Form-1
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1. Basic Informations
Project Name Aparna Techshore Company/Organisation Name . APARNA CONSTRUCTION AND ESTATES PRIVATE LIMITED & OTHERS
Registered Address Aparna Construction and Estates Private Limited & Others #802, Astral Heights, D.No.6-3-352/2&3, Road No.1, Banjara Hills, Hyderabad–500034 Telangana 500034 Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Sreenivasa Reddy BV
(b)Designation (Owner/ Partner/ CEO) Diretor
(c)Address Aparna Construction and Estates Private Limited & Others #802, Astral Heights, D.No.6-3-352/2&3, Road No.1, Banjara Hills, Hyderabad–500034,,Serilingampalle,Rangareddi,Telangana-500084
(d)Pin code 500084
(e)E-mail srinivasarao.m@aparnaconstructions.com
(f)Telephone No. 40-23352068
(g)Fax No.
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(a) Building and Construction projects
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/TG/MIS/142767/2020
(e)Master Proposal Number(Single Window) SW/142766/2020
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type(New/Expansion/Modernization) Fresh EC
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaRangareddiSerilingampalleRaidurga
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document NILL
Project Profile
Location of the project Survey no. 11(P) at Raidurga Khalsa, Survey no. 17 in Raidurga Nav Khalsa, Serilingampally Mandal and in Survey nos. 80 & 81 in Manikonda Jagir, Gandipet Mandal, Ranga Reddy District
Town / Village
(Name of more than one town may be entered by separating with)
Survey no. 11(P) at Raidurga Khalsa, Survey no. 17 in Raidurga Nav Khalsa, Serilingampally Mandal and in Survey nos. 80 & 81 in Manikonda Jagir, Gandi Plot/Survey/Khasra No.
(Name of more than one town may be entered by separating with)
Survey no. 11(P) at Raidurga Khalsa, Survey no. 17 in Raidurga Nav Khalsa, Serilingampally Mandal and in Survey nos. 80 & 81 in Manikonda Jagir, Gandi
State Telangana District Rangareddi
Tehshil Serilingampalle Pincode 500008
Nearest railway station Hi tech city railway station Distance from the project site 6.2
Nearest airport Rajiv gandhi international airport Distance from the project site 19.2
Nearest Town/City/District Headquarters Hyderabad Distance from the project site 18
Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) Survey no. 11(P) at Raidurga Khalsa, Survey no. 17 in Raidurga Nav Khalsa, Serilingampally Mandal and in Survey nos. 80 & 81 in Manikonda Jagir, Gandi Upload GPS file Copy of Kml File     
Uploaded GPS file
Shape of the project land Point Site alternative under consideration(If any) Uploaded Site alternative under consideration
Brief summary of project Uploaded Brief summary of project
Does your project location falls under out of any following areas None of above Areas
Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) 308849.5 Existing Built Up Area(In Meter /Sqr) 0
Does it attract any of the general conditions given below? No
Does it attract the specific condition given below? No
Interlinked Projects No
Whether separate application of interlinked projects has been submitted? Date of Submission
Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? No
Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? No
Whether the proposal involves approval/clearance under the C.R.Z notification,2011? No
Whether there is any Government Order/Policy relevent/relating to the site? No
Forest land involved(hectares) NA
Is there any litigation pending against the project? No


Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes The site area is located in Raidurga Khalsa, Raidurga Nav Khalsa, Serilingampally and Manikonda Jagir, Gandipet, Ranga Reddy District. The present land use is commercial Office. Presently the land is barren and is not used for any productive purpose. The proposed project shall enhance the land cover.
1.2 Clearance of existing land, vegetation and buildings? No
1.3 Creation of new land uses? No
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes The project is commercial Office construction project.
1.5 Construction works? Yes The project is commercial Office construction project.
1.6 Demolition works? No
1.7 Temporary sites used for construction works or housing of construction workers? No
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations Yes The project is commercial Office construction project.
1.9 Underground works including mining or tunneling? No
1.10 Reclamation works? No
1.11 Dredging? No
1.12 Offshore structures? No
1.13 Production and manufacturing processes? No
1.14 Facilities for storage of goods or materials? Yes Construction materials like cement, steel, sand, paints, aggregate etc shall be stored on site. The cement and paints are stored indoor, while the remaining is stored out doors.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes The wastewater shall be treated and reused for flushing the toilets, HVAC make up water requirement and on land irrigation. Hence all the recycled water is utilized completely and is considered as a zero discharge.
1.16 Facilities for long term housing of operational workers? Yes Required labour shall be drawn from neighboring areas/villages.
1.17 New road, rail or sea traffic during construction or operation? No
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No
1.20 New or diverted transmission lines or pipelines? No
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No
1.22 Stream crossings? No
1.23 Abstraction or transfers of water from ground or surface waters? Yes The domestic water requirement during occupation shall be drawn from HMWSSB
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Trucks shall be used for transporting the materials.
1.26 Long-term dismantling or decommissioning or restoration works? No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No
1.28 Influx of people to an area in either temporarily or permanently? Yes The local area is developing at a faster pace due to the commercial area development in the surrounding areas.
1.29 Introduction of alien species? No
1.30 Loss of native species or genetic diversity? No
1.31 Any other actions? No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes Undeveloped land of 2.43 hectares
2.2 Water (expected source & competing users) unit: KLD Yes Water requirement during occupation is 848.0 KLD.
2.3 Minerals (MT) No
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Quantity of construction material requirement.
2.5 Forests and timber (source – MT) Yes Local authorized Suppliers
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes DG sets and construction equipment shall be used during construction, which shall use mainly HSD as fuel.
2.7 Any other natural resources (use appropriate standard units) No
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The project is commercial Office construction project.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No
3.5 Any other causes No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) Yes 5653.5 kg/day
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Used oil: 220 l/year Used Batteries: 20 nos. /year
4.4 Other industrial process wastes No
4.5 Surplus product No
4.6 Sewage sludge or other sludge from effluent treatment Yes 40 kg/day sludge from STP shall be reused as manure.
4.7 Construction or demolition wastes Yes 15442.4 Tonnes
4.8 Redundant machinery or equipment No
4.9 Contaminated soils or other materials No
4.10 Agricultural wastes No
4.11 Other solid wastes No
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Emissions from DG sets, operated only during load shut down by TRANSCO.
5.2 Emissions from production processes No
5.3 Emissions from materials handling including storage or transport No
5.4 Emissions from construction activities including plant and equipment Yes Construction equipment and DG sets which mainly use HSD, as fuel shall generate emissions. emissions from temporary in-house batching plant etc.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No
5.6 Emissions from incineration of waste No
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No
5.8 Emissions from any other sources No
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Construction activity and the construction equipment are the main sources of noise and vibration during construction. While there are no major sources of noise during occupation phase.
6.2 From industrial or similar processes No
6.3 From construction or demolition Yes construction or demolition
6.4 From blasting or piling No No blasting activity envisaged.
6.5 From construction or operational traffic Yes There will be an increase in the traffic density, which shall increase the noise levels of the area both during construction and occupation phases.
6.6 From lighting or cooling systems No
6.7 From any other sources No
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No
7.3 By deposition of pollutants emitted to air into the land or into water No
7.4 From any other sources No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No
8.2 From any other causes No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The area is presently developing into a prime residential and commercial locality in view of the thrust given by Government of Telangana for the development of IT and ITES services.
9.2 Lead to after-use of the site, which could have an impact on the environment No
9.3 Set a precedent for later developments Yes The surrounding areas shall develop as residential/ Commercial areas.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Kothaguda RF at a distance of 4.78 km, KBR National park at a distance of 2.88 km & Mrugavani park at a distance of 6.78 km
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No
4 Inland, coastal, marine or underground waters No
5 State, National boundaries No
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No
7 Defence installations No
8 Densely populated or built-up area Yes The area is developing into a densely populated area other major developments in the vicinity etc.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Hospitals, Schools, Places of worship and community facilities are located in the project impact area.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSreenivasa Reddy BV
DesignationDiretor
Name of Company (Applicant Name should not be given here). APARNA CONSTRUCTION AND ESTATES PRIVATE LIMITED & OTHERS
AddressAparna Construction and Estates Private Limited & Others #802, Astral Heights, D.No.6-3-352/2&3, Road No.1, Banjara Hills, Hyderabad–500034
Print