Form-1 | APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE | | 1. Basic Informations | Project Name | Mandavi Casa Grande | Company/Organisation Name | J. J. BUILDERS & DEVELOPERS | Registered Address | 3rd Floor, Mandavi Trade Centre, Udupi-Manipal Road, Kunjibettu, Udupi Karnataka 576102 | Legal Status of the Company | Private |
| 2. | Address for the correspondence: | (a)Name of the Applicant | Glen Dias | (b)Designation (Owner/ Partner/ CEO) | Partner | (c)Address | 3rd Floor, Mandavi Trade Centre, Udupi-Manipal road, Kunjibettu, Udupi,,Udupi,Udupi,Karnataka-576102 | (d)Pin code | 576102 | (e)E-mail | mandaviec2019@gmail.com | (f)Telephone No. | 820-2529905 | (g)Fax No. | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 8(a) Building and Construction projects
| (b)Minor Project/Activity | NIL | (c)Category | B2 | (d)Proposal Number | SIA/KA/MIS/130699/2019 | (e)Master Proposal Number(Single Window) | SW/128225/2019 | (f)EAC concerned (for category A Projects only) | INFRA-2 | (g)Project Type(New/Expansion/Modernization) | Fresh EC |
|
| 4. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
| Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Karnataka | Udupi | Udupi | Puttur | | 5. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (c)Reason | -1 | (d)Supporting Document | NILL | |
| Location of the project | Sy. No. 216/2, 114/8C, 216/5, 114/8D2, 216/3, 114/8D1, 216/4, 114/8E of Village Puttur Udupi Taluk & District Karnataka | | | Town / Village (Name of more than one town may be entered by separating with) | Puttur | Plot/Survey/Khasra No. (Name of more than one town may be entered by separating with) | Sy. No. 216/2, 114/8C, 216/5, 114/8D2, 216/3, 114/8D1, 216/4, 114/8E | State | Karnataka | District | Udupi | Tehshil | Udupi | Pincode | 576102 | Nearest railway station | Udupi Railway Station | Distance from the project site | 7 | Nearest airport | Bajpe International Airport, Mangalore | Distance from the project site | 50 | Nearest Town/City/District Headquarters | Within the limits of Udupi City Municipal Council | Distance from the project site | 0 | Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) | Udupi city Municipal corporation
K M Marg, Udupi - 576101
Telephone no.: 0820 2520306 | Upload GPS file | Copy of Kml File Uploaded GPS file | Shape of the project land | Block (Polygon) | Site alternative under consideration(If any) | Uploaded Site alternative under consideration | Brief summary of project | Uploaded Brief summary of project | | | Does your project location falls under out of any following areas | None of above Areas | | | Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) | 25411.19 | Existing Built Up Area(In Meter /Sqr) | 0 | Does it attract any of the general conditions given below? | No | | | Does it attract the specific condition given below? | No | | | Interlinked Projects | No | | | Whether separate application of interlinked projects has been submitted? | | Date of Submission | | Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | | Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | | Whether the proposal involves approval/clearance under the C.R.Z notification,2011? | No | | | Whether there is any Government Order/Policy relevent/relating to the site? | No | | | Forest land involved(hectares) | 0 | | | Is there any litigation pending against the project? | No | | |
1. | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Land use of project site is commercial cum Residential. Site is with slight slope towards North-West direction. No gross change in topography is planned. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Existing old building in the front and the trees will be cut. | 1.3 | Creation of new land uses? | Yes | Barren land to multi-purpose use. Construction work in single building with Basement + Lower Ground + Upper Ground + 13 Upper floors. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Pre-construction investigation was carried out and the report is enclosed. | 1.5 | Construction works? | Yes | General civil construction, inter alia, comprising construction of a multi storied building with associate services. | 1.6 | Demolition works? | Yes | An old building with shops in the front and residence will be demolished | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Approx. 50 labours during peak construction will be hired from nearest area. No labor colony will be provided at the Project site. | 1.8 | Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations | Yes | The site ground level is slightly lower than the main road level and the basement will be natural at road level. 9,000 cum excavation work will be generated during construction of basement. Earthwork will involve foundation and refilling at Project site. | 1.9 | Underground works including mining or tunneling? | No | Not Applicable | 1.10 | Reclamation works? | No | Not Applicable | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | No | Not Applicable | 1.14 | Facilities for storage of goods or materials? | Yes | Temporary shed will be set up at the site. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Construction Phase:
Construction and demolition waste will be segregated and reused at the project site to the maximum possible. Recyclable waste such as steel and paper will be sold to recyclers. Proper facility for storage of construction wastes is made at Project site.
The sewage generating from the temporary toilets at the project site will be connected to the Soak pit and Septic tank.
Operation Phase:
1.Solid waste: The solid waste generated will be segregated into bio degradable, non-b | 1.16 | Facilities for long term housing of operational workers? | No | Not Applicable | 1.17 | New road, rail or sea traffic during construction or operation? | No | Construction phase: Temporary traffic of approx. 5 - 10 trucks per day for haulage of construction material.
Operation phase: The Edapalli Panvel Highway (NH 66) has substantial traffic throughout day and night. There will be slight increase in vehicular traffic on the road during peak hours. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Not Applicable | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Applicable | 1.20 | New or diverted transmission lines or pipelines? | No | Not Applicable | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Not Applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Construction phase: Approx.50 kld during peak construction
Source: Existing open well Operation phase: 62 kld of fresh water Source: Supply from Udupi City Municipal Council and an Open well in case of scarcity. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not Applicable | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Construction Phase:
? Construction materials will be transported to the site by the means of trucks/dumpers.
? Construction workers are brought to the site by contractor.
Operation Phase: ? Approx. 600 people as employees. Visitors during the operation phase will use self owned/ public transportation facilities. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Construction Phase:
Not significant.
Operation Phase: Approximately 600 commuters will be using Multipurpose building and Approx. 500 people will reside in the Apartments. | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | No change in landuse. The site already had a house and shops in front. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Construction phase: Source: Existing open well
Requirement: Approx. 50 kld
Operation phase:
Source: Udupi City Municipal Council and an Open well in case of scarcity.
Requirement:62 kld of Freshwater + 41 kld of Recycled water
Refer Annex V for Water Balance. Water NOC shall be obtained from UCMC. | 2.3 | Minerals (MT) | No | The proposal pertains to the construction activity only. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Approx. construction material requirement. Cement approx. : 15000 Bags Steel approx. : 950 MT Sand approx. : 2000cum Block Masonry approx. : 165000cum Concrete : 18000 cum Material shall be procured from local Dealers. | 2.5 | Forests and timber (source – MT) | No | Minimal use of timber runners for shuttering work in civil construction. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Construction phase:
Approx. 10 KW from MESCOM
Operation Phase:
Approx. 500 KW from MESCOM
Back up: 1 DG set of 100kvA + 1 DG set of 200KvA as backupwith fuel requirement of (Diesel) approx. 60 l/hr. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not Applicable | |
3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | Not applicable. No Hazardous substances or material will be used in any commercial and domestic activity during operation phase. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not Applicable | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | Not Applicable | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not Applicable | 3.5 | Any other causes | No | Not Applicable | |
4 | Production of solid wastes during construction or operation or decommissioning (MT/month) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not Applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | During operation phase: Total Solid waste: Approx. 255 kg/day, of which approx. 128 kg will be biodegradable, 102 kg inorganic and 26 kg of inert waste, respectively. After segregation, based on the requirement for horticulture, required amount of biodegradable waste shall be composted. Recyclable waste shall be sold to recyclers. Rest of the waste along with the non-biodegradable will be sent to Common Solid Waste management Facility. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Sump oil from the standby DG to be sold to Authorized Recyclers. | 4.4 | Other industrial process wastes | No | Not Applicable | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Operation phase: Total sewage sludge generated from the proposed activity will be about 2 kg per day which will be used as manure along with the manure from OWC in gardening. | 4.7 | Construction or demolition wastes | Yes | Concrete wastage and wasted mortar will be crushed, aggregated and mixed with other road sub-base construction material. Waste/damaged construction material, sieved sand, broken brick bats and chipped plaster will also be used in the construction of roads and for backfill and consolidation of surfaces under podia, under margins/pitching of storm water drains, periphery curbing of roads etc. Broken tiles, wasted sanitary ware, broken glass and other glazed/vitrified material will be collected, br | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Horticulture waste will be composted along with other biodegradable wastes and used as manure. | 4.11 | Other solid wastes | No | Not Applicable | |
5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | There will be minor vehicular pollution during construction and operation phase. Negligible emissions from DG set in case of power failure and from vehicles of the occupants. | 5.2 | Emissions from production processes | No | Not Applicable | 5.3 | Emissions from materials handling including storage or transport | No | During the construction phase, there will be dust generation due to handling of construction material and movement of construction vehicles. Hence, there will be a slight increase in particulate matter levels during construction phase. | 5.4 | Emissions from construction activities including plant and equipment | Yes | Fugitive emissions during unloading of construction material, concrete mixers and negligible emission from DG sets. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | No | During the construction phase, there will be some dust generation due to handling of raw material and movement of vehicles carrying raw material. Some odor is possible from STP. | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | Not Applicable | |
6 | Generation of Noise and Vibration, and Emissions of Light and Heat: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Construction phase - From concrete mixers, trucks, vibrators etc. Operation phase –Minimal traffic noise due to on-site traffic. | 6.2 | From industrial or similar processes | No | Not Applicable | 6.3 | From construction or demolition | No | Noise will be generated from the construction activity mainly from concrete mixers, trucks, tower cranes, etc. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | Construction phase:
Noise will be generated due to trucks carrying the construction raw material/ debris and construction activities. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Applicable | |
7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Not Applicable | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | Approx. 80 kld of sewage would be generated which will be treated to meet the discharge standards of KSPCB. The treated wastewater will be reused for flushing, washings & horticulture. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | Dust particles generated during construction will be made to settle by sprinkling of water. | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not Applicable | |
8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | Not applicable. | 8.2 | From any other causes | No | Not applicable. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Project is in Earthquake Zone III. The design of the building is as per the IS 1893: Part (1) 2002 (Criteria for earth quake resistance design of structures - Part 1 General Provisions and Buildings). | |
9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | Not Applicable | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | No | Not Applicable | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not Applicable | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Not Applicable | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | 1. Manipal Lake - Approx. 7 km* ~ South East Direction, 2. Swarna River - Approx. 1 km* ~ East Direction ((*Aerial Distances) | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | Not Applicable | 4 | Inland, coastal, marine or underground waters | Yes | Arabian Sea - Approx. 6 km* ~ West Direction | 5 | State, National boundaries | No | Not Applicable | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | Not Applicable | 7 | Defence installations | No | Not Applicable | 8 | Densely populated or built-up area | No | The site is sparsely populated locality within Udupi City Municipal Council. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | The Project site is within Udupi City Municipal Council limits where high quality educational and community facilities are available. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | Not applicable. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not applicable. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Project is in Seismic Zone III. The building will be designed as per IS 1893: Part (1) 2002 (Criteria for earth quake resistance design of structures - Part 1 General Provisions and Buildings). | | Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
NO Record | | Additional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | | | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. | | Name of Applicant | Glen Dias | Designation | Partner | Name of Company (Applicant Name should not be given here) | J. J. BUILDERS & DEVELOPERS | Address | 3rd Floor, Mandavi Trade Centre, Udupi-Manipal Road, Kunjibettu, Udupi |
|
|