Form-1 | APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE | | 1. Basic Informations | Project Name | Proposed Slum And Non-Slum Property Bearing C.T.S No- 58/A/3B/1(Pi) & 581/A/3/B/1 To 9 Of Village Malad, Taluka-Borivali At Rani Sati Marg Malad. | Company/Organisation Name | M/S. POONAM HOUSECON PRIVATE LIMITED | Registered Address | 501, 5th Floor, Office - 2, Shah Trade Centre, Rani sati Marg, Malad (East), Mumbai 400097 400097 Maharashtra 400097 | Legal Status of the Company | Private |
| 2. | Address for the correspondence: | (a)Name of the Applicant | Manojkumar Lalchand Singh | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | 501, 5th Floor, Office - 2, Shah Trade Centre, Rani sati Marg, Malad (East), Mumbai 400097,Mumbai (Suburban),Maharashtra-400097 | (d)Pin code | 400097 | (e)E-mail | poonammpcb82@gmail.com | (f)Telephone No. | 22-28880505 | (g)Fax No. | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 8(a) Building and Construction projects
| (b)Minor Project/Activity | NIL | (c)Category | B2 | (d)Proposal Number | SIA/MH/MIS/114455/2019 | (e)Master Proposal Number(Single Window) | SW/114447/2019 | (f)EAC concerned (for category A Projects only) | INFRA-2 | (g)Project Type(New/Expansion/Modernization) | Fresh EC |
|
| 4. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
| Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Mumbai (Suburban) | Borivali | Malad | | 5. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (c)Reason | -1 | (d)Supporting Document | NILL | |
| Location of the project | Proposed SRA "EKTA CHS" Scheme Property Bearing C.T.S No- 581/A/3B/1(PT) & 581/A/3B/1/1 To 9 Of Village Malad(EAST), Taluka-Borivali At Rani Sati Marg, Malad.(EAST )MUMBAI | | | Town / Village (Name of more than one town may be entered by separating with) | Malad | Plot/Survey/Khasra No. (Name of more than one town may be entered by separating with) | C.T.S No- 581/A/3B/1(PT) & 581/A/3B/1/1 To 9 | State | Maharashtra | District | Mumbai (Suburban) | Tehshil | Borivali | Pincode | 400097 | Nearest railway station | Malad | Distance from the project site | 0.95 | Nearest airport | Chhatrapati Shivaji International | Distance from the project site | 10.35 | Nearest Town/City/District Headquarters | Borivali | Distance from the project site | 5.37 | Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) | P.N. ward office building mamletdar wadi marg malad west mumbai-400064 | Upload GPS file | Copy of Kml File Uploaded GPS file | Shape of the project land | Block (Polygon) | Site alternative under consideration(If any) | Uploaded Site alternative under consideration | Brief summary of project | Uploaded Brief summary of project | | | Does your project location falls under out of any following areas | None of above Areas | | | Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) | 38308.16 | Existing Built Up Area(In Meter /Sqr) | 00 | Does it attract any of the general conditions given below? | No | | | Does it attract the specific condition given below? | No | | | Interlinked Projects | No | | | Whether separate application of interlinked projects has been submitted? | | Date of Submission | | Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | | Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | | Whether the proposal involves approval/clearance under the C.R.Z notification,2011? | No | | | Whether there is any Government Order/Policy relevent/relating to the site? | No | | | Forest land involved(hectares) | No | | | Is there any litigation pending against the project? | No | | |
1. | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | There will not be change in land use pattern. As per the DP Plan the site is under residential zone. The proposed project will be residential in nature. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | This is being a SRA project so, the existing slums on the site shall be demolished and the debris shall be reused for leveling of land & partly shall be disposed to authorized site. | 1.3 | Creation of new land uses? | No | There will not be change in land use pattern. As per the DP Plan the site is under residential zone. The proposed project will be residential in nature. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Geotechnical Investigation Report is carried out. | 1.5 | Construction works? | Yes | The site will be developed as residential and sale buildings | 1.6 | Demolition works? | Yes | Demolition of slums. | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Temporary labor sheds and adequate sanitation facilities has been provided to the construction laborers at the site during the construction work. | 1.8 | Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations | Yes | Excavated material generated shall be partly reused for leveling within the site and partly shall be disposed to the authorized sites.
Construction waste shall be disposed of by covered trucks to the authorized sites with the permission of M.C.G.M. | 1.9 | Underground works including mining or tunneling? | Yes | Building footling construction
Construction of basements | 1.10 | Reclamation works? | No | -- | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | No | Not applicable | 1.14 | Facilities for storage of goods or materials? | Yes | Temporary sheds will be constructed for the storage of construction materials during construction phase as per the material requirement. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Construction Phase: the waste water shall be discharged to the existing sewer line, Temporary sanitary toilets will also be provided during peak labor force.
Operation Phase:
Solid waste generated from the project will be segregated at source. The total quantities of solid waste that will be generated in the project will be 993Kg/day. Out of which 596 Kg/day will be non-biodegradable and 397 Kg/day will be biodegradable. Biodegradable waste will be treated in OWC.
Total 259 KLD of wastewat | 1.16 | Facilities for long term housing of operational workers? | No | No long-term housing facilities proposed as most of the skilled/unskilled manpower required for the construction /operational activities hired locally. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | The existing road near the site is been utilized. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | The entire essential infrastructure is already available. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | -- | 1.20 | New or diverted transmission lines or pipelines? | No | Not applicable | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable, as infrastructure is already in place. | 1.22 | Stream crossings? | No | There is no stream passing through the site. | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Not Applicable | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | There will be no change in the drainage pattern. The project will not materially affect the drainage or run-off in the area. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The existing road network which is in good condition near the site is been utilized for the transportation of material and personal. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Noise pollution of short duration due to machineries and marginal air pollution because of dust may occur. | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Construction Phase
During the construction phase about 150 persons will be deployed on the site from nearby places. Influx of these people was temporary in nature.
Operation Phase
On completion of the project, residents will occupy their property. Total population is expected to be 2244 occupants | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | Not Applicable | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The land is in developed infrastructure area. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Construction Phase
Total water requirement estimated is 16 KLD. The water demand will be met by local authority and water tankers.
Operation Phase
Source: MCGM /Recycled water/RWH/ tanker
Use Buildings Source
Rehab Sale
Domestic 96 102 MCGM
Flushing 49 51 Recycled water
Gardening 2 | 2.3 | Minerals (MT) | No | No minerals required in proposed project. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Quantity: As per requirement Stone aggregates demand will be met from the clay/soil generated after excavation and from open market.
Sources: The material required for construction activities shall
be procured from company’s authorized / approved vendors only.
The vendor’s performance will be monitored periodically. In case
of urgency or non-availability of materials from authorized /
approved vendors, it will be procured from the open market. | 2.5 | Forests and timber (source – MT) | Yes | Apartments will use timber for doors, windows etc. Timber will be sourced from local suppliers. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Electricity Source: MSEDCL
Power requirement (KW/h)for:
Construction Phase: 150 KW
Operation Phase:
Connected load 9307.59 KW
Maximum Demand 3610.61 KW
DG set 1 DG of capacity 600 KVA,
2 DG set of capacity 800 KVA
1 DG of capacity 500 KVA,
1 DG of capacity 300 KVA,
1 DG of capacity 400 KVA, | 2.7 | Any other natural resources (use appropriate standard units) | No | Use of solar system | |
3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | The Hazardous substances used in project would be paints, solvents, varnishes and waste oil, paints, cleaners, batteries and pesticides and petroleum products., Asbestos containing Dust, Glass, Plastics, steel are used .The quantity of waste generated would be very low. The waste oil generated from DG sets will be stored in sealed containers and will finally be sold to authorized recycling agency. Other hazardous waste will be handled as per Hazardous Waste Handling (2003) rules | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | -- | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Positive impact will be created due to enhanced and hygienic living conditions. Aesthetic value of area will be improved. It will generate employment opportunities to the local people in terms of skilled and unskilled labor during construction and service personnel during operational phase | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Noise and Air Pollution control measures will be implemented so as to cause no harm to nearby residents or vulnerable groups during construction phase. | 3.5 | Any other causes | No | -- | |
4 | Production of solid wastes during construction or operation or decommissioning (MT/month) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not Applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Construction Phase
During the construction phase waste will be handed over to authorized local vendor for recycling.
Operation Phase
Solid waste generated from the project will be segregated at source.
The total quantities of solid waste that will be generated in the project will be 993 Kg/day. Out of which 596 Kg/day will be non-biodegradable will be handed over to authorized local recyclers and 397 Kg/day will be biodegradable treated in OWC.STP sludge shall be used as a manure for plan | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | The hazardous substances used during construction phase would be mainly varnishes, solvents and paints from finishing works and Oil and Diesel from construction machinery.
During operation period hazardous waste would be D. G Set maintenance oil. The quantity of hazardous waste is considered to be negligible. By considering maintenance once in a year, the waste oil generated would be Negligible. Also the waste oil from DG set will be stored in sealed containers and will finally be sold to auth | 4.4 | Other industrial process wastes | No | Not Applicable | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Dewatered / dried sludge from STP will be used as manure in gardening. Excess will be disposed as per MCGM disposal norms | 4.7 | Construction or demolition wastes | Yes | Demolition debris generated shall be partly reused for leveling within the site and partly shall be disposed to the authorized sites.
Construction waste shall be disposed of by covered trucks to the authorized sites with the permission of M.C.G.M. | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Not Applicable | 4.11 | Other solid wastes | No | Not Applicable | |
5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | CPCB approved DG sets will be used only in case of emergency.
The operation of proposed project does not envisage any major source of air pollution | 5.2 | Emissions from production processes | No | There is no production as the proposed project comprises of residential buildings. | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive emissions will be generated, while handling of construction materials. Vehicular emissions will be released during transport of material. | 5.4 | Emissions from construction activities including plant and equipment | Yes | The project may cause rise in dust levels during construction phase. Precautions would be taken to reduce dust generation during construction phase.
• Water should be sprinkled within active earth-moving areas at sufficient frequency and quantity to prevent particulate matter from dispersing in surrounding region.
• Covering Dusty load on vehicles by impervious sheet. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Construction Phase
Fugitive dust emissions will be generated due to movement of vehicles and material handling, which will be temporary and marginal.
Operation Phase
Emissions will be generated only from operation of DG sets, on rare occasions, since power is supplied by Local Authority. Minimal emissions will be generated from movement of vehicles as fugitive dust as the roads will be paved roads.Odour can be from STP. However, the STP will be working on appropriate technology, so as to min | 5.6 | Emissions from incineration of waste | No | Not Applicable. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable. | 5.8 | Emissions from any other sources | No | Not Applicable. | |
6 | Generation of Noise and Vibration, and Emissions of Light and Heat: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | For control of noise following measures shall be adopted:
• Use of Personal Protective Equipment (PPE) like earmuffs and earplugs during construction activities.
• Provision of noise barriers.
• The noise generation activity should be carried out during normal working hours with adequate safety for workers.
• DG sets should be provided with acoustic enclosures. | 6.2 | From industrial or similar processes | No | Not Applicable | 6.3 | From construction or demolition | Yes | • The construction noise localized, intermittent in nature.
• This has subsided with the completion of the foundation work.
• The resultant noise levels will be within the tolerable levels. The operation will be restricted to day time.
• Adequate measures taken to keep noise and vibrations under control. | 6.4 | From blasting or piling | No | Not Applicable | 6.5 | From construction or operational traffic | Yes | During Construction phase:
There will be transport of materials for construction work. Precautions will be taken to reduce the impact of the vehicular movement such as vehicular trips will not be at peak traffic hours.
During operation Phase :
The vehicular parking will be restricted only in the adequate parking area provided, which would help in reducing noise pollution due to traffic congestion. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Applicable | |
7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Not Applicable | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Wastewater will be generated from Rehabilitation building 135 KLD & from sale building 143 KLD of the project which will be treated in Sewage Treatment Plant (STP).
The treated water coming from STP will be used for secondary purposes like gardening & flushing. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | The DG sets will be provided with stacks of sufficient height to disperse the pollutants effectively so that the flue gas emissions will be strictly within the norms stipulated by CPCB.
There will not be any deposition of pollutants emitted to air into the land or into water. | 7.4 | From any other sources | No | Not Applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | D.G sets will be used as a backup source only. | |
8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | Not Applicable. | 8.2 | From any other causes | No | Not Applicable. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | Earthquake: The project falls under seismic zone-III as per IS1893 (Part-1):2016, care has been taken in designs to withstand earthquake of maximum possible Richter scale in that area.
Flood: Regular cleaning of existing storm water drain to avoid flooding.
Landslide: Further it is not landslide prone areas. Hence, no risk due to natural hazards is envisaged | |
9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | Supporting and ancillary development will take place. The project provides a well-designed residential housing.
Residential development | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable. | 9.3 | Set a precedent for later developments | No | -- | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | -- | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Sanjay Gandhi National Park Approx 2.00 km | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Arabian sea coast approx 6.04 km
Malad creek approx 2.73 km | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | -- | 4 | Inland, coastal, marine or underground waters | Yes | Arabian sea coast approx 6.04 km
Malad creek approx 2.73 km | 5 | State, National boundaries | No | -- | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Ali Yavar Jung road approx 0.2 km | 7 | Defence installations | No | -- | 8 | Densely populated or built-up area | Yes | Mumbai Metropolitan City | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Sanjevani Hospital approx 0.45
Sai Krupa Hospital & ICU approx 0.20 km
Navjivan Vidayalaya High School approx 0.60 Km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | -- | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | -- | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | -- | | Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
NO Record | | Additional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
(1.) | 04/02/2020 | Please refer the Minutes of the 119thmeeting of the State Level Expert Appraisal Committee-2 (MMR & Konkan Division) held on 1st & 2nd November, 2019 and submit the compliance accordingly. | | | | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. | | Name of Applicant | Manojkumar Lalchand Singh | Designation | Director | Name of Company (Applicant Name should not be given here) | M/S. POONAM HOUSECON PRIVATE LIMITED | Address | 501, 5th Floor, Office - 2, Shah Trade Centre, Rani sati Marg, Malad (East), Mumbai 400097 |
|
|