, shear wave velocity etc. for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk Management in the area.
54. Action plan for solid/hazardous
waste generation, storage, utilization
and disposal particularly slag from all the sources, char and fly ash. Copies
of MOU regarding utilization of ash should also be included.
55. Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
56. A note on the treatment, storage and disposal of all
type of slag should be included.
Identification and details of land to be used for SMS slag disposal should be included. Details of
secured land fill as per CPCB guidelines should also be included.
57. End
use of solid waste and its composition
should be covered. Toxic metal content
in the waste material and its composition should also be incorporated
particularly of slag.
58. All stock piles will have to be on top of a stable
liner to avoid leaching of materials to ground water.
59. Acton plan for the green
belt development plan in 33 % area i.e.
land with not less than 1,500 trees per ha. giving details of species, width of
plantation, planning schedule etc. should
be included. The green belt should be around the project boundary and a scheme
for greening of the traveling roads should also be incorporated. All
rooftops/terraces should have some green cover.
60. Detailed description of the flora and
fauna (terrestrial and aquatic) should
be given with special reference to rare, endemic and endangered species.
61. At least 5 % of the total cost of the project should
be earmarked towards the corporate social responsibility and item-wise details
alongwith time bound action plan should be included. Socio-economic development activities need to be elaborated
upon.
62. Disaster
Management Plan including risk assessment and damage control needs to be addressed and included.
63. Occupational
health of the workers needs
elaboration. Health effects of other metals used and health hazard plans based
on monthly correlation of these metal related diseases and people affected and
mitigation plans; Arsenicosis Management Plan, if Arsenic is present in ore,
rock, coal, fly ash, water and action plan for protecting the workers against
hazardous chemicals such as Sulphuric acid, pesticides, solvents etc. should be
included
64. Occupational
health of the workers needs elaboration
including evaluation of noise, heat, illumination, dust, any other chemicals,
metals being suspected in environment and going into body of workers either
through inhalation, ingestion or through skin absorption and steps taken to
avoid musculo-skeletal disorders (MSD), backache, pain in minor and major
joints, fatigue etc. Occupational hazards specific pre-placement and periodical
monitoring and periodical monitoring should be carried out. The detailed plan
to carry out above mentioned activity should be mentioned.
65.
Details regarding infrastructure
facilities such as sanitation, fuel, restroom etc. to be provided to the labour
force during construction as well as to the casual workers including truck
drivers during operation phase.
66.
Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure need to be constructed and the agency responsible for the same
with time frame.
67. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for environmental pollution control measures should be included.
68. Plan for the implementation of the recommendations
made for the steel plants in the CREP
guidelines must be prepared.
69. A note on identification and implementation of
Carbon Credit project should be included.
70. Public
hearing issues raised and commitments
made by the project proponent on the same should be included separately in
EIA/EMP Report in the form of tabular chart with financial budget for complying
with the commitments made.
71. Any litigation
pending against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof should also be included.
In addition to the above, information on the
following may also be incorporated in the EIA report.
1. Is the
project intended to have CDM-intent?
(i) If not, then why?
(ii) If yes, then
(k) Has PIN (Project Idea Note) {or PCN (Project
Concept Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(l)
If not, then by when is that expected?
(m) Has PDD (Project Design Document) been prepared?
(n) What is the ‘Carbon intensity’ from your electricity
generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
(o) Amount of CO2 in Tons/year expected to be
reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding
1(i) above, data on (d) & (e) above to be worked out and
reported.
The Expert Appraisal Committee
(Industry-1) decided that PAs may be communicated the above ‘TORs’ for the
preparation of EIA/EMP. As soon as the
draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in
Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted
by the PAs to the Jharkhand Pollution Control Board (JPCB) for
conducting public hearing as per EIA Notification, 2006. On finalization of
EIA/EMP prepared as per TORs addressing all concerns raised during public
hearing/ consultation in EIA/EMP should be submitted to the MOEF for prior
environmental clearance.
4.11
Steel Plant at Khasra Nos. 899/5, 899/3,
867/1, 867/3, 867/5, 869/1, 895, 898, 859/2, 868/2, 899/6, 899/4, 867/2, 867/4,
859/1, 869/5, 896, 897, 865, 869/3, at Village Maharumkala, Tehsil Khairagarh,
District Rajnandgaon, Chhattisgarh by M/s Wallfort Steel & Power Pvt. Ltd. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Steel Plants are listed at
S.N. 3(a) under Primary Metallurgical Industries under Category ‘A’ and
appraised at the Central level.
M/s
Wallfort Steel & Power Pvt. Ltd. have proposed for the Steel Plant at Khasra Nos. 899/5,
899/3, 867/1, 867/3, 867/5, 869/1, 895, 898, 859/2, 868/2, 899/6, 899/4, 867/2,
867/4, 859/1, 869/5, 896, 897, 865, 869/3 at Village Maharum Kala, Tehsil Khairagarh, District Rajnandgaon,
Chhattisgarh. Total project area is 36 acres out of which 31 acres is acquired. No
forest land is involved. No national park/wildlife sanctuary/reserved
forest is located within 10 km. No litigation/court case is in pending against
the project. Town Rajnandgar is at 16 km.
Total cost of the project is Rs.
96.30 Crores. Rs. 6.0 Crores and Rs. 0.50 Crores are earmarked
towards capital cost and recurring cost/annum for pollution control
measures. Following facilities will be
installed:
Products |
Units |
Production
capacity (TPA) |
Steel Ingots/Billets through
Induction Furnace with CCM Unit |
4x12 MT |
1,44,000 |
Rolled Products |
1x300
TPD |
90,000 |
Manufacturing of Ferro Alloys |
3x9 MVA 5x2 MVA |
61,666 |
Steel Castings |
1x3 MT,
1x 2MT |
15,000 |
Stainless Steel (Through AOD Furnace) |
1x20 MT |
60,000 |
Oxygen Plant |
-- |
20,000
M3 per annum |
PAs have informed that following
Ferro Alloys products will be manufactured :
Details |
Products |
Annual
Production Capacity |
Ferro Alloys Unit |
Ferro- Manganese |
61,666 |
Silico- Manganese |
53,250 |
|
Ferro Silicon |
27,500 |
|
Ferro Chrome |
53,250 |
Chromite Ore (1,54,165 TPA), Mn Ore (1,23,332 TPA) and quartz (1,37,035
TPA), sponge iron (1,27,059 TPA), metal scrap (37,895 TPA), ferro alloy (1,440
TPA), dolomite (5,207 TPA) mill scales (3,700 TPA), coke (43,166 TPA),
electrode paste (1,650 TPA), charcoal (92,500 TPA) will be used as raw
materials. However, the Committee realized that proposed raw material
requirement does not correspond to the products to be manufactures and asked to
reassess the same.
Billets will be manufactured using sponge iron, scrap and ferro alloys and
casted in continuous casting machine. Rolled products/structural steels will be
manufactured using billets as raw material. Ferro Alloys will be produced using Manganese ore and coke as raw
materials. High grade Alloy Steel
and Stainless Steel will be
manufactured using AOD furnace involving
refining, decarburization, reduction and desulphurization. Oxygen plant will be
installed in LF/LRF furnace, AOD/VOD furnace, cutting of slabs in continuous
casting plant.
Fume extraction system and bag filter will be provided to control
secondary fugitive emissions from the SMS,
AOD furnace and ferro alloy plant. Water spraying will be done to
prevent dust emanation due to vehicular movement and unloading areas. During
PAs have informed that fume extraction system with bag filter will be provided
to induction furnace with concast and submerged electric arc furnace.
Total ground water requirement from bore
wells will be 300 m3/day
and have applied for the water permission. No effluent will be generated from
SMS, rolling mill, SEAF and AOD furnace as closed circuit cooling system will
be adopted. All the effluent will be treated ad used for cooling, dust
suppression and greenbelt development. No effluent will be discharged and ‘zero’ discharge will be adopted.
Sanitary waste will be treated in septic tank followed by soak pit.
IF slag will be crushed and passed
through a magnetic separator to separate ron ore and remaining inert material
will be utilized for land fill/road construction. Dust generated from AOD furnace will be recycled. Mill scales from re-rolling mill will
be reused in the ferro alloy plant.
Slag from Fe-Mn will be used for road construction. The slag
from Fe-Si will be reused in
cast iron Industries. Chrome
will be recovered from chrome slag
through jigging unit and disposed in secured landfill (SLF) after TCLP
test. End cuttings from shearing of
billets / bloom / ingots will be used as raw material in own induction
furnace.
Out
of 50 acre, 16.5 acres (33%)
land is earmarked for the green belt development. Ambient Noise will be
controlled within, 75 dBA during day time and 70 dBA during night time as per
Notification dated 14th February, 2000. Total power requirement will
be from CSPTDL grid. FO / LDO will be
used in reheating furnace.
After deliberating on the facts presented before the Expert Appraisal
Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1.
Proposal should be
submitted to the Ministry for environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
2.
A map indicating
distance between project site and critically polluted area and a certificate
from the CPCB/SPCB certifying the same.
3.
A site location map
on Indian
map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e.
circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
4.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image data having 1m-5m spatial
resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km
radius area from proposed site. The same should be used for land
used/land-cover mapping of the area.
5.
Location of
national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover,
reserved forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
6.
Project site layout
plan showing raw materials and other storage plans, bore well or water storage,
aquifers
(within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the
project site should be included.
7.
Details and
classification of total land (identified and acquired) should be included.
8.
Rehabilitation
& Resettlement (R & R) should
be as per policy of the State Govt. and a detailed action plan should be
included.
9.
Permission from the
tribals, if tribal land has also to be acquired alongwith details of the
compensation plan.
10. Permission and approval for the use of forest land, if any, and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests, if applicable, should be
included.
11. A list of industries
containing name and type in 25 km radius should be incorporated.
12. Residential colony should be located in upwind direction.
13. List of
raw material required, analysis of all
the raw materials and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
14. Petrological
and Chemical analysis and other
chemical properties of raw materials used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be
included..
15.
Petrography, grain size analysis and Major element analysis of raw material
and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
16. If the rocks, ores, raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
17. Action plan for excavation and muck disposal during construction phase.
18. Studies for muck, slurry, sludge material disposal and solid waste
generated, if the raw materials used has trace elements and a management plan should also be
included.
19. Manufacturing
process details for all the plants
should be included.
20. Mass
balance for the raw material and
products should be revised and included.
21. Energy
balance data for all the components of steel
plant should be incorporated.
22. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and
direction and rainfall should be collected.
23. Data generated in the last three
years i.e. air,
water, raw material properties and analysis (major, trace and heavy metals),
ground water table, seismic history, flood hazard history etc.
24. Ambient
air quality at 8 locations within the
study area of 10 km., aerial coverage from project site with one AAQMS in
downwind direction should be carried out.
25. The suspended particulate matter present in the ambient air must be
analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene
soluble fraction. Chemical
characterization of RSPM and
incorporating of RSPM data.
26. Determination of atmospheric inversion level at the project site and
assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
27. Air quality modelling for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
28. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
29. Ambient air
quality monitoring modeling alongwith
cumulative impact should be included for the day (24 hrs) for maximum GLC
alongwith following :
i)
Emissions
(g/second) with and without the air pollution control measures
ii)
Meteorological
inputs (wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii)
Model
input options for terrain, plume rise, deposition etc.
iv)
Print-out
of model input and output on hourly and daily average basis
v)
A
graph of daily averaged concentration (MGLC scenario) with downwind distance at
every 500 m interval covering the exact location of GLC.
vi)
Details
of air pollution control methods used with percentage efficiency that are used
for emission rate estimation with respect to each pollutant
vii)
Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii)
No.
I-VII are to be repeated for fugitive emissions and any other source type
relevant and used for industry
ix)
Graphs
of monthly average daily concentration with down-wind distance
x)
Specify
when and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi)
Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
30. A plan for the utilization of waste/fuel gases in the WHRB for generating power have to be
set out.
31. Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and
provided.
32. One season
data for gaseous emissions other than
monsoon season is necessary.
33. An action plan to control and monitor secondary fugitive
emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
34. Presence of aquifer(s) within 1 km of the project boundaries and management plan for recharging the aquifer
should be included.
35. Source of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph), metal trace element (as
above) chemical analysis for water to be used. If surface water is used from
river, rainfall, discharge rate, quantity, drainage and distance from project
site should also be included.
36. Ground water analysis with bore well data, litho-logs, drawdown and
recovery tests to quantify the area and
volume of aquifer and its management.
37. Ground
water modelling showing the pathways of
the pollutants should be included
38.
Column leachate study for all types of
stockpiles or waste disposal sites at 20oC-50oC should be
conducted and included.
39.
Action plan for rainwater harvesting measures
at plant site should be submitted to harvest rainwater from the roof tops and
storm water drains to recharge the ground water and also to use for the various
activities at the project site to conserve fresh water and reduce the water
requirement from other sources. Rain
water harvesting and groundwater recharge structures may also be constructed
outside the plant premises in consultation with local Gram Panchayat and
Village Heads to augment the ground water level. Incorporation of water harvesting plan for the project is necessary, if
source of water is bore well.
40. Permission for the drawl of 300 m3/day
ground water from bore well from the
SGWB/CGWA or concerned authority and water balance data including quantity of
effluent generated, recycled and reused and discharged is to be provided.
Methods adopted/to be adopted for the water conservation should be included.
41. A note on the impact of drawl of water on the nearby River during lean season.
42. Surface
water quality of nearby River (60 m
upstream and downstream) and other surface drains at eight locations must be
ascertained.
43. If the site
is within 10 km radius of any major river, Flood Hazard Zonation Mapping is required at 1:5000 to 1;10,000 scale
indicating the peak and lean river discharge as well as flood occurrence
frequency.
44. A note on treatment of wastewater from different plants, recycle and reuse for different purposes
should be included.
45. Provision of traps and treatment plants are to be made, if water is getting mixed with oil, grease and cleaning
agents.
46. If the water
is mixed with solid particulates,
proposal for sediment pond before further transport should be included. The
sediment pond capacity should be 100 times the transport capacity.
47. Wastewater
characteristics (heavy metals, anions
and cations, trace metals, PAH) from washed / beneficiated plants / washery or
any other source should be included.
48. The pathways
for pollution via seepages,
evaporation, residual remains are to be studied for surface water (drainage,
rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans.
49. Ground
water monitoring minimum at 8 locations
and near solid waste dump zone, Geological features and Geo-hydrological status
of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
50. Geotechnical
data by a bore hole of upto 40 mts. in
every One sq. km area such as ground water level, SPTN values, soil fineness,
geology, shear wave velocity etc. for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk Management in the area.
51. Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly slag from all
the sources and char. Copies of MOU regarding utilization of ash should also be
included.
52. A note on the treatment, storage and disposal of all type of slag should be included. Identification and
details of land to be used for SMS and ferro alloy slag disposal should be included. Details of
secured landfill for the disposal of Ferro chrome slag and other hazardous
waste as per CPCB guidelines should also be included.
53. End use of
solid waste and its composition should
be covered. Toxic metal content in the
waste material and its composition should also be incorporated particularly of slag.
54. All stock piles will have to be on top of a stable liner to avoid
leaching of materials to ground water.
55. Acton plan for the green belt development plan in 33 % area should be included. The green belt should
be around the project boundary and a scheme for greening of the traveling roads
should also be incorporated. All rooftops/terraces should have some green
cover.
56. Detailed description of the flora and fauna (terrestrial and aquatic) should be given with special reference to
rare, endemic and endangered species.
57. At least 5 % of the total cost of the project should be earmarked towards
the corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to be elaborated upon.
58. Disaster
Management Plan including risk assessment and damage control needs to be addressed and included.
59. Occupational
health of the workers needs
elaboration. Health effects of other metals used and health hazard plans based
on monthly correlation of these metal related diseases and people affected and
mitigation plans; Arsenicosis Management Plan, if Arsenic is present in ore, rock,
coal, fly ash, water and action plan for protecting the workers against
hazardous chemicals such as Sulphuric acid, pesticides, solvents etc. should be
included
60. Occupational
health of the workers needs elaboration
including evaluation of noise, heat, illumination, dust, any other chemicals,
metals being suspected in environment and going into body of workers either
through inhalation, ingestion or through skin absorption and steps taken to
avoid musculo-skeletal disorders (MSD), backache, pain in minor and major
joints, fatigue etc. Occupational hazards specific pre-placement and periodical
monitoring and periodical monitoring should be carried out. The detailed plan
to carry out above mentioned activity should be mentioned.
61. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for environmental pollution control measures should be included.
62. Plan for the implementation of the recommendations made for the steel
plants in the CREP guidelines must be
prepared.
63. A note on identification and implementation of Carbon Credit project
should be included.
64. Public
hearing issues raised and commitments
made by the project proponent on the same should be included separately in
EIA/EMP Report in the form of tabular chart with financial budget for complying
with the commitments made.
65. Any litigation pending
against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof should also be included.
In addition to the above, information on the
following may also be incorporated in the EIA report.
1. Is the
project intended to have CDM-intent?
(i) If not, then why?
(ii) If yes, then
(p) Has PIN (Project Idea Note) {or PCN (Project
Concept Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(q) If not, then by when is that expected?
(r) Has PDD (Project Design Document) been prepared?
(s) What is the ‘Carbon intensity’ from your
electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
(t)
Amount of CO2 in Tons/year
expected to be reduced from the baseline data available on the CEA’s
web-site (www.cea.nic.in)
2. Notwithstanding
1(i) above, data on (d) & (e) above to be worked out and
reported.
The Expert Appraisal
Committee (Industry-1) decided that PAs may be communicated the above ‘TORs’
for the preparation of EIA/EMP. As soon
as the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006, the same may be
submitted by the PAs to the Chhattisgarh Environment Conservation Board (CECB) for conducting public
hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as
per TORs addressing all concerns raised during public hearing/consultation in
EIA/EMP should be submitted to the MOEF for prior environmental clearance.
4.12
Expansion of Steel Plant alongwith Captive
Power Plant (20 MW to 50 MW) at Village R.G. Peta & Srirampuram, Mandal
L-Kota, District Vizianagaram, Andhra Pradesh by M/s Maa Mahamaya Industries
Limited. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Steel Plants are listed at S.N. 3(a) under Primary
Metallurgical Industries under Category ‘A’ and appraised at the Central level.
M/s Maa
Mahamaya Industries Ltd. have proposed for the expansion of Steel Plant
alongwith Captive Power Plant (20 MW to 50 MW) at Village R.G. Peta & Srirampuram, Mandal L-Kota, District
Vizianagaram, Andhra Pradesh. PAs
confirmed that project site is 60 km. from the critically/severely polluted
area. Total area was mentioned 113.67
acres and 29.95 acre. PAs
informed during presentation that project area is 132.17 acres. S. Kota is at
10 km. Vizianagram is at 35 km. Advnapalem RF and Ellappi RF is located
at 9.0 and 9.5 km respectively. Total cost of the project is Rs. 1,088.40 Crores. Following
are the details of existing and proposed expansion facility and products to be
manufactured:
S.N. |
Plants |
EXISTING |
PROPOSED |
||
Unit |
Capacity (TPA) |
Unit |
Capacity (TPA) |
||
1. |
DR Kiln |
1x350 |
Sponge Iron 1,12,000 |
1x350 |
Sponge Iron 1,12,000 |
2. |
Steel Melting shop |
|
|
|
|
|
Induction Furnace |
4x9 |
Liquid Steel 1,12,000 |
4x20 |
Billets/Blooms 2,63,200 |
|
Ladle Furnace |
1x20 |
|
1x40 |
|
|
Billet Caster |
1x2 strand |
|
1x2 Strand |
|
|
VDO Unit |
|
|
1x40 |
|
3 |
Rolling Mill |
1,00,000 |
TMT Bars 1,00,000 |
2,50,000 |
Structural Steel 2,50,000 |
4. |
Captive Power Plant |
2x10 MW |
Power 20 MW |
1x30 MW |
Power 30 MW |
|
Waste Heat Recovery Boiler |
36 |
8 MW |
42 |
8 MW |
|
FBC Boiler |
55 |
12 MW |
110 |
22 MW |
Dolomite/lime, coal, Iron
ore will be used as raw materials. Iron
ore, coal and limestone will be used for the production of sponge iron. Waste flue gases from the kiln will pass
through WHRB to generate
Power. Later, this sponge iron will be melted in induction
furnace alongwith scrap to
produce M.S. billets/blooms which will be fed to rolling mill to produce rolled products (beams, channels, angles,
rounds and other rolled products. The char and dolochar from the sponge iron
will be used in AFBC boiler as fuel to generate power.
Electrostatic precipitator (ESP) will be provided to
DRI kiln, WHRB and AFBC
boiler to control emissions within 50
mg/Nm3. Hot
gases from DRI kilns will be used in WHRB to generate power. Fume
extraction system with bag filters will be provided to control fugitive
emissions from SMS and treated
gas will be let out through a stack of adequate height. Dust
suppression at raw material unloading areas and dust extraction system
with bag filters at all other dust covered with GI sheets to prevent fugitive
emissions.
Total water
requirement for the expansion from Greater
Vishaka Municipal Corporation (GVMC) will be 7,200 m3/day.
During presentation, PAs have informed that water requirement will be reduced
to 2400 m3/day. Closed
circuit cooling system will be used
in DRI plants & SMS and rolling mill air cooled condensers will be installed to reduce water
consumption. Acidic and alkaline
effluent from cation and anion units of DM Plant will be neutralized in
neutralization tank. Boiler blow down will be neutralized in the
neutralization tank before mixing with other effluent streams. After
neutralization, these two effluents will be mixed with cooling tower blow down
in a Central Monitoring Basin. The treated effluent will be used for ash conditioning,
dust suppression and green belt development. Service water will be passed
through oil separator to remove oil content in the effluent. Sanitary
waste water will be treated in septic tank followed by soak pit. No
effluent will be discharged outside the premises and ‘Zero’ discharge will be adopted.
Char and dolochar from sponge iron
plant will be used in AFBC
boiler to generate power. Bag filter
dust will be given to brick
manufacturer and agarbatti manufacturers. Accretion
slag will be used for land fill. Slag from induction furnace will be
used for road construction. Ash from
FBC boiler and WHRB will be stored in silo and given to brick manufacturers / cement plants. Waste spent oil and used batteries will
be sold to authorized recyclers / re-processors.
Green belt will be developed n 33 % area. Ambient noise levels
will be controlled within 75 dBA during day time and 70 dBA during night time
as per notification dated 14th February, 2000. Total power generated
from CPP will be 50 MW. WHRB (8MW) and AFBC (12 MW) is existing and WHRB (8 MW)
and FBC (22MW) is proposed. LDO/HSD will
be used as fuel in rolling mill.
After deliberating on the facts presented before the Expert Appraisal
Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1.
Proposal should be
submitted to the Ministry for environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land viz. lease deed, allotment letter should be included.
2.
A map indicating
distance between project site and critically polluted area and a certificate
from the CPCB/SPCB certifying the same.
3.
A site location map
on Indian
map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e.
circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
4.
Present land use
should be prepared based on satellite imagery. High-resolution satellite image data having 1m-5m spatial
resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km
radius area from proposed site. The same should be used for land
used/land-cover mapping of the area.
5.
Topography of the area should be given
clearly indicating whether the site requires any filling. If so, details of
filling, quantity of fill material required, its source, transportation etc.
should be given.
6.
Location of
national parks/wildlife sanctuary/reserve forests within 10 km. radius should
specifically be mentioned. A map showing landuse/landcover,
reserved forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
7.
Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers
(within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the
project site should be included.
8.
Coordinates of the plant site as well as ash
pond with topo sheet co-ordinates of the plant site as well as ash pond with
topo sheet should also be included.
9.
Details and classification
of total land (identified and acquired) should be included.
10. Rehabilitation & Resettlement (R & R) should be as per policy of the State Govt.
and a detailed action plan should be included.
11. Permission from the tribals, if tribal land has also to be acquired
alongwith details of the compensation plan.
12. Permission and approval for the use of forest land, if any, and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests, if applicable, should be
included.
13. A list of industries
containing name and type in 25 km radius should be incorporated.
14. Residential colony should be located in upwind direction.
15. List of
raw material required, analysis of all
the raw materials and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
16. Petrological
and Chemical analysis and other
chemical properties of raw materials used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be included.
17.
Petrography, grain size analysis and Major element analysis of raw material
and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
18. If the rocks, ores, raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
19. Action plan for excavation and muck disposal during construction phase.
20. Studies for fly ash, muck, slurry, sludge material disposal and solid
waste generated, if the raw materials used has trace elements and a management plan should also be
included.
21. Manufacturing
process details for all the plants
should be included.
22. Mass
balance for the raw material and
products should be included.
23. Energy
balance data for all the components of steel
plant including proposed power plant
should be incorporated.
24. Data generated in the last three
years i.e. air,
water, raw material properties and analysis (major, trace and heavy metals),
ground water table, seismic history, flood hazard history etc.
25.
One season site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall and AAQ data (except monsoon) should be collected. The monitoring
stations should take into account the pre-dominant wind direction, population
zone and sensitive receptors including reserved forests.
26. Ambient
air quality at 8 locations within the
study area of 10 km., aerial coverage from project site with one AAQMS in
downwind direction should be carried out.
27. The suspended particulate matter present in the ambient air must be
analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene
soluble fraction. Chemical
characterization of RSPM and
incorporating of RSPM data.
28. Determination of atmospheric inversion level at the project site and
assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
29. Air quality modelling for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
30. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
31. Ambient air
quality monitoring modeling alongwith
cumulative impact should be included for the day (24 hrs) for maximum GLC
alongwith following :
i)
Emissions
(g/second) with and without the air pollution control measures
ii)
Meteorological
inputs (wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii)
Model
input options for terrain, plume rise, deposition etc.
iv)
Print-out
of model input and output on hourly and daily average basis
v)
A
graph of daily averaged concentration (MGLC scenario) with downwind distance at
every 500 m interval covering the exact location of GLC.
vi)
Details
of air pollution control methods used with percentage efficiency that are used
for emission rate estimation with respect to each pollutant
vii)
Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii)
No.
I-VII are to be repeated for fugitive emissions and any other source type
relevant and used for industry
ix)
Graphs
of monthly average daily concentration with down-wind distance
x)
Specify
when and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi)
Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
32. A plan for the utilization of waste/fuel gases in the WHRB for generating power have to be
set out.
33. Impact of the transport of the raw materials and end products on the surrounding environment should be assessed and
provided. The alternate method of raw material and end product transportation
should also be studied and details included.
34. One season
data for gaseous emissions other than
monsoon season is necessary.
35. Data on existing ambient air, stack emission, fugitive
emissions data; water requirement and water balance cycle; generation,
re-utilization and disposal of solid/ hazardous waste for the existing plant
and predicted increase in pollution load (GLCs) due to proposed expansion
should be incorporated.
36. All the environment clearances accorded by the Ministry, Consent to
Establish and Operate and point-wise compliance to the specific and general
conditions stipulated in the
environmental clearance and Consent to Establish and Operate for all the
existing plants.
37. An action plan to control and monitor secondary fugitive
emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
38. Presence of aquifer(s) within 1 km of the project boundaries and management plan for recharging the aquifer
should be included.
39. Source of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph), metal trace element (as
above) chemical analysis for water to be used. If surface water is used from
river, rainfall, discharge rate, quantity, drainage and distance from project
site should also be included. Information regarding surface hydrology
and water regime should be included.
40. Ground water analysis with bore well data, litho-logs, drawdown and
recovery tests to quantify the area and
volume of aquifer and its management.
41. Ground
water modelling showing the pathways of
the pollutants should be included
42.
Column leachate study for all types of
stockpiles or waste disposal sites at 20oC-50oC should be
conducted and included.
43.
Action plan for rainwater harvesting measures
at plant site should be submitted to harvest rainwater from the roof tops and
storm water drains to recharge the ground water and also to use for the various
activities at the project site to conserve fresh water and reduce the water
requirement from other sources. Rain
water harvesting and groundwater recharge structures may also be constructed
outside the plant premises in consultation with local Gram Panchayat and
Village Heads to augment the ground water level. Incorporation of water harvesting plan for the project is necessary, if
source of water is bore well.
44. Permission for the drawl of 2,400 m3/day
water from Greater Vishaka Municipal
Corporation (GVMC) from concerned authority and water balance data including
quantity of effluent generated, recycled and reused and discharged is to be
provided. Methods adopted/to be adopted for the water conservation should be
included.
45. A note on the impact of drawl of water on the nearby River during lean season.
46. Surface
water quality of nearby River (60 m
upstream and downstream) and other surface drains at eight locations must be
ascertained.
47. If the site
is within 10 km radius of any major river, Flood Hazard Zonation Mapping is required at 1:5000 to 1;10,000 scale
indicating the peak and lean river discharge as well as flood occurrence
frequency.
48. A note on treatment of wastewater from different plants, recycle and reuse for different purposes
should be included.
49. Provision of traps and treatment plants are to be made, if water is getting mixed with oil, grease and cleaning
agents.
50. If the water
is mixed with solid particulates,
proposal for sediment pond before further transport should be included. The
sediment pond capacity should be 100 times the transport capacity.
51. Wastewater
characteristics (heavy metals, anions
and cations, trace metals, PAH) from washed / beneficiated plants / washery or
any other source should be included.
52. The pathways
for pollution via seepages,
evaporation, residual remains are to be studied for surface water (drainage,
rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans.
53. Ground
water monitoring minimum at 8 locations
and near solid waste dump zone, Geological features and Geo-hydrological status
of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
54. Geotechnical
data by a bore hole of upto 40 mts. in
every One sq. km area such as ground water level, SPTN values, soil fineness,
geology, shear wave velocity etc. for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk Management in the area.
55. Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly slag from all
the sources, char and fly ash. Copies of MOU regarding utilization of ash
should also be included.
56. Details of
evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
57. A note on the treatment, storage and disposal of all type of slag should be included. Identification and
details of land to be used for SMS slag disposal should be included. Details of secured land fill as per CPCB
guidelines should also be included.
58. End use of
solid waste and its composition should
be covered. Toxic metal content in the
waste material and its composition should also be incorporated particularly of slag.
59. All stock piles will have to be on top of a stable liner to avoid
leaching of materials to ground water.
60. Acton plan for the green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt
should be around the project boundary and a scheme for greening of the
traveling roads should also be incorporated. All rooftops/terraces should have
some green cover.
61. Detailed description of the flora and fauna (terrestrial and aquatic) should be given with special reference to
rare, endemic and endangered species.
62. At least 5 % of the total cost of the project should be earmarked towards
the corporate social responsibility and item-wise details alongwith time bound
action plan should be included. Socio-economic development activities need to be elaborated upon.
63. Disaster
Management Plan including risk assessment and damage control needs to be addressed and included.
64. Occupational
health of the workers needs elaboration.
Health effects of other metals used and health hazard plans based on monthly
correlation of these metal related diseases and people affected and mitigation
plans; Arsenicosis Management Plan, if Arsenic is present in ore, rock, coal,
fly ash, water and action plan for protecting the workers against hazardous
chemicals such as Sulphuric acid, pesticides, solvents etc. should be included
65. Occupational
health of the workers needs elaboration
including evaluation of noise, heat, illumination, dust, any other chemicals,
metals being suspected in environment and going into body of workers either
through inhalation, ingestion or through skin absorption and steps taken to
avoid musculo-skeletal disorders (MSD), backache, pain in minor and major
joints, fatigue etc. Occupational hazards specific pre-placement and periodical
monitoring and periodical monitoring should be carried out. The detailed plan
to carry out above mentioned activity should be mentioned.
66.
Details regarding infrastructure facilities
such as sanitation, fuel, restroom etc. to be provided to the labour force
during construction as well as to the casual workers including truck drivers
during operation phase.
67.
Impact of the project on local infrastructure
of the area such as road network and whether any additional infrastructure need
to be constructed and the agency responsible for the same with time frame.
68. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring cost/annum for environmental pollution control measures should be included.
69. Plan for the implementation of the recommendations made for the steel
plants in the CREP guidelines must be
prepared.
70. A note on identification and implementation of Carbon Credit project
should be included.
71. Public
hearing issues raised and commitments
made by the project proponent on the same should be included separately in
EIA/EMP Report in the form of tabular chart with financial budget for complying
with the commitments made.
72. Any litigation
pending against the project and/or any
direction/order passed by any Court of Law against the project, if so, details
thereof should also be included.
In addition to the above, information on the
following may also be incorporated in the EIA report.
1. Is the
project intended to have CDM-intent?
(i) If not, then why?
(ii) If yes, then
(u) Has PIN (Project Idea Note) {or PCN (Project
Concept Note)} submitted to the ‘NCA’ (National CDM Authority) in the MoEF?
(v) If not, then by when is that expected?
(w) Has PDD (Project Design Document) been prepared?
(x) What is the ‘Carbon intensity’ from your
electricity generation projected (i.e. CO2 Tons/MWH or Kg/KWH)
(y) Amount of CO2 in Tons/year expected to be
reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)
2. Notwithstanding
1(i) above, data on (d) & (e) above to be worked out and
reported.
The Expert Appraisal Committee
(Industry-1) decided that PAs may be communicated the above ‘TORs’ for the
preparation of EIA/EMP. As soon as the
draft EIA/EMP report is prepared as per the ‘General Structure of EIA’ given in
Appendix III and IIIA in the EIA Notification, 2006, the same may be submitted
by the PAs to the A.P. Pollution Control
Board (APPCB) for conducting
public hearing as per EIA Notification, 2006. On finalization of EIA/EMP
prepared as per TORs addressing all concerns raised during public
hearing/consultation in EIA/EMP should be submitted to the MOEF for prior
environmental clearance.
4.13
Ferro-Alloy Plant (Ferro-Silicon 2,000 TPA)
at Sy.No. 376, Village ParGi, Mandal Hindupur, District Ananthapur, Andhra
Pradesh by M/s Vee Six Alloys Pvt. Ltd. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft
Term of References for the preparation of EIA/EMP. All the Ferro Alloy
Plants are listed at S.N. 3(a) under Primary Metallurgical Industries under
Category ‘A’ and appraised at the Central level.
M/s Vee
Six Alloys Pvt. Ltd. has proposed for the Ferro-Alloy Plant (Ferro-Silicon
2,000 TPA) at Sy. No. 376, Village Pargi, Mandal Hindupur, District Ananthapur,
Andhra Pradesh. Total project area is 3 acres. No national park/wildlife
sanctuary/ reserve forest is located within 10 km. Village Parigi is at 0.8 km. Parigi Cheruvu
and Jayamangal River is at 0.5 and 0.8 km respectively. Total cost of the
project is Rs. 6.0699 Crores. Rs. 10.66 Lakhs and Rs. 4.60 Lakhs are
earmarked towards capital cost and recurring cost/annum for environment
pollution control measures.
The
ferro-silicon will be manufactured in electric submerged arc furnace. It will involve blending of raw materials;
charging and smelting of the raw material in electric arc furnace at 1600-17000c,
tapping and cooling of the molten materials; breaking, cleaning and
packing of the material. Quartz, coke and M.S. scrap, electrode paste etc. will
be used as raw materials.
PAs have informed that existing ambient air quality status
of SPM (120.2–159.2 ug/m3), RSPM (36–52.8 ug/m3), SO2
(6.9–11.8 ug/m3) and NOx (10.5–13.2 ug/m3) is within the
permissible limit. Bag filters will be provided to point source emissions. The hood will be provided to the furnace to
collect flue gases and will be discharged through the chimney. Two-stage venturing scrubber will be provided
to control gases from the furnace.
Fugitive emissions will be controlled by sprinkling of water in loading
and unloading area and deducting by extraction of furnace. Bag filters followed
by stack discharge will be provided to conveyor and transfer points.
Total ground
water requirement from bore wells will be 15 m3/day and collected in
water storage tanks. A water softening
plant will be installed to restrict hardness below 20 ppm. The cooling water will be recycled/reused for
cooling. The treated effluent will be used for ash conditioning, dust
suppression and green belt development. Service water will be passed through
oil separator to remove oil content in the effluent. No effluent will be
discharged outside the premises and ‘Zero’ discharge will be adopted.
The slag will be sold to cast iron foundries for further
utilization. Cleaning rejects will be
recycled into the production process.
Dust from air pollution control devices will be given to brick and
cement manufacturers. Waste oil and used batteries will be sold to authorized
recyclers / re-processors.
10 m
wide green belt will be provided around the plant. Rain water harvesting and
ground water recharging by recharge structure will be adopted to conserve
water. Power requirement will be 2.174 MW. DG set (625 KVA) will be
installed.
After deliberating on the facts presented before the Expert
Appraisal Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1. Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
2. A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
3. Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
4. Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
5. Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within 1 km.) dumping, waste disposal, green areas,
water bodies, rivers/drainage passing through the project site should be
included.
6. Details
and classification of total land (identified and acquired) should be included.
7. A
list of industries containing name and type in 25 km radius should be
incorporated.
8. Residential
colony should be located in upwind direction.
9. List
of raw material required and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
10. Petrological
and Chemical analysis and other chemical properties of raw materials used (with
GPS location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
11. Petrography,
grain size analysis and Major element analysis of raw material and soil from
project site and raw material should be done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
12. If
the rocks, ores, raw material has trace elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
13. Studies
for slag, muck disposal, slurry, sludge material and solid waste generated
should also be included, if the raw materials used has trace elements and a
management plan.
14. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
15. Mass
balance for the raw material and products should be included.
16. Energy
balance data for all the components of ferro alloy plant should be
incorporated.
17. Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
18. Data
generated in the last three years i.e. air, water, raw material properties and
analysis (major, trace and heavy metals), ground water table, seismic history,
flood hazard history etc.
19. Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
20. The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
21.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
22.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50
mg/Nm3.
23.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
24. Ambient air quality monitoring modeling alongwith cumulative
impact should be included for the day (24 hrs) for maximum GLC alongwith
following :
i)
Emissions (g/second) with
and without the air pollution control measures
ii)
Meteorological inputs
(wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii)
Model input options for
terrain, plume rise, deposition etc.
iv)
Print-out of
model input and output on hourly and daily average basis
v)
A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi)
Details of air pollution control methods
used with percentage efficiency that are used for emission rate estimation with
respect to each pollutant
vii)
Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii)
No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix)
Graphs of monthly average daily concentration
with down-wind distance
x)
Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air
quality.
xi)
Fugitive dust protection
or dust reduction technology for workers within 30 m of the plant active areas.
25. Impact of the transport of the raw materials and end products on
the surrounding environment should be assessed and provided.
26. One season data for gaseous emissions other than monsoon season is
necessary.
27. An action plan to control and monitor secondary fugitive emissions
from all the sources as per the latest permissible limits issued by the
Ministry vide G.S.R. 414(E) dated 30th May, 2008.
28. Presence of aquifer/aquifers within 1 km of the project boundaries
and management plan for recharging the aquifer should be included.
29. Source of surface/ground water level, site (GPS), cation, anion
(Ion Chromatograph), metal trace element (as above) chemical analysis for water
to be used. If surface water is used from river, rainfall, discharge rate,
quantity, drainage and distance from project site should also be included.
30. Ground water analysis with bore well data, litho-logs, drawdown
and recovery tests to quantify the area and volume of aquifer and its management.
31. Ground water modeling showing the pathways of the pollutants
should be included
32. Column leachate study for all types of stockpiles or waste
disposal sites, at 20oC-50oC should be conducted and
included.
33. ‘Permission’ for the drawl of 15 m3/day ground water from
bore wells should be included. Water
balance cycle data including quantity of effluent generated, recycled and
reused and discharged is to be provided. Methods adopted/to be adopted for the
water conservation should be included.
34. A note on the impact of drawl of water on the nearby River during
lean season.
35. Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the
ground water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level.
36. Surface water quality of nearby River (60 m upstream and
downstream) and other surface drains at eight locations must be
ascertained.
37. If the site is within 10 km radius of any major river, Flood
Hazard Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the
peak and lean river discharge as well as flood occurrence frequency.
38. A note on treatment of wastewater from different plants, recycle
and reuse for different purposes should be included.
39. Provision of traps and treatment plants are to be made, if water
is getting mixed with oil, grease and cleaning agents.
40. If the water is mixed with solid particulates, proposal for
sediment pond before further transport should be included. The sediment pond
capacity should be 100 times the transport capacity.
41. Wastewater characteristics (heavy metals, anions and cations,
trace metals, PAH) from all sources should be included.
42. The pathways for pollution via seepages, evaporation, residual
remains are to be studied for surface water (drainage, rivers, ponds, lakes),
sub-surface and ground water with a monitoring and management plans.
43. Ground water monitoring minimum at 8 locations and near solid
waste dump zone, Geological features and Geo-hydrological status of the study
area are essential as also. Ecological
status (Terrestrial and Aquatic) is vital.
44. Geotechnical data by a bore hole of upto 40 mts. in every One sq.
km area such as ground water level, SPTN values, soil fineness, geology, shear
wave velocity etc. for liquefaction studies and to assess future Seismic Hazard
and Earthquake Risk Management in the area.
45. Action plan for solid/hazardous waste generation, storage,
utilization and disposal particularly slag from all the sources should also be
included.
46.
Identification and details of
land to be used for all type of slag disposal in the secured land fill as per
CPCB guidelines should be included.
47. All stock piles will have to be on top of a stable liner to avoid
leaching of materials to ground water.
48. End use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
49. Provision of Toxic Chemical Leachability Potential (TCLP) test for
the slag and its end use should be included.
50. Commitment that no Ferro chrome will be manufactured without prior
approval of the Ministry.
51. Acton plan for the green belt development plan in 33 % area should
be included. The green belt should be around the project boundary and a scheme
for greening of the traveling roads should also be incorporated. All
rooftops/terraces should have some green cover.
52. Detailed description of the flora and fauna (terrestrial and
aquatic) should be given with special reference to rare, endemic and endangered
species.
53. Disaster Management Plan including risk assessment and damage
control needs to be addressed and included.
54. Occupational health of the workers needs elaboration. Health
effects of other metals used and health hazard plans based on monthly
correlation of these metal related diseases and people affected and mitigation
plans. Arsenicosis Management Planif Arsenic is present in ore, rock, coal, fly
ash, water. Action Plan for protecting the workers against hazardous chemicals
such as Sulphuric acid, pesticides, solvents etc.
55.
Occupational
health of the workers needs elaboration including evaluation of noise, heat,
illumination, dust, any other chemicals, metals being suspected in environment
and going into body of workers either through inhalation, ingestion or through
skin absorption and steps taken to avoid musculo-skeletal disorders (MSD),
backache, pain in minor and major joints, fatigue etc. Occupational hazards
specific pre-placement and periodical monitoring and periodical monitoring
should be carried out. The detailed plan to carry out above mentioned activity
should be mentioned.
56.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details alongwith time bound action plan should be included.
Socio-economic development activities need to be elaborated upon.
57. Plan for the implementation of the recommendations made for the
ferro alloy plants in the CREP guidelines must be prepared.
58. Total capital cost and recurring cost/annum for environmental
pollution control measures should also be included.
59. Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
60. Any litigation pending against the project and / or any direction
/ order passed by any Court of Law against the project, if so, details thereof.
The Expert
Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for
the preparation of EIA/EMP. As soon as
the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006, the same may be
submitted by the PAs to the A.P. Pollution Control Board (APPCB) for conducting
public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per
TORs addressing all concerns set out in EIA/EMP should be submitted to the MOEF
for prior environmental clearance.
4.14
Ferro
Alloys Plant (2x6 MVA, 18,000 TPA,
Fe-Mn & Si-Mn) at Plot No. 213, Growth Centre, Mandal Bobbili, District
Vizianagaram, Andhra Pradesh by M/s Gee Bee Ferro & Power Private Ltd. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Ferro Alloy Plants are listed at S.N. 3(a) under
Primary Metallurgical Industries under Category ‘A’ and appraised at the
Central level.
M/s Gee
Bee Ferro & Power Private Ltd. have proposed for the Ferro Alloy Plant (2x6
MVA, 18,000 TPA, Fe-Mn & Si-Mn) at Plot No. 213, Growth Centre, Mandal
Bobbili, District Vizianagaram, Andhra Pradesh.
Total land acquired is 4 acres.
Mettaralasa village is at 2 km.
Total cost of the project is Rs. 18.00 Crores. No
litigation/court case is pending against the project. Rs. 72.00 Lakhs is
earmarked towards capital cost for pollution control measures.
Manganese ore, coal, coke, dolomite, quartz and carbon paste will be used as
raw materials. Coke will be used as one of the raw material and not as fuel in
the Ferro Alloy plant. Mixture of ore, coke, coal and briquettes will be
smelted in electric submerged arc furnace through electro-thermic process. The metal will be tapped at regular intervals
in pans/moulds.
The furnace will be provided with a
dust extraction system comprising of hood to collect the smoke and will
discharge filtered smoke to the chimney. The furnace stack will be maintained
as per CPCB standards. Pulse jet bag filters will be provided to control down
pollution.
Total ground
water requirement from bore wells will be 80 m3/day and have applied
for permission for the drawal of ground water. Treated wastewater will be used
for cooling purpose. Cooling water will
be passed through heat exchangers and collected in sump or holding tank. Screens and recirculation tanks will be
provided to recycle/reuse treated waste water. The treated effluent will be
used for ash conditioning, dust suppression and green belt development. Fines
generated during breaking and sizing of the finished metal will be sent to
jigging machine and cleaned in flow of water.
The wastewater from jigging machine will be recycled/reused. Service
water will be passed through oil separator to remove oil content in the
effluent. Domestic effluent will be treated in septic tank followed by
soak pit. No effluent will be discharged outside the premises and ‘Zero’
discharge will be adopted.
Ferro-Manganese slag will be reused in the manufacture of
Silico-Manganese. Silico-Manganese slag will be initially disposed off in slag
yard and later on used in filling low lying areas. Bag filter dust will be
provided to brick manufacturing units. The finer collected in pollution control
equipments will be taken back to raw material processing area and mixed with
the ore and charged in the furnace. Waste oil and used batteries will be
sold to authorized recyclers / re-processors.
Out of 4.00 acre, green belt will be developed in 1.32
acres. Equipment of less noise generation will be used. Total power
requirement will be 33 KVA increased to 132 KVA. HSD will be used as fuel.
After deliberating on the facts presented before the Expert
Appraisal Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1. Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
2. A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
3. Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
4. Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
5. Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within 1 km.) dumping, waste disposal, green areas,
water bodies, rivers/drainage passing through the project site should be
included.
6. Details
and classification of total land (identified and acquired) should be included.
7. A
list of industries containing name and type in 25 km radius should be
incorporated.
8. Residential
colony should be located in upwind direction.
9. List
of raw material required and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
10. Petrological
and Chemical analysis and other chemical properties of raw materials used (with
GPS location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
11. Petrography,
grain size analysis and Major element analysis of raw material and soil from
project site and raw material should be done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
12. If
the rocks, ores, raw material has trace elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management plan.
13. Studies
for slag, muck disposal, slurry, sludge material and solid waste generated
should also be included, if the raw materials used has trace elements and a
management plan.
14. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
15. Mass
balance for the raw material and products should be included.
16. Energy
balance data for all the components of ferro alloy plant should be
incorporated.
17. Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
18. Data
generated in the last three years i.e. air, water, raw material properties and
analysis (major, trace and heavy metals), ground water table, seismic history,
flood hazard history etc.
19. Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
20. The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
21.
Determination of
atmospheric inversion level at the project site and assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
22.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50
mg/Nm3.
23.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
24. Ambient air quality monitoring modeling alongwith cumulative
impact should be included for the day (24 hrs) for maximum GLC alongwith
following :
i)
Emissions (g/second) with
and without the air pollution control measures
ii)
Meteorological inputs
(wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii)
Model input options for
terrain, plume rise, deposition etc.
iv)
Print-out of
model input and output on hourly and daily average basis
v)
A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi)
Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii)
Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii)
No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix)
Graphs of monthly average daily
concentration with down-wind distance
x)
Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air
quality.
xi)
Fugitive dust protection
or dust reduction technology for workers within 30 m of the plant active areas.
25. Impact of the transport of the raw materials and end products on
the surrounding environment should be assessed and provided.
26. One season data for gaseous emissions other than monsoon season is
necessary.
27. An action plan to control and monitor secondary fugitive emissions
from all the sources as per the latest permissible limits issued by the
Ministry vide G.S.R. 414(E) dated 30th May, 2008.
28. Presence of aquifer/aquifers within 1 km of the project boundaries
and management plan for recharging the aquifer should be included.
29. Source of surface/ground water level, site (GPS), cation, anion
(Ion Chromatograph), metal trace element (as above) chemical analysis for water
to be used. If surface water is used from river, rainfall, discharge rate,
quantity, drainage and distance from project site should also be included.
30. Ground water analysis with bore well data, litho-logs, drawdown
and recovery tests to quantify the area and volume of aquifer and its
management.
31. Ground water modeling showing the pathways of the pollutants
should be included
32. Column leachate study for all types of stockpiles or waste
disposal sites, at 20oC-50oC should be conducted and included.
33. ‘Permission’ for the drawl of 80 m3/day ground water from
bore wells should be included. Water
balance cycle data including quantity of effluent generated, recycled and
reused and discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
34. A note on the impact of drawl of water on the nearby River during
lean season.
35. Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the
ground water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater recharge
structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
36. Surface water quality of nearby River (60 m upstream and
downstream) and other surface drains at eight locations must be ascertained.
37. If the site is within 10 km radius of any major river, Flood
Hazard Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the
peak and lean river discharge as well as flood occurrence frequency.
38. A note on treatment of wastewater from different plants, recycle
and reuse for different purposes should be included.
39. Provision of traps and treatment plants are to be made, if water
is getting mixed with oil, grease and cleaning agents.
40. If the water is mixed with solid particulates, proposal for
sediment pond before further transport should be included. The sediment pond
capacity should be 100 times the transport capacity.
41. Wastewater characteristics (heavy metals, anions and cations,
trace metals, PAH) from all sources should be included.
42. The pathways for pollution via seepages, evaporation, residual
remains are to be studied for surface water (drainage, rivers, ponds, lakes),
sub-surface and ground water with a monitoring and management plans.
43. Ground water monitoring minimum at 8 locations and near solid
waste dump zone, Geological features and Geo-hydrological status of the study
area are essential as also. Ecological
status (Terrestrial and Aquatic) is vital.
44. Geotechnical data by a bore hole of upto 40 mts. in every One sq.
km area such as ground water level, SPTN values, soil fineness, geology, shear
wave velocity etc. for liquefaction studies and to assess future Seismic Hazard
and Earthquake Risk Management in the area.
45. Action plan for solid/hazardous waste generation, storage,
utilization and disposal particularly slag from all the sources should also be
included.
46.
Identification and details of
land to be used for all type of slag disposal in the secured land fill as per
CPCB guidelines should be included.
47. All stock piles will have to be on top of a stable liner to avoid
leaching of materials to ground water.
48. End use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
49. Provision of Toxic Chemical Leachability Potential (TCLP) test for
the slag and its end use should be included.
50. Commitment that no Ferro chrome will be manufactured without prior
approval of the Ministry.
51. Acton plan for the green belt development plan in 33 % area should
be included. The green belt should be around the project boundary and a scheme
for greening of the traveling roads should also be incorporated. All
rooftops/terraces should have some green cover.
52. Detailed description of the flora and fauna (terrestrial and
aquatic) should be given with special reference to rare, endemic and endangered
species.
53. Disaster Management Plan including risk assessment and damage
control needs to be addressed and included.
54. Occupational health of the workers needs elaboration. Health
effects of other metals used and health hazard plans based on monthly
correlation of these metal related diseases and people affected and mitigation
plans. Arsenicosis Management Planif Arsenic is present in ore, rock, coal, fly
ash, water. Action Plan for protecting the workers against hazardous chemicals
such as Sulphuric acid, pesticides, solvents etc.
55.
Occupational
health of the workers needs elaboration including evaluation of noise, heat,
illumination, dust, any other chemicals, metals being suspected in environment
and going into body of workers either through inhalation, ingestion or through
skin absorption and steps taken to avoid musculo-skeletal disorders (MSD),
backache, pain in minor and major joints, fatigue etc. Occupational hazards specific
pre-placement and periodical monitoring and periodical monitoring should be
carried out. The detailed plan to carry out above mentioned activity should be
mentioned.
56.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details alongwith time bound action plan should be included.
Socio-economic development activities need to be elaborated upon.
57. Plan for the implementation of the recommendations made for the
ferro alloy plants in the CREP guidelines must be prepared.
58. Total capital cost and recurring cost/annum for environmental
pollution control measures should also be included.
59. Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
60. Any litigation pending against the project and / or any direction
/ order passed by any Court of Law against the project, if so, details thereof.
The Expert
Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for
the preparation of EIA/EMP. As soon as
the draft EIA/EMP report is prepared as per the ‘General Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006, the same may be
submitted by the PAs to the A.P. Pollution Control Board (SPCB) for conducting
public hearing as per EIA Notification, 2006. On finalization of EIA/EMP prepared as per
TORs addressing all concerns set out in EIA/EMP should be submitted to the MOEF
for prior environmental clearance.
During presentation, PAs have
submitted a copy of order dated 9.3.1998 from Panchyat Raj & Rural
Development in support of notification of industrial estate/area. PAs were
requested to submit a copy of the Gazette Notification issued by the Govt. of
A.P. and decision regarding exemption from public hearing will be taken
accordingly. Other-wise, decision as mentioned above is final.
4.15
Expansion of Ferro Alloy Plant (Fe-Mn &
Si-Mn) by installing 5.5 MVA SAF) at Mouza Nacrajoria, P.S. Salanpur, District
Burdwan, West Bengal by M/s Hira Concast Limited. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Ferro Alloy Plants are listed at S.N. 3(a) under
Primary Metallurgical Industries under Category ‘A’ and appraised at the
Central level.
M/s Hira
Concast Limited have proposed for
the expansion of Ferro Alloy Plant
(Fe-Mn & Si-Mn) by installing 5.5 MVA SAF) at Mouza Nacrajoria, P.S.
Salanpur, District Burdwan, West Bengal.
Total existing project area is 6.68 acres and expansion will be carried
out in the same campus. Environment
clearance for the existing plant is accorded by the Ministry vide letter
No.J-11011/533/2008 dated 11th December, 2008. ‘Consent for
Establishment’ for the existing is accorded by the WBPCB vide letter dated 6th
May, 2009. ‘Consent to Operate’ under
Air and Water Act has also been accorded.
Total cost of the project is Rs. 1,063.31 Lakhs. Following will be
manufactured:
Facilities |
Products
(TPA) |
Existing : |
|
M.S. Ingots (Induction Furnace |
53,000 |
* High Carbon Fe-Mn(7.5 MVA SAF) |
15,225 |
* High Carbon Si-Mn(SAF) |
11,455 |
Proposed : |
|
High Fe-Mn (5.5 MVA) |
12,330 |
High Carbon Si-Mn SAF |
9,280 |
*Under installation.
During
presentation, PAs have informed that existing plant is under trial run. Ferro
Alloy (Fe-Mn & Si-Mn) will be manufactured in submerged arc furnace by
reduction smelting process. Metallic
ores (Fe2O3, Silicon oxide, MnO2 etc.) and
reducing agent (coke, charcoal, wood chips) and lime stone as a flux material
will be used. High temperature in
reaction zone and carbon will heat the metal oxide to from CO and to reduce
ores to base metal. Hot liquid metal and slag will be tapped separately. The metal cokes after cooling will be broken
to 12 inch size and cleaned to chip off slag. Manganese ore, coke &
coal, Iron ore, High MnO2 ore and dolomite will be used as raw
materials.
Fume extraction system with smoke suction hood,
heat exchanger, bag filter scrubber ID fan and stack (30 m) will be provided to
control emission. Dust suppression system will be provided at raw material
handling areas. Covered conveyor belt will be provided to control fugitive
dust.
Total water
requirement from will be 4 m3/day. Cooling tower blow down will be
collected in the guard pond and recycled/reused for dust suppression and green
belt development. Service water will be passed through oil separator to remove
oil content in the effluent. Domestic effluent will be treated in septic
tank followed by soak pit. No effluent will be discharged outside the
premises and ‘Zero’ discharge will be adopted.
Slag
will be sold. Fe-Mn slag will be used in manufacturing Si-Mn. Waste/used/spent oil and used batteries
will be sold to authorized recyclers / re-processors. Solid waste(10 MTPM) is
being generated from existing induction furnace.
Power (5.5
MVA) will be sourced from DVC. Employment to 38 additional persons will be
provided.
After deliberating on the facts presented before the Expert
Appraisal Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs:
1. A site location map on Indian map of 1:10, 00,000 scale followed
by 1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of
terrains i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
2. Present land use should be prepared based on satellite imagery.
High-resolution satellite image data having 1m-5m spatial resolution like
quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10Km radius area from
proposed site. The same should be used for land used/land-cover mapping of the
area.
3. Location of national parks / wildlife sanctuary / reserve forests
within 10 km. radius should specifically be mentioned. A map showing
landuse/landcover, reserved forests, wildlife sanctuaries, national parks,
tiger reserve etc in 10 km of the project site.
4. Project site layout plan showing raw materials and other storage
plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing through the
project site should be included.
5. Details and classification of total land (identified and acquired)
should be included.
6. Rehabilitation & Resettlement (R & R) should be as per
policy of the State Govt. and a detailed action plan should be included.
7. A list of industries containing name and type in 25 km radius
should be incorporated.
8. Residential colony should be located in upwind direction.
9. List of raw material required and source alongwith mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
10. Petrological and Chemical analysis and other chemical properties
of raw materials used (with GPS location of source of raw material) i.e. ores,
minerals, rock, soil, coal, iron, dolomite quartz etc. using high definition and
precision instruments mentioning their detection range and methodology such
Digital Analyzers, AAS with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD,
Nano studies or at least as per I30-10500 and WHO norms. These analysis should
include trace element and metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg,
Se, S etc. Presence of radioactive elements (U, Th etc.).
11. Petrography, grain size analysis and Major element analysis of raw
material and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5,
H2O, CO2.
12. If the rocks, ores, raw material has trace elements their
petrography, ore microscopy, XRD, elemental mapping EPMA, XRF is required to
quantify the amount present in it and hence future risk involved while using it
and management plan.
13. Studies for slag, muck disposal, slurry, sludge material and solid
waste generated should also be included, if the raw materials used has trace
elements and a management plan.
14. Commitment
that instead of char from local sources, petro coke will be used as fuel should
be included.
15. Site-specific micro-meteorological data using temperature,
relative humidity, hourly wind speed and direction and rainfall is necessary.
16. Mass balance for the raw material and products should be included.
17. Energy balance data for all the components of ferro alloy plant
should be incorporated.
18. Design details of Ferro Alloy Plant including manufacturing
process details should be included.
19. Data generated in the last three years i.e. air, water, raw
material properties and analysis (major, trace and heavy metals), ground water
table, seismic history, flood hazard history etc.
20. Data on existing ambient air, stack emission, fugitive emissions
data; water requirement and water balance cycle; generation, re-utilization and
disposal of solid/ hazardous waste for the existing plant and predicted
increase in pollution load (GLCs) due to proposed expansion should be
incorporated.
21. Point-wise compliance to the specific and general conditions
stipulated in the environmental clearance for the existing plant.
22. Ambient air quality at 8 locations within the study area of 10
km., aerial coverage from project site with one AAQMS in downwind direction
should be carried out.
23. The suspended particulate matter present in the ambient air must
be analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene
soluble fraction. Chemical characterization of RSPM and incorporating of RSPM
data.
24.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
25.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50
mg/Nm3.
26.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
27. Ambient air quality monitoring modeling alongwith cumulative
impact should be included for the day (24 hrs) for maximum GLC alongwith
following :
i) Emissions (g/second) with and without the air pollution control
measures
ii) Meteorological inputs (wind speed, m/s), wind direction, ambient
air temperature, cloud cover, relative humidity & mixing height) on hourly
basis
iii) Model input options for terrain, plume rise, deposition etc.
iv) Print-out of model input and output on hourly and daily average
basis
v) A graph of daily averaged concentration (MGLC scenario) with
downwind distance at every 500 m interval covering the exact location of GLC.
vi) Details of air pollution control methods used with percentage
efficiency that are used for emission rate estimation with respect to each
pollutant
vii) Applicable air quality standards as per LULC covered in the study
area and % contribution of the proposed plant to the applicable Air quality
standard. In case of expansion project, the contribution should be inclusive of
both existing and expanded capacity.
viii) No. I-VII are to be repeated for fugitive emissions and any other
source type relevant and used for industry
ix) Graphs of monthly average daily concentration with down-wind
distance
x) Specify when and where the ambient air quality standards are exceeded
either due to the proposed plant alone or when the plant contribution is added
to the background air quality.
xi) Fugitive dust protection or dust reduction technology for workers
within 30 m of the plant active areas.
28.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
29.
One
season data for gaseous emissions other than monsoon season is necessary.
30.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
31.
Presence
of aquifer/aquifers within 1 km of the project boundaries and management plan
for recharging the aquifer should be included.
32.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
33.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
34.
Ground
water modeling showing the pathways of the pollutants should be included
35.
Column
leachate study for all types of stockpiles or waste disposal sites, at 20oC-50oC
should be conducted and included.
36.
‘Permission’
for the drawl of 4 m3/day water should be
included. Water balance cycle data
including quantity of effluent generated, recycled and reused and discharged is
to be provided. Methods adopted/to be adopted for the water conservation should
be included.
37.
A note
on the impact of drawl of water on the nearby River during lean season.
38.
Action plan for rainwater
harvesting measures at plant site should be submitted to harvest rainwater from
the roof tops and storm water drains to recharge the ground water and also to
use for the various activities at the project site to conserve fresh water and
reduce the water requirement from other sources. Rain water harvesting and groundwater recharge
structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
39.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
40.
If the
site is within 10 km radius of any major river, Flood Hazard Zonation Mapping
is required at 1:5000 to 1;10,000 scale indicating the peak and lean river
discharge as well as flood occurrence frequency.
41.
A note
on treatment of wastewater from different plants, recycle and reuse for
different purposes should be included.
42.
Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents.
43.
If the
water is mixed with solid particulates, proposal for sediment pond before
further transport should be included. The sediment pond capacity should be 100
times the transport capacity.
44.
Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from all
sources should be included.
45.
The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans.
46.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
47.
Geotechnical
data by a bore hole of upto 40 mts. in every One sq. km area such as ground
water level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies and to assess future Seismic Hazard and Earthquake Risk
Management in the area.
48.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
49.
Identification and details of
land to be used for all type of slag disposal in the secured land fill as per
CPCB guidelines should be included.
50.
All
stock piles will have to be on top of a stable liner to avoid leaching of
materials to ground water.
51.
End use
of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
52. Provision of Toxic Chemical Leachability Potential (TCLP) test for
the slag and its end use should be included.
53.
Commitment
that no Ferro chrome will be manufactured without prior approval of the
Ministry.
54.
Acton
plan for the green belt development plan in 33 % area should be included. The
green belt should be around the project boundary and a scheme for greening of
the traveling roads should also be incorporated. All rooftops/terraces should
have some green cover.
55.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
56.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
57.
Occupational
health of the workers needs elaboration. Health effects of other metals used
and health hazard plans based on monthly correlation of these metal related
diseases and people affected and mitigation plans. Arsenicosis Management
Planif Arsenic is present in ore, rock, coal, fly ash, water. Action Plan for
protecting the workers against hazardous chemicals such as Sulphuric acid,
pesticides, solvents etc.
58.
Occupational
health of the workers needs elaboration including evaluation of noise, heat,
illumination, dust, any other chemicals, metals being suspected in environment
and going into body of workers either through inhalation, ingestion or through
skin absorption and steps taken to avoid musculo-skeletal disorders (MSD),
backache, pain in minor and major joints, fatigue etc. Occupational hazards
specific pre-placement and periodical monitoring and periodical monitoring
should be carried out. The detailed plan to carry out above mentioned activity
should be mentioned.
59.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details alongwith time bound action plan should be included.
Socio-economic development activities need to be elaborated upon.
60.
Plan
for the implementation of the recommendations made for the ferro alloy plants
in the CREP guidelines must be prepared.
61.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
62.
Public hearing issues raised and
commitments made by the project proponent on the same should be included
separately in EIA/EMP Report in the form of tabular chart with financial budget
for complying with the commitments made.
63.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The Expert
Committee (Industry) decided that PAs may be communicated the above ‘TORs’ for
the preparation of EIA/EMP. As soon as the draft EIA/EMP report is prepared as
per the ‘General Structure of EIA’ given in Appendix III and IIIA in the EIA
Notification, 2006, the same may be submitted by the PAs to the West Bengal
Pollution Control Board (WBPCB) for conducting public hearing as per EIA
Notification, 2006. On finalization of
EIA/EMP prepared as per TORs addressing all concerns set out in EIA/EMP should
be submitted to the MOEF for prior environmental clearance.
4.16
Ferro Alloy Plant (1x9 MVA, SAF; Fe-Mn,
21,450 TPA or Si-Mn 14,700 TPA) at Village Dewandighi, P.O. Burdwan, District
Burdwan, West Bengal by M/s Himshila Ferro Alloys (Pvt.) Ltd. (TORs)
The project authorities and their consultant
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the preparation
of EIA/EMP. All the Ferro Alloy Plants are listed at S.N. 3(a) under
Primary Metallurgical Industries under Category ‘A’ and appraised at the
Central level.
M/s
Himshila Ferro Alloys (Pvt.) Ltd. have proposed for the Ferro Alloy Plant (1x9 MVA, SAF; Fe-Mn, 21,450 TPA or Si-Mn 14,700 TPA)
at Village Dewandighi, P.O. Burdwan, District Burdwan, West Bengal. Total land acquired is 2.77 acres. Total cost of the project is Rs. 2564.30
Lakhs. Following will be manufactured:
S.N. |
Product |
Capacity |
1st
Phase |
2nd
Phase |
3rd
Phase |
1. |
High Carbon Ferro- Manganese |
21,450 |
15,015 |
16,088 |
17,160 |
2. |
Silico-Manganese |
14,700 |
10,832 |
11,509 |
12,186 |
Mn Ore , coke coal and dolomite will be used as raw materials. Raw material will be smelted in submerged arc furnace. Molten alloy will be poured with the help of ladle. The mould will be cooled by circulation of cold water with the help of cooling tower. Molten alloy and slag will be tapped separately. Hot liquid metal will be moulded in moulds or cast iron pan.
Bag filters will be provided to submerged arc furnace to control
emissions within 100 mg/Nm3 but committee insisted for 50
mg/Nm3. Dust extraction system including bag filters/ scrubbers,
centrifugal fans and FD cooler, hood etc. will be provided. Dust suppression
system will be used to control fugitive emissions.
Total water
requirement from bore wells will be 6 m3/day and have applied for
the same on 21st August, 2009. Cooling tower blow down will be
collected in a guard pond and recycled/ reused for dust suppression and green
belt development. Service water will be passed through oil separator to remove
oil content in the effluent. Domestic effluent will be treated in septic
tank followed by soak pit. No effluent will be discharged outside the
premises and ‘Zero’ discharge will be adopted.
Ferro Manganese will be used for manufacture of Silico-Manganese. Silico-Manganese slag will be used for filling low lying areas. Waste oil and used batteries will be sold to authorized recyclers / re-processors.
Out of 2.77 acres, green belt will be developed in 0.9
acres. 8.5 MVA (8.500 MVA) power will be sourced from DVC. 50 and 30 persons will be employed during
construction and operation phase.
After deliberating on the facts presented before the Expert
Appraisal Committee (Industry), the committee recommended the proposal for the
preparation of EIA/EMP as per the following TORs :
1.
A site
location map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000
scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10
kms and further 10 kms on A3/A2 sheets with proper longitude/latitude/heights
with min. 100/200 m. contours should be included. 3-D view i.e. DEM (Digital
Elevation Model) for the area in 10 km radius from the proposal site.
2.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos, IRS
P-6 pan sharpened etc. for the 10Km radius area from proposed site. The same
should be used for land used/land-cover mapping of the area.
3.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
4.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within 1 km.) dumping, waste disposal, green areas,
water bodies, rivers/drainage passing through the project site should be
included.
5.
Details
and classification of total land (identified and acquired) should be included.
6.
A list
of industries containing name and type in 25 km radius should be incorporated.
7.
Residential
colony should be located in upwind direction.
8.
List of
raw material required and source alongwith mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
9.
Petrological
and Chemical analysis and other chemical properties of raw materials used (with
GPS location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
10.
Petrography,
grain size analysis and Major element analysis of raw material and soil from
project site and raw material should be done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
11.
If the
rocks, ores, raw material has trace elements their petrography, ore microscopy,
XRD, elemental mapping EPMA, XRF is required to quantify the amount present in
it and hence future risk involved while using it and management plan.
12.
Studies
for slag, muck disposal, slurry, sludge material and solid waste generated
should also be included, if the raw materials used has trace elements and a
management plan.
13.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
14.
Mass
balance for the raw material and products should be included.
15.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
16.
Design
details of Ferro Alloy Plant including manufacturing process details should be
included.
17.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
18.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
19.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
20.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50
mg/Nm3.
21.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
22.
Ambient
air quality monitoring modeling alongwith cumulative impact should be included
for the day (24 hrs) for maximum GLC alongwith following :
i)
Emissions (g/second) with
and without the air pollution control measures
ii) Meteorological inputs (wind speed, m/s), wind direction, ambient
air temperature, cloud cover, relative humidity & mixing height) on hourly
basis
iii) Model input options for terrain, plume rise, deposition etc.
iv) Print-out of model input and output on hourly and daily average
basis
v) A graph of daily averaged concentration (MGLC scenario) with
downwind distance at every 500 m interval covering the exact location of GLC.
vi) Details of air pollution control methods used with percentage
efficiency that are used for emission rate estimation with respect to each
pollutant
vii) Applicable air quality standards as per LULC covered in the study
area and % contribution of the proposed plant to the applicable Air quality
standard. In case of expansion project, the contribution should be inclusive of
both existing and expanded capacity.
viii) No. I-VII are to be repeated for fugitive emissions and any other
source type relevant and used for industry
ix) Graphs of monthly average daily concentration with down-wind
distance
x) Specify when and where the ambient air quality standards are
exceeded either due to the proposed plant alone or when the plant contribution
is added to the background air quality.
xi) Fugitive dust protection or dust reduction technology for workers
within 30 m of the plant active areas.
23.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
24.
One
season data for gaseous emissions other than monsoon season is necessary.
25.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
26.
Presence
of aquifer/aquifers within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.