Minutes of the 20th Meeting
of the Expert Appraisal Committee (Industry-1) held during 12th
March, 2011 at 623, Conference Room, 6th
floor, Ministry of Environment & Forests, Lodhi
Road, New Delhi - 110 003
20.1
Opening Remarks of the Chairman
At the outset, Chairman welcomed the members of the
Expert Appraisal Committee-1(Industry). Thereafter, agenda items were taken up
for discussion.
20.2.0 Consideration of the Projects
Proposals
for Environmental clearance
20.2.1 Proposed
Cement Grinding plant of 200 TPD
capacity at DAG no. 78-81,124-128 & 136-140, IID Growth Centre, Banderdewa, P.O. Pathali Pahar, District North Lakhimpur,
Assam by M/s Purvanchal
Infra and Industries Pvt. Limited- regarding Environmental Clearance
The
project authorities and their consultant
M/s. Envision Enviro Engineers Pvt. Ltd., Surat, Gujarat gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken as per Draft Terms of References (TORs) awarded during the 14th
Expert Appraisal Committee (Industry-1) held during 23rd - 25th
September, 2010 for preparation of EIA/EMP. All the Cement Grinding Units
are listed at S.No. 4(b) under Category ‘B’ and
appraised at the State level, but due to the absence of SEIAA/SEAC in Assam,
the proposal is appraised at the centre.
M/s. Purvanchal Infra and
Industries Pvt. Ltd. have proposed for the Cement Grinding Plant at Dag no. 78-81,124-128 & 136-140, IID Growth
Centre, Banderdewa, P.O. Pathali
Pahar, District North Lakhimpur,
Assam. The total project area is 13,380 sq.m. which
is located in IID Growth Centre, Banderdewa and already acquired. Green belt will be
developed in an area of 4,415 sq.m.
No national parks/wild life sanctuary/reserve forests are located within 10 km
radius. Total cost of the project is Rs. 492.76 Lakhs. Rs. 24 Lakhs and
Rs. 8 Lakhs are earmarked for capital cost and recurring cost/annum towards
pollution control measures.
The clinker will be taken to cement mill hoppers
for cement grinding. Clinker and Gypsum with slag, fly ash and mineral
components will be fed to cement mill and grounded. The mill discharge will be
segregated into fine product and coarse product will be transported to RCC
cement silos for dispatch.
Bag filters to cement mill will be provided to control particulate emissions
below 50 mg/Nm3. Bag filters will be provided for de-dusting of
storage areas and transfer points. Bag filters will be installed at crushers to
keep particulate matter below 50 mg/Nm3. Closed conveyor belts will
be installed along with bag filters for efficient de-dusting of storage areas
and transfer points. Fugitive emissions are envisaged from material handling
and transportation areas. Gaseous emissions will be generated from vehicles and
equipment deployed during the construction and operational phase. Water will be
sprayed for dust suppression during limestone transportation.
The total water requirement will be 4 KLD which
will be met from the ground water. No
wastewater will be discharged from the proposed plant. Rain water harvesting
structure will be constructed.
No solid waste will be generated from the
process. Material collected from bag filter will be recycled back in to
the process. Fly ash will be used in manufacturing of cement. Sewage sludge
will be used as manure for greenbelt development. Municipal waste generated
during construction and operation period will be composted after segregation
and used as manure. Waste oil and grease will be disposed through authorized
vendors.
Noise will be generated from crushing and grinding
operations and also from DG sets and vehicular movement. Personal Protective
equipments will be provided in noise generating areas. Regular maintenance of
the equipment will be carried out for reduction of noise at source. The power
requirement for the plant will be 400 KW and will be met from Assam State Electricity
Board. DG set (200 KVA) will be installed for emergency power
requirement.
The proposal was exempted from public hearing by categorizing in B-2 category
due to use of energy efficient technology, no clinker manufacturing at the
proposed site, no sensitive area within 10 km. radius, ‘zero’ effluent
discharge, utilization of all the solid waste in the process itself including
utilization of fly ash etc.
After detailed deliberations, the Committee recommended the proposal for
environmental clearance subject to stipulation of the following specific
condition along with other environmental conditions:
i.
Continuous
stack monitoring facilities to monitor gaseous emissions from all the stacks
shall be provided. Particulate emissions shall be controlled within 50 mg/Nm3 by installing adequate air pollution
control system viz. Bag
filters and stacks of adequate height etc. Data on ambient air, fugitive and stack emissions shall be submitted
to the Ministry’s Regional Office at Shillong, Assam State Pollution Control
Board (ASPCB) and CPCB regularly.
ii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be followed.
iii.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB should be followed.
iv.
The
company shall install adequate dust collection and extraction system to control
fugitive dust emissions at various transfer points, raw mill handling
(unloading, conveying, transporting, stacking), vehicular movement, bagging and
packing areas etc. All the raw material stock piles should be covered. A closed clinker stockpile system
shall be provided. All
conveyers should be covered with GI sheets. Covered sheds for storage of raw
materials and fully covered conveyers for transportation of materials shall be
provided besides coal, cement, fly ash and clinker shall be stored in
silos. Pneumatic
system shall be used for fly ash handling.
v.
Asphalting/concreting of roads and water spray all around the
stockyard and loading/unloading areas in the cement plant shall be carried out
to control fugitive emissions. Regular water sprinkling shall be carried out in
critical areas prone to air pollution and having high levels of SPM and RSPM
such as haul road, loading and unloading points, transfer points and other
vulnerable areas. It shall
be ensured that the ambient air quality parameters conform to the norms
prescribed by the Central Pollution Control Board in this regard.
vi.
Efforts shall be made to reduce impact of the transport of the raw
materials and end products on the surrounding environment including
agricultural land. All the raw materials including fly ash should be
transported in the closed containers only and should not be overloaded.
Vehicular emissions should be regularly monitored.
vii.
Total ground water requirement for the cement plant shall not exceed 4 m3/day and necessary
permission for the drawl shall be obtained. Efforts shall be made to further
reduce water consumption by using air cooled condensers. All the treated
wastewater should be recycled and reused in the process and/or for dust
suppression and green belt development and other plant related activities etc.
No process wastewater shall be discharged outside the factory premises and
‘zero’ discharge should be adopted.
viii.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir shall be enhanced to meet the maximum water
requirement. Only balance water requirement shall be met from other sources.
ix.
All the bag filter dust, raw meal dust, coal dust, clinker dust
and cement dust from pollution control devices should be recycled and reused in
the process used for cement manufacturing.
Spent oil and batteries should be sold to authorized recyclers / reprocessors only.
x.
Green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
xi.
At least 5 % of the total cost of the project shall be earmarked
towards the enterprise
social commitment (ESC) and item-wise details along
with time bound action plan should be prepared and submitted to the Ministry’s
Regional Office at Shillong.
Implementation of such program should be ensured
accordingly in a time bound manner.
20.2.2
Proposed Cement Plant (2.50 MTPA), Captive Power Plant (40 MW) and
Limestone Mine (395.05 ha.) at Risda, Kukurdih and Dhandhani , Tehsil Baloda Bazar, District
Raipur in Chhattisgarh by M/s Emami Cement Limited - regarding Reconsideration
Proposal of M/s
Emami Cement Limited for Cement
Plant (2.50 MTPA), Captive Power Plant (40 MW) and Limestone Mine (395.05 ha.)
at Risda, Kukurdih and Dhandhani , Tehsil Baloda Bazar, District Raipur in
Chhattisgarh was considered
and discussed in the 18th and 19th Expert
Appraisal Committee (Industry-1) meetings.
During the 19th
EAC meeting, the Committee after detailed
deliberations has sought the following:
1. A
revised plant lay out of the land excluding the land not acquired.
2. Approval
of the Panchayat
3. Approval of the Industry Department
The PP vide their letter dated 1.03.2011 has submitted the
revised plant lay out excluding the land not acquired and also made a
presentation before the committee. After detailed deliberations, the Committee
recommended the project for environmental clearance subject to submission of the following:
·
Revised plant lay out with a
boundary and green belt all along the coordinates. The coordinates in terms of
latitude and longitude should be provided.
·
Approval of the state government on
the revised plant lay out
The PP vide their letter dated 15.03.2011 has submitted the
revised plant lay out excluding the land not acquired and vide letter dated
31.03.2011 provided further details of bifurcated plant layout area. The plant
area (including green belt) will be 146.64 ha instead of 195.64 ha as
originally proposed till the entire 195.64 ha of land will be in the possession
of the PP.
The environmental clearance is recommended for the project
subject to following specific conditions along with
other environmental conditions:
1. The final lay out with a boundary and green belt all along
the coordinates all round the two sections of the plant shall be furnished to
the Ministry and only after the same is examined and is accepted to the
satisfaction of the Ministry approval may issue. The coordinates of the
principal points on the boundaries and of the plant in terms of latitude and
longitude should be provided.
2. Approval of the state government on the revised plant lay
out shall be first obtained including on the arrangements for installation of
the overhead conveyor between the two sections of the plant and on the access
arrangements made for owners of land in the hinterland who have to access their
property through the gap between the two sections of the plant and through the
space underneath the conveyor between the sections. This approval shall be
submitted to MOEF prior to issue of the approval letter.
3. Protected and covered conveyor shall be provided for
transportation of raw material.
4.
Compliance to all the specific and
general conditions stipulated for the existing plant by the Central/State
Government shall be ensured and regular reports submitted to the Ministry’s
Regional Office at Bhopal.
18. Proper utilization of
fly ash shall be ensured as per Fly Ash Notification, 1999 and subsequent
amendment in 2003 and 2010. All the fly ash should be provided to cement and
brick manufacturers for further utilization and Memorandum of Understanding
should be submitted to the Ministry’s Regional Office at Bhopal.
20.2.3
Expansion of Integrated Steel Plant by installing Sponge
Iron Plant (2x200 TPD) along with Captive Power Plant (40 MW= WHRB - 4MW + AFBC
- 36 MW) at Village Ankulapathuru & Udathavaripalem, Mandal Chillakuru, Sri Pottisriramlulu,
District Nellore in Andhra Pradesh by M/s SBQ Steels Limited - regarding
Reconsideration
Proposal of M/s
SBQ Steels Limited for Expansion of Integrated Steel Plant by installing Sponge
Iron Plant (2x200 TPD) along with Captive Power Plant (40 MW= WHRB - 4MW + AFBC
- 36 MW) at Village Ankulapathuru & Udathavaripalem, Mandal Chillakuru, Sri Pottisriramlulu,
District Nellore in Andhra Pradesh was considered and discussed in the 19th Expert Appraisal Committee
(Industry-1) meeting held during 22nd – 23rd February,
2011. The Committee after detailed deliberations sought the
following additional information for reconsideration of the project without
calling the PP:
·
Documents regarding no irrigation
under Ayacut of Yeruru tank
etc.
·
Point-wise
compliance to the existing clearances from MoEF &
SEIAA along with copy of environmental clearances.
·
Point-wise compliance to the
issues raised during public hearing/public consultation
The information sought above was furnished by the project
proponent to MoEF vide their letter dated 03.03.2011. A letter dated 24.02.2011 from the Tahsildar,
Chilakur is submitted certifying that no paddy or any
crop cultivation is being done under the Ayacut of Yeruru tank or by using Yeruru
tank water. Compliance to the existing environmental clearances and issues raised during public hearing/public
consultation are also submitted.
The PP has requested for issue of Consolidated Environmental Clearance for
both Unit # I and Unit # II along with the present proposal of expansion under
the banner “SBQ Steels Limited”. The consolidated Environmental Clearance will
be for the capacities mentioned below.
S. No |
Unit |
Production Capacity |
|||
Existing |
Expansion |
After expansion |
|||
Coke oven plant (Non-recovery) |
2,00,000 TPA |
--- |
2,00,00 TPA |
||
DRI Kiln |
60,000 TPA |
60,000 TPA |
1,20,000 TPA |
||
Cement plant |
2,90,000 TPA |
--- |
|||
Captive Power Plant |
30 MW |
60 MW (4MW WHRB
based) 56 MW AFBC
based) |
90 MW |
||
Sinter Plant |
5,00,000 TPA |
--- |
5,00,000 TPA |
||
Blast Furnace |
5,00,000 TPA |
--- |
5,00,000 TPA |
||
Energy Optimization Furnace |
5,90,000 TPA |
--- |
5,90,000 TPA |
||
Ladle Refining Furnace |
5,75,000 TPA |
--- |
5,75,000 TPA |
||
Vacuum degassing unit |
2,50,000 TPA |
--- |
2,50,000 TPA |
||
Continuous casting machine |
2 Twin Strand Bloom -3,25,000 TPA Billet casting lines – 2,25,000 TPA |
--- |
2 Twin Strand Bloom -3,25,000 TPA Billet casting lines – 2,25,000 TPA |
||
Rolling mill |
2x 2,50,000 TPA |
--- |
2x 2,50,000 TPA |
||
Oxygen plant |
200 TPD |
--- |
200 TPD |
||
After
detailed deliberations, the Committee has recommended for accordance of Consolidated Environmental
Clearance for both Unit # I and Unit # II along with the present proposal of
expansion subject to stipulation of following specific conditions along
with other environmental conditions:
i.
Efforts
shall be made to reduce RSPM levels in the ambient air and a time
bound action plan shall be submitted. On-line ambient air quality monitoring
and continuous stack monitoring facilities for all the stacks shall be provided
and sufficient air pollution control devices viz. Electrostatic precipitator
(ESP), gas cleaning plant, venturi scrubber, bag filters etc. shall be provided to
keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
ii.
As
proposed, Electrostatic precipitator (ESP) shall be provided to WHRB, AFBC and DRI
plants to control SPM levels within 50 mg/Nm3. Fume extraction
system shall be provided to induction furnaces to control the emissions within
the prescribed standards. Electrostatic precipitators
to clinker cooler, bag house to raw mill/kiln and bag filters to coal mill and cement
mill. Low NOX burners
should be provided to control NOX emissions.
iii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iv.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed. New
standards for the sponge iron
plant issued by the Ministry vide
G.S.R. 414(E) dated 30th May, 2008 should be followed.
v.
Multi
stage scrubber shall be installed to control gaseous and dust emission from the
coke oven stack. Measures shall be taken
to prevent leakages from the coke oven plant.
vi.
In-plant
control measures like bag filters, de-dusting and dust suppression system shall
be provided to control fugitive emissions from all the vulnerable sources. Dust extraction and suppression system shall
be provided at all the transfer points, coal handling plant and coke sorting
plant of coke oven plant. Bag filters
shall be provided to hoods and dust collectors to coal and coke handling to
control dust emissions. Water sprinkling system shall be provided to control
secondary fugitive dust emissions generated during screening, loading,
unloading, handling and storage of raw materials etc.
vii.
The
prescribed emission standards for coke oven plants, as notified vide
notification no. GSR 46 (E) dated 3rd February, 2006 and
subsequently amended shall be complied with.
viii.
Hot
gases from DRI kiln shall be passed through Dust Settling Chamber (DSC) to
remove coarse solids and After Burning Chamber (ABC) to burn CO completely and
used in waste heat recovery boiler (WHRB). The gas then shall be cleaned in ESP
before leaving out into the atmosphere through ID fan and stack.
ix.
Total
water requirement shall not exceed 11,155 KLD. Efforts shall further be made to
use maximum water from the rain water harvesting sources. Use of air cooled condensers shall be
explored and closed circuit cooling system shall be provided to reduce water
consumption and water requirement shall be modified accordingly. All the
effluent should be treated and used for ash handling, dust suppression and
green belt development. No
effluent shall be discharged and ‘zero’ discharge shall be adopted. Sanitary
sewage should be treated in septic tank followed by soak pit.
x.
Efforts shall be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement shall be met
from other sources.
xi.
Regular monitoring of influent and effluent
surface, sub-surface and ground water (including chromite)
should be ensured and treated wastewater should meet the norms prescribed by
the State Pollution Control Board or described under the E(P)
Act whichever are more stringent. Leachate study for
the effluent generated and analysis shall also be regularly carried out and
report submitted to the Ministry’s Regional Office at Bangalore, SPCB and CPCB.
xii.
The water consumption shall not
exceed as per the standard prescribed for the steel plants.
xiii.
All the coal fines, char
from DRI plant shall be utilized in AFBC boiler of
power plant and no char shall be used for briquette making or disposed off anywhere
else. AFBC boiler shall be installed simultaneously along with the DRI plant to
ensure full utilization of char from the beginning.
Scrap shall be used in steel melting shop (SMS) and SMS slag and kiln
accretions shall be properly utilized. All the
other solid waste including broken
refractory mass shall be properly disposed off in
environment-friendly manner.
xiv.
Waste
from the hard coke unit, shall be provided to the briquette manufacturing
units. Coal and coke fines shall be recycled and reused in the process. All the blast furnace (BF) slag shall be
granulated and provided to cement manufacturers for further utilization. The
bag filter dust shall be used for landfilling. The
waste oil shall be properly disposed off as per the Hazardous Waste
(Management, Handling, Handling and Trabsboundry
Movement) Rules, 2008.
xv.
Proper utilization of fly ash shall
be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003.
xvi.
Vehicular pollution due to
transportation of raw material and finished products shall be controlled. Proper
arrangements shall also be made to control dust emissions during loading and
unloading of the raw material and finished product. Efforts shall be made to
reduce impact of the transport of the raw materials and end products on the
surrounding environment including agricultural land. All the raw materials
including fly ash should be transported in the closed containers only and shall
not be overloaded. Vehicular emissions should be regularly
monitored.
xvii.
All internal roads shall be black
topped. The roads shall be regularly cleaned with mechanical sweepers. A 3-tier
avenue plantation using native species shall be developed along the roads.
Facilities for parking of trucks carrying raw coal from the linked coalmines
shall be created within the Unit.
xviii.
All the bag filter dust, raw mill dust, coal dust, clinker dust
and cement dust from pollution control devices should be recycled and reused in
the process and used for cement manufacturing. Spent oil and batteries shall be
sold to authorized recyclers / reprocessors only.
xix.
Efforts shall be made to use low-grade lime, more fly ash and
solid waste in the cement manufacturing.
xx.
An effort shall be made to use of high calorific hazardous waste
in the cement kiln and necessary provision should be made accordingly.
xxi.
Proper handling, storage,
utilization and disposal of all the solid waste shall be ensured and regular
report regarding toxic metal content in the waste material and its composition,
end use of solid/hazardous waste should be submitted to the Ministry’s Regional
Office at Bangalore, SPCB
and CPCB.
xxii.
A time bound action plan shall be
submitted to reduce solid waste, its proper utilization and disposal.
xxiii.
Risk and Disaster Management Plan
along with the mitigation measures shall be prepared and a copy submitted to
the Ministry’s Regional Office at Bangalore,
SPCB and CPCB within 3 months of issue of environment clearance
letter.
xxiv.
As proposed, green
belt shall be developed in 33 % of plant area as per the CPCB guidelines in
consultation with the DFO.
xxv.
All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the
Steel Plants and Cement Plants should be implemented.
xxvi.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 7th
December, 2010 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bangalore.
xxvii.
At least 5 % of the total cost of
the project should be earmarked towards the enterprise social commitment based on Public Hearing
& social responsibility and item-wise details along with
time bound action plan should be prepared and submitted to the Ministry’s
Regional Office at Bangalore.
Implementation of such program should be ensured accordingly in a time bound
manner.
xxviii.
Rehabilitation and Resettlement Plan for
the project affected population including tribals, if
any shall be implemented as per the policy of the State Govt. in consultation
with the State Govt. of Andhra Pradesh. Compensation paid in any case should
not be less than the norms prescribed under the National Resettlement and
Rehabilitation Policy, 2007.
xxix.
The company shall provide housing
for construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project.
20.2.4
Expansion of Ferro Alloy Plant from 7,200 TPA to 13,200 TPA
by installing a Submerged Arc Furnace (1x4 MVA, 30,000 TPA) at A-15, Sarua Industrial Estate, Post Sarua,
District Khurda, Orissa by M/s Saumyaa Alloys Private Limited - regarding Reconsideration
The project proponents did not attend the meeting and hence
the proposal was deferred till further request from the project proponent.
Proposal for TORs
20.2.5
Integrated expansion of Cement Plant (Clinker- 0.75 MMTPA
to 3.45 MMTPA, Cement - 0.95 MMTPA to 3.45 MMTPA), Setting up of 15 MW WHRB and
35 MW coal based CPP and enhancement of limestone production capacity of
existing limestone mine from 0.6 MMTPA to 1.6 MMTPA at Village Mangrol, Tehsil Nimbahera, District Chittorgarh
in Rajasthan by M/s
J K Cement Limited- regarding TORs
The
project authorities and their consultant,
M/s Enkay Enviro
Services, Jaipur
gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken along with the
draft TORs for preparation of EIA/EMP. All the Cement Plants
(> 1.0 MTPA) are listed at S.No. 3(b) under category ‘A’ of the Schedule of EIA Notification, 2006
and appraised at the Central level.
M/s JK Cement Limited have proposed for
expansion of existing cement unit (clinker from 0.75 to 3.45, cement from
0.95-3.45 MMTPA) at Village-Mangrol, Tehsil-Nimbahera, District Chittorgarh,
Rajasthan Total
existing plant area is 149.0 ha and the proposed expansion will be done in the
existing premises. No
National Park/Wild life sanctuary/Reserve Forest is located within
The
present manufacturing process is a dry process and there would be no change in
the process for the proposed expansion. Limestone, Red Ochre, Laterite, Coal/Pet Coke, Gypsum and Fly Ash are the raw
materials that will be used and will be transported by road/rail. Limestone
would be sourced from the captive mines.
Adequate
pollution control equipment like pulse jet type bag filters and ESPs have been
installed in the existing plant order to control to keep emissions within the
prescribed norms. The same will be practiced for the proposed expansion
project. Water sprinkling would be done in the raw material stockyards and
cement bags loading areas.
There
is no water required for industrial purposes; only domestic water is required.
Water demand is met from perennial Gambhir River. No
industrial wastewater is generated from the unit. The domestic effluent
generated is being disposed off in septic tank via soak pit. There is no
discharge outside the plant premises and the same will be maintained.
No
solid waste is being generated from the cement unit. However, material
collected by the dust collector (bag filters) is being recycled in the process.
The total power requirement will be 50
MW and will be met from CPP. DG sets of 2X6 MW will be used as a source of
emergency/standby power. Green belt will be developed in 35 ha area in addition
to the existing 16 ha.
The
committee noted that the green belt development is not upto
the mark.
The Committee prescribed the following
TORs for undertaking detailed EIA/EMP study for Cement Plant and CPP. The TORs
for EIA/EMP study for Mining shall
be obtained from the Expert Appraisal Committee (Mining) of MoEF
as per the MoEF Office Memorandum No.
J-11013/41/2006-IA.II(I) dated 24th
December, 2010.
1. Executive summary of the project.
2. Photographs of the existing and proposed plant area.
3.Compliance to the conditions stipulated for existing capacity in the
environmental clearance or NOC obtained from the
SPCB.
4. A line diagram/flow
sheet for the process and EMP
5. Coal linkage documents
6.
Proposal should be submitted to the Ministry for
environment clearance only after acquiring total land. Necessary documents indicating
acquisition of land should be included.
7. The earlier questionnaire for cement, captive power plant and mining
sectors should be submitted while submitting EIA/EMP.
8. A site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms
and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
9. Present land use should be prepared based on satellite imagery.
High-resolution satellite image data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
10. Location of national parks / wildlife sanctuary / reserve forests within
10 km. radius should specifically be mentioned. A map showing landuse /landcover, reserved forests, wildlife sanctuaries,
national parks, tiger reserve etc in 10 km of the project site.
11. Project site layout plan showing raw materials, fly ash and other storage
plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing through the
project site should be included.
12. Details and classification of total land (identified and acquired) should
be included.
13. Proposal should be submitted to the Ministry for environment clearance
only after acquiring total land. Necessary documents indicating acquisition of
land should be included.
14. Rehabilitation & Resettlement (R & R) should be as per policy of
the State Govt. and a detailed action plan should be included.
15. Permission and approval for the use of forest land and recommendations of
the State Forest Department regarding impact of proposed expansion on the
surrounding reserve forests, if applicable, should be included.
16. A list of industries containing name and type in 25 km radius should be
incorporated.
17. Residential colony should be located in upwind direction.
18. List of raw material required and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
19. Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS
location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano
studies or at least as per I30-10500 and WHO norms. These
analysis should include trace element and metal studies like Cr (vi) Ni,
Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
20. Petrography, grain size analysis and Major element analysis of raw
material and soil from project site and raw material should be done on the same
parameters along with analysis for SiO2, Al2O3,
MgO, MnO, K2O, CaO, FeO, Fe2O3,
P2O5, H2O, CO2.
21. If the rocks, ores, raw material has trace elements their petrography,
ore microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the
amount present in it and hence future risk involved while using it and
management plan.
22. Studies for fly ash, muck disposal, slurry, sludge material and solid
waste generated should also be included, if the raw materials used has trace
elements and a management plan.
23. Manufacturing process details for all the cement plant, captive power
plant and mine should be included.
24. Possibility of installation of WHRB will be explored and details included
25. Mass balance for the raw material and products should be included.
26. Energy balance data for all the components including proposed power plant
should be incorporated.
27. Site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall should be collected.
28. Sources of secondary emissions, its control and monitoring as per the
CPCB guidelines should be included. A full chapter on fugitive emissions and
control technologies should be provided.
29. An action plan to control and monitor secondary fugitive emissions from all the sources as per the latest
permissible limits issued by the Ministry vide G.S.R. 414(E) dated 30th
May, 2008.
30. A write up on use of high calorific hazardous wastes from all the sources
in kiln and commitment regarding use of hazardous waste should be included.
31. Ambient air quality at 8 locations within the study area of 10 km.,
aerial coverage from project site with one AAQMS in downwind direction should
be carried out.
32. The suspended particulate matter present in the ambient air must be
analyzed for the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene
soluble fraction. Chemical characterization of RSPM and incorporating of RSPM
data.
33. Determination of atmospheric inversion level at the project site and
assessment of ground level concentration of pollutants from the stack emission
based on site-specific meteorological features.
34. Air quality modelling for all the plants
proposed including mine for specific pollutants needs to be done. APCS for the
control of emissions within
50 mg/Nm3 should be
included.
35. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
36.
Ambient air quality monitoring modeling alongwith
cumulative impact of mine and the cement
plant should be included for the day (24 hrs) for maximum GLC alongwith
following :
i) Emissions (g/second) with and without
the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
37. Impact of the transport of the raw materials and end products on the
surrounding environment should be assessed and provided.
38. One season data for gaseous emissions other than monsoon season is
necessary.
39. Presence of aquifer(s) within 1 km of the project boundaries and
management plan for recharging the aquifer should be included.
40. Source of surface/ground water level, site (GPS), cation,
anion (Ion Chromatograph), metal trace element (as above) chemical analysis for
water to be used. If surface water is used from river, rainfall, discharge
rate, quantity, drainage and distance from project site should also be
included.
41. Ground water analysis with bore well data, litho-logs, drawdown and
recovery tests to quantify the area and volume of aquifer and its management.
42. Ground water modelling showing the pathways of
the pollutants should be included
43. Column leachate study for all types of
stockpiles or waste disposal sites, at 20oC-50oC should
be conducted and included.
44. Dam
break analysis and flood hazard analysis of the area shall be submitted
45. Plan
for water shed management shall be submitted
46. Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water
harvesting plan for the project is necessary, if source of water is bore well.
47. Permission for the drawl of 2,700 m3/day water from ground water source and water balance
data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
48. A note on the impact of drawl of water on the nearby
River during lean season.
49. Surface water quality of nearby River (60 m upstream
and downstream) and other surface drains at eight locations must be
ascertained.
50. If the site is within 10 km radius of any major
river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well as flood occurrence frequency.
51. A note on treatment of wastewater from different plants, recycle and
reuse for different purposes should be included.
52. Provision of traps and treatment plants are to be made, if water is
getting mixed with oil, grease and cleaning agents.
53. If the water is mixed with solid particulates, proposal for sediment pond
before further transport should be included. The sediment pond capacity should
be 100 times the transport capacity.
54. The pathways for pollution via seepages, evaporation, residual remains
are to be studied for surface water (drainage, rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans.
55. Ground water monitoring minimum at 8 locations and near solid waste dump
zone, Geological features and Geo-hydrological status of the study area are
essential as also. Ecological status
(Terrestrial and Aquatic) is vital.
56. Geo-technical data by a bore hole of upto 40 mts. in every One sq. km area such as ground water level,
SPTN values, soil fineness, geology, shear wave velocity etc. for liquefaction
studies and to assess future Seismic Hazard and Earthquake Risk Management in
the area.
57. Action plan for solid/hazardous waste generation, storage, utilization
and disposal. A note on the treatment, storage and disposal of all type of
solid waste should be included. End use of solid
waste viz. fly ash etc. and its composition should be covered.
58. All stock piles will have to be on top of a stable
liner to avoid leaching of materials to ground water.
59.
Acton plan for the green belt
development plan in 33 % area should be included. The green belt should be
around the project boundary and a scheme for greening of the travelling roads
should also be incorporated. All rooftops/terraces should have some green
cover.
60.
A
scheme for rainwater harvesting have to be
put in place. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well. Efforts should be made to make
use of rain water harvested. If needed, capacity of the reservoir should be
enhanced to meet the maximum water requirement. Only balance water requirement
should be met from other sources.
61. Detailed description of the flora and fauna
(terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
62. Action plan for the green belt
development plan in 33 % area should be included. The green belt should be
around the project boundary and a scheme for greening of the traveling roads
should also be incorporated. All rooftops/terraces should have some green
cover.
63. Detailed description of the flora and fauna (terrestrial and aquatic) should be given with special reference to
rare, endemic and endangered species.
64. Disaster Management
Plan including risk assessment and
damage control needs to be addressed and included.
65. Details regarding
expected Occupational & Safety Hazards. Protective measures for
Occupational Safety & Health hazards so that such exposure can be kept
within permissible exposure level so as to protect health of workers. Health of
the workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
66. Plan for the implementation of the recommendations made for the cement
plant in the CREP guidelines must be prepared.
67. At least 5 % of the total cost of the project should be earmarked towards
the enterprise
social commitment based on Public Hearing & social responsibility and item-wise details along with time bound
action plan should be prepared and incorporated.
68. A note on identification and implementation of Carbon Credit project
should be included.
69. Total capital cost and recurring cost/annum for environmental pollution
control measures.
70. Public hearing issues raised and commitments made by the project
proponent on the same should be included separately in EIA/EMP Report in the
form of tabular chart.
71.
Any litigation pending against the project and / or
any direction / order passed by any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be submitted
to the Rajasthan State Pollution Control Board for public hearing. The issues
emerged and response to the issues shall be incorporated in the EIA report. The
final EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP along with Public hearing
report.
20.2.6
Proposed Ferro Alloys Plant (SEAF- 2x9 MVA, Pig Iron -
60,000 TPA, Fe-Mn- 20,000 TPA, Si-Mn-
20,000 TPA, Sintering Plant- 1,50,000 TPA, iron Ore Beneficiation- 2,50,000 TPA
and Manganese Ore Beneficiation- 50,000 TPA) at Village Matwara,
Tehsil Bahoriband, District
Kathi in Madhya Pradesh by M/s Worldage Resources Pvt. Limited - regarding TORs
The project proponents did not
attend the meeting and hence the proposal was deferred till further request
from the project proponent.
20.2.7
Expansion of Cement Plant from 2.5 MTPA to 8.25 MTPA and
Captive Power Plant from 30 MW to 160 MW at Villages Sangem
and Kallur, Taluk Chincholi, District Gulbarga in Karnataka by M/s Chettinad Cement Corporation Limited - regarding TORs
The project authorities and their consultant, M/s Enviro Care India Private limited, Madurai, gave a detailed presentation
on the salient features of the project and proposed Terms of Reference (TORs) for
preparation of EIA/EMP. All the cement plants (>
1.0 MTPA) have been kept at S.No. 3(b)
under category ‘A’ of the Schedule of EIA Notification 2006
and appraised at the Central level.
M/s Chettinad
Cement Corporation Limited have proposed for Expansion
of Cement Plant from 2.5 MTPA to 8.25 MTPA and Captive Power Plant from 30 MW
to 160 MW at Villages Sangem and Kallur,
Taluk Chincholi, District
Gulbarga in Karnataka. The total area
for the cement plant is 75.0 ha and Power plant is 15 Ha. The total land requirement will be 566.810 ha., which includes cement plant, captive power plant &
township (143.870 ha.) and captive limestone mines (422.94 ha.). The
location of the site is falling under Survey of India Topo
No: 56 G/7. Plant Site at 17o 21’ 55” – 17o
22’ 31” N Latitude & 77o 25’ 50” – 77o 27’18” E
Longitude. No forest land is
involved. Mullamari
River flows North to South at a distance of 2 km from
the site in the west and confluences with Kagna River
which flows in the south at a distance of 13 km from the site boundary. Chincholi Town with a population of 17,144 persons
is at a distance of 7 km from the boundary. Inter-state boundary between
Karnataka and Andhra Pradesh falls within 10 km radius from the project site.
The site falls in Seismic zone-I. Nearest
town is Tandur at
The
existing project has a capacity of 2.5
Limestone 26075 MT/Day, Bauxite /Laterite 1040 MT/Day, Iron Ore 200 MT/Day, Gypsum 1130
MT/Day, Fly ash 2235 MT/Day, Slag 1025 MT/Day
will be used as raw materials. Fuel will be Imported/Indian coal of
around 2000 TPD. Coal is the fuel for
the proposed captive thermal power plant. The requirement of coal for the proposed 2 x 50 & 1 x 30 MW
thermal power plant is estimated as: Imported
coal - 1600 t / day (or) Indigenous coal - 2325 t / day. DG sets 2 x 2 MW will be operated only in
case of CPP/Grid breakdown. Future proposal is there for 26 MW Waste Heat
Recovery (WHR) Power Plant and plan to use Gas as fuel for CPP which will be
sourced from M/s RIL
Dry process
and 5 stage double string pre-heater with in-line calciner will be installed. Cement
manufacturing process will involve crushing the limestone, raw mix preparation
and homogenization, coal preparation, calcinations and clinkerization, cement
grinding and packing etc.
The major pollutants
expected from the power plant will be SPM, SO2 and NOx. ESPs to cooler
and CPP, bag house to kiln/raw mill and coal mill and bag filters to cement
mill and packing plants will be provided to control the SPM emissions
below 50 mg/m3. To control NOx, high
efficiency multi channel low NOx burner will be used
in the kiln firing. Fugitive emissions from Limestone handling, coal handling,
clinker hopper, storage silos, weight feeders, grinding mills and packing
machines will be controlled by providing covered sheds for storage of raw materials,
fully covered conveyors for transportation of materials, etc. Dust monitoring will be done
periodically and water will be sprayed on the roads to avoid dust in the
project area.
The total requirement of raw water for
the expansion unit will be 3,100 KLD. Out of total water requirement, 600 KLD
will be met out from bore wells in the plant and mining area and 2,500 KLD will
be drawn from Mullamari River. Rain water harvesting structure including check dams will
be constructed. 345 m3/day
of Filter back wash, R.O. Plant rejects and DM Regeneration, 125 m3/day
of cooling tower bleed off and 65 m3/day of boiler blow down will be
generated from both Cement and Power plants and treated with ETP having the
capacity of 600 KLD and treated waste water will be used for cement plant gas
and clinker cooling. Sewage quantity of 252 KLD will be treated in STP having
the capacity of 300 KLD and treated sewage will be used for green belt
development. “Zero Discharge’’ for waste water
is ensured.
The dust collected from various Air
Pollution Control Measures like Bag
House/Filters, ESPs, etc.
are totally recycled for cement manufacturing. Fly ash will be pneumatically transported to the cement plant to be
used in the PPC manufacturing.. Solid
waste from STP (10 TPA) will be used as manure for green belt. Organic wastes
(100 Kg/day) will be subjected to vermi-composting
and used as manure for green belt. Also other wastes like lime sludge from paper industries, ETP
sludge, filter cake from iron and steel industries, fly ash from thermal power
plants, red mud from Aluminium industries and agro
wastes will be used in the cement kiln. Inorganic wastes (papers and
other wastes) will be sold to rag pickers / scrap dealers. Waste oil of 20 KLD
from the plants shall be collected and sold to the CPCB/KSPCB authorized agency
for further treatment & disposal.
The noise level within the plant
building at a distance of one meter from the source is maintained at <85 dB(A). Noise
level at the nearest plant boundary is maintained to be <55 dB(A) during day times and <45 dB(A) during night times.
The
committee observed that the existing plant of 2.5
20.2.8
Expansion of 3x100 TPD Sponge Iron Plant and 8 MW Captive
Power Plant (WHRB) at Village Beldanga & Panagarh, District Burdwan in
West Bengal by M/s
Shree Mahalaxmi Vinimay
Pvt. Limited - regarding TORs
The project proponents did not attend the meeting and hence
the proposal was deferred till further request from the project proponent.
Any
Other Item
20.2.9
Expansion of existing
Steel and Cast Iron Foundry from 300 MTM to 2000 MTM at Plot no.
A-1/2, MIDC, Butibori, Nagpur in Maharashtra by M/s Hindustan Udyog Limited (Formerly known as M/s Acc Nihon Casting
Limited) – Clarification regarding
Environmental
Clearance to M/s Acc Nihon Casting Limited (currently M/s Hindustan Udyog
Limited) was accorded vide
MoEF letter No. J-11011/151/2007-IA II(I) dated 7th
August, 2007 for the Expansion of existing Steel and Cast Iron Foundry
from 300 MTM to 2000 MTM at Plot no. A-1/2, MIDC, Butibori, Nagpur in Maharashtra.
The project proponent vide their letter dated 20.12.2010 informed MoEF that due to
recession of global economy etc. the consent to operate from MPCB was obtained
only for 650 MTM and since last 24 months, the average production is only 157
MTM. The online continuous monitoring system (specific condition No. iv of the above EC i.e. “On-line Continuous monitoring
system for particulate emissions, SO2 and NOx
shall be provided and ……………….”) is not installed and they think is required to
be installed by the large units. Their unit is very small having installed
capacity of 650 MTM but producing only average 160 MTM.
In this regard, a clarification is sought from MoEF
whether installation of On-line Continuous monitoring system is required for
unit having installed capacity of 650 MTM but producing only average 160 MTM.
After
detailed deliberations, the Committee clarified that On-line Continuous monitoring system is not required till the
production capacity of 650 MTM. However, regular monitoring of stacks for
particulate emissions, SO2, NOx etc.
should be carried out as per the CPCB and SPCB norms.
20.2.10
Setting up new expansion of existing Aluminium
recycling project (30,000 MTPA and above by Metal Recycling Association of India -
Clarification regarding
Proposal of M/s
Metal Recycling Association of India for requirement of Prior
Environmental Clearance for expansion or establishment of new capacity above
30,000 MTPA of aluminum recycling units manufacturing Aluminum Alloy was considered and discussed in the 19th Expert Appraisal Committee
(Industry-1) meeting held during 22nd – 23rd February,
2011. The
Committee decided that the recommendation on the above clarifications will be
discussed in the next meeting.
The committee after detailed
deliberations made the following recommendations:
·
Environmental
Clearance is not required for the above units
·
Consent/NoC from SPCB shall be obtained
·
The
raw materials should not have radioactive elements, should not have harmful
alloying element additions like lithium, selenium, vanadium etc. and without
any hazardous chemical contamination
·
Gas
as a fuel should be preferred.
·
Oil
must be low sulphur containing, else, lime scrubbing shall be done to reduce
the SO2 emissions.
The meeting ended with a vote of thanks to the Chair. The
next meeting of the Expert Appraisal Committee (Industry-1) will be held on 25th
- 26th March, 2011.
************
LIST
OF PARTICIPANTS IN 20th EAC-1 (INDUSTRY) MEETING (12th
March, 2011)
Expert Appraisal Committee (Industry-1) : |
|||
1. |
Dr. T. S. Vijayaraghavan |
Chairman |
P |
2. |
Shri. Shiban Raina |
Vice-Chairman |
P |
3. |
Prof. Manju Mohan |
Member |
P |
4. |
Prof.
Jayanta Bhattacharya |
Member |
A |
5. |
Prof.
R.C. Gupta |
Member |
P |
6. |
Dr.
R.M. Mathur |
Member |
P |
7. |
Dr.
S. K. Dave |
Member |
P |
8. |
Prof.
C. S. Dubey |
Member |
P |
9. |
Prof.
Pradeep Kumar Garg |
Member |
P |
10. |
Dr.
K. Sankar |
Member |
P |
MOEF Officials : |
|||
11. Dr. P.L.
Ahujarai |
Scientist ‘F’ & Member Secretary (EAC-1) |
||
12. Shri Ramesh Motipalli |
Scientist ‘C’ |
||
13. Shri P.R. Sakhare |
Research Officer |
*******
AGENDA FOR THE 20th MEETING
OF THE EXPERT APPRAISAL COMMITTEE (INDUSTRY-1) TO BE HELD ON 12th
March, 2011
Venue:
623-Conference Room, 6th Floor, Ministry Of Environment &
Forests, Paryavaran Bhavan, Lodhi
Road, New Delhi - 110 003
TIME:
20.0 Opening Remarks of the Chairman
20.1 Confirmation of the Minutes of the 19th
Meeting of the Expert Appraisal Committee (Industry-1) held on 22nd
& 23rd February, 2011
20.2.0 Consideration of the Projects
Proposals
for Environmental clearance
20.2.1
Proposed Cement
Grinding plant of 200 TPD capacity at DAG no. 78-81,124-128 & 136-140, IID
Growth Centre, Banderdewa, P.O. Pathali
Pahar, District North Lakhimpur,
Assam by M/s
Purvanchal Infra and Industries Pvt. Limited-
regarding Environmental Clearance
20.2.2
Proposed Cement Plant
(2.50 MTPA), Captive Power Plant (40 MW) Lime Stone Mine (395.05 ha.) at Risda, Kukurdih and Dhandhani , Tehsil Baloda Bazar, District Raipur in
Chhattisgarh by M/s Emami Cement Limited
- regarding
Reconsideration
20.2.3
Expansion of Integrated Steel Plant by installing Sponge
Iron Plant (2x200 TPD) along with Captive Power Plant (40 MW= WHRB - 4MW + AFBC
- 36 MW) at Village Ankulapathuru & Udathavaripalem, Mandal Chillakuru, Sri Pottisriramlulu,
District Nellore in Andhra Pradesh by M/s SBQ Steels Limited - regarding
Environmental Clearance
20.2.4
Expansion of Ferro Alloy Plant from 7,200 TPA to 13,200 TPA
by installing a Submerged Arc Furnace (1x4 MVA, 30,000 TPA) at A-15, Sarua Industrial Estate, Post Sarua,
District Khurda, Orissa by M/s Saumyaa Alloys Private Limited - regarding Reconsideration
Proposal for TORs
20.2.5
Integrated expansion of Mangrol
Cement Plant (Clinker- 0.75 MMTPA to 3.45 MMTPA, Cement - 0.95 MMTPA to 3.45
MMTPA), Setting up of 13 MW WHRB and 35 MW coal based CPP and enhancement of
limestone production capacity of existing limestone mine from 0.6 MMTPA to 1.6
MMTPA at Village Mangrol, Tehsil
Nimbahera, District Chittorgarh
in Rajasthan by M/s
J K Cement Limited- regarding TORs
20.2.6
Proposed Ferro Alloys Plant (SEAF- 2x9 MVA, Pig Iron -
60,000 TPA, Fe-Mn- 20,000 TPA, Si-Mn-
20,000 TPA, Sintering Plant- 1,50,000 TPA, iron Ore Beneficiation- 2,50,000 TPA
and Manganese Ore Beneficiation- 50,000 TPA) at Village Matwara,
Tehsil Bahoriband, District
Kathi in Madhya Pradesh by M/s Worldage Resources Pvt. Limited - regarding TORs
20.2.7
Expansion of Cement Plant from 2.5 MTPA to 8.25 MTPA and
Captive Power Plant from 30 MW to 160 MW at Villages Sangem
and Kallur, Taluk Chincholi, District Gulbarga in Karnataka by M/s Chettinad Cement Corporation Limited - regarding TORs
20.2.8
Expansion of 3x100 TPD Sponge Iron Plant and 8 MW Captive
Power Plant (WHRB) at Village Beldanga & Panagarh, District Burdwan in
West Bengal by M/s
Shree Mahalaxmi Vinimay
Pvt. Limited - regarding TORs
Any
Other Item
20.2.9
Expansion of existing capacity of Steel cast Iron Foundry
from 300 MTM to 2000 MTM at Plot no. A-1/2, MIDC, Butibori,
Nagpur in Maharashtra by
M/s Hindustan Udyog Limited (Formerly known as M/s
Acc Nihon Casting Limited) – Amendment in Environmental Clearance
20.2.10
Setting up new expansion of existing Aluminium
recycling project
(30,000 MTPA and above by
Metal Recycling Association of India - Clarification regarding
************