Form-4

APPLICATION FOR AMENDMENT IN ENVIRONMENTAL CLEARANCE

(To be filled up by User Agency)
1. Details of Project
 
Proposal No. : SIA/TN/MIS/276842/2022  
(a) Name of the project : Proposed construction of 720 Tenements by M/s. Tamil Nadu Urban Habitat development Board  
(b) Name of Company / Organisation. : TAMIL NADU SLUM CLEARANCE BOARD  
(c) Registered Address. : 13A, West Arokkiasamy Road R.S.Puram Tamil Nadu 641002  
(d) Legal Status of the Company. : State Government  
(e) Joint Venture (Yes/No) : No
2. Address for the Correspondence
 
(a) Name of the Applicant. : S Venkatesan  
(b) Designation (Owner/Partner/CEO) : Executive Engineer  
(c) Address :-  
       State : Tamil Nadu  
       District : Coimbatore  
       Town / Village : No  
(d) Pin Code : 641026  
(e) Email : tnscbcbe@gmail.com  
(f) Telephone no : 2470064  
(g) Fax no : No  
(h) Mobile no : 9843020610  
(i) Contact Person. : S  
(j) Website (if any) : No
3. Category of the Project/Activity as per Schedule of EIA Notification,2006
 
(a). Major Activity. : 8(a) Building and Construction projects
                               
 
      Minor Activity : No  
      Major Sub Activity. : No  
      Minor Sub Activity : No  
(b). Category : B2  
      Reason for applicant at central level/state level(in case of B1 and B2 ): No  
(c). Reason : No  
      EAC Concerned (for category A Projects Only ): No
4. Location of the Project
 
(a) Plot No/Survey No/Khasra No : 296/1 & 296/2A  
(b) Village : Kuniamuthur  
(c) Tehsil : Coimbatore South  
(d) District : Coimbatore  
(e) State : Tamil Nadu  
(f) Pin Code : 621042  
(g) Bounded Latitudes (North) : Yes  
        From : Degree:10, Minutes : 56, Seconds :54  
        To    : Degree:10, Minutes : 57, Seconds :1  
(h) Bounded Longitudes (East) : Yes  
        From : Degree:76, Minutes : 56, Seconds :34  
        To    : Degree:76, Minutes : 56, Seconds :41  
(i) Survey of India Topo Sheet No : 58B/13
5 Details of Environmental Clearance
 
(a) Project Name : Proposed construction of 720 Tenements by M/s. Tamil Nadu Urban Habitat development Board  
(b) MoEF&CC / SEIAA File No : SEIAA/TN/F.6699/EC/8(a)/637/2019  
(c) Date of issue of EC : 07/03/2019   (d) Uploaded EC letter :
6 Details of Consent to Operate
 
(i) Whether Consent to operate obtained (Yes/No) ? : No
7 Amendment Sought for
 
Amendment in Configuration/ Amendments in Clearance condition/ Other (specify) : Other. Wastewater treatment in STP & GWTP to be replaced as wastewater disposal through UGD line of
8 Details of Product (as per the approved EC)
Details of Products
S.no Product / Activity (Capacity/ Area). Quantity Unit Mode of Transport/ Transmission of Product
1Construction of 720 Nos of residential tenements comprising 13 Blocks (G+3) with built-up area of26901.40 Sq.mOthersOthers
9 Details of Configuration (Multiple Entries Allowed)
Details of Configurations
S.no Plant/ Equipment/ Facility Existing Configuration Proposed Configuration Final configuration after Amendment Remarks if Any
1Block A (2nd Floor)598.24 Sqm0.0598.24 SqmNo Change
2Block B (1st Floor)435.96 Sqm0.0435.96 SqmNo change
3Block C (3rd Floor)301.76 Sqm0.0301.76 SqmNo change
4Block B (3rd Floor)435.96 Sqm0.0435.96 SqmNo change
5Block C (1st Floor)301.76 Sqm0.0301.76 SqmNo change
6Block C (2nd Floor)301.76 Sqm0.0301.76 SqmNo change
7Block C (Ground Floor)301.76 Sqm0.0301.76 SqmNo change
8Block B (Ground Floor)435.96 Sqm0.0435.96 SqmNo change
9Block B (2nd Floor)435.96 Sqm0.0435.96 SqmNo change
10Block A (Ground Floor)598.24 Sqm0.0598.24 SqmNo Change
11Fresh Water Requirement327 KLD184 KLD511 KLDDomestic-327 KLD,Toilet Flushing-164 KLD,Gardening-20 KLD
12Block A (3rd Floor)598.24 Sqm0.0598.24 SqmNo Change
13Block A (1st Floor)598.24 sqm0.0598.24 SqmNo Change
10 Reasons for Amendment
 
Reasons for Amendment : Proposed to drop the proposal of providing STP & GWTP as UGD line is under execution with a pump house inside the project premises
11 Any Other Amendment required
Any Other Amendment Required
S.no Reference of Approved EC Description as per Approved EC Description as per Proposal. Remarks
1Annexure-I 12(iii) Page-3Disposal(KLD):Flushing-164,Greenbelt-20,UGD-275UGD line of COimbatore Corporation - 459 KLDSTP & GWTP is not proposed
2Annexure-I 12(iii) Page-4STP sludge-50Kg/d-manure for GreenbeltNo generation of STP sludgeSTP & GWTP is not proposed
3Annexure-I 11(iii) Page-3Greenbelt Development (Recycled Water) - 20 KLDGreenbelt Development - 20 KLDSTP & GWTP is not proposed
4Annexure-I 12(i) Page-3Sewage Generation: Greywater-295KLD, Sewage-164KLDSewage Generation - 459 KLDSTP & GWTP is not proposed
5Annexure-I (16) Page-4Capital cost-350Lakhs,Recurring cost-56LakhsCapital cost-95Lakhs,Recurring cost-28.7LakhsSTP & GWTP is not proposed
6Annexure-I (11) Page-2Total Water Recruitment - 491 KLDTotal Fresh Water Recruitment - 511 KLDSTP & GWTP is not proposed
7Annexure-I 12(ii) Page-3Details of Treatment: GWTP-295KLD, STP-164KLDDetails of Treatment - NilSTP & GWTP is not proposed
12 Details of EIA Consultant
 
Have you hired Consultant for preparing document (Yes/No) ? : No  
(i)Reason for not engaging the Consultant : Since it is an amendment project we have not engaged any consultants
13. Documents to be Attached
  (a) Uploaded addendum to EIA/EMP Report:   (b) Uploaded Copy of revised -Feasibility Report /Detailed Project Report (DPR) / Detailed Engineering Report / Detailed Conceptual Plan / Approved Mining Plan (in case of mining proposals):   (c) Uploaded Copy of final Layout Plan:   (d)Uploaded Cover Letter duly signed by the project proponent or authorized person:   (e)Uploaded a copy of authorization duly signed by the project proponent in support of the person making this application on behalf of the User Agency:   (f)Uploaded Additional File, If any:
Essential Details Sought
Essential Details Sought
S.no. EDS Sought Date EDS Sought Letter
1.07/09/2022Please find the attachmentEDS Letter
2.28/03/2023The corrections have been made as per the instruction received.
3.12/06/2023he project proponent is requested to upload the signed PPT. Without submission of signed PPT, file will not be placed before the SEAC/SEIAA Meeting. Hence, the Proponents is requested to submit the signed copy of PPT and with KML Link.
4.03/01/2024The corrections have been made as per the instruction received.
5.31/01/2024The project proponent is requested to upload the signed PPT. Without submission of signed PPT, file will not be placed before the SEAC/SEIAA Meeting. Hence, the Proponents is requested to submit the signed copy of PPT and KML Link.
6.13/03/2024The corrections have been made as per the instruction received.
 
Additional Detail Sought:   NIL
14. Undertaking
(a): I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, The project will be rejected and clearance given, If any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity / construction / expansion has since been taken up. (b)Name : S Venkatesan (c)Designation: Executive Engineer (d)Company: TAMIL NADU SLUM CLEARANCE BOARD (e)Address: 13A, West Arokkiasamy Road R.S.Puram Tamil Nadu 641002