MINUTES OF THE 21st MEETING
OF THE EXPERT APPRAISAL COMMITTEE (INDUSTRY-1) HELD DURING 25th &
26th March, 2011 at 623 - Conference Room, 6th Floor,
Ministry Of Environment & Forests, Paryavaran Bhavan, Lodhi Road, New Delhi
– 110 003.
Opening Remarks of the Chairman
At the outset, Chairman welcomed the members of the
Expert Appraisal Committee-1(Industry). Thereafter, agenda items were taken up
for discussion.
21.1 Confirmation of the Minutes of the 20th
Meeting of the Expert Appraisal Committee (Industry-1) held on 12th
March, 2010
21.2.0 Consideration of the Projects
25th March, 2011
Proposals
for Environmental clearance
21.2.1
Proposed Cement Grinding Unit of 200 TPD Capacity at Sy No:
417/2, 417/3, Gollapalli Village, Katpadi Taluk,
Vellore District in Tamil Nadu by M/s Sri Kaarpaga Vinayagar Cements Pvt.
Limited - regarding
Environmental Clearance
The project authorities and Team Labs and Consultants, Hyderabad gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded in the 13th Meeting of the Expert Appraisal Committee-1
(Industry) held during 26th - 28th August, 2010 for
preparation of EIA/EMP reports. Public hearing was exempted as the
project was categorized as B-2.
The Stand Alone Cement
Grinding Units are listed at S. No. 3(b) under Category ‘B’ and should have
been appraised by the SEIAA/SEAC at the State level. As the unit is
located within 1.5 km distance of interstate boundary, as per the general
condition of EIA Notification, 2006, proposal has been appraised by the Expert
Appraisal Committee (Industry) in the Ministry.
M/s. Sri Kaarpaga Vinayagar Cements Pvt. Ltd
have proposed for Cement grinding unit of 200 TPD Capacity at Sy No: 417/2, 417/3,
Gollapalli Village, Katpadi taluk, Vellore District, Tamil Nadu. No forest land
and R&R is involved. No national park / Wildlife Sanctuary and bio-sphere
reserve is located within 10 km radius. Amudala RF (5.5 km - NE direction),
Reddigunta RF (7.1 km - NW direction) and Chaseskonda RF (6.8 km - NW
direction) are located within 10 km distance of the project site. The
company has already acquired 1.21 ha of land of which 0.45 ha of the area will
be brought under green belt. Capital cost of the project is Rs. 1.50 Crores has
been earmarked towards the capital cost for environmental protection.
To
control the particulate emissions, bag filters will be installed. All the raw
material will be stored in the covered storage area. The total water
requirement of 3.5m3/day will be met from the ground water source. No
process effluent will be generated. Domestic
effluent (1.3 KLD) will be sent to septic tank followed by soak pit. It is
proposed to develop rain water harvesting structure to recharge the ground
water. No solid
waste would be generated from the cement plant. The cement dust collected in
the pollution control devices is recycled back to the process. The waste oil
(10lt/annum) will be provided tor registered recyclers. The total power requirement of 425 HP will be met from the State grid.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other environmental conditions:
i.
Continuous
stack monitoring facilities to monitor gaseous emissions from all the stacks
shall be provided. Particulate emissions shall be controlled within 50 mg/Nm3 by installing adequate air pollution
control system viz. Bag
filters and stacks of adequate height etc. Data on ambient air, fugitive and
stack emissions shall be submitted to the Ministry’s Regional Office at Bangalore,
Tamil Nadu State Pollution Control Board (TNSPCB) and CPCB regularly.
ii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iii.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed.
iv.
The
company shall install adequate dust collection and extraction system to control
fugitive dust emissions at various transfer points, raw mill handling
(unloading, conveying, transporting, stacking), vehicular movement, bagging and
packing areas etc. All the raw material stock piles shall be covered. A closed clinker stockpile system
shall be provided. All
conveyers shall be covered with GI sheets. Covered sheds for storage of raw
materials and fully covered conveyers for transportation of materials shall be
provided besides coal, cement, fly ash and clinker shall be stored in
silos. Pneumatic
system shall be used for fly ash handling.
v.
Asphalting/concreting of roads and water spray all around the
stockyard and loading/unloading areas in the cement plant shall be carried out
to control fugitive emissions. Regular water sprinkling shall be carried out in
the critical areas prone to air pollution and having high levels of RSPM such
as haul road, loading and unloading points, transfer points and other
vulnerable areas. It shall
be ensured that the ambient air quality parameters conform to the norms
prescribed by the Central Pollution Control Board in this regard.
vi.
Efforts shall be made to reduce impact of the transport of the raw
materials and end products on the surrounding environment including
agricultural land. All the raw materials including fly ash shall be transported
in the closed containers only and shall not be overloaded. Vehicular emissions
should be regularly monitored.
vii.
Total water requirement for cement plant from bore wells shall not
exceed 3.5m3/day. All the treated wastewater shall be
recycled and reused in the process and/or for dust suppression and green belt
development and other plant related activities etc. No process wastewater shall
be discharged outside the factory premises and ‘zero’ discharge shall be
adopted.
viii.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir shall be enhanced to meet the maximum water
requirement. Only balance water requirement shall be met from other sources.
ix.
All the bag filter dust, raw mill dust, coal dust, clinker dust
and cement dust from the pollution control devices shall be recycled and reused
in the process for cement manufacturing.
Spent oil and batteries shall be sold to authorized recyclers /
reprocessors only.
x.
Green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
xi.
At least 5 % of the total cost of the project shall be earmarked
towards the corporate social responsibility and item-wise details along with time
bound action plan should be prepared and submitted to the Ministry’s Regional
Office at Bangalore. Implementation of such program
shall be ensured accordingly in a time bound manner.
xii.
The
company shall provide housing for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
21.2.2
Cement Grinding Unit (1.6 MTPA) with Captive Power Plant
(10 MW) at Village Kahalgaon, District Bhagalpur in Bihar by M/s Cement
Manufacturing Company Limited - regarding Environmental Clearance
The project authorities and their consultant
Shiva Test House, Patna gave a detailed presentation on the salient features of the project and proposed environmental
protection measures to be undertaken as per Terms of Reference (TORs) awarded in the 9th Meeting of the
Expert Appraisal Committee-1 (Industry) held during 7th
-8th April, 2010 for preparation of EIA/EMP reports.
Public hearing was exempted as per para 7 (i) III stage 3 (i) (e) of the EIA
Notification, 2006 as the unit is categorized as ‘B-2’ category.
The
Cement grinding units are listed at S.N. 3(b) under Category ‘B’ and appraised by
the SEIAA / SEAC. As the proposal was received before the constitution of SEIAA/SEAC,
Bihar, the proposal has been appraised by the Expert Appraisal Committee
(Industry) in the Ministry.
M/s
Cement Manufacturing Company Ltd. have proposed for the Cement Grinding Unit (1.6 MTPA) with Captive Power Plant (10 MW) at
Village Kahalgaon, District Bhagalpur, Bihar.
Total plant area is 60 acres of which 19.8 acres is earmarked for green
belt development. About 90,750 TPA of coal will be required which will be
purchased through e-auction till the coal linkage is granted by Ministry of
Coal. No national park / wildlife sanctuary /reserve forest are located
within 10 km radius. River Ganga flows at a distance of 3.5 km. Total cost of the project is Rs. 248.97 Crores. Rs. 4.85 Crores and Rs. 0.55
Crores/annum has been earmarked towards capital cost and recurring cost/annum
for environment protection measures. No litigation/court case is pending
against the project.
Clinker (8,58,330 TPA), coal (90, 750 TPA), gypsum (32, 010 TPA), fly ash
(2,61,360 TPA) and blast furnace slag (4,48,140 TPPA) will be used a s raw
material. The proposed project will be based on vertical roller mill
technology. Power requirement of 8.7 MW will be met through CPP. However, for
initial start and to meet minimum power requirement to keep the packing plant
in operation during maintenance of CPP, sourcing of 2.0 MW power through 132 KV
grid substation power through Bihar State Electricity Board is envisaged.
Ambient air quality monitoring has
been carried for PM 2.5, PM 10, SO2 and NOx. The values of these parameters are
within prescribed standards. It is proposed to install pulse jet type bag
filters at the raw material handling and finished good storage area to control
the particulate emissions. ESP will be installed in power plant to control the
particulate emissions below 50 mg/Nm3 and gases emissions will be
dispersed through stack of 60 m height. For
dust suppression, regular water spraying will be carried.
Water
requirement of 1,900m3/day will be met from the ground water source.
No process effluent will be generated from the cement grinding unit. It is
proposed to install air cooled condensers to minimize the water requirement. Cooling
water system in the captive power plant will be operated in a closed cycle. The
blow down water will be treated in the neutralizing pit. The treated effluent
will be used for cooling, dust suppression and green belt development. Domestic
effluent will be treated in septic tank followed by soak pit. The
domestic effluent will be treated in sewage treatment plant (STP). No effluent will be discharged outside the plant
premises and ‘Zero’ discharge will be adopted. It is proposed to collect the
rain water from the roof tops through the rain water harvesting structures to
recharge the ground water
Fly ash and bottom ash will be used
in cement grinding unit. Sewage sludge
will be periodically removed, disinfected and utilized as manure for green belt
development.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other
environmental conditions:
i.
Continuous
stack monitoring facilities to monitor gaseous emissions from all the stacks
shall be provided. Particulate emissions shall be controlled within 50 mg/Nm3 by installing adequate air pollution control
system viz. ESP, bag
filters and stacks of adequate height etc. Data on ambient air, fugitive and
stack emissions shall be submitted to the Ministry’s Regional Office at Bhubaneswar,
Bihar State Pollution Control Board (BPCB) and CPCB regularly.
ii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iii.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed.
iv.
The
company shall install adequate dust collection and extraction system to control
fugitive dust emissions at various transfer points, raw mill handling
(unloading, conveying, transporting, stacking), vehicular movement, bagging and
packing areas etc. All the raw material stock piles shall be covered. A closed clinker stockpile system
shall be provided. All
conveyers shall be covered with GI sheets. Covered sheds for storage of raw
materials and fully covered conveyers for transportation of materials shall be
provided besides coal, cement, fly ash and clinker shall be stored in
silos. Pneumatic
system shall be used for fly ash handling.
v.
Asphalting/concreting of roads and water spray all around the
stockyard and loading/unloading areas in the cement plant shall be carried out
to control fugitive emissions. Regular water sprinkling shall be carried out in
critical areas prone to air pollution and having high levels of RSPM such as
haul road, loading and unloading points, transfer points and other vulnerable
areas. It shall be ensured
that the ambient air quality parameters conform to the norms prescribed by the
Central Pollution Control Board in this regard.
vi.
Efforts shall be made to reduce impact of the transport of the raw
materials and end products on the surrounding environment including
agricultural land. All the raw materials including fly ash shall be transported
in the closed containers only and shall not be overloaded. Vehicular emissions
should be regularly monitored.
vii.
Total water requirement for cement plant from bore wells shall not
exceed 1900m3/day. Permission to draw water from the
competent authority shall be obtained. Air cooled condensers for the boilers in
the captive power plant shall be installed. All the treated wastewater shall be
recycled and reused in the process and/or for dust suppression and green belt
development and other plant related activities etc. No process wastewater shall
be discharged outside the factory premises and ‘zero’ discharge shall be
adopted.
viii.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir shall be enhanced to meet the water
requirement for two months. Only balance water requirement shall be met from
other sources.
ix.
All the bag filter dust, raw meal dust, coal dust, clinker dust
and cement dust from pollution control devices shall be recycled and reused in
the process used for cement manufacturing.
Spent oil and batteries shall be sold to authorized recyclers /
reprocessors only.
x.
Green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
xi.
At least 5 % of the total cost of the project shall be earmarked
towards the corporate social responsibility and item-wise details along with
time bound action plan should be prepared and submitted to the Ministry’s
Regional Office at Bhubaneswar. Implementation of such program
shall be ensured accordingly in a time bound manner.
xii.
The
company shall provide housing for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
21.2.3
Expansion of the Cement Plant [Cement from 4.2 MTPA to 8.7
MTPA; Clinker from 4.7 to 9.0 MTPA], Captive Power Plant (58.2 to 190 MW) and
Captive Limestone Mines from 6.7 MTPA to 13.4 MTPA at Aditya Nagar, P.O Malkhed
Road, District Gulbarga, Karnataka by M/s Rajashree Cement - regarding
Environmental Clearance
The project authorities and their consultant
M/s J.M. EnviroNet Pvt.
Ltd., Gurgaon gave a detailed presentation on the salient features of the project and proposed environmental
protection measures to be undertaken as per Terms of Reference (TORs) awarded in the 9th Meeting of the
Expert Appraisal Committee-1 (Industry) held during 7th
-8th April, 2010 for preparation of EIA/EMP reports.
Public
hearing for the project was held on 23rd February, 2011. The issues
raised during the public hearing were regarding controlled blasting. Measures
for control of dust emissions, adoption of best available technology, independent
health survey in the area, plantation of trees, construction of roads,
provision of water, community health centre, assistance to the blind school
etc. All the above issues were addressed and incorporated in the final EIA /
EMP report.
All
the Cement, Captive Power Plant and Limestone mines are listed at S.N. 3(a)
under 4(b) respectively under Category ‘A’ and appraised at the Central
level.
M/s Rajashree Cement have proposed
for the expansion of the Cement Plant (Cement
from 4.2 MTPA to 8.7 MTPA; Clinker from 4.7 to 9.0 MTPA, Captive Power
Plant from 58.2 to 190 MW including 15
MW of WHRB and Captive Limestone Mines from 6.7 MTPA to 13.4 MTPA, 733.82 ha.)
at Village Malkhed, Hanganahli, Udgi & Diggaon, Aditya Nagar, Taluka Sedam,
P.O. Malkhed Road, District Gulbarga, Karnataka. A DG set of 5.8 MW has
already been installed. The total area for the cement plant and captive power
plant is 453.00 ha, 733.82 ha for mine and total area is 1186.82 ha for
expansion of clinker production (4 MTPA to 4.7 MTPA) vide letter dated march
13, 2008 and its compliance report is submitted. A copy of environment clearance accorded for
limestone mine accorded vide letter dated July 06, 2007 and its compliance
report is also submitted. PAs further
informed to the Committee that Unit I, Unit II and Unit III of the cement plant
have been commissioned in 1984, 1990 and 1993 respectively. A copy of Consent
to Operate accorded by Karnataka State Pollution Control Board vide dated 1st
September, 2009, Consent to Establish accorded vide dated 16th
March, 2007 and it compliance report has been furnished. No rehabilitation and
resettlement is involved in the project. No reserve forest is located within 10
km. Kagina River flows at a distance of
6 km. Mine site is located within 2 km
distance of the cement plant. No national park, wild life sanctuary and reserve
forest are located within 15 km. radius.
Nearest village & towns are at 2-8 km. Project site falls in seismic zone-2. Total
cost of the project is Rs. 3,000.00 Crores. Rs. 300.00 Crores is earmarked
towards environment protection measures. Rs. 15.00 Crores is earmarked towards
recurring cost/annum. No litigation/court case is pending against the
project.
Details
of existing and proposed capacity of plant:
Unit |
Existing
Production |
Proposed
Expansion |
Production
after expansion |
Clinker
production |
4.7 MTPA |
4.3 MTPA |
9.0 MTPA |
Cement
Production |
4.2 MTPA |
4.5 MTPA |
8.7 MTPA |
Captive
Power Plant |
58.2 MTPA |
131.8 MTPA (including 15 MW of WHRB) |
190 MTPA |
DG
Set (MW) |
5.8 |
- |
- |
Limestone
mine |
6.7 MTPA |
6.7 MTPA |
13.4 MTPA |
Limestone
(13.4 MTPA), laterite/bauxite (0.88 MTPA), coal (2.55 MTPA), chemicals gypsum (0.20
MTPA) and fly ash (2.05 MTPA) will be used as raw materials. PPC will be
manufactured using fly ash from CPP. Fuel supply agreement between M/s The
Singareni Collieries Limited and M/s Grasim Industries Limited to meet the coal
requirement from Indaram Opencast Project has been submitted.
Open
cast mechanized method of mining will be adopted. The top soil will be removed
and used for green belt development. The
limestone bench of 10 m height will be drilled and blasted. The overall pit slope will be kept at 450. Blasted limestone will be transported by
tippers to the crushers.
The
Committee noted that land requirement at the time of prescribing TORs project
was 1186 ha. However, at the stage of environmental clearance, requirement has
been projected as 1358.94 ha. Area for the cement plant and CPP has been
increased which is deviation from the TORs. The Committee expressed its
displeasure that additional land has been acquired. The Committee advised the
proponent to redraw the plant boundary, revise the lay out and the area of the
plant be restricted to what has been mentioned at the time of prescription of
TOR. The proponent have submitted the revised lay out plan by restricting the
plant area which was mentioned at the time of TOR.
High efficiency ESP, bag house, bag
filters will be installed to mitigate particulate emissions within 50 mg/Nm3. Proper stack height will be provided as per
CPCB guidelines. Fly ash will be stored in silos and closed shed. Dust
suppression and extraction system with bag filters and atomized water
sprinklers will be provided to prevent fugitive dust emissions at limestone and
coal uploading hopper and handling area.
The Committee noted that in the three
existing line, the company is complying with the prescribed standards of
150mg/Nm3. The Committee advised that the company shall submit an
action plan to mitigate the particulate emissions below 100 mg/Nm3.
Water
requirement of 14,817m3/day will be met from River Kagina and mine sump.
Permission to draw water has been obtained 14,317m3/day (as per
submitted document water requirement will be 14,817 KLD). The waste water from
the CPP will be recycled back to the process and used for cooling and dust
suppression. Domestic effluent will be treated in the sewage treatment
plant and treated effluent will be used for green belt and dust suppression in
the mines. No effluent will be
discharged outside the premises and ‘Zero’ discharge will be adopted. Excavated
mine pits will be used for rain water harvesting. Rain water harvesting structures
will be constructed in plant and colony area.
No solid waste will be generated from
the cement manufacturing process. Dust collected from the air pollution control
equipments will be recycled in process. Fly ash will be used for manufacturing
PPC cement. Sludge from STP will be used
as manure for green belt. Overburden will be used for bund formation and
horticulture as per approved mining plan.
No mine waste will be generated.
Process dust/spillages will be recycled.
STP sludge will be used as manure for horticulture purpose.
Waste/used/spent oil and used batteries will be sold to authorized
recyclers/re-processors.
Out of 625.12 ha of plant and colony
area, 100.12 ha has already been developed under green belt. It is proposed to
bring 33% of total area under green belt.
After
detailed deliberations, the Committee recommended the project for environmental
clearance subject to following specific conditions along with other environmental conditions:
i).
Rehabilitation and Resettlement Plan for the project
affected population including tribals, if applicable, shall be implemented as
per the policy of the State Govt. in consultation with the State Govt. of
Karnataka. Compensation paid in any case shall not be less than the norms
prescribed under the National Resettlement and Rehabilitation Policy, 2007.
ii).
The
gaseous and particulate matter emissions from various units shall conform to
the standards prescribed by the Karnataka Pollution Control Board. At no time,
particulate emissions from the cement plant including kiln, coal mill, cement
mill, cooler and captive power plant (CPP) shall not exceed 50 mg/Nm3.
The company shall control particulate emissions below 100 mg/Nm3 in the
existing three lines in a time bound manner for which action plan shall be
submitted to Ministry’s Regional Office at Bangalore.
iii).
Continuous
on-line monitors for particulate emissions shall be installed. Pyrites,
fluoride and Hg emissions shall be monitored.
Interlocking facility shall be provided in the pollution control
equipment so that in the event of the pollution control equipment not working,
the respective unit (s) is shut down automatically.
iv).
Data
on ambient air quality (PM10, S02, NOx) shall be regularly submitted
to the Ministry including its Regional office located at Bangalore and the
State Pollution Control Board / Central Pollution Control Board once in six
months. The critical parameters such as
PM10, NOx in the ambient air within the impact zone, peak particle velocity at
300m distance or within the nearest habitation, whichever is closer shall be
monitored periodically. Further, quality of discharged water shall also be
monitored [(TDS, DO, pH) and total Suspended solids (TSS)]. The monitored data
shall be uploaded on the website of the company as well as displayed on a
display board at the project site at a suitable location near the main gate of
the company in public domain.
v).
The
Company shall install low NOx burner with Kiln/calciner for control of NOx
emissions below 400 mg/Nm3.
vi).
Secondary
fugitive emissions shall be controlled within the prescribed limits and
regularly monitored. Guidelines / Code of Practice issued by the CPCB in this
regard shall be followed.
vii).
The National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 shall be
followed.
viii).
Efforts
shall be made to reduce impact of the transport of the raw materials and end
products on the surrounding environment including agricultural land. All the
raw materials including fly ash shall be transported in the closed containers
only and shall not be overloaded.
Vehicular emissions should be regularly monitored.
ix).
Fly
ash shall be utilized as per the provisions of Fly Ash Notification, 1999,
subsequently amended in 2009. Fly ash shall be stored in ash silo and 100% used
in the cement manufacturing.
x).
The
company shall make the efforts to utilize the high calorific hazardous waste in
the cement kiln and necessary provisions shall be made accordingly. The company
shall keep the record of the waste utilized and shall submit the details to
ministry’s Regional Office at Bangalore, CPCB and SPCB.
xi).
Rainwater
harvesting measures shall be adopted for the augmentation of ground water at
cement plant, colony including check dams at mine site. The company must also
collect rain water in the mined out pits of captive lime stone mine and use the
same water for the various activities of the project to conserve fresh water
and reduce the water requirement from the ground water. An action plan shall be
submitted to Ministry’s Regional Office at Bangalore within 3 months from date
of issue of this letter. Efforts should be made to make use of rain water
harvested. If needed, capacity of the reservoir should be enhanced to meet the
maximum water requirement. Only balance water requirement shall be met from
other sources.
xii).
Total
requirement shall not exceed 14,817m3/day. The water stored in the artificial
reservoir made in the mine pit shall be used maximum to reduce ground water
consumption. No effluent should be discharged from the mine to any water body
or nearby river.
xiii).
Top
soil, if any, shall be stacked with proper slope at earmarked site(s) only with
adequate measures and shall be used for reclamation and rehabilitation of mined
out areas.
xiv).
The
project proponent shall ensure that no natural water course shall be obstructed
due to any mining and plant operations. The company shall make the plan for
protection of the natural water course passing through the plant and mine area
premises and submit to the ministry’s Regional Office at Bangalore.
xv).
The
inter burden and other waste generated shall be stacked at earmarked dump
site(s) only and shall not be kept active for long period. The total height of
the dumps shall not exceed
xvi).
The
void left unfilled shall be converted into water body. The higher benches of
excavated void/mining pit shall be terraced and plantation to be done to
stabilize the slopes. The slope of higher benches shall be made gentler for
easy accessibility by local people to use the water body. Peripheral fencing
shall be carried out along the excavated area.
xvii).
Catch
drains and siltation ponds of appropriate size shall be constructed for the
working pit, inter burden and mineral dumps to arrest flow of silt and
sediment. The water so collected shall be utilized for watering the mine area,
roads, green belt development etc. The drains shall be regularly desilted,
particularly after monsoon, and maintained properly.
xviii).
Garland
drain of appropriate size, gradient and length shall be constructed for both
mine pit and inter burden dumps and sump capacity shall be designed keeping 50%
safety margin over and above peak sudden rainfall (based on 50 years data) and
maximum discharge in the area adjoining the mine site. Sump capacity shall also
provide adequate retention period to allow proper settling of silt material.
Sedimentation pits shall be constructed at the corners of the garland drains
and desilted at regular intervals.
xix).
Dimension
of the retaining wall at the toe of inter burden dumps and inter burden benches
within the mine to check run-off and siltation shall be based on the rain fall
data.
xx).
Regular
monitoring of ground water level and quality shall be carried out by establishing
a network of existing wells and constructing new piezometers at suitable
locations by the project proponent in and around project area in consultation
with Regional Director, Central Ground Water Board. The frequency of monitoring
shall be four times a year- pre-monsoon (April / May), monsoon (August),
post-monsoon (November), and winter (January). Data thus collected shall be
sent at regular intervals to Ministry of Environment and Forests and its
Regional Office at Bangalore, Central Ground Water Authority and Central Ground
Water Board.
xxi).
Wet
drilling sequential and controlled blasting method and provision for the
control air emissions during blasting using dust collectors etc. shall be used.
The mitigative measures for control of ground vibrations and to arrest fly
rocks and boulders shall be implemented.
xxii).
Bench
height, width and slope for individual bench shall be properly assessed and
implemented. Adequate measures should be adopted to stabilize the slope before
abandonment. The fencing around the reservoir should be provided to prevent accidents.
xxiii).
Action
plan for the mining, management of over burden (removal, storage, disposal
etc.), reclamation of the mined out area and mine closure should be submitted
to the Ministry and its Regional Office at Bangalore.
xxiv).
As
proposed, green belt shall be developed in 33% of the plant and mine area as per the CPCB guidelines in consultation
with DFO.
xxv). All the recommendations of the
Corporate Responsibility or Environmental Protection (CREP) for the cement
plants shall be strictly followed.
xxvi).
Vehicular
emissions shall be kept under control and regularly monitored. Measures shall
be taken for maintenance of vehicles used in mining operations and in
transportation of mineral. The vehicles shall be covered with a tarpaulin and
shall not be overloaded.
xxvii).
Risk
and Disaster Management Plan alongwith the mitigation measures should be
prepared and a copy submitted to the Ministry’s Regional Office at Bangalore,
KPCB and CPCB within 3 months of issue of environment clearance letter.
xxviii).
Final
Mine Closure Plan along with details of Corpus Fund shall be submitted to the
Ministry of Environment & Forests 5 years in advance of final mine closure,
for approval.
xxix).
The
company shall comply with the commitments made during public hearing held on 23rd
February, 2011 and a separate budget for implementing the same shall be
allocated and information submitted to the Ministry’s Regional Office at
Bangalore.
xxx).
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details along with time bound
action plan shall be prepared and submitted to the Ministry’s Regional Office
at Bangalore. Implementation of such program should be ensured accordingly in a
time bound manner.
xxxi).
Provision
shall be made for the housing of construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, Safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project
21.2.4
Proposed project for manufacturing of manmade fiber -
Partially Oriented Yarn (POY) @ 1200 TPD & Fully Drawn Yarn (FDY) @ 600 TPD
through Continuous polymerization process
and 30 MW CPP at Industrial Zone, Village Naroli, Silvassa, U.T. of D
& NH by
M/s Bhilosa Industries Pvt. Limited – regarding Environmental Clearance
The
project authorities and their consultant
M/s Precitech Laboratories, Vapi, gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded in the 16th Meeting of the Expert Appraisal
Committee-1 (Industry) held during 25th
- 27th October, 2010 for preparation
of EIA/EMP reports. Public
hearing in this case is not required as the unit is located in the notified
industrial area.
The activity regarding
manmade fibre is listed at Sl.
No. 5 (d) of EIA
Notification, 2006. This is a ‘B’ category project. However, as per the general
condition of the EIA notification, 2006, the proposal has been appraised at the
Centre as it is located within 10 km distance of interstate boundary.
M/s Bhilosa Industries Pvt. Limited have proposed for manufacturing of
manmade fiber - Partially Oriented Yarn (POY) @ 1200 TPD & Fully Drawn Yarn
(FDY) @ 600 TPD through Continuous polymerization process from raw materials such as PTA + MEG and 30
MW captive gas based power plant at Industrial Zone, Village Naroli, Silvassa,
U.T. of D & NH. The proposed site is situated in a Notified Industrial Zone
and falls under Seismic Zone III. The Dadra and Nagar Haveli wildlife sanctuary
is at a distance of 4 km from the project site. The project does not fall in
100 m buffer zone boundary of Dadra and Nagar Haveli Wildlife Sanctuary.
Comments from the Deputy Conservator of Forests were also obtained. Vide his
letter no. 7-2/FD/WL/2011/128 dated 01.04.2011, it is informed that the
location of the project which is proposed to be setup in village Naroli,
Silvasa does not fall within boundries
of the Dadra & Nagra Haveli Wildlife Sanctuary. Further, the survey numbers
of the land where the project is proposed to be setup, does not fall within 100
m distance from boundry of Dadra & Nagar Haveli Sanctuary, which has been
declared as eco-sensitive zone by UT Administration of Dadra & Nagar
Haveli. It is further, mentioned that
the proposed plant will not have any significant impact on the Dadra and Nagar
Haveli wildlife sanctuary, Silvassa. River Damanganga flows at a distance of
6.48 km and tributaries of Damanganga flow at a distance of 1.76 km. Patches of
RF are located at a distance of 4-5 km. The total plot area of the unit is
2,68,611m2, out of which 27,300 m2 will be earmarked for
green belt area. The total project cost for proposed activity will be Rs. 401.40
Crores. Rs. 6.8 Crores and Rs. 9.8 Lakhs will be earmarked towards capital cost
and recurring cost/month for EHS system.
The details of the products along with
production capacity are as given below:
Sr. No. |
Name of the Products |
Quantity |
1. |
Partially Oriented Yarn (POY) |
1200 MT/Day |
2. |
Fully Drawn Yarn (FDY) |
600 MT/Day |
3. |
Power Generation through Captive Gas Fired Power Engine
(7.5 MW – 4 Nos each) |
30 MW |
There will be no process gas emissions
due to proposed project. The company proposes to install 1 no of Steam boiler
of 4 MT/Hr capacity, 6 Nos of Thermic Fluid Heater having capacity of 12 M
K.cal/Hr. and Gas Fired Power Engine (4 Nos) of 7.5 MW capacity. The company
will provide adequate chimney height to the utilities in order to control the
utility emissions.
The total fresh water requirement will
be 2723m3/day will be met from the Daman Ganga Canal Distributary.
The water will be sourced from Canal/Bore well. The total waste water
generation will be 427m3/day. The industrial waste water (367m3/day)
from process, utility & washing and will be treated in the effluent
treatment plant for primary, secondary & tertiary treatment. The treated
effluent will be recycled back as cooling tower make-up. The cooling water blow
down will be utilized for gardening/plantation purpose. Hence, there will be no
discharge of treated effluent. The domestic waste water (8 KLD) generated will
be disposed through Soak pit / Septic tank.
The hazardous wastes generated from
process, ETP, machinery and raw material consumption will be stored separately
in a designated storage area. The company will send its ETP waste to the TSDF
site of GEPIL, Silvassa for final disposal. Polymer
waste from process will be sold to actual users. Used oil from machinery will
be sold to registered recycler/re-processor. Empty drums and bags will be sold
to authorized re-conditioner & authorized scrap vendor.
The Committee after detailed
deliberation recommended the project for environmental clearance subject to
stipulation of following specific conditions:
ii.
The
total water requirement shall not exceed 2723 m3/day and permission shall be obtained to draw the water from the Competent
Authority. The effluent after treatment shall be used for green belt. The
domestic effluent shall be discharged to septic tank followed by soak pit.
iv.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir shall be enhanced to meet the maximum water
requirement. Only balance water requirement shall be met from other sources.
v.
Noise
control management plan and Risk & Disaster
Management Plan along with the mitigation measures shall be prepared and a copy
submitted to the Ministry’s Regional Office at Bhopal, UTPCC and CPCB within 3 months
of issue of environment clearance letter.
vi.
As proposed, green belt shall be developed in 33 % of the plant
area. Selection of plant species shall be as per the CPCB guidelines in consultation
with the DFO.
vii.
At least 5 % of the total cost of the project shall be earmarked
towards the corporate social responsibility and item-wise details along with
time bound action plan shall be prepared and submitted to the Ministry’s
Regional Office at Bhopal.
Implementation of such program should be ensured accordingly in a time bound
manner.
21.2.5
Proposed 2x9 MVA Ferro Alloy Plant (Fe-Si: 12,780 TPA or
Si-Mn: 28,620 TPA or Fe- Mn: 37,080 TPA) at Village Taraimal, Tehsil Tamnar,
District Raigarh in Chhattisgarh by M/s Sumit Ispat Private Limited - regarding
Environmental Clearance
The project authorities
and their consultant Pioneer Enviro Laboratories &
Consultants Pvt. Limited, Hyderabad gave a detailed presentation on the salient features of the project and proposed environmental
protection measures to be undertaken as per Terms of Reference (TORs) awarded in the 7th Meeting of the
Expert Appraisal Committee-1 (Industry) held during 2nd
- 3rd February, 2010 for preparation of EIA/EMP reports.
Public
hearing for the project was held on 26th November, 2010. The issues
raised during the public hearing were regarding socio economic and educational
development of local villagers, measures to prevent pollution of ponds in the
nearby villagers and impact on agriculture and forests, source of coal and raw
material etc. All the above issues were addressed and incorporated in the final
EIA / EMP report.
The Ferro Alloy Plants are listed at S.N. 3(a) under Primary
Metallurgy Industries under Category ‘A’ and appraised at the Central
level.
M/s Sumit Ispat Private Limited have proposed for the Ferro Alloy Plant
(2x9MVA; 30,000 TPA) at Village Taraimal, Tehsil Tamnar, District Raigarh,
Chhattisgarh. No ferro-chrome will be manufactured. Total land acquired is
Fume extraction and cleaning system with bag filters will be
provided to control particulate emissions below 50mg/Nm3 from
furnace. The fugitive emissions from the submerged electric arc furnaces
through hoods and fume extraction system comprising of bag filters. The
emission will be dispersed through stack of 30 m height. Dust emissions will be
controlled by water spraying generated due to vehicular movement.
Water requirement of 45m3/day will be met from the
ground water source. Permission to draw water from the Central Ground Water
Authority vide letter no. 21-4(82)/ CGWA/ NCCR/2010-196 dated 3.05.2010 has
been obtained. No effluent will be
generated from the ferro alloy plant due to adoption of closed circuit cooling
system. The treated effluent will be used for dust suppression and green belt
development. Service water will be passed through oil separator to remove oil
content in the effluent. Sanitary waste water will be treated in septic
tank followed by soak pit. No effluent will be discharged outside the
premises and ‘Zero’ discharge will be adopted. Rain water harvesting through
recharge pits, trenches, dug wells, hand pumps and recharge shafts will be
carried to recharge the ground water.
Ferro-Manganese
slag will be used as raw material for manufacture of Silico-Manganese. Slag
from Silico-Manganese will be provided to brick manufacturers. Ferro - silicon slag
will be used in cast iron foundries. Waste / used / spent oil and used
batteries will be sold to authorized recyclers / re-processors.
Out
of 5.7 ha of plant area, 1.92 ha will be used for green belt development.
Ambient noise levels will be in accordance with MoEF notification dated 14th
February, 2000 i.e. noise level < 75 dB (A) during day time and <70 dB(A)
during night time. Power requirement will be 18 MW and sourced from
Chhattisgarh State Electricity Board grid. The company has proposed to
undertake measures for occupational health and safety hazards.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other
environmental conditions:
i.
No charcoal shall be used as fuel. Pet coke shall be used as fuel
instead of charcoal from unknown sources.
ii.
Continuous
monitoring facilities for all the stacks and sufficient air pollution control
equipments viz. fume extraction system with bag filters, I D fan and stack of
adequate height to submerged arc furnace shall be provided to control
particulate emissions below 50 mg/Nm3. At no time, the emission
level shall go beyond the prescribed standards. Interlocking facilities shall
be provided so that process can be automatically stopped in case emission level
exceeds the limit.
iii.
Ambient
air quality monitoring stations shall be set up as per statutory requirement in
consultation with the Chhattisgarh Environment Conservation Board. Ambient air
quality including ambient noise levels shall not exceed the standards
stipulated under the Environment (Protection) Act, 1986 or by the State
authorities. The instruments used for
ambient air quality monitoring shall be calibrated time to time.
iv.
The
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 shall be followed.
v.
The project proponent shall upload the status of
compliance of the stipulated environment clearance conditions, including results
of monitored data on their website and shall update the same periodically. It shall simultaneously be sent to the Regional Office of the MOEF, the respective Zonal Office of CPCB and the
SPCB. The criteria pollutant levels namely; PM
10, SO2, NOx (ambient levels
as well as stack emissions) or critical sectoral parameters, indicated for the
projects shall be monitored and displayed at a convenient location near the
main gate of the company in the public domain.
vi.
Secondary
fugitive emissions from all the sources shall be controlled within the latest
permissible limits issued by the Ministry and regularly monitored. Guidelines /
Code of Practice issued by the CPCB shall be followed.
vii.
In-plant
control measures for checking fugitive emissions from all the vulnerable
sources shall be provided. Highly efficient bag filters shall be provided at
all material transfer points. Dust suppression system like water spraying shall
be provided at unloading and raw material handling areas, storage yards, to
control fugitive dust emissions to meet the CECB norms.
viii.
Total
water requirement shall not exceed 45m3/day. The wastewater from all the sources shall be
collected and treated and treated wastewater shall be recycled/ reused in the
process and/or used for dust suppression and green belt development. No process
water shall be discharged outside the premises and zero discharge shall be
strictly followed.
ix.
Efforts
shall be made to make use of rain water harvested. If needed, capacity of the
reservoir shall be enhanced to meet the maximum water requirement. Only balance
water requirement shall be met from other sources.
x.
Regular
monitoring of influent and effluent surface, sub-surface and ground water
should be ensured and treated wastewater shall meet the norms prescribed by the
State Pollution Control Board or described under the E (P) Act, 1986 whichever
are more stringent. Leachate study for the effluent generated and analysis
shall also be regularly carried out and report submitted to the Ministry’s
Regional Office at Bhopal, CECB and CPCB.
xi.
Slag
produced in Ferro Manganese (Fe-Mn) production shall be used in manufacture of
Silico Manganese (Si-Mn).
xii.
All
the ferro alloy slag shall be used for land filling inside the plant or used as
building material only after passing through Toxic Chemical Leachability
Potential (TCLP) test. Otherwise,
hazardous substances should be recovered from the slag and output waste and be
disposed in secured landfill as per CPCB guidelines.
xiii.
No
Ferro chrome shall be manufactured without prior approval of the Ministry.
xiv.
Proper
handling, storage, utilization and disposal of all the solid waste shall be
ensured and regular report regarding toxic metal content in the waste material
and its composition, end use of solid/hazardous waste shall be submitted to the
Ministry’s Regional Office at Bhopal, SPCB and CPCB.
xv.
Green
belt shall be developed in 33% of plant area in and around the plant premises
to mitigate the effects of fugitive emissions all around the plant as per the
CPCB guidelines in consultation with DFO.
xvi.
Risk
and Disaster Management Plan alongwith the mitigation measures shall be
prepared and a copy submitted to the Ministry’s Regional Office at Bhopal, CECB
and CPCB within 3 months of issue of environment clearance letter.
xvii.
Recommendations
made in the Charter on Corporate Responsibility for Environment Protection
(CREP) for the Ferro Alloy Units shall be strictly implemented.
xviii. At least 5 %
of the total cost of the project shall be earmarked towards the corporate
social responsibility and item-wise details alongwith time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at Bhopal.
Implementation of such program should be ensured accordingly in a time bound
manner.
xix.
The
company shall provide housing for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
21.2.6
Sponge Iron Plant (1,20,000 TPA, 2x200 TPD) along with 16
MW Captive Power Plant (WHRB - 8 MW &
AFBC - 8 MW) at Village Thirumalaiyampalayam, Coimbatore South Taluk, District
Coimbatore in Tamilnadu by M/s Raja Sponge Iron and Energy Private Limited - regarding
Environmental Clearance
The project authorities and their consultant Vimta Labs, Hyderabad gave a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken as per Terms of Reference
(TORs) awarded in the 4th
Meeting of the Expert Appraisal
Committee-1 (Industry) held during 26th
- 27th October, 2009 for preparation of EIA/EMP reports.
Public hearing for the
project was held on 29th September, 2010. The issues raised during
the meeting were regarding impact of water drawl on ground water, provision of
employment to the local people, drainage facility, solid waste disposal,
control of dust pollution etc. All the above issues were addressed and
incorporated in the final EIA / EMP report.
The Sponge Iron Plants
(> 200 TPD) are listed at S.N. 3(a), under Primary Metallurgy Industries
under Category ‘A’ and are appraised by the Expert Appraisal Committee in the
Ministry.
M/s Raja Sponge Iron &
Energy Pvt. Ltd. have proposed for Sponge Iron Plant
(1,20,000 TPA, 2x200 TPD) alongwith Captive Power Plant (16 MW), WHRB - 8 MW,
AFBC - 8 MW) at SG Nos. 122/1A, 123/2, 126, 126/1, 2 B, 3, 127/1 & 128/2, Village
Thirumalayampalayam, near Madukkarai, Taluk Coimbatore South,
District Coimbatore, Tamil Nadu. Total land area required for the project is 54.97 acres of which
18.35 acres has been earmarked for green belt. No R & R is involved.
Bolampatti RF (
Iron
ore (2,40,000 TPA) from mines of Bellary/Hospet, dolomite (400 TPA) from local
market, coal (1,44,000 MTPA) for sponge iron and 37,740 TPA for power plant from
Singharani Coal fields, imported coal from South Africa and Indonesia (1,44,000
MTPA) and char (30, 940 TPA) will be used as raw material. Waste gases will be
used in power generation.
To control the particulate emissions, ESP will
be provided to the AFBC boiler. Efforts will be made to control emissions
within 50 mg/Nm3. Bag filters will be provided at all the transfer
points. Water spraying system will be provided at coal yard, unloading of truck
tipplers. Bag filter will be provided to
coal circuit, iron ore circuit, stock house, kiln cooler tower, cooler
discharge product separation in storage buildings. Dust emissions from crushing and screening
will be controlled by watering, windscreens, hooding and ducting. Suitable dust
suppression and extraction methods will be provided to raw material handling,
loading and unloading and transfer points.
Total water requirement of
46m3/hr will be met from the Bhabani River water scheme by Tamil Nadu Water
Authority Department (TWAD). Power requirement of 4.6 MW will be met from the
captive power plant. Acidic and alkaline
effluent from cation and anion units of de-mineralized (DM) Plant will be
neutralized in neutralization tank. Boiler blow down will be neutralized in the
neutralization tank before mixing with other effluent streams. After
neutralization, these two effluents will be mixed with cooling tower blow down
in a re-circulation tank. The treated
effluent will be recycled / reused in the process and also for ash
conditioning, dust suppression and green belt development. Service water will
be passed through oil separator to remove oil content in the effluent. The
sewage will be treated in sewage treatment plant (STP) and treated sewage water
will be used for green belt development.
No effluent will be discharged and ‘zero’ discharge will be adopted.
Char will be used as fuel
in the AFBC boiler. Solid waste from STP
will be used as manure within the plant premises. Fly ash and bottom ash will
be sold to brick / cement manufacturers and for road embankment. Kiln accretion
will be used as base material for road construction. ESP dust will be given to
cement / brick industries. Fines from separator system will be recycled. Iron
ore fines from iron ore screening circuit, bag filters and vibrating screen
will be reused in the pellet plant. Coal fines from the coal crushing and
screening circuit will be recycled as fuel in the power plant. Bag filter dust
will be recycled to DRI plant. The oily sludge and waste oil will be provided
to authorized users/recyclers.
The Committee discussed
the project in detail and noted that information is required regarding
mitigation of NOx emission, existing stack emission data, hydro geology report
etc.
The Committee sought the
following additional information and deferred the project for reconsideration:
i.
Photographs of the existing plant area where rolling mill is
located.
ii.
Revised lay out of the plant indicating the green belt all around
the plan`.
iii.
Plan for mitigation of SO2 and NOx emissions.
iv.
Stack emission data of the existing rolling mill.
v.
Characteristics of the raw material in RSPM rather than
percentage.
vi.
Ground water analysis with bore well data, letho logs, draw down
and recovery test to quantify the area and volume of aquifer and its
management.
vii. Ground water modeling
showing the path ways of pollutants.
viii. Commitment that no ground
water shall be used during the construction and operation of the plant
ix.
Details regarding solid waste management plan.
x.
Details regarding disaster management plan.
xi.
Trend of health patterns of people / workers.
21.2.7
Ferro Alloy Plant (0.50 MTPA) and Captive Power Plant (2x130
MW) at Bodundakalan Industrial Area, Tehsil Kiranpur, District Balaghat in
Madhya Pradesh by M/s
Rashmi Cements Limited - regarding Environmental Clearance
The project authorities and their consultant EMTRC Consultants Pvt. Limited, gave a detailed
presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded in the 93rd
Meeting of the Expert Appraisal Committee-1 (Industry) held during 15th
- 16th April, 2009 for preparation of EIA/EMP reports.
Public hearing is not
required as the unit is located in the notified Bodundakalan Industrial area as
per section (iii), Stage (3), Para (i) (b) of EIA Notification, 2006.
The Ferro Alloy plants are listed at S.N.
3(a), under Primary Metallurgy Industries under Category ‘A’
are appraised at the Central level.
The proponent informed
that Committee that they have planned to implement only part of the project due
to financial and other constrains. They plan to establish 0.5 MTPA of ferro
alloy plant and 2x130 CPP. The remaining units namely DRI Plant, blast furnace,
Sinter plant, Coke oven, SMS, Rolling Mill and lime plants will be established
later.
M/s
Rashmi Cements Ltd. have proposed for Integrated Steel Plant (1.20 MTPA)
alongwith Ferro Alloy Plant (0.50 MTPA) Captive Power Plant (645 MW) and
Associated facilities at Khasra No. 367, 412, 413, 420, 464, 329, 426, 459, 463,
362, 366, 391, 427 & 409 of Village Bodudakalan and Khasra No. 501/8 &
501/9 of Village Khara, Bodundakalan Industrial Area, Tehsil Kiranpur District
Balaghat, Madhya Pradesh. Total project
area is 242.06 acres of which 80 acres will be under green belt. No national
park and wild life sanctuary is located within
High efficiency ESP and bag house will
be provided to control emissions within 50mg/Nm3. Fume extraction system to control fugitive
dust and fumes from the submerged arc furnaces will be installed. Adequate
water sprinkling devices, closed conveyors and bag houses will be provided to
reduce fugitive emissions.
Make-up water requirement will be 710 k/hr. Permission to draw 7000m3/day of water from
Wainganga and 5000m3/day from Bag River has been obtained. About
70m3/hr of waste water will be generated. The wastewater will be treated
in Effluent Treatment Plant (ETP) and 100% reused for ash handling, dust
suppression and green belt development. No effluent will be discharged and ‘zero’
discharge will be adopted. It is proposed to construct water reservoir to
collect the run out from the catchment area for use during the summer season.
The slag and dust from the
ferro alloy plant will be used in bricks manufacturing and construction materials.
Fly ash and bottom ash will be used for cement and brick manufacturing,
aggregates and road construction.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other
environmental conditions:
i.
No charcoal shall be used as fuel. Pet coke shall be used as fuel
instead of charcoal from unknown sources.
ii.
Continuous
monitoring facilities for all the stacks and sufficient air pollution control
equipments viz. fume extraction system with bag filters, I D fan and stack of
adequate height to submerged arc furnace shall be provided to control
particulate emissions below 50 mg/Nm3. At no time, the emission
level shall go beyond the prescribed standards. Interlocking facilities shall
be provided so that process can be automatically stopped in case emission level
exceeds the limit.
iii.
Ambient
air quality monitoring stations shall be set up as per statutory requirement in
consultation with the Madhya Pradesh Pollution Control Board. Ambient air
quality including ambient noise levels shall not exceed the standards
stipulated under the Environment (Protection) Act, 1986 or by the State
authorities. The instruments used for
ambient air quality monitoring shall be calibrated time to time.
iv.
The
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 shall be followed.
v.
The project proponent shall upload the status of
compliance of the stipulated environment clearance conditions, including
results of monitored data on their website and shall update the same
periodically. It shall simultaneously be
sent to the Regional Office
of the MOEF, the respective Zonal
Office of CPCB and the SPCB. The criteria pollutant levels namely; PM
10, SO2, NOx (ambient levels
as well as stack emissions) or critical sectoral parameters, indicated for the
projects shall be monitored and displayed at a convenient location near the
main gate of the company in the public domain.
vi.
Secondary
fugitive emissions from all the sources shall be controlled within the latest
permissible limits issued by the Ministry and regularly monitored. Guidelines /
Code of Practice issued by the CPCB shall be followed.
vii.
In-plant
control measures for checking fugitive emissions from all the vulnerable
sources shall be provided. Highly efficient bag filters shall be provided at
all material transfer points. Dust suppression system like water spraying shall
be provided at unloading and raw material handling areas, storage yards, to
control fugitive dust emissions to meet the CECB norms.
viii.
Total
water requirement shall not exceed 710m3/hr. The wastewater from all the sources shall be
collected and treated and treated wastewater shall be recycled/ reused in the
process and/or used for dust suppression and green belt development. No process
water shall be discharged outside the premises and zero discharge shall be strictly
followed.
ix.
Efforts
shall be made to make use of rain water harvested. If needed, capacity of the
reservoir shall be enhanced to meet the maximum water requirement. Only balance
water requirement shall be met from other sources.
x.
Regular
monitoring of influent and effluent surface, sub-surface and ground water
should be ensured and treated wastewater shall meet the norms prescribed by the
State Pollution Control Board or described under the Environment (Protection)
Act, 1986 whichever are more stringent. Leachate study for the effluent
generated and analysis shall also be regularly carried out and report submitted
to the Ministry’s Regional Office at Bhopal, CECB and CPCB.
xi.
Slag
produced in Ferro Manganese (Fe-Mn) production shall be used in manufacture of
Silico Manganese (Si-Mn).
xii.
All
the ferro alloy slag shall be used for land filling inside the plant or used as
building material only after passing through Toxic Chemical Leachability
Potential (TCLP) test. Otherwise,
hazardous substances should be recovered from the slag and output waste and be
disposed in secured landfill as per CPCB guidelines.
xiii.
No
Ferro chrome shall be manufactured without prior approval of the Ministry.
xiv.
Fly
ash utilization from the CPP shall be as per the Fly Ash Utilization Notification,
2009.
xv.
Proper
handling, storage, utilization and disposal of all the solid waste shall be
ensured and regular report regarding toxic metal content in the waste material
and its composition, end use of solid/hazardous waste shall be submitted to the
Ministry’s Regional Office at Bhopal, SPCB and CPCB.
xvi.
Green
belt shall be developed in 33% of plant area in and around the plant premises
to mitigate the effects of fugitive emissions all around the plant as per the
CPCB guidelines in consultation with DFO.
xvii.
Risk
and Disaster Management Plan alongwith the mitigation measures shall be
prepared and a copy submitted to the Ministry’s Regional Office at Bhopal, CECB
and CPCB within 3 months of issue of environment clearance letter.
xviii.
Recommendations
made in the Charter on Corporate Responsibility for Environment Protection
(CREP) for the Ferro Alloy Units shall be strictly implemented.
xix. At least 5 %
of the total cost of the project shall be earmarked towards the corporate
social responsibility and item-wise details alongwith time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at Bhopal.
Implementation of such program should be ensured accordingly in a time bound
manner.
xx.
The
company shall provide housing for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
Proposal for TORs
21.2.8
Proposed Asbestos Cement Products manufacturing unit at
Plot no. 405, GIDC Estate, Dhokla, District Ahmedabad in Gujarat by M/s Bhakti Associate
- regarding TORs
The project authorities and their
consultant M/s Consulting Engineers Group Ltd., Jaipur in Rajasthan gave a
detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken along with the draft Term of
References for the preparation of EIA/EMP. The Asbestos Cement Pipes
Units are listed at S.N. 4(c) under Category ‘A’ and are appraised by the
Expert Appraisal Committee (Industry) in the Ministry.
M/s Bhakti Associates have proposed
Asbestos cement pipes and couplings manufacturing unit at Plot No. 405, GIDC
Estate, Dholka, Ahmedabad in Gujarat. The capacity of the proposed project is
3,600 MTPA. The proposed site is situated on Dholka - Nadiad state highway.
Nearest railway station is Dholka at about 4 Kms west of the proposed unit. Raw
materials required are Chrysotile (White Asbestos), cement and fly ash. Total
land area is 2444 m2. Total cost of the
project is Rs. 80 lakhs.
The palletized compact bags of asbestos fibres
will be emptied in an enclosed automatic debagging device. The shredded bags
will be sent to fibre mill. There
will be no manual handling/opening of asbestos fiber bags. The company will
install fully automatic asbestos fiber debagging system before commissioning
the unit.
To
control the particulate emissions, it is proposed to install bag filters to
cement & ash silos and dust collector will be attached to the fibre bag
opening machine to arrest dust during loading and unloading. Power Supply shall be obtained from State Electricity Board, Gujarat. Total water requirement of 6m3/day
will be met from the Water Supply and Sewerage Board, Gujarat. Tanks of adequate
capacity will be developed for the collection and settlement of liquid
effluent. Supernatant liquid will be recycled for making fresh slurry. Zero
discharge will be adopted. Domestic effluent will be disposed of through
septic tank and soak pit. Solid
waste after pulverization will be recycled in the process as raw material.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1 Executive summary of
the project.
2 Photographs of the
plant area
3 A copy of Gazette
Notification for the notified Industrial Area.
4
Modern
up-to-date Asbestos plant with automatic bag opening devices should be
installed.
5 The safety measures
adopted during import and transport of Asbestos from Canada or any other
country should be included.
6 Present land use of
study area for 10 Km radius should be included. Detailed topographical map
indicating drainage pattern and other features of the area should also be
included.
7 Proposal should be
submitted to the Ministry for environment clearance only after acquiring total
land. Necessary documents indicating acquisition of land viz. allotment letter
should be included.
8
High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 km radius area from proposed site should
be incorporated. The same should be used
for land used /land-cover mapping of the area.
9
Project
site layout plan, raw materials, fly ash and other storage plans, bore well or
water storage, aquifers (within 1 Km.) dumping, waste disposal, green areas,
water bodies, rivers/drainage passing through the project site should be
included.
10
Cumulative
data base of last 2 yrs. for emissions e.g. aerosols size, optical depth, CO,
CO2, surface and air temperature, NO, CH4,
anions/cations/trace metals as given below in surface/subsurface water with
present GW level and its fluctuation for last 5-10 yrs from CGWB as may be
applicable.
11
For
the project location within 10 km radius of any major river, Flood Hazard
Zonation Mapping is required at 1:5000 to 1;10,000 scale indicating the peak
and lean river discharge as well as flood occurrence frequency.
12
Geo-technical
data by a bore hole of upto 40 mts. in every One sq. km area such as ground
water level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies. This will help making a future Seismic Hazard and Earthquake
Risk Management area.
13 Site-specific
micro-meteorological data including inversion height and mixing height should
be included
14 Details of the other
industries located in 10 km radius should be included
15 One season base line
data on air, water, soil & noise etc. should be included
16 A chapter on
chemistry of asbestos, handling of asbestos material, precautions proposed for
the direct contact, arrangements made for storage and monitoring of asbestos
fibres etc. other details as per given below:
i. Size of silica sand, transportation,
storage, spillway of melt and temperature management for float glass and mirror
Industry along with silicosis management and toxicity studies and management
for Ag etc.
ii. Source and location of Asbestos (GPS)
even if imported, size in F/ml, levels in environment, Chemical composition of
raw material as especially amount of Tremolite, Crocidolite, Amosite and other
amphiboles, Hexavalent chromium in raw material especially in serpentine, talc
and chrysotile, Electron microscopy, XRD and Raman Spectra studies.
iii. Health Management Plan for
Mesothalmia, Lung cancer and Asbestosis related problems in asbestos
industries.
17 Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS
location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS with
Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least as
per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of radioactive elements (U, Th
etc.),
18 Petrography, grain
size analysis and Major element analysis of raw material and soil from project
site and raw material should be done on the same parameters along with analysis
for SiO2, Al2O3, MgO, MnO, K2O, CaO, FeO, Fe2O3, P2O5, H2O, CO2.
19 If the rocks, ores,
raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
20 Mode of transport of
raw materials from sources are to be shown. All the trucks for raw material and
finished product transportation must be “Environmentally Compliant”
21 Studies are also
required for management of muck
disposal, slurry, sludge material and solid waste generated if the raw
materials used has trace elements and a management plan.
22 Air quality modelling
for the Asbestos handling system. Ambient air quality monitoring modelling
alongwith cumulative impact. Following are to be included as an annexure for
the day (24 hrs) considered for maximum GLC:
i. Emissions (g/second) with and without
the air pollution control measures
ii. Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii. Model
input options for terrain, plume rise, deposition etc.
iv. Print-out of model input and output on
hourly and daily average basis
v. A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi. Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii. Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii. No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix. Graphs of monthly average daily
concentration with down-wind distance
x. Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi. Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
xii. Existing stack emission data and fibre
concentration in the work zone.
23 Sources of secondary
emissions, its control and monitoring as per the CPCB guidelines and latest
notification vide G.S.R. 414(E) dated 30th May, 2008 should be
included.
24 Chemical
characterization of RSPM and incorporation of RSPM data. Location of one AAQMS
in downwind direction.
25 Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
26 Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater recharge
structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
Incorporation of water harvesting plan for the project is necessary, if source
of water is bore well.
27 Actual source and
permission for the drawl of water from bore well from the SGWB/CGWA or
concerned authority and water balance data including quantity of effluent
generated, recycled and reused and discharged is to be provided. Methods
adopted/to be adopted for the water conservation should be included
28 Ground water
monitoring minimum at 8 locations should be included.
29 Scheme for proper
storage of asbestos fibres and disposal of solid/hazardous waste should be
included.
30
Presence
of an aquifer/aquifers within 1 km of the project boundaries should be
included. Management plan for recharging the aquifer should be given so as to
limit the water extraction within permissible limit of CWC or CGWB should be
included.
31
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
32
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management should be included.
33
Ground
water modeling showing the pathways of the pollutants should be included
34
Column
leachate study for all types of stockpiles or waste disposal sites, at 20oC-50oC
should be conducted and included.
35
All
samplings for water have to be done during the peak summer time (Sampling
number, dates and standard deviation should be included.
36
Incorporation
of water harvesting plan for the project is necessary, if source of water is
bore well should be ensured.
37
Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents should be included.
38
If
the water is mixed with solid particulates, proposal for sediment pond before
further transport should be included.
The sediment pond capacity should be 100 times the transport capacity.
39
Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from
asbestos bearing effluent should be included.
40
The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans should be included.
41
All
stock piles should be on top of a stable liner to avoid leaching of materials
to ground water.
42
The
green belt should be around the project boundary in 33 % area and a scheme for
greening of the traveling roads should also be incorporated. All
rooftops/terraces should have some green cover.
43
The
details of green belt plan along SE direction of the plant area.
44 Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
45 Arrangements for the
proper monitoring of the occupational health of the workers should be included.
Occupational hazards specific pre-placement and periodical monitoring and
periodical monitoring should be carried out. The detailed plan to carry out
above mentioned activity should be mentioned. The measures to protect the
workers from accidents and other safety issues. Detailed plan for the same. Man
machine relationship. How the issue of man-machine relationship to protect the
workers from musculo-skeletal disorder such as backache, arthritis, body ache etc.
46 Detailed action plan
for compliance of the directions of the Hon’ble Supreme Court of India
regarding occupational health and safety measures in asbestos industries should
be included.
47 Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
48 Compliance to the
recommendations mentioned in the CREP guidelines should be included.
49 An action plan on entire
operation should be automatic and closed system for all operations for fibre
handling and processing should be included.
50 Details of
arrangement for measurement and monitoring of asbestos fibre (Phase contrast
microscope) should be included.
51 Detailed Environment
management Plan (EMP) with specific reference to details of air pollution
control system water & wastewater management, monitoring frequency,
responsibility and time bound implementation plan for mitigation measure should
be provided.
52 EMP should include
the concept of waste-minimization, recycle/reuse/recovery techniques, Energy
conservation, and natural resource conservation.
53 EMP should include a
clear map for plantation/green belt.
54
Commitment
that laboratory for monitoring asbestos fibres will be established at the site.
55 At least 5 % of the
total cost of the project should be earmarked towards the enterprise social
commitment and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
56
Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It
was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. The EIA/EMP report shall be submitted to
the Ministry for obtaining environmental clearance. Public hearing has been
exempted as the unit is located in the Notified Industrial Area.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports.
21.2.9
Proposed 6000 TPA Low & Medium Carbon Ferro Alloys
Project at Adityapur Industrial Area, Jamshedpur, District Saraikela Kharsawam
in Jharkhand by M/s
Jamshedpur Minerals & Chemicals - regarding TORs
The
project proponent requested to consider their proposal in the next meeting and
hence the proposal was deferred for next meeting.
21.2.10
Proposed expansion of 1.2 MTPA Pellet Plant with addition
of 0.1 MTPA Integrated Steel Plant at Matkambeda Industrial Estate, Tehsil
Barbil, District Keonjhar, Orissa by M/s Arya Iron & Steel Company Pvt.
Limited (AISCO) - regarding TORs
The
project authorities and their consultant
M/s M/s S S Environics
(India) Pvt. Ltd., Bhubaneswar, Orissa gave
a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken along with the draft TORs
for preparation of EIA/EMP. The
Steel Plants are listed at S.No. 3(a) as Primary Metallurgical Industries under
category ‘A’ of the Schedule of EIA Notification,
2006 and appraised at the Central level.
M/s Arya Iron and Steel Company Pvt. Ltd. (AISCO) have proposed for the expansion of existing
pellet plant of 1.2 MTPA capacity with addition of 0.1 MTPA Integrated Steel
Plant at Matkambeda Industrial Estate, Tehsil-Barbil, District Keonjhar,
Orissa. The unit is located in the
Notified Industrial Area. The expansion will be carried in the existing plant area of 55.49 acres.
No additional land is required. Green belt will be developed in 17.9 acres of plant
area. No national
Park/wild life sanctuary/ Biosphere sanctuaries is located within 10
km radius of the project site. Total cost of the project is Rs. 90 Crores. Rs. 2.45 Crores and Rs. 49.06 Lakhs
will be earmarked towards capital cost and recurring cost/annum for
environmental pollution control measures.
Raw materials required
will be Iron Ore Fines (145000 TPA), Anthracite Coal (35000 TPA) to be imported
from South Africa, Russia & Vietnam, Bituminous Coal (45000 TPA) sourced
from local market, Scrap 9200 TPA, Silico Manganese 1000 TPA & Limestone
10000 TPA).
The existing 1.2 MTPA Pellet Plant is
operating for the last two years for which NOC / Consent to Operate from SPCB
has been obtained. Proposed expansion will include 0.1 MTPA of Integrated Steel
Plant with; HGPIN (High Grade Pure Iron Nuggets) 0.1 MTPA of MS billets using
0.1 MTPA of nuggets and three numbers of Producer Gas Plants of capacity13500
NM3/hr.
The
proposed project envisages use of HGPIN technology to minimize the process
water consumption & coal consumption, in order to manufacture Hi-Grade Iron
nuggets.
Water
requirement of 192m3/day will be met from the River Karo. Permission
has been obtained for drawl of 1443.48m3/day of water from Karo
River, vide letter no. 2459/WR.Irr-II-WRC-33/2010 dated 02.02.2010 from Department
of Water Resources, Govt. of Orissa. No effluent will be discharged and ‘zero’
discharge will be adopted. Domestic wastewater will be treated through STP. Power
requirement will be supplied from NESCO, for which permission has been
obtained. Emergency power will be utilized from existing 1 x 1000 KVA DG Set.
Solid
waste generated will be in the form of SMS slag (10200 TPA) which will be used
in internal road making. Fly ash from HGPIN (4200TPA) will be fully utilized
for pellet making. Ash from Producer Gas Plant (6237 TPA) will be utilized for
pellet making. STP Sludge (41 TPA) will be used as manure for green belt development
, RWTP sludge (45 TPA) will be used for land filling and ETP Sludge (0.5 TPA) will
be used in secured land fill.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the existing and proposed plant area.
3.
A
copy of Gazette Notification for notified Industrial Area.
4.
Compliance to the
conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
5.
A
line diagram/flow sheet for the process and EMP
6.
A
copy of firm coal linkage
7.
Detailed
lay out plan of the project.
8.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. Present land use should be prepared based on satellite
imagery. High-resolution satellite image data having 1m-5m spatial resolution
like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area
from proposed site. The same should be used for land used/land-cover mapping of
the area.
9.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
10. Location of national
parks / wildlife sanctuary / reserve forests within 10 km. radius should
specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
11. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
12.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
13. Details and
classification of total land (identified and acquired) shall be included.
14. A list of industries
containing name and type in 10 km radius shall be incorporated.
15. Residential colony
shall be located in upwind direction.
16. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
17. Action plan for
excavation and muck disposal during construction phase.
18. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
19. Manufacturing process
details for all the plants shall be included.
20. Mass balance for the
raw material and products shall be included.
21. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
22. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
23. Data generated in the
last two years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
24.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
25. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
26. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
27. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
28. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
29. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
30.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models. Cumulative impacts due
to the existing plant and proposed expansion on the ambient air quality along
with data on the stack emissions.
31.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
32. A plan for the
utilization of waste/fuel gases in the WHRB for generating power have to be set
out.
33. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
34. One season data for
gaseous emissions other than monsoon season is necessary.
35. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
36. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
37. Source of surface/ground
water level, site (GPS), cation, anion (Ion Chromatograph), metal trace element
(as above) chemical analysis for water to be used. If surface water is used
from river, rainfall, discharge rate, quantity, drainage and distance from
project site should also be included. Information regarding surface hydrology
and water regime should be included.
38. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
39. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
40. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
41. A note on the impact
of drawl of water on the nearby River during lean season.
42. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
43. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
44. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
45. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
46. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
47. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
48. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
49. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
50. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
51. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
52. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
53. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
54. At least 5 % of the
total cost of the project should be earmarked towards the enterprise social
commitment and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
55. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
56. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray, Audiometry,
Spirometry Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations and plan of monthly and yearly report of the
health status of workers with special reference to Occupational Health and
Safety.
57. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
58. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
59. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
60. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
61. A note on
identification and implementation of Carbon Credit project should be included.
62. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to the Ministry for obtaining environmental
clearance. Public hearing has been exempted as the unit is located I the
Notified Industrial Area.
The TORs prescribed
shall be valid for a period of two years for submission of the EIA/EMP reports.
21.2.11
Proposed 0.3 MTPA Integrated Steel Plant at Village Malda,
Dhanurjayapur, Tehsil Barbil, District Keonjhar, Orissa by M/s Arya Integrated
Steel Private Limited - regarding TORs
The project
authorities and their consultant
M/s S. S. Environics
(India) Pvt. Ltd. Bhubaneswar Orissa gave
a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken along with the draft TORs
for preparation of EIA/EMP report. The
Steel Plants are listed at S.No. 3(a) in Primary Metallurgical Industries under
category ‘A’ of the Schedule of EIA Notification,
2006 and appraised at the Central level.
M/s Arya Integrated Steel Pvt. Ltd. (AISPL)
have proposed to set up an Integrated Steel Plant at Village Malda,
Dhanurjaypur, Tehsil Barbil, Dist: Keonjhar, Orissa. Proposed Integrated Steel
Plant will comprise of Iron Ore Beneficiation Plant (1.8 MTPA), Iron Ore Pellet
Plant (2 X 1.2 MTPA), Integrated Steel
Plant (0.3 MTPA), High Grade Pure Iron nuggets
(HGPIN) (0.3 MTPA), M.S. billets (0.3 MTPA),
TMT rods / structurals (0.2 MTPA) and Producer Gas Plant (9 nos. of producer
gas plant of capacity 4500Nm3/hr
each with total capacity of 40,500Nm3/hr). No national Park/wild
life sanctuary/ Biosphere reserve is located within 10 km radius of
the project site. Total land area required for the project is 187 Acres of which 157 acres is for the plant and 30
acres for the railway siding. About 51.8 acres of plant area will be earmarked
for green belt development. Total cost of the project is Rs. 546.38
crores Rs. 27.00 Crores and Rs. 5.40 crores will be earmarked towards capital
cost and recurring cost/annum for environmental pollution control
measures.
Raw materials required will be low grade
Iron Ore (18,00,000 TPA), Iron Ore Fines (13,50,000 TPA), Anthracite Coal
(1,70,000 TPA) to be imported from Australia / Indonesia. Bituminous Coal (1,35,000 TPA) to be sourced
from coalfields in Orissa through open market, Scrap (25,000 TPA) from local
vendors, Bentonite (16,8000 TPA) from Local vendors, Silico Manganese (3000 TPA)
from local ferro alloy plant, limestone (20,000 TPA) from nearby mines in
Sundargarh District and Dolomite (15,000 TPA) from nearby mines.
Fresh water requirement of 1774m3/day
will be drawn from River Baitarani which flows at a distance of 0.6 Km (West)
from the project site. Power requirement of 45 MVA will be met from the NESCO.
DG sets (2x500 KVA) will be installed for emergency. The effluent will be
treated in the ETP and recycled back to the process. The domestic waste water
will be treated in the STP and treated effluent will be used for green belt. No
effluent will be discharged and ‘zero’ discharge will be adopted. The storm
water drains will be segregated and channelized to water harvesting area.
Solid
waste generated will be in the form of SMS Slag (33,000 TPA) and used in
internal road making and filling up low land area after metal recovery. Fly ash
from HGPIN (12,600 TPA) will be fully utilized for pellet making. Ash from
Producer Gas Plant (18,900 TPA) will be fully utilized for pellet making. STP
Sludge (41 TPA) will be used as manure for green belt development. RWTP Sludge (45
TPA) will be used for land filling and ETP sludge (0.5 TPA) used in secured
land fill. Tailings from the beneficiation plant (3,00,000 TPA) will be
disposed off in the designated tailing area in form of cake to be used in
future for quarry filling / further value addition.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
Documents
regarding firm Coal linkage
5.
Detailed
lay out plan of the project area
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. Present land use should be prepared based on satellite
imagery. High-resolution satellite image data having 1m-5m spatial resolution
like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area
from proposed site. The same should be used for land used/land-cover mapping of
the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
Project
site layout plan showing raw materials, fly ash and other storage plans, bore
well or water storage, aquifers (within 1 km.) dumping, waste disposal, green
areas, water bodies, rivers/drainage passing through the project site should be
included.
10.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
11. Details and
classification of total land (identified and acquired) shall be included.
12. A list of industries
containing name and type in 10 km radius shall be incorporated.
13. Residential colony
shall be located in upwind direction.
14. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
15. Action plan for
excavation and muck disposal during construction phase.
16. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
17. Manufacturing process
details for all the plants shall be included.
18. Mass balance for the
raw material and products shall be included.
19. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
20. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
21. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
22.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
23. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
24. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
25. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
26. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
27. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
28.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
29.
Petrological
and Chemical analysis and other chemical properties of raw materials used (with
GPS location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
30.
Petrography,
grain size analysis and Major element analysis of raw material and soil from
project site and raw material should be done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
31.
If
the rocks, ores, raw material has trace elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
32.
Studies
for fly ash, muck disposal, slurry, sludge material and solid waste generated
should also be included, if the raw materials used has trace elements and a
management plan.
33.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
34. A plan for the
utilization of waste/fuel gases in the WHRB for generating power have to be set
out.
35. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
36. One season data for
gaseous emissions other than monsoon season is necessary.
37. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
38. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
39. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
40. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
41. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
42. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
43. A note on the impact
of drawl of water on the nearby River during lean season.
44. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
45. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
46. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
47. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
48. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the transport
capacity.
49. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
50. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
51. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
52. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
53. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
54. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500 trees
per ha. giving details of species, width of plantation, planning schedule etc.
should be included. The green belt should be around the project boundary and a
scheme for greening of the travelling roads should also be incorporated. All
rooftops/terraces should have some green cover.
55. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
56. At least 5 % of the
total cost of the project should be earmarked towards the enterprise social
commitment and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
57. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
58. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
59. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
60. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
61. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
62. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
63. A note on
identification and implementation of Carbon Credit project should be included.
64. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Orissa State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The TORs prescribed shall
be valid for a period of two years for submission of the EIA/EMP reports, after
public consultation.
21.2.12
Proposed 0.6 Million TPA Iron Ore Pellet Plant & 50 MW
Gas based Power Plant at Sy No. 27-40 & 58, Village Endlapalli, Mandal
Suryapet, District
Nalgonda in Andhra Pradesh by M/s Sri Soudhamini Projects Private Limited -
regarding TORs
The project
authorities and their consultant
M/s Global Enviro Labs,
Hyderabad gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP. The Steel Plants are listed at S.No. 3(a)
in Primary Metallurgical Industries under category ‘A’ of the Schedule of EIA Notification, 2006 and appraised at the Central
level.
M/s. Sri Soudhamini Projects Private Limited have proposed
0.6 Million TPA Iron Ore Pellet Plant & 50 MW Gas Based Power Plant in Sy. No. 27 – 40 & 58 of Endlapalli Village, Suryapet
Mandal, Nalgonda District, Andhra Pradesh.
The project proponent has acquired 100 acres of the land for the
proposed plant. No habitation exists in the proposed project site. Hence,
displacement and rehabilitation of people is not involved. The total cost of the project is Rs. 435 Crores.
Raw materials required for Pellet
Plant will be Iron Ore (6,30,000 TPA) from Bellary /
Hospet, Bentonite (12000 TPA) from Kutchh, Coke (19,600 TPA) form South Africa, Austraila and lime stone (17260
TPA) from Dhone and Piduralla. For the Power Plant, natural Gas (0.313 MSCMD)
will be sourced from RIL/GAIL, HSD-(236 MT/day as Secondary fuel) (Backup fuel
which will be used in emergencies) from IOCL/BPCL/HPCL.
To control the particulate emissions, ESP / cyclone with bag
filters will be installed. Two nos. of
stacks in Pellet plant of 45 m height and one stack in power plant of 50 m height
have been proposed for proper dispersion of gaseous emissions.
The water requirement will be 2820 m3/day
which will be sourced from ground & Musi River. There will be no generation
of waste water from the proposed iron ore pellet plant. The waste water
generation from the proposed power plant includes cooling tower blow down,
boiler & DM plant regeneration. The waste water after primary treatment
will be used for green belt development.
Bag filter dust will be generated and this
will be reused in the feed mix. There will be no solid waste from the gas based
power plant.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the existing and proposed plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
A
copy of gas supply agreement.
5.
Detailed
lay out plan
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. Present land use should be prepared based on satellite
imagery. High-resolution satellite image data having 1m-5m spatial resolution
like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area
from proposed site. The same should be used for land used/land-cover mapping of
the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
Project
site layout plan showing raw materials, fly ash and other storage plans, bore
well or water storage, aquifers (within 1 km.) dumping, waste disposal, green
areas, water bodies, rivers/drainage passing through the project site should be
included.
10.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
11. Details and
classification of total land (identified and acquired) shall be included.
12. A list of industries
containing name and type in 10 km radius shall be incorporated.
13. Residential colony
shall be located in upwind direction.
14. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
15. Action plan for
excavation and muck disposal during construction phase.
16. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
17. Manufacturing process
details for all the plants shall be included.
18. Mass balance for the
raw material and products shall be included.
19. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
20. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
21. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
22.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors including
reserved forests.
23. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
24. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
25. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
26. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
27. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
28.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
29.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
30. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
31. One season data for
gaseous emissions other than monsoon season is necessary.
32. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
33. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
34. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
35. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
36. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
37. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
38. A note on the impact
of drawl of water on the nearby River during lean season.
39. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
40. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at 1:5000
to 1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency.
41. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
42. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
43. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
44. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
45. Ground water monitoring
minimum at 8 locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
46. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
47. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be lined,
if so a detail of the lining etc. needs to be addressed.
48. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
49. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
50. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
51. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
52. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
53. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
54. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
55. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
56. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
57. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
58. A note on
identification and implementation of Carbon Credit project should be included.
59. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Andhra Pradesh Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports, after public consultation.
21.2.13
Proposed Ferro Alloy
Plant (Si-Mn - 30,000 TPA, Fe-Mn- 39,000 TPA and Sinter plant for
sintering of Mn Ore- 2,79,000 TPA) at Village Ethora, Tehsil Salanpur, District
Burdwan in West Bengal by
M/s Sangeeta Ispat Pvt. Limited- regarding TORs
The project authorities and their consultant
M/s Envirotech East Pvt. Ltd., Kolkata gave a detailed presentation on the
salient features of the project and proposed environmental protection measures,
to be undertaken along with the draft Term of References for the preparation of
EIA/EMP report. The integrated steel plants are listed at S.No. 3(a) under
primary metallurgical industry under category- A of the Schedule of the EIA notification, 2006 and
appraised at Central level.
M/s Sangeeta Ispat Pvt. Limited have
proposed for the installation of Ferro Alloy Plant (Si-Mn - 30,000 TPA, Fe-Mn- 39,000 TPA
and Sinter plant for sintering of Mn Ore- 2,79,000 TPA) at Village Ethora, Tehsil Salanpur, District
Burdwan in West Bengal. No
National Park / Wildlife Sanctuary / Biosphere reserve is located within 10 km
distance from the project site. Total land required for the project is of 8.28
acres, out of which 33% area will be developed under green belt. Damodar River
flows at a distance of 10 kms. Barakar River at 8.8 kms and Ajoy River flows at
12 kms from the project site. Total cost of the project is Rs. 432.60
Crores.
Details of the plant configuration
along with production capacity is given below:
Sl. No. |
UNIT |
CAPACITY |
1 |
Ferro Alloys Plant (2x18 MVA SAF) |
30,000 TPA Silico-Manganese 39,000 TPA Ferro-Manganese |
2 |
Sinter Plant for Manganese Ore (3x300 TPD) |
2,79,000
TPA Mn Ore Sinter |
To control the particulate emissions
from the plant within 50 mg/Nm3, high efficiency bag filters / ESP would be installed. Adequate stack height shall be provided for
proper dispersion of air emissions.
Make up water
requirement of 38.25m3/hr will be sourced from Damodar Valley
Corporation (DVC) water supply system. There will be zero discharge of
effluent. Ferro-manganese slag will be used in silico-manganese production. The
slag generated in silico-manganese will be used for roads and building
construction. Flue dust will be recycled in the sinter plant. The total power requirement will be
around 36 MVA, which will be sourced from WBSEDCL supply system.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive summary of the project.
2.
Photographs
of the existing and proposed plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
Detailed
lay out plan of the project
5.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
7.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
8.
Location
of national parks / wildlife sanctuary / reserve forests within
9.
A
list of industries within 10 km radius of the plant area.
10.
Details
and classification of total land (identified and acquired) should be included.
11.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within
12.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
13.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
14.
Mass
balance for the raw material and products should be included.
15.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
16.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
17.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
18.
Ambient
air quality at 8 locations within the study area of
19.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
20.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
21.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
22.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
23.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
24.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
25.
An
action plan to control and monitor secondary fugitive emissions from all the sources
as per the latest permissible limits issued by the Ministry vide G.S.R. 414(E)
dated 30th May, 2008.
26.
Presence
of aquifer/aquifers within
27.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
28.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
29.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
30.
A
note on the impact of drawl of water on the nearby River during lean season.
31.
Action
plan for rainwater harvesting measures.
32.
Surface
water quality of nearby River (
33.
If
the site is within
34.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
35.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
36.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
37.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
38.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
39.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
40.
Action plan for chrome recovery and its solid waste
management plan.
41.
Acton
plan for the green belt development plan in 33 % area should be included.
42.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
43.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
44.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
45.
At
least 5 % of the total cost of the project should be earmarked towards the enterprise
social commitment and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
46.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
47.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
48.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the West Bengal Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA report.
The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP along with Public hearing
proceedings.
21.2.14
Installation of Pellet Plant (6,00,000 TPA) in the existing
Steel Plant at Village Poradiha, District Purulia in West Bengal by M/s Vikash Metal
& Power Limited- regarding TORs
The project authorities and their consultant,
M/s Envirotech East Pvt. Ltd., Kolkata gave a detailed presentation on the
salient features of the project and proposed environmental protection measures,
to be undertaken along with the draft Term of Reference for the preparation of
EIA/EMP report. The steel plants are listed at S.N. 3(a) under Primary Metallurgical
Industries, falling under “Category A” projects. Hence, the project will be
appraised at the Central level.
M/s Vikash Metal & Power Limited
have proposed for installation of Pellet Plant (6,00,000 TPA) in the existing
Steel Plant at Village Poradiha, District Purulia in West Bengal.
In the existing plant, the company is operating Sponge Iron plant (1,30,000
TPA), Induction Furnace (1,14,000 TPA), Rolling Mill (1,50,000 TPA), Ferro
Alloy Plant (15,400 TPA) and Captive power plant based on WHRB and AFBC (10 MW).
No national Park / wild life sanctuary / Biosphere reserves are located
within 10 km radius of the project site. The proposed project will be
set up in 9 acres of land, which is already in possession of the company. Green
belt will be developed in 33% of the total plant area. Damodar River flows at a
distance of 4 kms & Barakar River at 11 kms from the project site. Total
cost of the project is Rs. 313.74 Crores.
Details of
the existing as well as proposed units along with their production capacity are given below:
Unit |
Existing Capacity |
Product |
Sponge Iron Plant (4x100 TPD) |
1,30,000 TPA |
Sponge Iron |
Induction Furnace (4x8 T) |
1,14,000 TPA |
Billets |
Rolling Mill |
1,50,000 TPA |
TMT Bars and HR Strips
|
Ferro Alloy Plant (1X9 MVA) |
15,400 TPA |
Ferro Manganese |
Captive Power Plant |
10 MW (Based on WHRB &
AFBC) |
Power |
Iron Ore
Pelletization Plant (6,00,000
TPA) |
- |
Pellet |
The
major raw materials required will be Iron Ore, Coal, Lime Stone and Bentonite
in the plant process.
To
control the particulate emissions, all the transfer points will be provided
with dry fogging system. Dust Suppression Systems/ Foggy Dust Arresters will be
installed to control fugitive emissions at various facilities inside the plant.
Dust suppression will be done by water sprinkling to control fugitive emissions
due to transportation activities. Particulate emissions from the plant will be
controlled within 50 mg/ Nm3 with the use of high efficiency ESPs,
Bag Filters etc. Stacks of adequate height will be provided at the respective
units.
Make
up water requirement for the proposed expansion project is about 50m3/day,
which will be sourced from Damodar Valley Corporation (DVC) water supply
system. The plant will be designed as a zero discharge plant. The entire
treated waste water will be recycled for various purposes inside the plant. The
water will be re-circulated through cooling and treatment. Iron ore tailings
generated from the proposed plant will be disposed off in abandoned mines. Power
requirement will be around 3250 KVA, which will be sourced from DVC. Ear
muffs/ear plugs will be provided to workers working in high noise prone areas. Solid
waste generated in the form of iron ore tailing will be disposed off in the
abandoned mines.
The
Committee prescribed the following TORs for undertaking detailed EIA/EMP study:
1.
Executive summary of the project.
2.
Photographs
of the existing and proposed plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
Compliance to the
conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
5.
A
copy of the coal linkage document
6.
Detailed
lay out plan of the plant
7.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
8.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
9.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
10.
Location
of national parks / wildlife sanctuary / reserve forests within
11.
A
list of industries within 10 km radius of the plant area.
12.
Details
and classification of total land (identified and acquired) should be included.
13.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within
14.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
15.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
16.
Mass
balance for the raw material and products should be included.
17.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
18.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
19.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
20.
Ambient
air quality at 8 locations within the study area of
21.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
22.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
23.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
24.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
25.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
26.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
27.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
28.
Presence
of aquifer/aquifers within
29.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
30.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
31.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
32.
A
note on the impact of drawl of water on the nearby River during lean season.
33.
Action
plan for rainwater harvesting measures.
34.
Surface
water quality of nearby River (
35.
If
the site is within
36.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
37.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
38.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
39.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
40.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
41.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
42.
Acton
plan for the green belt development plan in 33 % area should be included.
43.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
44.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
45.
Details
regarding expected Occupational & Safety Hazards. Protective measures for Occupational
Safety & Health hazards so that such exposure can be kept within
permissible exposure level so as to protect health of workers. Health of the
workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far &
Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations and
plan of monthly and yearly report of the health status of workers with
special reference to Occupational Health and Safety.
46.
At
least 5 % of the total cost of the project should be earmarked towards the enterprise
social commitment and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
47.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
48.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
49.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the West Bengal Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA
report. The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed shall be valid for a period of two
years for submission of the EIA/EMP along with Public hearing proceedings.
21.2.15
Enhancement in production capacity from 6000 TPA to 18,000
TPA Ferro Alloys at Village Matkambeda, Tehsil Barbil, District Keonjhar,
Orissa by M/s
Pankaj Ferro Tech Pvt. Limited - regarding TORs
The project
authorities and their consultant, Kalyani Laboratories Pvt. Limited,
Bhubaneswar gave a detailed presentation on the salient features of project and
proposed environmental protection measures to be undertaken along with the
draft Terms of Reference for the preparation of EIA/EMP report. The Ferro
Alloy Plants have been listed at S.N.3 (a) under Primary Metallurgical
Industries and appraised by Expert Appraisal Committee in the Ministry.
M/s. Pankaj Ferro Tech Pvt. Ltd have
proposed for expansion of Ferro Alloy plant from 6000 TPA to 18000 TPA at Plot
No. 17, 5 & 8 Matkambeda, Industrial Area, Barbil District Keonjhar Orissa.
Existing Ferro Alloy plant started its operation in 2005. The company has
already acquired 5.5 acres (2 acres for existing plant and 3.5 acres has
already been acquired for expansion programme). The unit is located in the notified
industrial area. No national park /
wildlife sanctuary / eco sensitive areas are located within 10 km radius from
the proposed site. Total cost of the project is Rs.6.92 Crores
The raw materials required for
expansion will be Mn Ore + Slag (26400 TPA), Coke (9600 TPA), Quartz (3000 TPA),
Dolomite (5000 TPA) which will be source from Orissa, Nagpur, Dhanbad, Ramgarh,
Rajgangpur etc. Power requirement will be met from the State Electricity Board.
The sources of air pollution from the
plant will be Submerged Electric arc furnaces and stand by DG sets. It is
proposed to provide Fume Extraction System with bag filters to control the
particulate emissions. Make up water requirement will be 65m3/day. No
process effluent will be generated. Only domestic effluent of 3m3/day
and cooling tower blow down i. e. 60 m3/day will be generated. The
water will be used for dust suppression and fire fighting. .
The solid waste generated from the unit will
be bag filter dust (290 TPA) and solids from settling tank, Slag (10800 TPA)
from the Ferro alloy plant which will be used for land filling. The used oil will
be sold to the authorized recyclers.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive summary of the project.
2.
Photographs
of the existing and proposed plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
Copy
of Notification for notified Industrial
Area.
5.
Compliance
to the conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
6.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
8.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
9.
Location
of national parks / wildlife sanctuary / reserve forests within
10.
A
list of industries within 10 km radius of the plant area.
11.
Details
and classification of total land (identified and acquired) should be included.
12.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within
13.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
14.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
15.
Mass
balance for the raw material and products should be included.
16.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
17.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
18.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
19.
Ambient
air quality at 8 locations within the study area of
20.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
21.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
22.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
23.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
24.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
25.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
26.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
27.
Presence
of aquifer/aquifers within
28.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
29.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
30.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
31.
A
note on the impact of drawl of water on the nearby River during lean season.
32.
Action
plan for rainwater harvesting measures.
33.
Surface
water quality of nearby River (
34.
If
the site is within
35.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
36.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
37.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
38.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
39.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
40.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
41.
Action plan for chrome recovery and its solid waste
management plan.
42.
Acton
plan for the green belt development plan in 33 % area should be included.
43.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
44.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
45.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
46.
At
least 5 % of the total cost of the project should be earmarked towards the enterprise
social commitment and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
47.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
48.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The EIA/EMP report shall be submitted to
the Ministry for obtaining
environmental clearance. Public hearing is exempted as the unit is located in
the Notified Industrial Area.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP.
21.2.16
Expansion of Cement Plant from 4.50 MTPA to 7.00 MTPA along
with Captive Power Plant from 48 MW to 98 MW by addition of Cement Line-III of
2.50 MTPA and CPP of 1x50 MW at Villages Karikkali and Dholipatti, Taluk
Vedasandur, District Dindigul in Tamil Nadu by M/s Chettinad Cement Corporation
Limited - regarding TORs
The project authorities and their
consultant M/s Enviro Care India Private limited,
Madurai, Tamil Nadu gave a detailed presentation on the salient features
of the project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP report. The Cement Plants (>
1.0 MTPA) are listed at S.No. 3(b) under category ‘A’ of the Schedule of EIA
Notification, 2006 and appraised at the Central level.
M/s
Chettinad Cement Corporation Ltd is already operating a cement plant of capacity
4.5 MTPA and Coal based Captive Power Plant of 48 MW in two phases. The company
intends to put up a third line having
capacity of 2.5 MTPA cement plant and 50 MW coal based thermal power
plant within the same plant premises. The expansion of cement plant and Power
plant will be carried at S.F. Nos. 652-655,658,659,704,710-713,715-726 at
Karikkali Villages, Vedasandur Taluk, Dindigul District, Tamil Nadu. Limestone
requirement for the cement plant including expansion will be met from the
existing mines in Karikkali and Dholipatti Villages. The total plant area is
105.60 ha of which 34.90 ha is earmarked for the green belt. The total cement
grinding capacity of the plant will be 7.0 MTPA and Captive power plant capacity
will be 98 MW on expansion. There is no National Parks, Wildlife
sanctuaries and Eco Sensitive areas located within 10 km radius of the project
area. Total project
cost for expansion project will be Rs. 638 Crores (Cement Rs 453 Crore and CPP
Rs. 175 Crores). For pollution control measures Rs. 60 Crores have been
earmarked.
Raw material requirement for the
expansion will be 6.278 MTPA of limestone, 0.095 MTPA of Iron Ore, 0.122 MTPA
of bauxite, 0.420 MTPA of gypsum, 1.474 MTPA of fly ash, 0.727 MTPA of slag,
0.448 MTPA of Indian coal and 0.298 MTPA of coal for the power plant. Fuel will
be Imported/Indian coal and pet coke of around 1300 TPD. Power Plant coal 1850 MT.
It is proposed
to adopt dry process kiln with suspension preheated (5 stage) and precalciner
with suitable cooler, vertical roller mill for raw material grinding, cement
grinding, coal/lignite grinding with a provision to use 80% imported coal and
20% lignite.
The major pollutants
expected from the power plant will be SPM, SO2 and NOx. To control
particulate emissions ESPs to cooler
and CPP, bag house to kiln/raw mill and coal mill and bag filters to cement
mill and packing plants will be provided. To control NOx, high efficiency
multi channel low NOx burner will be used in the kiln firing. Fugitive
emissions from limestone handling, coal handling, clinker hopper, storage
silos, weight feeders, grinding mills and packing machines will be controlled
by providing covered sheds for storage of raw materials, fully covered
conveyors for transportation of materials, etc.
The water requirement of 800m3/day
will be met from the mine pit water. About 35 m3/day of filter
back wash, R.O. plant rejects and DM regeneration, 40 m3/day of cooling
tower bleed off and 15 m3/day of boiler blow down will be generated
from both Cement and Power plants and treated in ETP having capacity of 100
m3/d and treated waste water will be used for cement plant gas and clinker
cooling. Sewage quantity of 80m3/d will be treated in STP having
capacity of 150 m3/d and treated sewage will be used for green belt
development.
Solid water generation from captive power
plant will be fly ash (310 TPD) and the entire fly ash will be pneumatically
transported to the Cement Plant and will be used in the PPC manufacturing. Solid wastes from STP Plants (10 Tons/year)
will be composted and used as manure for green belt. The dust collected from
various air pollution control measures like Bag House/Filters, ESPs, etc. are
totally recycled for cement manufacturing. Dust monitoring will be done
periodically and water will be sprayed on the roads to avoid dust in the
project area. Fly ash will be pneumatically transported to the cement plant to
be used in the PPC manufacturing. Solid
waste from STP (15 TPA) will be used as manure for green belt.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1. Executive summary of
the project
2. Photographs of the
existing and proposed plant area.
3. Compliance to the conditions stipulated for existing capacity in the
environmental clearance or NOC obtained from the
SPCB.
4.A line diagram/flow
sheet for the process and EMP
5. A copy of documents regarding coal
linkage
6. The earlier
questionnaire for industry sector should be submitted while submitting EIA/EMP.
7. A site location map
on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an
A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in 10 km radius from the proposal site.
8. Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
9. Location of national
parks / wildlife sanctuary / reserve forests within 10 km. radius should
specifically be mentioned. A map showing landuse / landcover, reserved forests,
wildlife sanctuaries, national parks, tiger reserve etc. in 10 km of the
project site. A map duly authenticated by the Chief Wild Life Warden showing
the location of wildlife sanctuaries vis-à-vis the project location including
the cement plant and the recommendations or comments of Chief Wild Life Warden.
10. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
11. Details and
classification of total land (identified and acquired) should be included.
12. Proposal should be
submitted to the Ministry for environment clearance only after acquiring total
land. Necessary documents indicating acquisition of land should be included.
13. Rehabilitation &
Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
14. Permission and
approval for the use of forest land and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests, if applicable, should be included.
15. A list of industries
containing name and type in 10 km radius shall be incorporated.
16. Residential colony
should be located in upwind direction.
17. List of raw material
required and source along with mode of transportation should be included. All
the trucks for raw material and finished product transportation must be
“Environmentally Compliant”.
18. Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS
location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS with
Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least as
per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
19. Petrography, grain
size analysis and Major element analysis of raw material and soil from project
site and raw material should be done on the same parameters along with analysis
for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
20. If the rocks, ores,
raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
21. Studies for fly ash,
muck disposal, slurry, sludge material and solid waste generated should also be
included, if the raw materials used has trace elements and a management plan.
22. Manufacturing process
details for all the cement plant, captive power plant and mine should be included.
23. Possibility of
installation of WHRB will be explored and details included
24. Mass balance for the
raw material and products should be included.
25. Energy balance data
for all the components including proposed power plant should be incorporated.
26. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
27. Sources of secondary
emissions, its control and monitoring as per the CPCB guidelines should be
included. A full chapter on fugitive emissions and control technologies should
be provided.
28. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
29. Vehicular pollution
control and its management plan should be submitted.
30. A write up on use of
high calorific hazardous wastes from all the sources in kiln and commitment
regarding use of hazardous waste should be included.
31. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
32. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
33. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
34. Air quality modelling
for all the plants proposed including mine for specific pollutants needs to be
done. APCS for the control of emissions within 50 mg/Nm3 should be
included. Cumulative impacts of cement plant, Captive Power Plant and mines
located at a distance of 2.0 km on the
ambient air quality shall be assessed. Stack emissions data of the existing
plant. AAQ data for the cement plant line-I for a period of three years and
three months for the cement line-II.
35. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
36.
Ambient
air quality monitoring modeling alongwith cumulative impact should be included
for the day (24 hrs) for maximum GLC alongwith following :
i) Emissions (g/second) with and without
the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
37. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided.
38. One season data for
gaseous emissions other than monsoon season is necessary.
39. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
40. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
41. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
42. Ground water
modelling showing the pathways of the pollutants should be included
43. Column leachate study
for all types of stockpiles or waste disposal sites, at 20oC-50oC
should be conducted and included.
44. Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
45. Permission for the
drawl of water from the concerned authority and water balance data including
quantity of effluent generated, recycled and reused and discharged is to be
provided. Methods adopted/to be adopted for the water conservation should be
included.
46. A note on the impact
of drawl of water on the nearby River during lean season.
47. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
48. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
49. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
50. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
51. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
52. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
53. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
54. Geo-technical data by
a bore hole of upto 40 mts. in every One sq. km area such as ground water
level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies and to assess future Seismic Hazard and Earthquake Risk
Management in the area and impacts due to land slides.
55. Action plan for
solid/hazardous waste generation, storage, utilization and disposal. A note on
the treatment, storage and disposal of all type of solid waste should be
included. End use of solid waste viz. fly ash etc. and its composition should
be covered.
56. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
57. Action plan for the
green belt development plan in 33 % area should be included. The green belt
should be around the project boundary and a scheme for greening of the
travelling roads should also be incorporated. All rooftops/terraces should have
some green cover.
58. A scheme for
rainwater harvesting has to be put in place. Incorporation of water harvesting
plan for the project is necessary, if source of water is bore well. Efforts
should be made to make use of rain water harvested. If needed, capacity of the
reservoir should be enhanced to meet the maximum water requirement. Only
balance water requirement should be met from other sources.
59. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
60. Action plan for the
green belt development plan in 33 % area should be included. The green belt
should be around the project boundary and a scheme for greening of the
traveling roads should also be incorporated. All rooftops/terraces should have
some green cover.
61. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
62. At least 5 % of the
total cost of the project should be earmarked towards the enterprises social commitment
and item-wise details along with time bound action plan should be included.
Socio-economic development activities need to be elaborated upon.
63. Disaster Management
Plan including risk assessment & damage control needs to be addressed and
included. Landslide hazard map and mitigation plan, Earthquake history and
management plan should be submitted.
64. Details regarding
expected Occupational & Safety Hazards. Protective measures for
Occupational Safety & Health hazards so that such exposure can be kept
within permissible exposure level so as to protect health of workers. Health of
the workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far &
Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
65. Plan for the
implementation of the recommendations made for the cement plant in the CREP
guidelines must be prepared.
66. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan should
be prepared and incorporated.
67. A note on
identification and implementation of Carbon Credit project should be included.
68. Total capital cost
and recurring cost/annum for environmental pollution control measures.
69. Public hearing issues
raised and commitments made by the project proponent on the same should be
included separately in EIA/EMP Report in the form of tabular chart.
70. Any litigation
pending against the project and / or any direction / order passed by any Court
of Law against the project, if so, details thereof.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Tamilnadu Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports, after public consultation.
21.2.17
Proposed Ferro Alloy Plant at Sy. No. 759, 762, 763/1 &
763/2, Village Peddapolamada, Mandal Tadipatri, District Anantapur in Andhra
Pradesh by M/s
Jatadhara Alloys Private Limited - regarding TORs
The project
authorities and their consultant M/s Team labs, Hyderabad gave a detailed
presentation on the salient features of project and proposed environmental
protection measures to be undertaken along with the draft Terms of Reference
for the preparation of EIA/EMP report. The Ferro Alloy Plants have been
listed at S.N.3 (a) under Primary Metallurgical Industries appraised at the
Central level.
M/s. Jatadhara Alloys Pvt. Limited
have proposed to establish 2x9 MVA Submerged electric arc furnaces in two
phases at Sy. No: 759, 762, 763/1 & 763/2 of Peddapolamada Village,
Tadipatri Mandal, Anantapur District, Andhra Pradesh. The company has already
acquired 18.5 Acres of land for the proposed ferro alloy unit of which 6.2
acres of the area will be developed as green belt. The nearest human settlement
from the site is Peddapolmada village which is at a distance of 1.2 km in
Northeast direction. Pennar River is flowing from west to east through
the study area and flowing from the site at a distance of 2.5 Km in northeast
direction. There are no
ecologically sensitive areas like national parks and wild life sanctuaries
within 10 km radius from the proposed site. Total cost of the project is Rs.25
Crores and Rs. 250 Lakhs have been earmarked towards the capital cost for
environmental protection.
Details of
the products along with their production capacity are given below:
Manufacturing
capacities:
S. No |
Description |
Capacity (TPA) |
||
Phase -I (9 MVA- Submerged arc furnace) |
Phase - II (9 MVA- Submerged arc furnace) |
Total |
||
1 |
Ferro Silicon
(Fe Si) * |
6333 |
6333 |
12666 |
2 |
Silico
Manganese (Si Mn) * |
14250 |
14250 |
28500 |
3 |
Ferro Manganese (Fe Mn) * |
18500 |
18500 |
37000 |
It is proposed to manufacture the
above alloys on campaign basis.
The sources of air pollution from the
plant are Submerged Electric arc furnaces and stand by DG sets. It is proposed
to provide Fume Extraction System with bag filters to control the particulate
emissions.
The total water requirement for the two
phases would be 95 m3/day which will be drawn from the ground water through bore wells within the
plant premises. The waste water generated from the cooling tower blow down (10
KLD) will be reused for dust suppression and irrigation after treatment. Domestic
effluent (8 KLD) will be sent to septic tank followed by soak pit. Power requirement will be sourced from
APTRANSCO.
The solid waste generation will be in the
form of slag which will be used for construction material or land filling. The
slag from the ferro manganese plant will be used as raw material for silico
manganese. The bag filter dust and solids from the settling tanks will be sold
to the brick manufacturers. The waste oil and the used batteries will be sold
to the authorized recyclers.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive summary of the project.
2.
Photographs
of the existing and proposed plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
5.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
6.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
7.
Location
of national parks / wildlife sanctuary / reserve forests within
8.
A
list of industries within 10 km radius of the plant area.
9.
Details
and classification of total land (identified and acquired) should be included.
10.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within
11.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
12.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
13.
Mass
balance for the raw material and products should be included.
14.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
15.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
16.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
17.
Ambient
air quality at 8 locations within the study area of
18.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
19.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
20.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
21.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
22.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
23.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
24.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
25.
Presence
of aquifer/aquifers within
26.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
27.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
28.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
29.
A
note on the impact of drawl of water on the nearby River during lean season.
30.
Action
plan for rainwater harvesting measures.
31.
Surface
water quality of nearby River (
32.
If
the site is within
33.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
34.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
35.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
36.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
37.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
38.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
39.
Action plan for chrome recovery and its solid waste
management plan.
40.
Acton
plan for the green belt development plan in 33 % area should be included.
41.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
42.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
43.
Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
44.
At
least 5 % of the total cost of the project should be earmarked towards the enterprises
social commitment and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
45.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
46.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
47.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be submitted
to the Andhra Pradesh Pollution Control Board for public hearing. The issues
emerged and response to the issues shall be incorporated in the EIA report. The
final EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP along with Public hearing
proceedings.
21.2.18
Proposed Steel Plant at Village Bhootpur, District
Mahaboobnagar in Andhra Pradesh by M/s Anand Shree Steels Pvt. Limited -
regarding TORs reconsideration
The project authorities and their consultant
M/s Consafe Science (India), Hyderabad, gave a detailed Presentation on the
Salient Features of the Project and proposed Environmental Protection Measures
to be undertaken along with the draft term of Reference for Preparation of
EIA/EMP. The Steel Plants
are listed at S.No. 3(a) in Primary Metallurgical Industries under category ‘A’
of the Schedule of EIA Notification, 2006 and
appraised at the Central level.
The proposal was considered by the
Expert Appraisal Committee (Industry) in its meeting held during 22nd
- 23rd February, 2011. After detailed deliberations, the Committee
noted that the proposed steel plant will be located in 30 acres of area at the
cost of Rs. 900.00 crores for 3 million MTPA steel plant. Details submitted
indicated that the proposed plant is not feasible due to inconsistency in
components and recommended that detailed and revised Feasibility of the project
should be submitted. It was also suggested to either go for induction furnace
or arc furnace but not for both at the same time. Proposal in the proposed form
was rejected. On receipt of revised proposal, it was brought back before the
Committee.
M/s. Anand Shree Steels Pvt. Limited have proposed pelletization plant with Iron Ore Beneficiation
– 1500 TPD / 4,50,000TPA, reduced Iron blocks ( 150 TPDx8 Tunnel Oven Furnaces)
= 1200 TPD / 3,60,000 TPA, Induction Furnace (40TPCx2)=800TPD/2,40,000TPA(Ingots/Billets),
Arc Furnace with LRF(40TPcx1) = 400 TPD/1,20,000 TPA (Billets), and Rolling Mill
(600TPDx2) = 1200 TPD/3,60,000TPA(M/.S. Structures / TMT Bars/ Sheets),Ferro
Alloys(10 MVAx1) = 70 TPD/21,000TPA,Ferro Manganese / Silico Manganese) at Village & Mandal Buthpur, Mahaboobnagar
District, Andhra Pradesh. Land area required for the project is 105 acres of
which 35 acres area is
earmarked for green belt development. No national Park/wild life sanctuary/
Biosphere sanctuaries is located within 10 km radius of the project
site. Total cost of the proposed project cost will be Rs.
425 Crores. Budget for Environment Management and Pollution Control measures is
Rs. 45 Crores.
Raw material required will be Iron Ore, Coal,
Bentonite, Limestone Quartz, Manganese, Pig iron/steel scrap etc. Coal will be
sourced from Singareni Collieries.
Details of the
products along with their production capacity are given below:
S.No |
Name of the
Proposed Project |
Product (TPA) |
1 |
Pelletization with Iron Ore Benefication |
4,50,000 TPA |
2 |
Tunnel Oven Furnace (150TPDx8) (Iron Blocks) |
3,60,000 TPA |
3 |
Induction Furnace (40 TPC X2) (Ingots / Billets) |
2,40,000 TPA |
4 |
Arc Furnace (40 TPCx1) (Billets) |
1,20,000 TPA |
5 |
Rolling Mill (600 TPDx2) (M.S. Structures / TMT Bars / Sheets) |
3,60,000 TPA |
6 |
Ferro alloys (10 MVAx1) (Ferro Manganese / Silico Manganese) |
21,000 TPA |
To control the particulate and gaseous emissions, ESP
would be installed along with stack of 75 m height. To control fugitive
emissions, dust extraction system with bag filters will be provided. The total water requirement of 360 m3/day will be sourced from the bore well and surface water. Closed recirculation cooling water system
shall be adopted. The total power requirement is 65,500 KVA/day will be
obtained from APSEB.
The
slag from induction Arc furnace units will be crushed and segregated for the
iron particles and reused in the furnace. Further, the non-magnetic waste
contains silica which is used to prepare bricks. The dust will be sold to
brick manufacturers and. The fly ash from Tunnel Oven Furnace will be sold to brick
manufactureres.
After detailed deliberations, the Committee
prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the site
3.
A
copy of documents regarding Coal linkage
4.
Detailed
lay out plan
5.
A
line diagram/flow sheet for the process and EMP
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. Present land use should be prepared based on satellite
imagery. High-resolution satellite image data having 1m-5m spatial resolution
like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area
from proposed site. The same should be used for land used/land-cover mapping of
the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
Project
site layout plan showing raw materials, fly ash and other storage plans, bore
well or water storage, aquifers (within 1 km.) dumping, waste disposal, green
areas, water bodies, rivers/drainage passing through the project site should be
included.
10.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
11. Details and
classification of total land (identified and acquired) shall be included.
12. A list of industries
containing name and type in 10 km radius shall be incorporated.
13. Residential colony
shall be located in upwind direction.
14. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
15. Action plan for
excavation and muck disposal during construction phase.
16. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
17. Manufacturing process
details for all the plants shall be included.
18. Mass balance for the
raw material and products shall be included.
19. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
20. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
21. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
22.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
23. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
24. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
25. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
26. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
27. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
28.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
29.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
30. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
31. One season data for
gaseous emissions other than monsoon season is necessary.
32. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
33. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
34. Source of surface/ground
water level, site (GPS), cation, anion (Ion Chromatograph), metal trace element
(as above) chemical analysis for water to be used. If surface water is used
from river, rainfall, discharge rate, quantity, drainage and distance from
project site should also be included. Information regarding surface hydrology
and water regime should be included.
35. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
36. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
37. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
38. A note on the impact
of drawl of water on the nearby River during lean season.
39. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
40. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
41. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
42. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
43. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
44. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
45. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
46. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
47. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
48. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
49. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
50. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
51. At least 5 % of the
total cost of the project should be earmarked towards the enterprises social
commitment and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
52. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
53. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
54. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
55. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
56. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
57. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
58. A note on
identification and implementation of Carbon Credit project should be included.
59. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Andhra Pradesh Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports, after public consultation.
21.2.19
Expansion of Cement Plant from 2.5 MTPA to 8.25 MTPA and
Captive Power Plant from 30 MW to 160 MW at Villages Sangem and Kallur, Taluk
Chincholi, District Gulbarga in Karnataka by M/s Chettinad Cement Corporation Limited -
regarding TORs reconsideration
The proposal was placed before the EAC to prescribe the
TORs in its meeting held during 22nd -23rd February,
2011.The Committee was of the view that the Project Proponent needs to first
provide evidence to the entire satisfaction of the Committee that significant
progress has been achieved in the implementation of the approval already
accorded on 18th June, 2010 for the first stage of the project
and that steps are underway for its commissioning in due time. The construction
schedule, state on ground and the compelling need to take up expansion even
while the first stage of the project is under way needs to be scrutinized by
the Committee. The Committee has to satisfy itself that the application for
expansion is not only opportune but justified from environmental point of view.
As of now no evidence of the need to take up expansion of a plant still under
construction has been furnished. The Committee accordingly recommended that
consideration of the expansion proposal be deferred till then.
On receipt of requisite information, the proposal was
placed before the EAC. The project authorities and
their consultant, M/s Enviro
Care India Private limited, Madurai, gave a detailed presentation on the progress achieved for
the existing capacity and on the salient features of the project and proposed
Terms of Reference (TORs) for preparation of
EIA/EMP. The cement plants (> 1.0 MTPA) have been kept at S.No.
3(b) under category ‘A’ of the Schedule of EIA Notification 2006 and appraised at the
Central level.
M/s Chettinad Cement
Corporation Limited have proposed for evxpansion
of Cement Plant from 2.5 MTPA to 8.25 MTPA and Captive Power Plant from 30 MW
to 160 MW at Villages Sangem and Kallur, Taluk Chincholi, District Gulbarga in
Karnataka. The total area for the cement
plant is 75.0 ha and Power plant is 15 Ha. The total land requirement will be 566.810 ha, which includes cement
plant, captive power plant & township (143.870 ha.) and captive limestone
mines (422.94 ha.). The location of the site is falling
under Survey of India Topo No: 56 G/7. Plant Site at 17o 21’ 55” –
17o 22’ 31” N Latitude & 77o 25’ 50” – 77o
27’18” E Longitude. No forest land is
involved. Mullamari River flows North to
South at a distance of 2 km from the site in the west and confluences with
Kagna River which flows in the south at a distance of 13 km from the site
boundary. Chincholi Town with a population of 17,144 persons is at a
distance of 7 km from the boundary. Inter-state boundary between Karnataka and
Andhra Pradesh falls within 10 km radius from the project site. The site falls
in Seismic zone-I. Nearest town
is Tandur at
The
existing project has a capacity of 2.5
Limestone (26075 MT/day), Bauxite
/Laterite (1040 MT/day), Iron Ore (200 MT/day), Gypsum (1130 MT/day), Fly ash (2235
MT/Day), Slag (1025 MT/Day) will be used
as raw materials. Coal is the fuel for the proposed captive thermal power
plant. The requirement of coal for the
proposed 2 x 50 & 1 x 30 MW thermal power plant is estimated as: Imported coal - 1600 t / day (or) Indigenous
coal - 2325 t / day. DG sets of 2 x 2
MW will be operated only in case of CPP/Grid breakdown. Future proposal is
there for 26 MW Waste Heat Recovery (WHR) Power Plant and plan to use Gas as
fuel for CPP which will be sourced from M/s RIL
Dry process
and 5 stage double string pre-heater with in-line calciner will be installed. Cement
manufacturing process will involve crushing the limestone, raw mix preparation
and homogenization, coal preparation, calcinations and clinkerization, cement
grinding and packing etc.
The major pollutants
expected from the power plant will be SPM, SO2 and NOx. ESPs to cooler and CPP, bag house to kiln/raw
mill and coal mill and bag filters to cement mill and packing plants
will be provided to control the SPM emissions below 50 mg/m3. To
control NOx, high efficiency multi channel low NOx burner will be used in the
kiln firing. Fugitive emissions from Limestone handling, coal handling, clinker
hopper, storage silos, weight feeders, grinding mills and packing machines will
be controlled by providing covered sheds for storage of raw materials, fully
covered conveyors for transportation of materials, etc. Dust monitoring will be done
periodically and water will be sprayed on the roads to avoid dust in the
project area.
The total requirement of raw water for
the expansion unit will be 3,100 KLD. Out of total water requirement, 600 KLD
will be met from bore wells in the plant and mining area and 2,500 KLD will be
drawn from Mullamari River. Rain water harvesting
structure including check dams will be constructed. 345 m3/day of Filter back
wash, R.O. Plant rejects and DM Regeneration, 125 m3/day of cooling
tower bleed off and 65 m3/day of boiler blow down will be generated
from both Cement and Power plants and treated in ETP of 600 KLD capacity and
treated waste water will be used for cement plant gas and clinker cooling.
Sewage quantity of 252 KLD will be treated in STP having the capacity of 300
KLD and treated sewage will be used for green belt development. “Zero Discharge’’ for waste water is ensured.
The dust collected from various Air
Pollution Control Measures like Bag
House/Filters, ESPs, etc.
are totally recycled for cement manufacturing. Fly ash will be
pneumatically transported to the cement plant to be used in the PPC
manufacturing.. Solid waste from STP (10
TPA) will be used as manure for green belt. Organic wastes (100 Kg/day) will be
subjected to vermi-composting and used as manure for green belt. Also other
wastes like lime sludge from paper
industries, ETP sludge, filter cake from iron and steel industries, fly ash
from thermal power plants, red mud from Aluminium industries and agro wastes
will be used in the cement kiln. Inorganic wastes (papers and other
wastes) will be sold to rag pickers / scrap dealers. Waste oil (20 KLD) from
the plants shall be collected and sold to the CPCB/KSPCB authorized agency for
further treatment & disposal.
The noise level within the plant
building at a distance of one meter from the source is maintained at <85 dB(A). Noise level at the
nearest plant boundary is maintained to be <55 dB(A) during day times and <45 dB(A) during night times.
The Committee observed that the existing plant of 2.5
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1. Executive summary of
the project
2. Photographs of the
existing and proposed plant area.
3. Compliance to the conditions stipulated for existing capacity in the
environmental clearance or NOC obtained from the
SPCB.
4.A line diagram/flow
sheet for the process and EMP
5. A copy of documents regarding coal
linkage
6. The earlier
questionnaire for industry sector should be submitted while submitting EIA/EMP.
7. A site location map
on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an
A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in 10 km radius from the proposal site.
8. Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
9. Location of national
parks / wildlife sanctuary / reserve forests within 10 km. radius should
specifically be mentioned. A map showing landuse / landcover, reserved forests,
wildlife sanctuaries, national parks, tiger reserve etc. in 10 km of the
project site. A map duly authenticated by the Chief Wild Life Warden showing
the location of wildlife sanctuaries vis-à-vis the project location including the
cement plant and the recommendations or comments of Chief Wild Life Warden.
10. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the project site should be included.
11. Details and
classification of total land (identified and acquired) should be included.
12. Proposal should be
submitted to the Ministry for environment clearance only after acquiring total
land. Necessary documents indicating acquisition of land should be included.
13. Rehabilitation &
Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
14. Permission and
approval for the use of forest land and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests, if applicable, should be included.
15. A list of industries
containing name and type in 10 km radius shall be incorporated.
16. Residential colony
should be located in upwind direction.
17. List of raw material
required and source along with mode of transportation should be included. All
the trucks for raw material and finished product transportation must be
“Environmentally Compliant”.
18. Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS
location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
19. Petrography, grain
size analysis and Major element analysis of raw material and soil from project
site and raw material should be done on the same parameters along with analysis
for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
20. If the rocks, ores,
raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
21. Studies for fly ash,
muck disposal, slurry, sludge material and solid waste generated should also be
included, if the raw materials used has trace elements and a management plan.
22. Manufacturing process
details for all the cement plant, captive power plant and mine should be
included.
23. Possibility of
installation of WHRB will be explored and details included
24. Mass balance for the
raw material and products should be included.
25. Energy balance data
for all the components including proposed power plant should be incorporated.
26. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
27. Sources of secondary
emissions, its control and monitoring as per the CPCB guidelines should be
included. A full chapter on fugitive emissions and control technologies should
be provided.
28. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
29. Vehicular pollution
control and its management plan should be submitted.
30. A write up on use of
high calorific hazardous wastes from all the sources in kiln and commitment
regarding use of hazardous waste should be included.
31. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
32. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
33. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
34. Air quality modelling
for all the plants proposed including mine for specific pollutants needs to be
done. APCS for the control of emissions within 50 mg/Nm3 should be
included. Cumulative impacts of cement plant, Captive Power Plant and mines on
the ambient air quality shall be assessed. Stack emissions data of the existing
plant. AAQ data for the existing cement plant for one month.
35. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
36.
Ambient
air quality monitoring modeling alongwith cumulative impact should be included
for the day (24 hrs) for maximum GLC alongwith following :
i)Emissions
(g/second) with and without the air pollution control measures
ii)Meteorological
inputs (wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii)Model
input options for terrain, plume rise, deposition etc.
iv)Print-out
of model input and output on hourly and daily average basis
v)A
graph of daily averaged concentration (MGLC scenario) with downwind distance at
every 500 m interval covering the exact location of GLC.
vi)Details
of air pollution control methods used with percentage efficiency that are used
for emission rate estimation with respect to each pollutant
vii)Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii)No.
I-VII are to be repeated for fugitive emissions and any other source type relevant
and used for industry
ix)Graphs
of monthly average daily concentration with down-wind distance
x)Specify
when and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi)Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
37. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided.
38. One season data for
gaseous emissions other than monsoon season is necessary.
39. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
40. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
41. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
42. Ground water
modelling showing the pathways of the pollutants should be included
43. Column leachate study
for all types of stockpiles or waste disposal sites, at 20oC-50oC
should be conducted and included.
44. Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
Incorporation of water harvesting plan for the project is necessary, if source
of water is bore well.
45. Permission for the
drawl of water from the concerned authority and water balance data including
quantity of effluent generated, recycled and reused and discharged is to be
provided. Methods adopted/to be adopted for the water conservation should be
included.
46. A note on the impact
of drawl of water on the nearby River during lean season.
47. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
48. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
49. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
50. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
51. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
52. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
53. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
54. Geo-technical data by
a bore hole of upto 40 mts. in every One sq. km area such as ground water
level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies and to assess future Seismic Hazard and Earthquake Risk
Management in the area and impacts due to land slides.
55. Action plan for
solid/hazardous waste generation, storage, utilization and disposal. A note on
the treatment, storage and disposal of all type of solid waste should be
included. End use of solid waste viz. fly ash etc. and its composition should
be covered.
56. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
57. Action plan for the
green belt development plan in 33 % area should be included. The green belt
should be around the project boundary and a scheme for greening of the
travelling roads should also be incorporated. All rooftops/terraces should have
some green cover.
58. A scheme for
rainwater harvesting has to be put in place. Incorporation of water harvesting
plan for the project is necessary, if source of water is bore well. Efforts
should be made to make use of rain water harvested. If needed, capacity of the
reservoir should be enhanced to meet the maximum water requirement. Only
balance water requirement should be met from other sources.
59. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
60. Action plan for the
green belt development plan in 33 % area should be included. The green belt
should be around the project boundary and a scheme for greening of the
traveling roads should also be incorporated. All rooftops/terraces should have
some green cover.
61. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
62. At least 5 % of the
total cost of the project should be earmarked towards the enterprises social
commitment and item-wise details along with time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
63. Disaster Management
Plan including risk assessment & damage control needs to be addressed and
included. Landslide hazard map and mitigation plan, Earthquake history and
management plan should be submitted.
64. Details regarding
expected Occupational & Safety Hazards. Protective measures for
Occupational Safety & Health hazards so that such exposure can be kept
within permissible exposure level so as to protect health of workers. Health of
the workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far & Near
vision, colour vision and any other ocular defect) ECG, during pre placement
and periodical examinations and plan of monthly and yearly report of the health
status of workers with special reference to Occupational Health and Safety.
65. Plan for the implementation
of the recommendations made for the cement plant in the CREP guidelines must be
prepared.
66. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan should
be prepared and incorporated.
67. A note on
identification and implementation of Carbon Credit project should be included.
68. Total capital cost
and recurring cost/annum for environmental pollution control measures.
69. Public hearing issues
raised and commitments made by the project proponent on the same should be
included separately in EIA/EMP Report in the form of tabular chart.
70. Any litigation
pending against the project and / or any direction / order passed by any Court
of Law against the project, if so, details thereof.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Karnataka Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports, after public
consultation.
25th March, 2011
Any
Other Item
21.2.20
Clinker Grinding Unit at (1.0 MTPA) at J &K Industrial
Estate, Ghati, Kathua, Jammu & Kashmir by M/s Shree Cement Limited- regarding Reconsideration
The project authorities and their consultant,
M/s J.M. Environet Pvt. Ltd., Gurgaon gave a detailed presentation on the
salient features of the project in its meeting held on 14th
December, 2011 and proposed environmental protection measures to be undertaken
as per Terms of Reference (TORs) awarded during the 7th
Meeting of the Expert Appraisal Committee-1 (Industry) held during 2nd –
3rd February, 2010 for preparation of
EIA/EMP.
All the Cement Plants (> 1.0 MTPA) are listed
at S.No. 3(b) under category ‘A’ of the Schedule of EIA Notification, 2006 and
appraised at the Central level.
M/s Shree Cement Limited
have proposed for Clinker
Grinding Unit (1.0 MTPA) at J &K Industrial Estate, Ghatti, Tehsil &
District Kathua, Jammu & Kashmir. Total project area is 12 ha and is
allotted by SIDCO, J & K vide letter dated 27th August, 2009. Green belt will be developed in 3.9 ha (33%)
of total plant area. Jasrota wild life sanctuary (3.5-4.0 km,
NW), Barot RF (5.0 km N), Jathona RF (5.0 km N), Kathar RF (7 km N) and
Jasoda Garh Forest (8.25 km NE) are located within 10 km radius of the proposed
site. Total cost of the project is Rs. 160.34 Crores. Rs. 5.0 Crores and
Rs. 0.20 Crores will be earmarked towards total capital cost and recurring
cost/annum for environmental pollution control measures.
It
is proposed to manufacture 30 % OPC (3.02 MTPA) and 70 % PPC (7.03 MTPA).
Clinker,
Gypsum and fly ash will be used as raw materials. Covered storage facilities will be
provided. Gypsum, fly ash and clinker
will be stored in silos. PAs have also
applied for the mining lease to the State Govt. During the process of grinding,
clinker, slag / fly ash and gypsum will be mixed together in the prescribed ratio
and fed to grinding mill through baggage and discharged to cement silo, which
will be taken to peeling machine for automatic filling of cement bags.
Bag filters will be
provided at all the material transfer points. High efficiency bag house will be provided to the mill to control
particulate emissions within 50 mg/Nm3. Dust collected from air
pollution control equipment will be 100% recycled in process. Dry fly ash will
be transported into closed bunkers / closed trucks. Fly ash shall be pumped
directly from the tankers to silos pneumatically in closed loop or mechanically
to prevent fugitive emissions. The packing machines will be equipped with dust
extraction arrangement. The dust will be captured in bag filters and reused in
process. All roads within the plant premises will be concreted and sweeping
will be done by vacuum sweeping machine. Dust generated due to vehicle
movement will be controlled by water sprinkling. Covered conveyor belts will be
provided.
Total water requirement is 85 m3/day
which will be sourced
from bore wells. No waste water will be
generated from the Cement Grinding process. Domestic effluent will be treated in septic tank followed by soak pit. No
effluent will be discharged outside the premises and ‘Zero’ discharge will be
adopted.
No solid waste will be generated in Grinding Process.
Dust collected from air pollution control equipment will be 100% recycled in
process. Fly ash will be sourced from Thermal Power Plant at Ropar, Punjab and
transported in closed tankers/covered trucks and ultimately stored in silos. Only Used Oil will be generated from
the plant machineries as hazardous waste which will be used for self
lubrication and rest will be sold to CPCB authorized recyclers.
Power
(5,600 hp) will be used from State Power Grid. DG set (6,750 KVA) will
also be installed for emergency use.
The Committee also noted that no public hearing/consultation
is required due to project being located in notified industrial area as
per Section (iii), Stage (3), Para (i)(b) of EIA Notification, 2006.
The Committee desired that proponent shall submit the map showing
the location of plant and the Jasrota Wildlife Sanctuary authenticated by the
Chief Wildlife Warden along with his comments or recommendations and a copy of
application submitted to National Board on Wildlife.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other environmental conditions:
i.
Continuous stack monitoring facilities to monitor gaseous
emissions from all the stacks shall be provided. After expansion, limit of SPM shall be
controlled within 50 mg/Nm3 by
installing adequate air pollution control system. Electrostatic precipitators to clinker
cooler, bag house to raw mill/kiln and bag
filters to cement mill. Low NOX burners
should be provided to control NOX emissions.
ii.
Environmental
clearance is subject to obtaining clearance from the National Board of
wildlife.
iii.
A
wildlife conservation plan shall be prepared in consultation with the Office of
the Chief Wildlife Warden concerned and reputed wildlife expert / institute and
submitted to the Ministry within six months along with a road map for
implementation. The plan shall specify budget earmarked for activities to be
undertaken.
<