Form-4

APPLICATION FOR AMENDMENT IN ENVIRONMENTAL CLEARANCE

(To be filled up by User Agency)
1. Details of Project
 
Proposal No. : SIA/TG/MIS/137851/2020  
(a) Name of the project : M/s. Terminus KG Ventures (P) Ltd – “ONE WEST”  
(b) Name of Company / Organisation. : TERMINUS KG VENTURES PRIVATE LIMITED  
(c) Registered Address. : SUITE NO:902, LEVEL 9, SLN TERMINUS, BESIDE BOTANICAL GARDEN, SY.NO:133, GACHIBOWLI, HYDERABAD Telangana 500032  
(d) Legal Status of the Company. : Private  
(e) Joint Venture (Yes/No) : No
2. Address for the Correspondence
 
(a) Name of the Applicant. : Solipuram PrabhakarReddy  
(b) Designation (Owner/Partner/CEO) : Director  
(c) Address :-  
       State : Telangana  
       District : Rangareddi  
       Town / Village : No  
(d) Pin Code : 500032  
(e) Email : propertymanager@terminus-global.com  
(f) Telephone no : 64564155  
(g) Fax no : 00  
(h) Mobile no : 9963570009  
(i) Contact Person. : Solipuram  
(j) Website (if any) : No
3. Category of the Project/Activity as per Schedule of EIA Notification,2006
 
(a). Major Activity. : 8(a) Building and Construction projects
                               
 
      Minor Activity : No  
      Major Sub Activity. : No  
      Minor Sub Activity : No  
(b). Category : B2  
      Reason for applicant at central level/state level(in case of B1 and B2 ): No  
(c). Reason : No  
      EAC Concerned (for category A Projects Only ): No
4. Location of the Project
 
(a) Plot No/Survey No/Khasra No : 88/E & 88/A  
(b) Village : No  
(c) Tehsil : No  
(d) District : No  
(e) State : No  
(f) Pin Code : 500008  
(g) Bounded Latitudes (North) : Yes  
        From : Degree:17, Minutes : 24, Seconds :54  
        To    : Degree:17, Minutes : 24, Seconds :56  
(h) Bounded Longitudes (East) : Yes  
        From : Degree:78, Minutes : 21, Seconds :14  
        To    : Degree:78, Minutes : 21, Seconds :18  
(i) Survey of India Topo Sheet No : 56 K / 7
5 Details of Environmental Clearance
 
(a) Project Name : M/s.Terminus KG Ventures Pvt Ltd  
(b) MoEF&CC / SEIAA File No : SEIAA/TS/OL/RRD-177/2017  
(c) Date of issue of EC : 22/12/2017   (d) Uploaded EC letter :
6 Details of Consent to Operate
 
(i) Whether Consent to operate obtained (Yes/No) ? : No
7 Amendment Sought for
 
Amendment in Configuration/ Amendments in Clearance condition/ Other (specify) : Amendment in configuration of BUA from 1,19,303.0 Sqm to 1,25,097.41 Sqm
8 Details of Product (as per the approved EC)
Details of Products
S.no Product / Activity (Capacity/ Area). Quantity Unit Mode of Transport/ Transmission of Product
1Mixed use development project119303.0OthersRoad
9 Details of Configuration (Multiple Entries Allowed)
Details of Configurations
S.no Plant/ Equipment/ Facility Existing Configuration Proposed Configuration Final configuration after Amendment Remarks if Any
1WASTE WATER GENERATION264.80 KLD348.0 KLD348.0 KLD
2STP CAPACITY275.0 KLD420.0 KLD420.0 KLD
3VEHICLES PARKING4W-1075 & 2W-754W -1507 & 2W 5674W-1507 & 2W 567
4STP SLUDGE20.035.035.0
5Net plot area9461.37 Sqm9461.79 Sqm9461.79 Sqm
6Parking area35324.0 sqm35816.4135816.41
7TOTAL WATER REQUIREMENT608.15 KLD553.0553.0
8NO. OF FLOORS3B+G+20 UPPER FLOORS3B + G+1+3 STILT+20 UPPER FLOORS3B+G+1+3 STILT+20 UPPER FLOORS
9BUA SQM119303125097.41125097.41
10SOLID WASTE865.13 KG/DAY2063.0 KG / DAY2063.0 KG/DAY
11Project cost150.0160.0160.0
12D.G.SETS4 * 1500 KVA4 * 1500 KVA4*1500 KVA
13Floors BUA83979.0 Sqm89281.0 Sqm89281.0 Sqm
10 Reasons for Amendment
 
Reasons for Amendment : Due to change in project proposal from Mixed use development project to Mixed development commercial and office space. Due to this our project built up area is increasing from 1,19,303.0 sqm to 1,25,097.41 sqm. hence we are requesting to amendment in issued EC
11 Any Other Amendment required
Any Other Amendment Required
S.no Reference of Approved EC Description as per Approved EC Description as per Proposal. Remarks
1SEIAA/TS/OL/RRD-177/2017119303.0 SQM BUA125097.41 SQM BUACHANGE IN BUA
12 Details of EIA Consultant
 
Have you hired Consultant for preparing document (Yes/No) ? : Yes  
(i) Accereditation No : NABET/EIA/1922/IA0043  
(ii) Name of EIA Consultant : MS SPACE ENVIRO SOLUTIONS  
(iii)Address : H.NO-1-4-69/7, Street no. 8, Habsiguda,Near Heritage fresh,Hyderabad.  
(iv)Mobile No: 9848199516  
(v)Landline No : 04048503377  
(vi)E-mail Id : info@spaceenviro.com  
(vii)Category of Accreditation : A  
(viii)Sector of Accreditation : 1(a)  
(ix)Validity of Accreditation : 05-03-2022   (x)Uploaded certificate of Accreditation certified by QCI/NABET :
13. Documents to be Attached
  (a) Uploaded addendum to EIA/EMP Report:   (b) Uploaded Copy of revised -Feasibility Report /Detailed Project Report (DPR) / Detailed Engineering Report / Detailed Conceptual Plan / Approved Mining Plan (in case of mining proposals):   (c) Uploaded Copy of final Layout Plan:   (d)Uploaded Cover Letter duly signed by the project proponent or authorized person:   (e)Uploaded a copy of authorization duly signed by the project proponent in support of the person making this application on behalf of the User Agency:   (f)Uploaded Additional File, If any:
Essential Details Sought
Essential Details Sought
S.no. EDS Sought Date EDS Sought Letter
NIL
 
Additional Detail Sought:   NIL
14. Undertaking
(a): I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, The project will be rejected and clearance given, If any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity / construction / expansion has since been taken up. (b)Name : Solipuram PrabhakarReddy (c)Designation: Director (d)Company: TERMINUS KG VENTURES PRIVATE LIMITED (e)Address: SUITE NO:902, LEVEL 9, SLN TERMINUS, BESIDE BOTANICAL GARDEN, SY.NO:133, GACHIBOWLI, HYDERABAD Telangana 500032