Ministry of Environment
& Forests
(IA Division)
******
SUMMARY RECORD OF THE 14TH MEETING OF EXPERT APPRAISAL COMMITTEE FOR ENVIRONMENTAL APPRAISAL OF MINING PROJECTS CONSTITUTED UNDER EIA NOTIFICATION, 2006.
The 14th meeting of the Expert Appraisal
Committee for Environmental Impact Assessment of Mining Projects of the
Ministry of Environment and Forests was held on April 25-27, 2011. The list of participants is annexed.
After
welcoming the Committee Members, discussion on each of the agenda items was
taken up ad-seriatim.
Item No. 1:
1.1 Confirmation
of the minutes of the 13th Meeting.
The minutes of
the 13th meeting were confirmed as circulated.
Item No. 2: Consideration of the Proposals listed in
the Agenda:
2.1 Dubna-Sakradih Iron & Manganese
Ore Mining Project of M/s Orissa Mining Corporation Ltd., villages Handibhanga,
Jampani, Badakalimati, Dubna, Purunadih, Naibaga and Basantpur, District
Keonjhar, Orissa (Consultant: MECON,
Ranchi)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for renewal of mine lease which fell due in December, 2009 and enhancement of production of iron ore to 1.0 million TPA and manganese ore to 0.06 million TPA. The additional TOR for this project were prescribed on 22.12.2008. Public hearing has been held on 3.9.2009. The mine lease area is 1332.019 ha, which includes 1148.88 ha of forestland. No National Park / Sanctuary is reported within 10 km of the mine lease area. A map duly authenticated by DFO cum Wildlife Warden, Keonjhar Division has been submitted by the proponent. The mine is reported to be closed since 2007. It is a violation case as the proponent had started production of iron ore after 1994, without obtaining requisite prior environmental clearance. It was stated that temporary working permission has been granted for 253.229 ha of already broken up forestland and mine working will be restricted to the already broken up area. No private land is to be acquired for the project. The life of the mine for working within the already broken up area of 253.229 ha of area is estimated to be 6 to 7 years. Mine working will be opencast semi-mechanised. Peak water requirement is estimated as 289 kld, which will be obtained from Jalpa nadi. The ultimate working depth will be 509 m AMSL. The groundwater table is reported to vary between 410 – 418 m AMSL. Mine working will not intersect groundwater table. It is estimated that 8.048 million m3 of OB will be generated. Backfilling is proposed, which will be commenced from 3rd year. It is estimated that about 189 ha of excavated area will be backfilled and afforested. The baseline AAQ data showed that the RSPM levels are higher side. It was also observed that the information and data contained in the EIA report and the mine plan do not reconcile especially in terms of equipment and machinery to be used and GLC values. The issues raised during public hearing were also considered and discussed in the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussions held, the Committee sought information on the following:-
(i) The EIA report and the mine plan should be mutually consistent in terms of data and information.
(ii) Specific safeguard measures proposed for control of RSPM levels should be detailed.
(iii) Mineralogical composition of dust especially the concentration of manganese in air should be given.
(iv) Water requirement to be rechecked and reconfirmed.
(v) Permission from the Competent Authority for drawl of requisite quantity of water for the project shall be secured and a copy furnished.
(vi) Detailed scheme / plan for diversion / realignment of seasonal drains / channels passing through the lease area should be given. Based on detailed analysis, it may be shown whether it will affect the hydrology of the area.
(vii) It may also be shown whether the dump site is getting drained properly. The relevant details in this regard should be furnished.
(viii) Information relating to flora & fauna should be collected afresh and details furnished which may inter-alia include frequency, density and abundance. The period of which the data has been collected should be specified.
(ix) Primary survey of critical wildlife habitat should be carried out and details furnished.
(x) Information relating to input parameters used for modeling should be given as specified in the TORs.
(xi) Statement in tabular form giving details of compliance of TOR in the EIA report should be given along with crossed referencing of the EIA report with relevant sections and pages.
It was decided that the proponent will
submit the response / information on the above-mentioned points by 30.8.2011
and simultaneously circulate the same to the Members of the EAC and thereafter
the proposal will be considered by the EAC during its meeting to be held in September,
2011.
2.2 Bhadrasahi
Iron and Manganese Ore Mining Project of M/s Orissa Minerals Development Co.
Ltd., Village Bhadrasahi,
District Keonjhar, Orissa.
The consideration of the proposal was deferred for want of stage-I forestry clearance in accordance with the office memorandum no. J-11015/200/2008-IA.II(M) dated 31st March, 2011.
2.3 Bhadrasahi
(Kolha-Roida) Iron & Manganese Ore Mine of M/s (Bharat Process &
Mechanical Engineers Ltd.) C/O The Orissa Minerals Development Co. Ltd.,
Village Bhadrasahi, District Keonjhar, Orissa (Consultant: Geomin Consultants Pvt. Ltd, Bhubaneswar)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for renewal of mine lease and enhancement of production of iron ore to 3.0 million TPA and manganese ore to 0.24 million TPA. TOR for this project were prescribed on 8.6.2009. Public hearing has been held on 3.11.2010. The total mine lease area is 254.952 ha, which includes 188.496 ha of forestland. Forestry clearance has been obtained for 119.001 ha (55.502 ha fresh and 63.499 ha of already broken up area). No National Park / Wildlife Sanctuary is reported within 10 km of the mine lease. A map authenticated by DFO cum Wildlife Warden, Keonjhar has been submitted in this regard. Mine working will be opencast mechanized involving drilling and blasting. Water requirement is estimated as 350 kld/day, which will be obtained from Sona river. It has been stated that mine working will not intersect groundwater table. It is estimated that 47,11,000 m3 of waste will be generated. Life of the mine is estimated as 10 years.
It was pointed out that the project coordinates as given in different documents (Mine Plan, EIA and Presentation) submitted by the proponent were at variance with each other. It was stated by the proponent that the information in this regard as given in the EIA report was correct and they would get the necessary correction made in the approved mine plan and submit the same.
It was observed that the AAQ data in respect of some of the air sampling stations was found to be erroneous and also the air sampling stations chosen did not cover the core zone and pre-dominant southward wind direction. The Committee stated that the baseline ambient air quality data needs to be rechecked and revalidated by collecting the baseline AAQ data afresh for at least a month by including two more stations in addition to the existing stations; one in core zone and another within distance of 500 m in the pre-dominant downwind direction (south direction). The data so collected may be submitted.
Further, ambiguity was observed regarding date and time of public hearing as given in the recorded public hearing proceedings. The proponent stated that they would take up the matter with the SPCB for getting the requisite clarifications in this regard.
It was pointed out that the list of flora and fauna submitted by the proponent was not comprehensive and needs to be supplemented. The plan for conservation of flora and fauna was also found to be sketchy and needs to be augmented in respect of all such reported scheduled species.
It was further pointed out that the data base of occupational health survey of the target group of employees, as reported in the EIA, should inter-alia, include age, gender, date of employment, exposure to hazards etc.
In the light of the deficiencies as pointed out above, it was decided that the project may be brought back before the Committee for its consideration after the requisite information as stated above, has been collected and submitted by the proponent.
2.4 Baldhwa
Limestone Mine of Shri R.P. Tiwari located at village Baldhwa, District
Sirmour, Himachal Pradesh (Consultant:
Udaipur Min-Tech Pvt. Ltd., Udaipur)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for renewal of mine lease and enhancement of production of limestone to 1,50,000 TPA. TOR for this project were prescribed on 20.4.2009. Public hearing has been held on 2.11.2010. It is a violation case as the production from the mine was increased after EIA Notification coming into force. The mine lease area is 12.38 ha. It was stated by the proponent that the State Govt. had renewed this lease for an area of 4.91 ha only (from 29.11.2005 to 28.11.2025). However, during inspection of mine plan by IBM and based on their recommendations the State Govt. have informed them in 2009 for inclusion of the remaining area for the balance period of the mine lease. Thus, it amounts to expansion of mine lease area from 4.91 ha to 12.38 ha and thus attracts the provisions of EIA Notification, 2006. Further, the mine lease area is within 10 km of the inter-state boundary of Uttarakhand and Himachal Pradesh and hence has been considered in MoEF as Category ‘A’ Project. No forestland is involved. It was also stated that no National Park / Sanctuary falls within 10 km of the mine lease. In addition, an area of 1.2 ha, outside the mine lease would be required for waste dump. Mine working will be opencast semi-mechanised involving drilling and blasting. Life of mine will be 55 years. Ultimate pit levels will be 1630 mRL. The ground water table is reported to vary between 1540 -1545 mRL. Mine working will not intersect groundwater table. The baseline AAQ data showed the levels within permissible limit. The water requirement for the project is estimated as 6 kld, which will be obtained from Kalhon ka khala. It is estimated that 1,90,400 m3 of waste will be generated during the lease period. No backfilling is proposed. It was observed that the waste dump is located close to the nallah and in order to ensure that no solid waste / debris get into the nallah, appropriate safeguard measures would need to be taken and stability of dump would also need to be ensured. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to following conditions:-
(i) Appropriate safeguard measures shall be taken to ensure stability and drainage of dump so that no solid waste / debris flows into the nallah.
(ii) Regular monitoring of free silica in the dust will be carried out and records maintained. It shall be ensured that the levels of silica do not exceed the prescribed limit. The workers will be provided with personal protective measures to guard against inhailing silica dust.
2.5 Nuagaon
Iron Ore Beneficiation Plant of M/s Kamaljeet Singh Ahluwalia, Village Guali
& Barpada, District Keonjhar, Orissa (Consultant: Creative Engineers & Consultant, Chennai)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for setting up of a iron ore beneficiation plant with a throughput capacity of 2.0 million TPA. The plant will be located within the existing mine lease. The TOR for this project were prescribed on 18.1.2010. Public hearing has been held on 12.1.2011. Land requirement for the project is 4 ha. It was stated by the proponent that the beneficiation plant will be located in the exhausted quarry area for which diversion of forestland was obtained. No National Park / Sanctuary is reported within 10 km of the project. A map duly authenticated by DFO cum Wildlife Warden, Keonjhar has been submitted in this regard. The raw material for the beneficiation plant will be the low grade ore from the mine as well as from re-handling of the old stacks of sub-grade ore. The water requirement is estimated as 1025 kld, which will be obtained from groundwater. The area is reported to fall in safe category from groundwater point of view and necessary permission for drawl of groundwater has been obtained from CGWA. The waste water will be recovered and re-circulated. There will be zero discharge from the project. The groundwater table is reported at 480 m AMSL. It was stated by the proponent that the iron ore production from the Nuagaon Iron Ore Mine including the beneficiation plant will not exceed 5.6 million TPA for which the approval has been obtained. There will be no tailing pond. It is estimated that 0.6 million TPA of rejects will be generated, which will be refilled in the mined out area. The baseline AAQ data showed the PM10 values on higher side. It was also stated that the mineral transportation after 5 years will be only by rail. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the
Committee recommended the project for environmental clearance subject to
following conditions:-
(i) Appropriate safeguard measures shall be taken to ensure that the particulate levels remain within permissible limit.
(ii) Mineral transportation after 5 years will be only by rail.
2.6 Bauxite
Mine of M/s Vyaghreshwar Mineral Industrial Producer’s located at village
Mahal-Mirya and Panchganu, District Raigad, Maharashtra (Consultant: Yogiraj Industrial Consultant, Pune)
The proposal was earlier considered by the Expert Appraisal Committee during its meeting held on January 19-21, 2011 wherein the Committee had sought additional information/clarifications on various related issues. Based on the additional information/clarifications submitted by the proponent, the proposal was considered further. It was observed that the information / clarifications submitted by the proponent did not clarify the issues raised in the last meeting. The response submitted by the proponent was found to be deficient and incomplete. It was, therefore, decided to give one more chance to the proponent to resubmit their response to the various issues latest by 10th May, 2011 and thereafter the proposal be listed for consideration by the EAC in its next Meeting in May, 2011.
2.7 Meghahatuburu
Iron & Manganese Ore Mine of M/s Arcellor Mittal
India Ltd., Village Meghahatuburu, Tehsil Noamundi, District West Singhbhum, Jharkhand (Consultant: Bhagavathi Anna Labs Ltd., Hyderabad)
The proposal was earlier considered by the Expert Appraisal Committee during its meeting held on October 20-22, 2010 wherein the Committee had taken note of the observations made by Jharkhand State Pollution Control Board regarding the higher levels of RSPM and felt that appropriate action may be taken collectively by all concerned to bring down the AAQ levels in the area before any new proposal for mining is considered. Based on the information/data now submitted by SPCB vide their letter dated 15.2.2011, the proposal was included in the agenda for consideration by the EAC. As the entire mine lease area is a forestland and the project proponent is yet to obtain stage-I forestry clearance, keeping in view the office memorandum dated 31st March, 2011 issued by MoEF regarding the procedure to be followed for grant of EC in respect of projects involving forestland, the EAC deferred further consideration of the proposal till the stage-I forestry clearance has been obtained and submitted.
2.8 Iron Ore
Beneficiation Plant of M/s VSL Mining Co. Pvt. Ltd., village Bhujanganagara,
Sandur Taluka, District Bellary, Karnataka (Consultant: Bhagavathi Anna Labs Ltd., Hyderabad)
The proposal was
considered by the Committee to determine the Terms of Reference (TOR) for
undertaking detailed EIA study for the purpose of obtaining environmental
clearance in accordance with the provisions of the EIA Notification, 2006. For this purpose, the proponent had submitted
information in the prescribed format (Form-1) along with project report.
The proposal is for setting up of a iron ore
beneficiation plant having a capacity of 1.0 million TPA throughput. It was stated by the project proponent that
the filter press technology will be adopted.
The total area for the project is 16.15 ha including land for staking
tails cake in the tailing dump area. No
forestland is involved. Make up water
requirement of the project is estimated as 75m3/hr, which will be obtained from
groundwater. It was noted that the baseline AAQ data collection has already
started which will be continued during the pre-monsoon season.
Based on the
information furnished and presentation made, the Committee prescribed the
following TORs for undertaking detailed EIA study:-
1) The alternate sites considered, the relative merits and demerits and the reasons for selecting the proposed site may be furnished.
2) Details of the technology and process involved in the project may be given.
3) The study area will comprise of 10 km zone around the project area and the data contained in the EIA such as waste generation etc should be for the life of the project.
4) Size distribution of the iron ore with percentage weight (Particulate size analysis) shall also be done to assess the source of fugitive dust emission of the ore feed to the plant.
5) Measures to manage the over size waste from the feed ore shall be provided.
6) Details of the solid waste to be generated and its management should be described. The State of the art technology in this regard and supporting documents and literature in support thereof, to show that such a technology is being adopted successfully in other parts of the World or in the country anywhere, should be given. The related environmental issues associated such technology including the incremental requirement of power in adopting such technology vis-a-vis other technologies should also be discussed in the EIA report. Management of fines and mitigation measures to control these fines from getting airborne should also be discussed.
7)
Land use of the
study area should be indicated delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features.
8)
The land
requirement should be optimized and furnished.
9)
Land use plan
of the project area should be prepared to encompass pre-operational,
operational and post operational phases.
10)
Location of the
proposed plant w.r.t. the source of raw material and mode of transportations of
the ore from mines to the beneficiation plant should be brought out.
11)
Treatment of
run off water/affluents from the fines/waste dump should be described.
12)
Estimation of
the fines going into the washings and its management should be made.
13)
Details of the
equipment, settling pond etc. should be provided.
14)
Detailed
material balance should be provided.
15)
Source of raw
material and its transportation should be indicated. Steps proposed to be taken to protect the ore from getting air
borne should be furnished.
16)
Management and
disposal of tailings/filter press cake and closure plan of the tailing pond, if
any, after the project is over should be given.
17)
Biological as
well as health impact of fines and other dust generated in the plant should be
studied with reference to National and International Standards (WHO and ILO
standards including CPCB norms). The
proposed mitigation measures with EMP should also be provided.
18) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife corridors, Tiger/Elephant reserves (existing as well as proposed), if any, within 10 km of the mine lease should be clearly indicated. Necessary clearance, if any, as may be applicable to such projects due to proximity of the ecologically sensitive areas as mentioned above should be obtained from the State Wildlife Department/ Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
19)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
20)
R&R plan /
compensation details for the project affected people, if any, should be
given.
21)
Collection of
one season (non-monsoon) primary baseline data on ambient air quality, water
quality, noise level, soil and flora and fauna should be carried out and
included in the EIA report.
Site-specific meteorological data should also be collected and included
in the EIA report. The location of the
monitoring stations should be justified keeping in view the pre-dominant down
wind direction and location of sensitive receptors. The baseline data already collected could be utilized provided it
meets the monitoring protocol.
22)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area and results furnished in the EIA report. It should also
take into account the impact of movement of vehicles for transportation of
mineral. The details of the model used and input parameters used for modeling
should be provided. The air quality
contours may be shown on a location map clearly indicating the location of the
site, location of sensitive receptors, if any and the habitation. The wind roses showing pre-dominant wind
direction may also be indicated on the map.
The modelling should also take into account the impact due to operation
of generator sets to meet the emergency power requirement for the project.
23) Details of maximum inventory of fuel for the generator sets to be stored at site, if any, and its associated risk analysis in the worst case scenario should be given. The risk contours should be plotted on the location map.
24)
The water
requirement for the project, its availability and source to be furnished. A detailed water balance should also be
provided. Fresh water requirement for
the project should also be indicated.
25)
Necessary
clearance from the Competent Authority for drawl of requisite quantity of water
for the project should be provided.
26)
Details of
water conservation measures proposed to be adopted in the project should be
furnished.
27)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required, should be provided.
28)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
29)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided.
30)
Impact on local
transport infrastructure due to the project should be studied and results provided. Projected increase in truck traffic as a
result of the project in the present road network (including those outside the
project area) and whether it is capable of handling the increased load should
be given. Arrangement for improving the
infrastructure, if contemplated including action to be taken by other agencies
such as State Government, if any, should be covered.
31)
Details of the
infrastructure facilities to be provided for the workers should be detailed.
32)
Phase-wise plan
of greenbelt development, plantation and compensatory afforestation clearly
indicating the area to be covered under plantation and the species to be
planted should be detailed. The details of plantation already done should also be
given.
33)
Occupational
health impact of the project should be furnished. Details of pre-placement medical examination and periodical
medical examination schedules should be incorporated in the EMP.
34)
Measures of
socio economic influence to the local community proposed to be provided by
project proponent should be given. As
far as possible, quantitative dimension to be given.
35)
Detailed
environmental management plan to mitigate the environmental impacts due to the
project should be furnished.
36)
Public hearing
points raised and commitment of the project proponent on the same should be
given in the EIA.
37)
Any litigation
pending against the project and /or any direction /order passed by any Court of
Law against the project, if so, details thereof should be given in the EIA
report.
38)
The cost of the
project (capital cost and recurring cost) as well as the cost towards
implementation of EMP should clearly be spelt out.
Besides the above, the below mentioned
general points are also to be followed:-
a) All
documents to be properly referenced with index and continuous page
numbering.
b) Where data are presented in the report
especially in tables, the period in which the data were collected and the
sources should be indicated.
c) Where the documents provided are in a
language other than English, an English translation should be provided.
d) The Questionnaire for environmental appraisal
of industrial projects as devised earlier by the Ministry shall also be filled
and submitted.
e)
While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No.
J-11013/41/2006-IA.II(I) dated 4th August, 2009, which are available
on the website of this Ministry, should also be followed.
The EIA report should also include (i) surface plan of the area indicating contours of main topographic features, drainage and mining area, (ii) geological maps and sections and (iii) sections of the mine pit and external dumps, if any, clearly showing the land features of the adjoining area.
After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will get the public hearing conducted and take further necessary action for obtaining environmental clearance in accordance with the procedure prescribed under the EIA Notification, 2006.
2.9 Mangrol
Tilakhera Limestone Mine of M/s JK Cement Works, Mangrol, Tehsil Nimbahera,
District Chittorgarh, Rajasthan (299 ha) (TOR)
The consideration of the
proposal was deferred at the request of the project proponent.
2.10 Expansion
of Mining Project of Minor Mineral Sand Quarries of M/s S.S. & Company,
District Panipat, Haryana (TOR)
The
consideration of the proposal was deferred at the request of the project
proponent.
2.11 Expansion
of Mining Project of Minor Mineral Sand Quarries of M/s S.S. & Company,
District Sonipat, Haryana (TOR)
The consideration of the proposal was deferred at
the request of the project proponent.
2.12 Golden
Hills Resort Mine of M/s Golden Hills Resort Pvt. Ltd. Village Jai Surjana,
Achora, Nagri and Bhilpakher, Tehsil and District Chittoragarh, Rajasthan
(Consultant: Enkay Enviro Services, Jaipur)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose, the
proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for opening of a new mine for production of 1.38 million
TPA of limestone and 0.4 million TPA of red ochre. The mineral will be used for their cement plant at a distance of
above 27 km for which TORs have reportedly been prescribed by the Industry
Committee in November, 2010. The mine
lease area is 242.104 ha. No forestland
is involved. No National Park /
Sanctuary is reported within 10 km of the mine lease. Mine working will be opencast mechanized involving drilling and
blasting. Life of mine is 32
years. The water requirement is 70 kld,
which will be obtained from groundwater.
It was noted that the baseline AAQ data collection has already started
which will be continued during the pre-monsoon season.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
4)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
5)
Land use plan of the mine lease area should be prepared to encompass pre-operational,
operational and post operational phases and submitted.
6)
A confirmation may be adduced, duly authenticated by the competent
authority in the State Government, to the effect whether the project falls in
Aravalli and whether it is covered by the order of the Hon’ble Supreme Court
dated 8.4.2005 in the contempt petition (c) 412/2004 in writ petition 202 of
1995 in the matter of Godavarman vs Union of India.
7)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
8)
A detailed primary
biological survey of the study area [core zone and buffer zone (10 km radius from
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished, based on field studies, clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
9)
Impact of
change of land use should be given.
10)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes should be prepared accordingly,
integrating the sectoral programme of line departments of the State
Government.
11)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10, particularly
for free silica, should be given. The baseline data already collected could be
utilized provided it meets the monitoring protocol.
12)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
13)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water requirement for the project
should be indicated.
14)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be secured and copy thereof provided.
15)
Details of water conservation measures proposed to be adopted in the
project should be given.
16)
Impact of the
project on the water quality, both surface and below ground, should be assessed
and necessary safeguard measures, if any required, should be provided.
17) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
18) Details of first order streams, if any, passing through lease area and modification/ diversion proposed, if any, and the impact of the same on the hydrology, should be brought out.
19)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
20)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
21)
Quantity of
solid waste generation should be estimated and details of its disposal and management
should be provided. The quality, volumes and methodology planned for removal
and utilisation (preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly indicated that out of the total waste
generated during the mine life, how much quantity would be backfilled and how
much quantity would be disposed off in the form of external dumps (number of
dumps, their height, terraces etc. to be brought out).
22)
The reclamation
plan, post mine land use and progressive greenbelt development plan shall be
prepared in tabular form (prescribed format) and submitted.
23)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
24)
Details of the
infrastructure facilities to be provided for the mine workers should be included
in the EIA report.
25)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
26)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
27)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
28)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
29)
Detailed environmental management plan to mitigate the environmental
impacts, which should inter-alia include the impact due to change of land use,
due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the project.
30)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
31) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
32) The cost of the project (capital cost and recurring cost) as well as the cost towards implementation of EMP should be clearly spelt out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry, shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter from the
concerned Authority for the proposed capacity should be submitted.
g)
While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No.
J-11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.13 Consideration
of the order of the Hon’ble National Environment Appellate Authority dated 15th
September, 2010 in Appeal no. 18/2009 in the matter of Shri Prafulla Samantra
Vs MoEF and others relating to EC to Lanjigarh Bauxite Mining Project of M/s
Orissa Mining Corporation Ltd. in Kalahandi and Rayagada Districts of Orissa. (Internal Consideration)
Pursuant to the directions of the Hon’ble National Environment
Appellate Authority, Ministry of Environment & Forests has referred the
matter to the Expert Appraisal Committee for their consideration. The EAC after deliberating the matter during
its meetings held in December 2010, constituted a Sub-Committee of the EAC to
go into the details of the two EIA reports referred to in the order of the
Hon’ble NEAA. Accordingly, the two EIA
reports, namely the one prepared by M/s TATA AIG and the other prepared by
Vimta Labs were obtained by the Ministry and made available to the members of the
said Sub-Committee. The Sub-Committee examined
both these reports in detail and apprised the EAC about their observations on
the two reports in the EAC Meeting held in March, 2011. Based further on the observations of the EAC
on their findings, the Sub-Committee finalized and submitted its report to the
EAC, which was discussed and deliberated during this Meeting. The EAC agreed
with the observations and recommendations of the Sub-Committee and the report
submitted by the Sub-Committee is accepted by the EAC. The Sub-Committee has concluded as under:-
“The Sub-Committee has
scrutinized the entire case of the Lanjigarh Bauxite Project of M/s Orissa
Mining Corporation Ltd with reference to the directive of NEAA, including the
documents submitted, the deliberations in the Supreme Court, the orders of the
Honourable Supreme Court, deliberations in the NEAA, the orders of NEAA and the
relevant minutes of the various meetings of the EAC whenever this project has
come up for discussions. The Sub-Committee
is of considered opinion that all the aspects relating to the Environment
Management have been thoroughly scrutinized by the various agencies and have
brought out an effective Management Plan for the Lanjigarh Bauxite
project. The Sub-Committee also felt
that the absence of Vimta Lab Report in public domain and the absence of Tata
AIG report to the EAC in no way had any tangible effect on the outcome, more so,
when additional reports from independent agencies viz, Wildlife Institute of
India, CMPDI etc have been prepared to augment the management plan. The formation of Special Purpose Vehicle for
the benefit of the tribal community inhabitants, serves as an antidote to human
miseries. Hence the Sub-Committee opines
that the Environment Clearance recommended by the previous EAC (Mining) is in
order. However, it is felt that
additional three conditions may be considered to be incorporated in the special
conditions as additional conditions along with already stipulated conditions.
a)
Effective monitoring
of the functioning of the SPV is of paramount importance to see that the real
benefits are reaching the target group.
To this effect a special condition may be laid for monitoring and
reporting to the authorities concerned.
b)
That the transport
system of ore by Pipe Conveyors from the mine to the refinery, as committed by
the proponent may be insisted as an additional condition to dissuade the
proponent from switching over to any other mode of transportation.
c)
That the installation
of Dry Fog system of dust suppression in the Crusher House as committed by the
proponent before start of the operation of the crusher be reiterated.”
2.14 Dhelana
Soapstone Mine of M/s Resurgere located at village Dhelan, Tehsil Kherwara,
District Udaipur, Rajasthan (Consultant: Apex Mintech Consultants, Udaipur)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for enhancement of production of soapstone from 6,000 TPA to 0.15 million TPA. TOR for this project were prescribed on 12.5.2009. Public hearing has been held on 9.4.2010. The mine lease area is 52.03 ha. No forest land is involved. Life of mine is 30 years. Mine working will be opencast semi-mechanised involving drilling and blasting. No National Park / Sanctuary is reported within 10 km of the mine lease. The water requirement for the project is estimated as 14 kld, which will be obtained from pit water and groundwater. The ultimate working depth will be 245 mRL. The groundwater table is reported to vary between 235 – 240 mRL. Mine working will not intersect groundwater table. The baseline AAQ data showed that the RSPM levels at the mine site were on higher side while at other locations the levels were within permissible limits. It was felt that effective safeguard measures would need to be taken to bring down the RSPM levels within permissible limits. It is estimated that 13,51,000 m3 of waste will be generated during the life of the mine. It was stated that backfilling will start after 10 years. Till such time, the OB will be stored in the form of an external OB dump in earmarked site covering an area of 4 ha. Rehandling of OB is not proposed. At the conceptual stage, an area of 2.5 ha will be converted into water body, plantation will be raised in an area of 17.5 ha, which includes backfilled area, dump and greenbelt. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to the following conditions:
(i) Development of greenbelt should start immediately and should be completed within first 4 years.
(ii) As part of the post project monitoring of mine dust analysis, it is advised to check for presence of Tremolite/Asbestos fiber, if any, by carrying out fibre analysis of the dust samples. In the eventuality of presence of such fibers, necessary safeguard measures including provision of personal protective devices for the workers should be made.
(iii) Effective measures for control of RSPM level in the mine lease area shall be implemented in the project and their effectiveness monitored regularly.
2.15 Habbigegudda
Iron Ore Mine of M/s Karnatak Mining Co. Pvt. Ltd., Honnebagi, Bullenahalli and
Yerekatte Village, Chikkanayakanahalli Taluk, District Tumkur, Karnataka (Consultant: Global Environment and Mining
Services, Bellary)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for enhancement of production of iron ore from 0.442 million TPA to 0.879 million TPA. TOR for this project were prescribed on 31.7.2008. Public hearing has been held on 8.9.2009. The mine lease area is 128.68 ha. No forestland is involved. Mine working will be opencast mechanized involving drilling and blasting. Life of mine is 19 years. Water requirement will be 50 kld, which will be obtained from bore well. No National Park / Sanctuary is reported within 10 km of the mine lease. It was noted that nallahs are passing through the mine lease and it would be desirable to take effective safeguard measures for ensuring slope stability to arrest silt from going into the nallahs. It was categorically stated by the proponent that there is no proposal for beneficiation plant as part of this project. The RSPM levels were observed to be on higher side. It was also observed that the locations of the AAQ monitoring stations have not been selected properly. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussions held, the Committee sought information on the following:-
(i) The baseline AAQ data should be collected afresh for one month continuously during the ongoing pre-monsoon season by properly selecting the monitoring stations. There should be at least two monitoring stations in the north west direction (one within 500 m of mine lease) and one in eastern direction, in addition to the earlier selected monitoring stations. The monitoring parameters should be as per the latest AAQ standards.
(ii) The particulate dust should be analysed for its mineralogical composition. The concentration of free silica in the dust should also be analysed.
(iii) Modeling should take into account the cumulative impacts and the isopleths plotted.
(iv) Slope stability study for the dump should be carried out and details furnished.
(v) Information regarding gradient of the road should be given.
(vi) Specific safeguard measures proposed to arrest silt from going into the nallahs passing through the mine lease should be given.
(vii) Details of waste to be generated during the lease period / conceptual stage and its management should be detailed.
(viii) A written confirmation to the effect that there is no proposal for beneficiation plant as part of this project should be submitted.
It was decided that the proponent will submit the response / information on the above-mentioned points by 30th June, 2011 and simultaneously circulate the same to the Members of the EAC and thereafter the proposal will be considered by the EAC during its meeting to be held in July, 2011.
2.16 Bauxite
Mining Project (Survey No 275) of M/s Orient Abrasives Ltd., Moti Balachor
Village, Abdasa Taluka, District Kuchchh, Gujarat (Consultant: Kadam Environmental Consultants, Vadodra)
The proposal was
considered by the Committee to determine the Terms of Reference (TOR) for
undertaking detailed EIA study for the purpose of obtaining environmental
clearance in accordance with the provisions of the EIA Notification, 2006. For this purpose, the proponent had
submitted information in the prescribed format (Form-1) along with mine plan.
The proposal is
for enhancement of production of bauxite to 85,228 TPA. It is a violation case as the proponent has
increased production in the year 2000-2001 without obtaining requisite prior
environmental clearance. It was noted that the lease was originally granted in
September, 1973 for a period of 20 years.
The lessee had applied for first renewal for 10 years, which is
pending. The lessee had applied for 2nd
renewal in 2003, which is also reported to be pending. The Committee observed that as such, the
position regarding grant of mine lease is unconfirmed. It was also observed that the Naria river is
passing through the mine lease and a part of the water reservoir is falling
within the mine lease area.
In view of the above, the Committee desired that in the first place, an
unambiguous commitment from the State Government should be obtained conforming that they are willing to grant
mine lease for the said mine to the lessee and a copy furnished to MoEF for
further consideration of the proposal.
In case, no response is received within 3 months, the proposal will
stand rejected. Till such time the file
may be closed.
2.17 Sand Stone
and Khanda (minor mineral) Mine of M/s Laxmi Chand Goyal, Village Chaikora
& Kharaga Ka Nagala, Tehsil-Rupbas and District Bharatpur, Rajasthan (Consultant: Enkay Enviro Services, Jaipur)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose, the
proponent had submitted information in the prescribed format (Form-1) along
with mine plan.
The proposal is
for renewal of mine lease for production of 1,00,037 TPA of sand stone and
khanda (minor mineral). The mine lease
area is 48.70 ha. No forestland is
involved. It has been considered as
category ‘A’ project because of inter-state boundary of U.P. and Rajasthan at a
distance of 1 km. No National Park /
Sanctuary is reported within 10 km of the mine lease. Mine working will be opencast manual. Life of the mine is 41 years.
Water requirement is 15 kld, which will be obtained from nearby
villages. It was noted that the
baseline AAQ data collection has already started which will be continued during
the pre-monsoon season. The mine is
reported to be closed for the last 7 years.
Based on the information furnished and presentation made, the Committee
prescribed the following TORs for undertaking detailed EIA study:-
1)
Year-wise production prior to EIA Notification, 2006 coming into force
and clearly stating the highest production achieved in any one year prior to
2006. It may also be categorically
informed whether there had been any increase in production after the EIA
Notification, 2006 coming into force w.r.t. the highest production achieved
prior to 2006.
2)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
3)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
4)
The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
5)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
6)
Land use plan of the mine lease area should be prepared to encompass pre-operational,
operational and post operational phases and submitted.
7)
A confirmation may be adduced, duly authenticated by the competent
authority in the State Government to the effect whether the project falls in
Aravalli and whether it is covered by the order of the Hon’ble Supreme Court
dated 8.4.2005 in the contempt petition (c) 412/2004 in writ petition 202 of
1995 in the matter of Godavarman vs Union of India.
8)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
9)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
10)
Impact of
change of land use should be given.
11)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
12)
One season (non-monsoon)
primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data
should also be collected. The location
of the monitoring stations should be justified. There should be at least one monitoring station within 500 m of
the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given. The
baseline data already collected could be utilized provided it meets the
monitoring protocol.
13)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
14)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
15)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
16)
Details of water conservation measures proposed to be adopted in the
project should be given.
17)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
18) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
19) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
20)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
21)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
22)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
23)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
24)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
25)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
26)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
27)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done should be given.
28)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
29)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
30)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects.
31)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
32) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
33)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.18 Bimta
Limestone & Dolomite Mines of M/s Rasiklal & Co. at Bimta, Sub Division
Panposh, District Sundargarh, Orissa (Consultant:
Earth & Environment, Bhubaneswar)
The proposal was considered by the Committee
to determine the Terms of Reference (TOR) for undertaking detailed EIA study
for the purpose of obtaining environmental clearance in accordance with the
provisions of the EIA Notification, 2006.
For this purpose, the proponent had submitted information in the
prescribed format (Form-1) along with pre-feasibility report.
The proposal is for renewal of mine lease which fall due in November,
2011 and enhancement of production of limestone to 60,000 TPA. The mine lease area is 42.148 ha, which
includes 1.343 ha of forestland. The
proposal has been considered as Category ‘A’ because of the inter-state boundary
between Orissa and Jharkhand at a distance of 4.6 km. In view of the office memorandum dated 31st March,
2011, the proponent was asked to provide a copy of the application submitted
for diversion of forestland involved in the project for further consideration
of the proposal. The proponent
requested for deferment which was agreed to by the Committee. It was decided that the proposal will be
taken up for consideration after the requisite documents have been submitted by
the proponent.
2.19 Limestone Mine of M/s Zawar Cement located at village
Chittapur, District Gulbarga, Karnataka (Consultant:
Mineral Engineering Services, Bellary)
The proposal was earlier considered by the Expert Appraisal Committee during its meetings held on November 24-26, 2010 and March 23-25, 2011 wherein the Committee had sought additional information/clarifications on various related issues. Based on the additional information/clarifications submitted by the proponent, the proposal was considered further. It was stated that the Zawar Cement is a wholly owned subsidiary of J.P. Associates. It is estimated that 7,70,523 m3 of OB will be generated. A part of it will be utilized for construction of bund wall approach road and remaining will be backfilled. The backfilled area will be utilized for afforestation and development of greenbelt. The authenticated list of flora and fauna was also provided. The issues raised during public hearing were also discussed and clarified. The other issues raised by the Committee were also clarified.
Based on the presentation made and discussion held, the
Committee recommended the project for environmental clearance.
2.20 Kathpal Chromite Mine of M/s Ferro
Alloys Corp. Ltd., Village Kathpal, Taluka Kamakhyanagar, District Dhenkanal,
Orissa (TOR)
The consideration of the
proposal was deferred at the request of the project proponent.
2.21 Argat
Limestone Deposit of M/s Jaiprakash Associated Ltd., Thanghatia, Bihri, Jhopa,
Kothari, Argat & Jigna Villages, Ramnagar Tehsil, Satna District, M.P. (Vimta Labs Ltd., Hyderabad)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose, the
proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for opening of a new mine for production of 1.2 million
TPA of limestone to meet the enhanced limestone requirement of their cement
plant. The mine lease area is 363.07
ha. No forestland is involved. No National Park / Sanctuary is reported
within 10 km of the mine lease. Mine
working will be opencast mechanized involving drilling and blasting. Life of mine is 11 years. Ultimate working depth will be 36 m bgl (314
mRL). Water requirement is 150 kld/day,
which will be obtained from mine sump water.
The groundwater table is reported to vary between 305 – 308 mRL. Mine working will not intersect groundwater
table.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
Explore the use of surface miners and details in this regard should be
furnished.
4)
Due to location of the mine in proximity of the habitation and a village
is sandwiched between the mine, the impact of the project on habitation and the
specific precautions to be taken to minimize the impact of the project should
be detailed.
5)
Cumulative impact of the cement plant and other mines in the impact zone
should be taken into account.
6)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
7)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
8)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
9)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
10)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
11)
Impact of
change of land use should be given.
12)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
13)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring
station within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given.
14)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
15)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
16)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
17)
Details of water conservation measures proposed to be adopted in the
project should be given.
18)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
19) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
20) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
21)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
22)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
23)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any, should
also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
24)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
25)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
26)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
27)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
28)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
29)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
30)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
31)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects.
32)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
33) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
34)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.22 Mogalgad Bauxite Mining Project of M/s
Hindalco Industries Ltd., Village Mogalgad, Chandgad Taluka, District Kolhapur,
Maharashtra (Consultant: Metamorphosissm,
Bangalore)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for opening of a new mine for production of 0.1 million
TPA of bauxite. The mine lease area is
7.5 ha, which is a forestland. In
addition, 1.55 ha of land outside the mine lease will be required for haul
road. The proposal has been considered
as category ‘A’ because of its location within 10 km of the inter-state
boundary of Maharashtra and Karnataka. The said project was earlier recommended
for environmental clearance in July, 1996; however, environmental clearance
letter was not issue for want of forestry clearance. Stage-I forestry clearance
has been obtained vide letter dated 6.10.2009.
Mine working will be opencast with conventional drilling and blasting
with manual sorting and breaking. No
crushing is proposed at site. Mine
working will not intersect groundwater table.
Life of the mine is 10 years.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
4)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
5)
Land use plan of the mine lease area should be prepared to encompass pre-operational,
operational and post operational phases and submitted.
6)
Status of
forestry clearance for the forestland involved in the project including
deposition of net present value (NPV) and compensatory afforestation (CA).
7)
Implementation
of status of recognition of forest rights under the Scheduled Tribes and other
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006.
8)
Impact of the
project on the wildlife in the surrounding and any other protected area and
accordingly detailed mitigative measures required should be worked out with
cost implications and submitted.
9)
The vegetation
in the RF / PF area should be given.
Details in this regard should be given.
10)
A study shall
be got done to ascertain the impact of the mining project on wildlife of the
area and details furnished.
11)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
12)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
13)
Impact of
change of land use should be given.
14)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
15)
The already
collected baseline AAQ data should be revalidated by collecting one month (non-monsoon)
primary baseline data on ambient air quality (PM10, SO2
and NOx). Further, data on water
quality, noise level, soil and flora and fauna shall be collected. The AAQ data so collected should be
presented date-wise in the EIA and EMP report and compared with the data
collected earlier. Site-specific
meteorological data should also be collected.
The location of the monitoring stations should be justified. There should be at least one monitoring
station within 500 m of the mine lease in the pre-dominant downwind
direction. The location of AAQ station
should include one in the west direction at about 500 m, another in the west direction
at 3 km and another in south east direction at 3 km, in addition to the
existing monitoring stations. The
mineralogical composition of PM10 particularly for free silica
should be given. The groundwater data
should have at least four observations during the month i.e. per week and in
west direction at a distance of 2 -3 km from the mine lease.
16)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
17)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance should
also be provided. Fresh water
requirement for the project should be indicated.
18)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
19)
Details of water conservation measures proposed to be adopted in the
project should be given.
20)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
21) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
22) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
23)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
24)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
25)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
26)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
27)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
28)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
29)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
30)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
31)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
32)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
33)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects.
34)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
35) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
36)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.23 Arutla Mining (minor mineral) Project
of M/s The A.P. Mineral Development Corp. Ltd., Village Arutla, Manchal Mandal,
Ranga Reddy District Hyderabad, Andhra Pradesh (Consultant: EPTRI, Hyderabad)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with feasibility report.
The proposal is for opening of a new mine for production of 4.0 million
TPA of granite mineral to be used as road metal and for construction
activities. The mine lease areas is
301.98 ha. No forestland is
involved. No National Park / Sanctuary
is reported within 10 km of the mine lease.
Mine working will be opencast involving drilling and blasting. Ultimate working depth will be 15 m bgl.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
4)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
5)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
6)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas
as mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
7)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
8)
Impact of
change of land use should be given.
9)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
10)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given.
11)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
crushers and movement of vehicles for transportation of mineral. The details of
the model used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
12)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
13)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
14)
Details of water conservation measures proposed to be adopted in the
project should be given.
15)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
16) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
17) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
18)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
19)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
20)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
21)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form (prescribed
format) and submitted.
22)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
23)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
24)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
25)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
26)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
27)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
28)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects. Specific safeguard measures to control particulate level (PM10
and PM2.5) as also the noise levels due to crushers should be built
into the EMP.
29)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
30) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
31)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.24 Dandumailaram Mining Zone of M/s The
A.P. Mineral Development Corp. Ltd., Village Dandumailaram, Ibrahimpatnam
Mandal, District Ranga Reddy, Andhra Pradesh (Consultant: EPTRI, Hyderabad)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with feasibility report.
The proposal is for opening of a new mine for production of 4.0 million
TPA of granite mineral to be used as road metal and for construction
activities. The mine lease areas is
192.0 ha. No forestland is
involved. No National Park / Sanctuary
is reported within 10 km of the mine lease.
Mine working will be opencast involving drilling and blasting. Ultimate working depth will be 10 m bgl.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
4)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
5)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
6)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
7)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
8)
Impact of
change of land use should be given.
9)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
10)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given.
11)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
crushers and movement of vehicles for transportation of mineral. The details of
the model used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
12)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
13)
Necessary clearance from the Competent Authority for drawl of requisite quantity
of water for the project should be provided.
14)
Details of water conservation measures proposed to be adopted in the
project should be given.
15)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
16) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
17) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
18)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
19)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
20)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
21)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
22)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
23)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
24)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
25)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
26)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
27)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
28)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects. Specific safeguard measures to control particulate level (PM10
and PM2.5) as also the noise levels due to crushers should be built
into the EMP.
29)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
30) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
31)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.25 Iron Ore Beneficiation Plant of M/s K.
Rajamohan Reddy Mine Owner, Village Chabali, Tehsil Pendlimarry Mandal,
District Kadapa, Andhra Pradesh (TOR)
The
proposal was taken up for consideration by the Committee; however, it was noted
that the consultant accompanying the proponent namely, M/s Palle Consultants
Pvt. Ltd., Hyderabad was not amongst the consultants listed with QCI as per the
list given on the website of MoEF. In
view of the same, the Committee did not allow the presentation to be made.
2.26 Proposed Expansion of Iron Ore Mines
of M/s Mideast Integrated Steel Ltd., Village Tonto, Tehsil Barbil, District
Keonjhar, Orissa (Consultant: S.S.
Environics (India) Pvt. Ltd., Bhubaneswar)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose, the
proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for enhancement of production of iron ore from 3.0
million TPA to 6.0 million TPA and to have a new crushing and screening plant
of 1400 TPH capacity while the existing one of 800 TPH capacity will be phased
out. In addition, conveyor for
transportation of fines with a capacity of 850 TPH will be installed. The mine lease area is 104.68 ha, which is a
forestland. Out of this, 23.393 ha is
broken up area prior to 1980 and forestry clearance was obtained for another
28.597 ha, thus totaling to 51.99 ha.
For the balance 44.109 ha diversion proposal has been submitted. No National Park / Sanctuary is reported
within 10 km of the mine lease. Mine
working will be opencast mechanized.
Ultimate working depth will vary between 538 - 522 mRL. Groundwater table varies between 480 – 490
mRL. Mine working will not intersect
groundwater table. Life of the mine is
11 years. Water requirement is 600 kld,
which will be met from karo river.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
Status of
compliance of the earlier EC conditions along with supporting documents and
photographs should be submitted.
2)
Year-wise production details since 1994 onwards should be given clearly
stating the highest production achieved in any one year prior to 1994. It may also be categorically informed
whether there had been any increase in production after the EIA Notification,
1994 coming into force w.r.t. the highest production achieved prior to
1994.
3)
A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
4)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
5)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
6)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
7)
Land use plan of the mine lease area should be prepared to encompass pre-operational,
operational and post operational phases and submitted.
8)
Status of
forestry clearance for the broken up area and virgin forestland involved in the
project including deposition of net present value (NPV) and compensatory
afforestation (CA). A copy of the
forestry clearance should also be furnished.
9)
Implementation
of status of recognition of forest rights under the Scheduled Tribes and other
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006.
10)
Impact of the
project on the wildlife in the surrounding and any other protected area and
accordingly detailed mitigative measures required should be worked out with
cost implications and submitted.
11)
The vegetation
in the RF / PF area should be given.
Details in this regard should be given.
12)
A study shall
be got done to ascertain the impact of the mining project on wildlife of the
area and details furnished.
13)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors, Tiger/Elephant
Reserves (existing as well as proposed), if any, within 10 km of the mine lease
should be clearly indicated supported by a location map duly authenticated by
Chief Wildlife Warden Necessary clearance, if any, as may be applicable to such
projects due to proximity of the ecologically sensitive areas as mentioned
above should be obtained from the State Wildlife Department/ Chief Wildlife
Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
14)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
15)
Impact of
change of land use should be given.
16)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
17)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10
should be given.
18)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
19)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
20)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
21)
Details of water conservation measures proposed to be adopted in the
project should be given.
22)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
23) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
24) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
25)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
26)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
27)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
28)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
29)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
30)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
31)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
32)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done should be given.
33)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
34)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
35)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects.
36)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
37) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
38)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.27 Limestone Mineral of M/s Rithesh Rathod, Village Nishani,
Mandal: Kerameri, District Adilabad, Andhra Pradesh (Consultant: Pioneer Enviro Laboratories and Consultant Pvt. Ltd.,
Hyderabad)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for opening of a new mine for production of 3.2 million
TPA of limestone. The mine lease area
is 282.99 ha, which is a forestland.
The proponent have already applied for forestry clearance. Mine working will be opencast mechanized
involving drilling and blasting. Life
of mine is 32 years. Water requirement
is 30 kld, which will be obtained from groundwater. Ultimate working depth will be 41 m from surface. Groundwater table is at 20 m bgl. Mine working will not intersect groundwater
table. The inter-state boundary is
abutting the mine lease. No National
Park / Sanctuary is within 10 km of the mine lease.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee.
3)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
4)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be indicated.
5)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
6)
Status of
forestry clearance for the forestland involved in the project including
deposition of net present value (NPV) and compensatory afforestation (CA). A copy of the forestry clearance should also
be furnished.
7)
Implementation
of status of recognition of forest rights under the Scheduled Tribes and other
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006.
8)
Impact of the
project on the wildlife in the surrounding and any other protected area and
accordingly detailed mitigative measures required should be worked out with
cost implications and submitted.
9)
The vegetation
in the RF / PF area should be given.
Details in this regard should be given.
10)
A study shall
be got done to ascertain the impact of the mining project on wildlife of the
area and details furnished.
11)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
12)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be
furnished based on field survey clearly indicating the Schedule of the fauna
present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project
cost.
13)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
14)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given.
15)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of movement
of vehicles for transportation of mineral. The details of the model used and
input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map.
16)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
17)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
18)
Details of water conservation measures proposed to be adopted in the
project should be given.
19)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
20) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
21) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
22)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
23)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
24)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
25)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
26)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
27)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
28)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
29)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted.
30)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP.
31)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
32)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects.
33)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
34) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
35)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After preparing the draft EIA (as per
the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above
mentioned issues, the proponent will get the public hearing conducted and take
further necessary action for obtaining environmental clearance in accordance
with the procedure prescribed under the EIA Notification, 2006.
2.28 Quartz,
Mica, Kyanite & Vermiculite Mining Project of M/s Shri Radha Kishan Sharma,
Village Dhangras, District Bhilwara, Rajasthan (EC)
The proposal was listed for consideration by the Committee based on the information submitted by the proponent. It was observed that the said proposal was earlier considered by the EAC during its meeting held on December 22-24, 2010, wherein the Committee had recommended rejection of the proposal as the data contained in the EIA report was found to be unreliable. In accordance with the recommendations of the EAC, MoEF had rejected the proposal vide letter dated 17th March, 2011. Further, that the consultant who prepared the report was also de-barred from undertaking preparation of EIA. The proponent have now reportedly submitted the correct documents after necessary correction prepared by the same consultant namely M/s R.K. Consultant.
The Committee after discussion decided that the EIA needs to be prepared by an accredited consultant after generating baseline data afresh and thereafter public hearing should also be redone. The proposal for EC should be submitted thereafter for consideration by the EAC.
2.29 Tikarpara
Pyrophylite & Quartzite Mines of Sri Banwarilall Newatia, villages Tikarpara
& Ambadhara, District Keonjhar,
Orissa (Consultant: M/s Envowmin
Consultant Pvt. Ltd., Bhubaneswar)
The consideration of the proposal was deferred for want of approved mine plan for the revised mine lease area.
2.30 Metabadeli
Iron Ore Deposit of M/s Jayaswal Neco Industries Ltd., Village Metabadeli,
District Kanker, Chhattisgarh (Reconsideration Case)
The consideration of the proposal was deferred for
want of forestry clearance.
2.31 Sand Stone and Bajri of M/s Golden Karamjot Stone Crusher, Village Riyali, Tehsil Fatehpur, District Kangra, H.P. (Consultant: IDMA Laboratories Ltd., Panchkula)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is
for terrace mining of 80,000 TPA of sand, stone and bajri put together. The mine lease area is 21.0784 ha. No forestland is involved. It was stated that river Bias is at a
distance of about 400 m from the mine.
The dam location is at a distance of about 7 - 8 km from the mine. It
has been considered as Category ‘A’ because of inter-state boundary of Punjab
within 10 km. Life of mine is 10
years. Ultimate working depth will be 4
m from surface. In this regard, the
Committee observed that the depth of mining should be restricted to at least
1.5 m above HFL of the river. It was noted that the
baseline AAQ data collection has already started which will be continued
through pre monsoon season.
Based on the information furnished and presentation made, the Committee
prescribed the following TORs for undertaking detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee. The mine
plan should take into account the conditions of the mine lease, if any, in
terms of distance to be left un-worked from the river flowing nearby.
3)
The impact of other mines and the crusher located within the impact zone
should also be taken into account.
4)
While working out the impacts and their mitigation, the standards
prescribed under EP Act, for stone crushers should be taken into account.
5)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
6)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
7)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
8)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
9)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out covering both
terrestrial and aquatic flora and fauna. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
field survey clearly indicating the Schedule of the fauna present.
10)
Impact of
change of land use should be given.
11)
Impact of
mining on the hydrology of the area including water flow in the river adjoining
the mine lease. It should also take
into account the inundation of mined out area due to flow of water from the
river.
12)
R&R plan/compensation
details for the project affected people should be furnished. While preparing
the R&R plan, the National Rehabilitation & Resettlement Policy should
be kept in view. In respect of
SCs / STs and other weaker sections, need based sample survey, family-wise,
should be undertaken to assess their requirement and action programmes prepared
accordingly integrating the sectoral programme of line departments of the State
Government.
13)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring
station within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given. The already collected baseline data could be
utilized provided it meets the monitoring protocol.
14)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality
contours may be shown on a location map clearly indicating the location of the
site, location of sensitive receptors, if any and the habitation. The wind roses showing pre-dominant wind
direction may also be indicated on the map.
The impact of stone crusher nearby should also be taken into
account.
15)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water requirement for the project
should be indicated.
16)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
17)
Details of water conservation measures proposed to be adopted in the
project should be given.
18)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
19) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
20) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
21)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
22)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
23)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
24)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
25)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
26)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
27)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
28)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done should be given.
29)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP. Special attention should be given in view of
the stone crusher nearby.
30)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
31)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects. It should also take into account the impacts due to stone crusher
nearby and also provide for preventing the silt from going into the river.
32)
Risk assessment and disaster management plan due to inundation of mine as
a result of its location close to the river should also be examined and
addressed.
33)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
34) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
35)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After
preparing the draft EIA (as per the
generic structure prescribed in Appendix-III of the EIA Notification, 2006)
covering the above mentioned issues, the proponent will get the public hearing
conducted and take further necessary action for obtaining environmental
clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.
2.32 Sand,
Stone and Bajri of M/s Krishna Stone Crusher, village Riyali, Tehsil Fatehpur,
District Kangra, H.P. (Consultant: IDMA
Laboratories Ltd., Panchkula)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for terrace mining of 50,000 TPA of sand, stone and bajri
put together. The mine lease area is
13.0076 ha. No forestland is
involved. It has been considered as
Category ‘A’ because of inter-state boundary of Punjab within 10 km. Life of mine is 7 years. Ultimate working depth will be 2 m from
surface. It was noted that the baseline
AAQ data collection has already stated which will be continued through pre
monsoon season.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee. The mine
plan should take into account the conditions of the mine lease, if any, in terms
of distance to be left un-worked from the river flowing nearby.
3)
The impact of other mines and the crusher located within the impact zone
should also be taken into account.
4)
While working out the impacts and their mitigation, the standards
prescribed under EP Act, for stone crushers should be taken into account.
5)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
6)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
7)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
8)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated, supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above, should be obtained from the State Wildlife
Department/ Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and
copy furnished.
9)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out covering both
terrestrial and aquatic flora and fauna. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
field survey clearly indicating the Schedule of the fauna present.
10)
Impact of
change of land use should be given.
11)
Impact of
mining on the hydrology of the area including water flow in the river adjoining
the mine lease should be brought out. It should also take into account the inundation
of mined out area due to flow of water from the river.
12)
R&R plan /
compensation details for the project affected people should be furnished. While
preparing the R&R plan, the National Rehabilitation & Resettlement
Policy should be kept in view. In
respect of SCs / STs and other weaker sections, need based sample survey,
family-wise, should be undertaken to assess their requirement and action
programmes prepared accordingly integrating the sectoral programme of line
departments of the State Government.
13)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring
station within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10, particularly
for free silica should be given. The already collected baseline data could be
utilized provided it meets the monitoring protocol.
14)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map. The impact of stone crusher
nearby should also be taken into account.
15)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
16)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
17)
Details of water conservation measures proposed to be adopted in the
project should be given.
18)
Impact of the
project on the water quality both surface and below ground should be assessed
and necessary safeguard measures, if any required, should be provided.
19) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
20) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
21)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
22)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
23)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
24)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
25)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
26)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
27)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
28)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done should be given.
29)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP. Special attention should be given in view of
the stone crusher nearby.
30)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
31)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects. It should also take into account the impacts due to stone crusher
nearby and also provide for preventing the silt from going into the river.
32)
Risk assessment and disaster management plan due to inundation of mine as
a result of its location close to the river should also be examined and
addressed.
33)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
34) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
35)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After
preparing the draft EIA (as per the
generic structure prescribed in Appendix-III of the EIA Notification, 2006)
covering the above mentioned issues, the proponent will get the public hearing
conducted and take further necessary action for obtaining environmental
clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.
2.33 Sand, Stone and
Bajri of M/s Himachal Stone Crushing Co., village Riyali, Tehsil Fatehpur, District
Kangra, H.P. (IDMA Laboratories Ltd.,
Panchkula)
The proposal was considered by the Committee to determine the Terms of
Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA
Notification, 2006. For this purpose,
the proponent had submitted information in the prescribed format (Form-1) along
with pre-feasibility report.
The proposal is for terrace mining of 80,000 TPA of sand, stone and bajri
put together. The mine lease area is 18.4597
ha. No forestland is involved. It has been considered as Category ‘A’
because of inter-state boundary of Punjab within 10 km. Life of mine is 12 years. Ultimate working depth will be 5 m from
surface. It was noted that the baseline
AAQ data collection has already stated which will be continued through pre
monsoon season.
Based on the information furnished and
presentation made, the Committee prescribed the following TORs for undertaking
detailed EIA study:-
1)
A copy of the document in support of the fact that the proponent is the
rightful lessee of the mine should be given.
2)
All documents including approved mine plan, EIA and public hearing should
be compatible with one another in terms of the mine lease area, production
levels, waste generation and its management and mining technology and should be
in the name of the lessee. The mine
plan should take into account the conditions of the mine lease, if any, in
terms of distance to be left un-worked from the river flowing nearby.
3)
The impact of other mines and the crusher located within the impact zone
should also be taken into account.
4)
While working out the impacts and their mitigation, the standards
prescribed under EP Act, for stone crushers should be taken into account.
5)
The study area will comprise of 10 km zone around the mine lease from
lease periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
6)
Land use of the study area delineating forest area, agricultural land,
grazing land, wildlife sanctuary and national park, migratory routes of fauna,
water bodies, human settlements and other ecological features should be
indicated.
7)
Land use plan of the mine lease area should be prepared to encompass
pre-operational, operational and post operational phases and submitted.
8)
Location of
National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive
areas as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
9)
A detailed
biological study for the study area [core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be carried out covering both
terrestrial and aquatic flora and fauna. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
field survey clearly indicating the Schedule of the fauna present.
10)
Impact of change
of land use should be given.
11)
Impact of
mining on the hydrology of the area including water flow in the river adjoining
the mine lease. It should also take
into account the inundation of mined out area due to flow of water from the
river.
12)
R&R plan /
compensation details for the project affected people should be furnished. While preparing the R&R plan, the
National Rehabilitation & Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
13)
One season
(non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological
data should also be collected. The
location of the monitoring stations should be justified. There should be at least one monitoring
station within 500 m of the mine lease in the pre-dominant downwind direction. The mineralogical composition of PM10 particularly
for free silica should be given. The
already collected baseline data could be utilized provided it meets the
monitoring protocol.
14)
Air quality
modeling should be carried out for prediction of impact of the project on the
air quality of the area. It should also take into account the impact of movement
of vehicles for transportation of mineral. The details of the model used and
input parameters used for modeling should be provided. The air quality contours may be shown on a
location map clearly indicating the location of the site, location of sensitive
receptors, if any and the habitation.
The wind roses showing pre-dominant wind direction may also be indicated
on the map. The impact of stone crusher
nearby should also be taken into account.
15)
The water requirement for the project, its availability and source to be
furnished. A detailed water balance
should also be provided. Fresh water
requirement for the project should be indicated.
16)
Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
17)
Details of water conservation measures proposed to be adopted in the
project should be given.
18)
Impact of the
project on the water quality both surface and groundwater should be assessed
and necessary safeguard measures, if any required should be provided.
19) Based on actual monitored data, it may clearly be shown whether working will intersect groundwater. Necessary data and documentation in this regard may be provided. In case the working will intersect groundwater table, a detailed hydro geological study should be undertaken and report furnished. Necessary permission from Central Ground Water Authority for working below ground water and for pumping of ground water should also be obtained and copy furnished.
20) Details of first order stream, if any passing through lease area and modification/ diversion proposed, if any and the impact of the same on the hydrology should be brought out.
21)
Details of
rainwater harvesting proposed, if any, in the project should be provided.
22)
Information on
site elevation, working depth, groundwater table etc. should be provided both
in AMSL and bgl. A schematic
diagram may also be provided for the same.
23)
Quantity of
solid waste generation to be estimated and details for its disposal and
management should be provided. The
quality, volumes and methodology planned for removal and utilisation
(preferably concurrently) of top soil should be indicated. Details of backfilling proposed, if any,
should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be
brought out).
24)
The reclamation plan, post mine land use and
progressive greenbelt development plan shall be prepared in tabular form
(prescribed format) and submitted.
25)
Impact on local
transport infrastructure due to the project should be indicated. Projected
increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies
such as State Government) should be
covered.
26)
Details of the
infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
27)
Conceptual post
mining land use and Reclamation and Rehabilitation of mined out area (with
plans and with adequate number of sections) should be given in the EIA report.
28)
Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done should be given.
29)
Occupational health impact of project should be anticipated and
preventive measures initiated. Details
in this regard should be provided. Details of pre-placement medical examination
and periodical medical examination schedules should be incorporated in the EMP. Special attention should be given in view of
the stone crusher nearby.
30)
Measures of socio economic significance and influence
to the local community proposed to be provided by project proponent should be
indicated. As far as possible,
quantitative dimensions may be given with time frame for implementation.
31)
Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational
health impacts besides other impacts of the projects. It should also take into account the impacts due to stone crusher
nearby and also provide for preventing the silt from going into the river.
32)
Risk assessment and disaster management plan due to inundation of mine as
a result of its location close to the river should also be examined and
addressed.
33)
Public hearing points raised and commitment of the project proponent on
the same along with time bound action plan to implement the same should be
provided.
34) Details of litigation pending against the project, if any, with direction /order passed by any Court of Law against the project should be given.
35)
The cost of the project (capital cost and recurring
cost) as well as the cost towards implementation of EMP should clearly be spelt
out.
Besides the above, the below mentioned general points should also be
followed:-
a) A note confirming compliance of the TOR, with cross referencing of the relevant sections / pages of the EIA report should be provided.
b)
All documents may be properly referenced with index and continuous page
numbering.
c)
Where data are presented in the report especially in tables, the period
in which the data were collected and the sources should be indicated.
d)
Where the documents provided are in a language other than English, an
English translation should be provided.
e)
The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f)
Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g)
While preparing
the EIA report, the instructions for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II(I) dated 4th
August, 2009, which are available on the website of this Ministry should also
be followed.
The EIA report should also include (i) surface plan of the area
indicating contours of main topographic features, drainage and mining area,
(ii) geological maps and sections and (iii) sections of the mine pit and
external dumps, if any, clearly showing the land features of the adjoining
area.
After
preparing the draft EIA (as per the
generic structure prescribed in Appendix-III of the EIA Notification, 2006)
covering the above mentioned issues, the proponent will get the public hearing
conducted and take further necessary action for obtaining environmental
clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.
2.34 Ordinary Sand Quarry of M/s Department
of Industries and Commerce, Village Talwandi Kalan, Balliewal, Bhukhri Khurd,
Boont, Gorsian Hakam Rai, Jodhwal, Kassabad, Kutbewal Araian, Ludhiana Distt.,
Punjab (TOR)
The consideration of the proposal was
deferred at the request of the project proponent.
2.35 Bharat China Clay Mines (Block 2),
villge Raikaman, Lunti, P.S. Kumardungi, District Singhbhum West, Jharkhand (TOR)
The consideration of the proposal was
deferred at the request of the project proponent.
2.36 River Bed Mining (9.31 ha) of Sand,
Bajri & Boulders (minor mineral) of M/s Vikas Agarwal & Wajid Ali,
village Tatohal, Tehsil Behat, District Saharanpur, U.P. (EC)
The consideration of the
proposal was deferred at the request of the project proponent.
2.37
River Bed Mining (19.83 ha) of Sand, Bajri &
Boulders (minor mineral) of M/s Amit Jain & Naseem, village Allauddinpur
Bans Ahatmaal, Tehsil Behat, District Saharanpur, U.P. (EC)
The
consideration of the proposal was deferred at the request of the project
proponent.
2.38
River Bed Mining (7.69 ha) of Sand, Bajri &
Boulders (minor mineral) of M/s Mahmood Ali & Dilshad, village Sherpur
Pelon, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 45,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Khalronwala Rao in Sherpur Pelon village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 8.11.2010. The mine lease area is 7.69 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Uttarakhand and U.P. and Haryana within 10 km. Elephant reserve boundary at a distance of 0.156 km. The proponent have submitted a map authenticated by Chief Wildlife Warden in this regard. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project. During the meeting the proponent further stated that the existing lease period for this mine is due to expired on 22.5.2011 and that they have already applied for renewal of mine lease and as such their proposal may be considered for environmental clearance for renewal of mine lease at the existing rated capacity. The Committee agreed for the same.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance for renewal of mine lease for production of 45,000 TPA of sand, bajri and boulder subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
2.39
River Bed Mining (22.67 ha) of Sand, Bajri &
Boulders (minor mineral) of M/s Amit Jain & Naseem, village Akbarpur Bans
Ahatmaal, Tehsil Behat, District Saharanpur, U.P. (EC)
The
consideration of the proposal was deferred at the request of the project
proponent.
2.40
River Bed Mining (24.29 ha) of Sand, Bajri &
Boulders (minor mineral) of M/s Mahmood Ali, Punit Jain & Mukesh Jain,
village Nunyari Aahtmal, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 90,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Yamuna in Nunyari Aahtmal village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 20.11.2010. The mine lease area is 24.29 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Haryana within 10 km. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project. During the meeting the proponent further stated that the existing lease period for this mine is due to expired on 22.5.2011 and that they have already applied for renewal of mine lease and as such their proposal may be considered for environmental clearance for renewal of mine lease at the existing rated capacity. The Committee agreed for the same.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance for renewal of mine lease for production of 90,000 TPA of sand, bajri and boulder subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
2.41
River Bed Mining (6.88 ha, Lot No. 8) of Sand, Bajri
& Boulders (minor mineral) of M/s Mahmood Ali & Dilshad, village
Faizabad, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 90,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Gejrarao in Faizabad village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 18.11.2010. The mine lease area is 6.88 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Haryana and U.P. and Uttarakhand within 10 km. Elephant reserve boundary at a distance of 0.8 km. The proponent have submitted a map authenticated by Chief Wildlife Warden in this regard. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
2.42
River Bed Mining (12.39 ha, Lot no. 6) of Sand,
Bajri & Boulders (minor mineral) of M/s Mahmood Ali & Dilshad, village
Faizabad, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 1,26,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Yamuna in Faizabad village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 15.11.2010. The mine lease area is 12.39 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Haryana and U.P. and Uttarakhand within 10 km. Elephant reserve boundary at a distance of 1.6 km. The proponent have submitted a map authenticated by Chief Wildlife Warden in this regard. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
2.43
River Bed Mining (6.25 ha, Lot no. 15) of Sand,
Bajri & Boulders (minor mineral) of M/s Mohd. Inam & Mahboob Aalam,
village Fatehpur Pelon, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 54,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Shahjahanpur Rao in Fatehpur Pelon village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 18.11.2010. The mine lease area is 6.25 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Uttarakhand within 10 km. Elephant reserve boundary at a distance of 1.6 km. The proponent have submitted a map authenticated by Chief Wildlife Warden in this regard. Rajaji National Park is at a distance of 6.5 km from the mine lease. NOC from Chief Wildlife Warden, Uttarakhand dated 24.12.2010 has been submitted. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
2.44
River Bed Mining (12.55 ha) of Sand, Bajri &
Boulders (minor mineral) of M/s Mohd. Inam & Mahboob Aalam, village
Naurangpur, Tehsil Behat, District Saharanpur, U.P. (EC)
The consideration of the
proposal was deferred at the request of the project proponent.
2.45
River Bed Mining (18.75 ha, Lot no. 34) of Sand,
Bajri & Boulders (minor mineral) of M/s Vikas Agarwal & Wajid Ali,
village Kaluwala Paharipur, Tehsil Behat, District Saharanpur, U.P. (Consultant: J.M. Environet Pvt Ltd., Gurgaon)
The proposal was considered by the Committee and the proponent made a presentation on the same. The proposal is for environmental clearance for mining of 90,000 TPA of sand, bajri, boulders (minor mineral) put together from the bed of river Kothri Rao in Kaluwala Paharipur village, District Saharanpur, U.P. TOR for this project were prescribed on 31.5.2010. Public hearing has been held on 19.11.2010. The mine lease area is 18.75 ha. No forestland is involved. It has been considered as Category ‘A’ because of the inter-state boundary of U.P. and Uttarakhand within 10 km. Elephant reserve boundary is at a distance of 2.56 km. The proponent have submitted a map authenticated by Chief Wildlife Warden in this regard. It is a violation case as the mine started functioning without obtaining requisite prior environmental clearance. Mine working will be semi-mechanised. Ultimate working depth will be 2 m from river bed level. Excavation will be done in half meter slice at a time with a maximum of 4 slices. The river bed water level is reported to be 3 - 6 m below river bed level. The baseline AAQ data showed the PM10 values in the crushing zone were on higher side. It was also reported that no nesting of turtles was observed during their primary observation period although secondary data reports nesting of turtles in the region. The proponent have also submitted a letter from the Directorate of Geology and Mines, Govt. of U.P. dated 25.3.2011 stating that there is no provision for approval of mine plan for minor minerals other than in-situ rock deposit. The issues raised during public hearing were also considered and discussed during the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended the project for environmental clearance subject to following conditions:-
(i) The proponent will observe every 15 days for nesting of any turtle in the area. Based on the observations so made, if turtle nesting is observed, necessary safeguard measures shall be taken in consultation with the State Wildlife Department.
(ii) A study shall be carried out through an expert agency like CWC relating to replenishment of the mineral (siltation study) so as to ensure that the quantity of mineral to be removed does not exceed the siltation to avoid over exploitation of mineral, which may adversely affect the dynamics of the river.
(iii) Effective safeguard measures shall be taken to ensure that the AAQ levels at various locations including crushing zone, are within permissible limit as prescribed by CPCB. The standards prescribed for stone crushers shall be followed.
3.0 Any other item:
The office memorandum no. J-11015/200/2008-IA.II(M) dated 31st
March, 2011 relating to consideration of projects for grant of environmental
clearance under EIA Notification, 2006, which involve forestland – procedure to
be followed was brought to the notice of the Committee and a copy of the same
was circulated to all the members. In
addition, a copy of the Notification dated 4th April, 2011 making
amendments in the EIA Notification, 2006 was also circulated to all the members
of EAC.
Next Meeting:
It was decided that the next
meeting will be held on May 25-27, 2011.
The
meeting ended with a vote of thanks to the Chair.
*********
Annexure
List of Participants
1.
Shri Mukunda
Shenoy Nagar - Chairman
2. Dr. S. Subramaniyan - Vice
Chairman
3. Shri
K.S. Anandan - Member
4. Shri Vinay Mahajan - Member
5. Dr. L. Ajay Kumar - Member
6. Prof.
C.K. Varshney - Member
7. Shri
Sunil Peshin - Member
8. Shri Mihir Moitra - Member
9. Dr.
B.K. Mishra - Member
10. Shri
T.K. Joshi - Member
11. Shri
Rajesh Srivastava - Member
12. Er.
Pardeep Gupta, Punjab PCB - Invitee
13. Dr. S.K. Aggarwal, Director - Member
Secretary
14. Dr. Satish C. Garkoti,
Director
15. Representative of M/s Orissa Mining
Corporation Ltd.
16. Representative
of M/s Orissa Minerals Development Co. Ltd.
17. Representative
of Shri R.P. Tiwari
18. Representative
of M/s Kamaljeet Singh Ahluwalia
19. Representative
of M/s Vyaghreshwar Mineral Industrial Producer’s
20. Representative
of M/s Arcellor Mittal India Ltd.
21. Representative
of M/s VSL Mining Co. Pvt. Ltd.
22. Representative
of M/s Golden Hills Resort Pvt. Ltd.
23. Representative
of M/s Resurgere
24. Representative
of M/s Karnatak Mining Co. Pvt. Ltd.
25. Representative
of M/s Orient
Abrasives Ltd.
26. Representative
of M/s Laxmi Chand Goyal
27. Representative of M/s Rasiklal & Co.
28. Representative of M/s Zawar Cement
29. Representative
of M/s Jaiprakash Associated Ltd.
30. Representative
of M/s Hindalco Industries Ltd.
31. Representative
of M/s The A.P. Mineral Development Corp. Ltd.
32. Representative
of M/s Mideast Integrated Steel Ltd.
33. Representative
of M/s Rithesh Rathod
34. Representative of Shri Radha Kishan Sharma
35. Representative
of M/s Golden Karamjot Stone Crusher
36. Representative of M/s Krishna Stone
Crusher
37. Representative of M/s Himachal Stone
Crushing Co.
38. Representative of M/s Mahmood Ali
& Dilshad
39. Representative of M/s Mahmood Ali,
Punit Jain & Mukesh Jain
40. Representative of M/s Mohd. Inam &
Mahboob Aalam
41. Representative
of M/s Vikas Agarwal & Wajid Ali
********