| Form-1 | | APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE | | | | 1. Basic Informations | | Project Name | Nest HiTek Park Pvt Ltd | Company/Organisation Name | NEST HI-TEK PARK PRIVATE LIMITED | | Registered Address | Nest Hi-Tek Park Pvt Ltd
Plot NO-2,Cochin Special Economic Zone
Kakkanad, Cochin, Kerala -682037 Kerala 682037 | Legal Status of the Company | Private |
| | 2. | | Address for the correspondence: | | (a)Name of the Applicant | JEHANGIR N | | (b)Designation (Owner/ Partner/ CEO) | GENERAL MANAGER | | (c)Address | Nest Hi-Tek Park Pvt Ltd
Plot NO-2,Cochin Special Economic Zone
Kakkanad, Cochin, Kerala -682037,,,Ernakulam,Kerala-682037 | | (d)Pin code | 682037 | | (e)E-mail | Roy.James@nestgroup.net | | (f)Telephone No. | 0- | | (g)Fax No. | | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| | 3. | | Category of the Project/Activity as per Schedule of EIA Notification,2006: | | (a)Major Project/Activity | 8(a) Building and Construction projects
| | (b)Minor Project/Activity | NIL | | (c)Category | B2 | | (d)Proposal Number | SIA/KL/MIS/275257/2022 | | (e)Master Proposal Number(Single Window) | SW/275255/2022 | | (f)EAC concerned (for category A Projects only) | INFRA-2 | | (g)Project Type(New/Expansion/Modernization) | Modernization |
|
| | 4. | | (a)Number of States in which Project will be Executed | 1 | | (b)Main State of the project | Kerala | |
| | Details of State(s) of the project |
|---|
| S. No. | State Name | District Name | Tehsil Name | Village Name |
|---|
| (1.) | Kerala | Ernakulam | Kanayannur | Thrikkakara North | | | 5. | | Details of Public Consultation: | | (a)Whether the Project Exempted from Public Hearing? | Yes | | (c)Reason | -1 | | (d)Supporting Document | NILL | |
| | Location of the project | KALAMASSERY | | | Town / Village (Name of more than one town may be entered by separating with) | THRIKKAKARA NORTH | Plot/Survey/Khasra No. (Name of more than one town may be entered by separating with) | 321 | | State | Kerala | District | Ernakulam | | Tehshil | Kanayannur | Pincode | 683101 | | Nearest railway station | KALAMASSERY | Distance from the project site | 4.2 | | Nearest airport | COCHIN INTERNATIONAL AIRPORT | Distance from the project site | 11 | | Nearest Town/City/District Headquarters | KAKKANAD | Distance from the project site | 4 | | Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) | Kalamassery Municipality
Address:
Kalamassery Municipality
Changampuzha Nagar P O
Kalamassery
Ernakulam – 682033
Phone:0484 2532026
Email: sec | Upload GPS file | Copy of Kml File  Uploaded GPS file | | Shape of the project land | Block (Polygon) | Site alternative under consideration(If any) | Uploaded Site alternative under consideration | | Brief summary of project | Uploaded Brief summary of project | | | | Does your project location falls under out of any following areas | None of above Areas | | | | Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) | 139866.17 | Existing Built Up Area(In Meter /Sqr) | 7710.68 | | Does it attract any of the general conditions given below? | No | | | | Does it attract the specific condition given below? | Yes | | | | Interlinked Projects | No | | | | Whether separate application of interlinked projects has been submitted? | | Date of Submission | | | Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | | | Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | | | Whether the proposal involves approval/clearance under the C.R.Z notification,2011? | No | | | | Whether there is any Government Order/Policy relevent/relating to the site? | Yes | Upload Order/Policy | Uploaded Order/Policy | | Forest land involved(hectares) | NIL | | | | Is there any litigation pending against the project? | No | | |
| 1. | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The proposal is the development of already existing industrial area, hence significant change in the existing land use pattern is not expected.
Vide F.2/5/2005-EPZ dated 21st August 2006 the subject project site had decalred as Sector Specific Special Economic Zone for Electronic industries and the subject proposal is to develop an Electronic Indutrial Park. Hence Porposed developmnets are intune with approved landuse policy. | | 1.2 | Clearance of existing land, vegetation and buildings? | No | Clearance of existing vegetation is note expected since the site is devoid of trees and the only existing vegetation is shrubs which will be partially cleared.
Also Demolition of Existing Buildings are not expected . | | 1.3 | Creation of new land uses? | No | Vide F.2/5/2005-EPZ dated 21st August 2006 the subject project site had decalred as Sector Specific Special Economic Zone for Electronoc industries and the subject proposal is to develop an Elctronic Indutrial Park. Hence Porposed developmnets are intune with approved landuse policy.
More over th proposal is the development of already existing industrial area, hence creation of new land use is not expected | | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil investigation of the site is executed .The soil investigation report is as attached in Annexure I.
Geotechnical investigation was conducted at NeST Hi-Tek Park site from 13/04/2022 to 26/04/2022 and followed by necessary laboratory studies. Eight borehole locations were investigated by taking 150 mm boreholes up to hard strata (17.2 m) below existing ground level. The analysis summary of the geotechnical investigation of the site NeST Hi-Tek Park are as follows | | 1.5 | Construction works? | Yes | The proposed project involves the construction of proposed buildings and completion of work in progress. i.e ;
1. Construction of 4 new building with total built up area 81158 sqmt
2. Work in progress :50996.83 sqmt | | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Material storage will provided within the site. Accommodation facility for construction labors will be provided by the contractor as per the contract terms. | | 1.8 | Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations | Yes | Entire buildings within the master plan of NeST Hi-Tek Park Pvt Ltd, Kalamassery is above Ground level. | | 1.9 | Underground works including mining or tunneling? | No | No underground works including mining/tunneling required except | | 1.10 | Reclamation works? | No | | | 1.12 | Offshore structures? | No | | | 1.13 | Production and manufacturing processes? | No | The project site is dedicated for the development of Electronic industries which include assembling of micro chips, cable, electronic tools, transformers etc. Kindly note that operations of above said industries will include assembling of sub parts which were imported from their manufacturing centers. (no effluent generation involved) | | 1.14 | Facilities for storage of goods or materials? | Yes | During the construction phase, temporary facilities for storage of construction material and goods will be provided.
During Operational phase , a warehouse of 32,000sq.ft area is porposed within the master plan for the storage of both raw material and finished products | | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Liquid Waste Management
Liquid waste generated during the construction period will be disposed to septic tank attached with soak pit. Sufficient number of toilets attached with septic tank of sufficient capacity will provided at the construction site. Same will be made as part of agreement with contractor.
During operational phase liquid waste generation is estimated as 315 KLD. STP of capacity 410 KLD with provision for augmentation if required will be provided for treating liquid waste. Tre | | 1.16 | Facilities for long term housing of operational workers? | No | | | 1.17 | New road, rail or sea traffic during construction or operation? | No | | | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | | | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | | | 1.20 | New or diverted transmission lines or pipelines? | No | | | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | | | 1.22 | Stream crossings? | No | | | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Water source during operational phase is KWA | | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | After Development, run off generated from the entire plot will be enhanced and optimum measures shall be included in the project site towards containing the storm water generated within plot itself. | | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | During the construction phase there will be transit of material and workers to the site. During the operational phase there will be influx of people near to the site seeking new job openings | | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | | | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | Yes | Since the proposal is the expansion of already existing industrail araea, ongoing activities of industry may be temporarily disturbed during the construction phase. Proper isolation of the construction site will be done prior to the construction so as to minimize the extent of impacts. | | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During the construction phase there will be transit of material and workers to the site. During the operational phase there will be influx of people near to the site seeking new job openings | | 1.29 | Introduction of alien species? | No | Only native trees and shrubs existing in the surrounding premises will be used for the creation of green spaces and ornamental garden | | 1.30 | Loss of native species or genetic diversity? | No | | | 1.31 | Any other actions? | No | | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The proposal is an expansion project and the area is reserved for developing SEZ projects with processing and non-processing area. | | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Regular supply of water will be arranged under contractor’s scope
The water demand for the construction phase is as below;
No Particular Water Demand
1 Domestic water demand for workers (assuming 250 no’s per day) 11 KLD
2 Water demand for tyre wash using flood basin 4 KLD
3 Water demand for concreting 25000KL
4 Water demand for curing 25000KL
5 Water demand for dust suppression 0.6 KLD
Operational Phase
Total Water Demand during operational phase is estimated as 485 KLD
The | | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Cement 20896 cubic m
Sand 75877 cubic m
Aggregates 56908 cubic m
Steel 602 Tonne | | 2.5 | Forests and timber (source – MT) | No | | | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Total Connected Load 20 MW
Power Source : KSEB & D. G sets(2 MW) as standby power arrangement)
Fuel – HSD (High Speed Disel) | | 2.7 | Any other natural resources (use appropriate standard units) | No | | |
| 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | The proposed project is SEZ project with processing and non processing area and no storage of hazardous chemicals will be done, apart from diesel storage for D.G.It will be stored in HDPE drums and kept in covered rooms under lock and key. | | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Suitable drainage and waste management measures will be adopted in both the construction and in operation phase which will restrict stagnation of water or accumulation of water within the site and surroundings. This will effectively restrict the reproduction and growth of disease vectors.
Good house keeping and hygienic measures will be followed during construction and operation phase to avoid any cause which can lead to occurance of disease. | | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Since the project is development of NeST Hi-Tek Park it will bring significant benefit for the public. Also the proposed project will increase the employment potential during construction and operation phase. The whole project will lead to the overall development of area. | | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | Yes | Since the project site is located near to Cooperative Medical College, Kalamasery vulnerable groups of people will be affected during construction phase.
Proper isolation of construction site will be made so as to minimize the impact due to air emissions, Noise to surroundings. | |
| 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 4.1 | Spoil, overburden or mine wastes | No | No such spoil over burden or mine waste will be generated. The construction debris will be used for back filling purpose. | | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Management of Municipal waste during construction phase:
Type and management of solid wastes generated during the construction period include;
• Construction waste will be reused within site for filling /recycle/send to vendors as per nature
• Organic waste generated form labour camp and construction site will be collected in closed green coloured bins and send to the bio-gas plant under scope of contractor.
• Inorganic waste generated form labour camp and construction site will be collecte | | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | E-waste generated from various operations and microchip assembly will be managed by licensed external agency for proper disposal | | 4.4 | Other industrial process wastes | Yes | The project site is dedicated for the development of Electronic industries which include assembling of micro chips, cable, electronic tools, transformers etc. Kindly note that operations of above said industries will include assembling of sub parts which were imported from their manufacturing centers. | | 4.5 | Surplus product | Yes | Surplus product will be return back to supplier | | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sludge will be generated during operation phase from the proposed STP and the sludge will be treated in the sludge digestor tank. | | 4.7 | Construction or demolition wastes | Yes | Construction waste will be generated at site which will be used for back filling purpose | | 4.8 | Redundant machinery or equipment | No | | | 4.9 | Contaminated soils or other materials | No | | | 4.10 | Agricultural wastes | No | | | 4.11 | Other solid wastes | No | | |
| 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | During construction phase air emission will be resulted from the mobile sources such as construction machineries and vehicles. Proper isolation of construction site will be made so as to minimize the impact of air emissions to surroundings.
During operation phase, the vehicle usage along the project area and generator usage during the time of power failures will be the sources of fossil fuel related emissions. Thick green belt is proposed to reduce the impact of air emission during operational | | 5.2 | Emissions from production processes | No | The proposal only include assembling of microchips and does not involve any manufacturing process. Hence there will not be any emission during production | | 5.3 | Emissions from materials handling including storage or transport | Yes | During construction phase, the material transit will lead to dust emissions.
Proper dust emission control measures adopted are as follows;
• All the materials will be properly covered during transportation.
• Sprinkling of water would be conducted periodically to subside the generated dust. | | 5.4 | Emissions from construction activities including plant and equipment | Yes | Air emission will be resulted from the mobile sources such as construction machineries and vehicles.
Proper dust emission control measures adopted are as follows;
• The site shall be isolated by installing tall fabric fences to obstruct noise and dust.
• Sprinkling of water would be conducted periodically to subside the generated dust.
• Adequate traffic management measures shall be adopted to monitor the movement of men, vehicles and materials within the project site. | | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Handling of construction materials and earth excavation could lead to dust and noise emissions. Sufficient mitigation measures adopted are as follows;
• The site shall be isolated by installing tall fabric fences to obstruct noise and dust.
• All the materials will be properly covered during transportation.
• Sprinkling of water would be conducted periodically to subside the generated dust.
• Adequate traffic management measures shall be adopted to monitor the movement of men, vehicles and m | | 5.6 | Emissions from incineration of waste | No | | | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Open combustion of the waste during construction and operation phase will be strictly avoided | | 5.8 | Emissions from any other sources | No | | |
| 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Construction machineries and operation of Crusher (offsite) will generate noise and vibration.
Sufficient preventive measures incorporated during construction phase in order to reduce the generation of noise ,light and vibration are as follows;
• Diesel generator should have noise control measures to meet the noise standards set by Central Pollution Control Board (75 dB(A) at 1 m from the enclosure surface for generators with integral acoustic enclosure.
• Acoustic enclosure for generators | | 6.2 | From industrial or similar processes | Yes | Noise will be generated during various industrial activities. Proper mitigation measures will be adopted to reduce the same | | 6.3 | From construction or demolition | Yes | Noise will be generated during construction activities. Proper mitigation measures will be etaken to reduce the noise during construction activities. | | 6.4 | From blasting or piling | Yes | During piling noise will be experienced along project site.
However proper mitigation measures will be adopted as presented in above sections | | 6.5 | From construction or operational traffic | Yes | Noise and vibration will be generated form vehicular movement during both construction and operation phase. | | 6.6 | From lighting or cooling systems | No | The lighting proposed within the project area during construction phase and operation phase will be limited to the permissible limit | | 6.7 | From any other sources | Yes | Diesel generators used during the time of power failure during both construction and operation phase is expected to produce noise. Generator with acoustic and vibration control as per CPCB guidelines alone will be used | |
| 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Oil spillage from construction machineries will be negligible. The amount of oil contaminated runoff from the construction yard will be detained in temporary ponds during construction phase | | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | The sewage will be conveyed to the Sewage Treatment Plant. Hence risk of contamination of land or water will not be there | | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | | | 7.4 | From any other sources | No | | | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | | |
| 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | Accidents may occur in the construction phase, for height works, which will be avoided by giving proper instructions and use of PPE | | 8.2 | From any other causes | No | | | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The project site has a stable stratography. The site is Zone III as per the earth quake classification. Structures will be designed based on these facts. | |
| 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | During construction skilled, unskilled and professional work force including temporary and permanent employee shall be hired locally in order to generate the employment to the local people.while during the project operation stage more employment will be created as a result of positive induceddevelopment in the immediate vicinity of the project area.
The proposed project is SEZ project with processing area and non-processing area and there is special residential area | | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | | | 9.3 | Set a precedent for later developments | Yes | The proposal will create a positive economic activities /projects in line with the proposed development in the vicinity areas | | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | | | | (III) | Environmental Sensitivity | | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Mangalavanam Bird Sanctuary covering about 2.74 Ha is situated at a distance of 12.4 Km from the proposed site | | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Periyar River – 4km Coastal regulation zone is located near to 15km radius of the proposed site
Branch of Kadambrayar -2km
Muttar river – about 3.5 km
Chitrapuzzha –about 7km
Backwater – about 10km | | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Mangalavanam Bird Sanctuary covering about 2.74 Ha is situated at a distance of 12.4 Km from the proposed site | | 4 | Inland, coastal, marine or underground waters | Yes | Periyar River – 4km Coastal regulation zone is located near to 15km radius of the proposed site
Branch of Kadambrayar -2km
Muttar river – about 3.5 km
Chitrapuzzha –about 7km
Backwater – about 10km | | 5 | State, National boundaries | No | | | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | | | 7 | Defence installations | No | | | 8 | Densely populated or built-up area | Yes | Project site is within kalamaserry Municipality area and is densely populated. | | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | The list and map of sensitive features within 15 km of project site are listed in Annexure II | | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | | | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | | | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | | | | Essential Details Sought |
|---|
| S. No. | EDS Sought Date | EDS Sought | Letter |
|---|
| (1.) | 05/08/2022 | Kindly submit an application in the PARIVESH Portal via ModEC (Since the project is for the extension/ expansion) along with all the relevant following documents for further processing of application for building.
1.Older EC and Extension order issued from MoEF & CC.
2.Scrutiny Fee.
3.Covering Letter signed by the proponent.
4.Form1, Form 1A.
5.Conceptual Plan of the Project.
6.EMP/EIA Report (EIA for 8(b) Projects only).
7.Corporate Environment Responsibility in physical targets as part of EMP.
8.Land documents (Possession Certificate, Tax Receipt, NOC/Land Assignment Details, if lessor, undertaking from the owner.
9.Location Sketch from VO.
10.NABET Accreditation Certificate of the Consultant.
11.Valid NABL Accreditation Certificate of lab.
12.Air, Water and Noise Test details and report.
13.Soil Analysis Report, Water Balance Study/Details.
14.Affidavit of the proponent regarding the publishing of EC, fulfilment of EC Conditions etc. | | | | Additional Details Sought |
|---|
| S. No. | ADS Sought Date | ADS Sought | Letter |
|---|
| NO Record | | | | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. | | | | Name of Applicant | JEHANGIR N | | Designation | GENERAL MANAGER | | Name of Company (Applicant Name should not be given here) | NEST HI-TEK PARK PRIVATE LIMITED | | Address | Nest Hi-Tek Park Pvt Ltd
Plot NO-2,Cochin Special Economic Zone
Kakkanad, Cochin, Kerala -682037 |
|
|