S.No.Item Details
Whether proposal involved violation of EIA notification No
Weather Consent to Establishment Obtained NA
Upload copy of CTE NA
1.Name of the Project Residential Apartments (Site B) by M/s. EKTHA WESTERN WINDSOR PARK LLP
Proposal No SIA/TG/MIS/64413/2021
2.Project Sector INFRA-2
3.Location of the project 341, 340(P), 342(P), 282(P), Situated at Puppalguda Village, Gandipet Mandal, Ranga Reddy District, Telangana
4.
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
5.Brief summary of projectAnnexure-Brief summary of project
6.State of the projectTelangana
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)TelanganaRangareddiGandipet
7.Town / Village341, 340(P), 342(P), 282(P) Puppalguda Village, Gandipet Mandal, Ranga Reddy District, Telangana.
8.Plot/Survey/Khasra No.341, 340(P), 342(P), 282(P) Puppalguda Village, Gandipet Mandal, Ranga Reddy District, Telangana.
9.S. No. in the schedule8(b) Townships and Area Development projects.
10. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 4,51,948.16 sq.m ha.
11.
New/Expansion/ModernizationNew
12. Category of project B
13. Does it attract the general condition? If yes, please specify No
15. Does it attract the specific condition? No
16.Is there any litigation pending against the project?No
17. Nearest railway station along with distance in kms. Secunderabad Railway station, 20 km
18. Nearest airport along with distance in kms Rajiv Gandhi International Airport, 22 km
19. Nearest Town/City/District Headquarters along with distance in kms hyderabad , 16 km
20. Distance of the project from nearest Habitation 3.00 , 3.00 km
21.
Details of alternative sites examined shown on a toposheetNo
22.
Whether part of interlinked projects?No
23.
Whether the proposal involves approval/clearance under the Forest (Conservation)Act,1980?No
24.
Whether the proposal involves approval/clearance under the wildlife (Protection)Act,1972?No
25.Whether the proposal involves approval/clearance under the C.R.Z notification,2011?No
26.
Whether there is any Government Order/Policy relevent/relating to the site?No
27.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
28. Project Cost(in Lac.) 111900
30. Whether the proposed project/activity located in notified Industrial area(Yes/No) No
Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes There will be changes in the existing land use pattern due to proposed construction activity. The proposed project is in accordance with the approved Development plan. The development starts only after getting the permission of Environment clearance.
1.2 Clearance of existing land, vegetation and buildings? Yes The existing land is plain and filled with shurbs. It will be leveled and graded for site preparation shall involve clearing of shrubs and vegetation.
1.3 Creation of new land uses? No The project site is earmarked for development as per the Telangana building by-laws.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil investigation has been done and the site is suitable for construction activity.
1.5 Construction works? Yes The proposed project will have the following Net Plot Area : 53,115.64sq.m Proposed Builtup area : 4,51,948.16 sq.m
1.6 Demolition works? No Demolition is not required. It is a plain open land.
1.7 Temporary sites used for construction works or housing of construction workers? No The construction activities including storing of raw materials will be confined within the project site only. No temporary labour hutment is proposed. Construction workers will be hired from the local area.
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations No Total Excavation quantity will be used for refilling or foundation trenches and the balance shall be used for leveling of low-lying areas within the plot premises.
1.9 Underground works including mining or tunneling? No No underground works including mining / tunneling will be required.
1.10 Reclamation works? No No reclamation work required.
1.11 Dredging? No No dredging required.
1.12 Offshore structures? No No offshore structures required.
1.13 Production and manufacturing processes? No No manufacturing activity
1.14 Facilities for storage of goods or materials? Yes Raw material will be stored at site in a covered area. Cement will be separately stored under cover in bales. Sand will be stacked neatly under tarpaulin cover. Bricks and steel will be laid in open.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste : Solid wastes generated will be segregated into biodegradable (waste vegetables and foods etc.) and non-biodegradable (paper, plastic, glass etc.) components and collected in separate bins. Recyclable wastes will be sold off to vendors. Dewatered/ dried sludge from STP will be used as manure in horticulture. Liquid Effluent: During construction phase, sewage will be treated and disposed through septic tanks followed by soak pits. The wastewater in operation phase generate
1.16 Facilities for long term housing of operational workers? No There will be no facilities for long-term housing of operational workers.
1.17 New road, rail or sea traffic during construction or operation? No In construction stage some vehicles will be operated at the site for construction work and transport of construction materials. During operation traffic will increase to some extent for employees. But there will be no rail or sea traffic.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not applicable.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not applicable.
1.20 New or diverted transmission lines or pipelines? No Not required
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No impoundment, damming, culverting, realignment or other changes to the hydrology of surface watercourses is proposed.
1.22 Stream crossings? No There are no Water Bodies flowing within the site. The nearby water bodies are as follows. 1. Pedda cheruvu 2.0km N 2. Chinta Kunta 4.10km NW 3. Durgam Cheruvu 3.0km NE 4. Bettemma Cheruvu 1.54km NE 5. Khajaguda Lake 0.90km NNW 6. Suram Cheruvu 6.40km NE 7. Kamunoni Cheruvu 7.60km NE 8. Maisamma Cheruvu 8.10km NE 9. Muskin Cheruvu 4.00km S 10. Musi River 6.70km S 11. Osman sagar 7.30km WSW 12. Nallagandla Cheruvu 7.00km NW 13. Gopi Cheruvu 6.60km NNW 14. Patel Cheruvu 7.40km NNW
1.23 Abstraction or transfers of water from ground or surface waters? No During construction phase, water supply will be met through existing bore wells/ tankers. During operation phase, water will be from municipal supply. Treated water from STP will be recycled in operation phase.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Surface drainage will not be affected.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transport of personnel/ material during construction and operation phase are envisaged. Adequate road facilities of existing 30mts. During operation phase, adequate parking space will be provided as follows. Proposed Parking Area: 1,32,952.16 sq.m Total parking area proposed is 1,32,952.16 sq.m. It will provide space for 2619 cars and 1500 (two wheelers)
1.26 Long-term dismantling or decommissioning or restoration works? No Not applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable
1.28 Influx of people to an area in either temporarily or permanently? No Construction workers from nearby areas will be hired.
1.29 Introduction of alien species? No Not applicable.
1.30 Loss of native species or genetic diversity? No Not applicable.
1.31 Any other actions? No No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Project site is earmarked for development by the local development authority.
2.2 Water (expected source & competing users) unit: KLD Yes During construction phase, required water will be supplied through tankers and existing bore wells. operation phase 1. Total water requirement during initial phase of occupancy is 1252KLD. 2. Wastewater estimated to be generated from the project is 976KLD 3. Total 439KLD water will be recycled in the process used for flushing, green belt development, DG set cooling. Source: Water will be met through municipal supply from HMWSSB
2.3 Minerals (MT) No Not applicable.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction materials required: Source: Steel and cement will be procured from authorized vendors. Sand & aggregate will be procured from local material suppliers.
2.5 Forests and timber (source – MT) No None
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Overall maximum demand is estimated approximately 6611KVA. The source of electricity will be Telangana State Electricity Board. DG Set of capacity 8x750 KVA+2x160 KVA for lighting and other services will be provided as Back up of Power supply.
2.7 Any other natural resources (use appropriate standard units) No None
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No The proposed project is a Residential Apartments project, and hence, no storage of hazardous chemicals (as per MSIHC rules) will be done.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Suitable covered drainage and waste management measures will be adopted in both construction and operational phase, which will restrict stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Construction of Residential Apartments will provide employment for local labors in both construction and operation phase. Better infrastructure will be provided in the project location. Thus, the project will have beneficial impacts.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not applicable.
3.5 Any other causes No -
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No No such spoil, overburden or mine wastes will be generated.
4.2 Municipal waste (domestic and or commercial wastes) Yes Solid wastes to be generated in project will be of domestic in nature. During operation phase, Total Solid waste estimated to be generated from the project would be 4531.5kg/Day. Composition & quantity of solid wastes estimated to be generated in operation phase are : Biodegradable: 2718.9kg/day (Waste vegetables and foods etc.) Recyclable 1359.45kg/day (Papers, cartons, thermocol, plastics, glass etc.) Inerts 453.15kg/day Total: 4531.5 kg/day Biodegradable waste will be composted using t
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No No hazardous waste will be generated.
4.4 Other industrial process wastes No Not applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes The sludge generated from STP will be dewatered/ dried and used as compost/manure for the green belt development within the site.
4.7 Construction or demolition wastes Yes The construction waste will consist of excess earth and construction debris along with cement bags, steel in bits and pieces, insulating and packaging materials etc. Recyclable waste construction materials will be sold to recyclers. Unusable and excess construction debris will be disposed as per Construction and Demolition waste management rules 2016.
4.8 Redundant machinery or equipment No Not applicable
4.9 Contaminated soils or other materials No Not applicable
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes No -
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes The proposed project does not envisage any major air pollution sources except operation of backup DG sets during power failure and vehicular traffic.
5.2 Emissions from production processes No Not envisaged
5.3 Emissions from materials handling including storage or transport Yes This will be restricted to the construction phase and to the construction site only.
5.4 Emissions from construction activities including plant and equipment Yes This will be restricted to the construction phase and to the construction site only.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust, which will be generated during construction, will be water sprinkled. Tarpaulin cover will be provided on stored raw material to reduce the dust emission. Green belt will be developed with 2meter width all along the boundary with large leave foliage.
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Open burning of biomass/ other material will be strictly avoided
5.8 Emissions from any other sources No Not applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Source of noise in the operational phase will be from backup DG sets (which will be in operation only during power failure) and pumps & motors. All the machinery will be of highest standard of reputed make and will comply with national/ international standards that take care of air and noise pollution control/ vibration control. Therefore, no significant impact due to operation of machinery is anticipated.
6.2 From industrial or similar processes No Not applicable
6.3 From construction or demolition Yes Due to various construction activities, there will be short-term noise impacts in the immediate vicinity of the project site. The construction activities will include the following noise generating activities: • Concreting, mixing & operation of DG sets • Construction plant and heavy vehicle movement • During operation phase the DG sets will be provided with suitable noise abatement methods, like acoustically treated enclosures will be adopted.
6.4 From blasting or piling No No blasting or mechanized piling will be used in the construction phase.
6.5 From construction or operational traffic Yes Some noise will be generated from vehicular movement in the construction and operational phase.
6.6 From lighting or cooling systems No No
6.7 From any other sources No Not applicable.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No The only hazardous wastes in the project will be used/ spent oil from backup DG sets. The spent oil will be carefully stored in HDPE drums under isolated storage, and periodically sold to authorized recyclers. All precautions will be taken to avoid spillage from storage.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No There will be no discharge of untreated sewage on water or land, as wastewater after treatment will be reused for toilet flushing, and horticultural. Hence no adverse effect is envisaged.
7.3 By deposition of pollutants emitted to air into the land or into water No There will be no deposition of pollutants in to air and water
7.4 From any other sources No Not applicable.
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not applicable.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No This is a construction project and does not involve major hazardous construction activity. No industrial or process activity is involved in this project. Hence, chances of explosions, spillages, fires are minimal. During construction, all construction workers will be provided with personal protective equipment (PPE) by the contractors as required under the health & safety norms. Training and awareness about the safety norms will be provided to all involved in construction activities. Suitable
8.2 From any other causes No Not applicable.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes Suitable seismic consideration will be adopted while designing the structures to mitigate the seismic impacts.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The proposed project will lead to development of the area by providing well infrastructure, clean atmosphere, employment of the local people during construction and operation phase. All supporting infrastructure is in place. Group Housing project improves infrastructure development of the location. Not applicable Not applicable Not applicable
9.2 Lead to after-use of the site, which could have an impact on the environment No Not applicable
9.3 Set a precedent for later developments No Not applicable
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not applicable
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No none
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Water Bodies Pedda cheruvu 2.0km N Chinta Kunta 4.10km NW Durgam Cheruvu 3.0km NE Bettemma Cheruvu 1.54km NE Khajaguda Lake 0.90km NNW Suram Cheruvu 6.40km NE Kamunoni Cheruvu 7.60km NE Maisamma Cheruvu 8.10km NE Muskin Cheruvu 4.00km S Musi River 6.70km S Osman sagar 7.30km WSW Nallagandla Cheruvu 7.00km NW Gopi Cheruvu 6.60km NNW Patel Cheruvu 7.40km NNW
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No none
4 Inland, coastal, marine or underground waters No none
5 State, National boundaries No none
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No none
7 Defence installations No none
8 Densely populated or built-up area Yes Puppalguda Village 3.00km from project site in SE direction
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No none
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No none
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No none
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No none
(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
5 Uploaded Form-1A Annexure-Form-1A
6 Uploaded Conceptual Plan Annexure-Conceptual Plan
(V) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge
V.(i)
NameM/S. EKTHA WESTERN WINDSOR PARK LLP.,
DesignationDesignated partner
Company M/S. EKTHA WESTERN WINDSOR PARK LLP.,
Address341, 340(P), 342(P), 282(P), Puppalguda village, Gandipet mandal, Ranga reddy district, Telangana
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
           Transferred Details(Category A To B)
S. No.Category A(Proposal No)Category B(Proposal No)Transferred DateReasonLetter
NO Record
Print