Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) GOLDFISH ABODE PRIVATE LIMITED
(b)Name of the Company / Organisation M/S. GOLDFISH ABODE PVT.LTD
(c)Registered Address #7G,SEVENTH FLOOR, VAISHNAVI CYNOSURE, OLD MUMBAI HIGHWAY, TELECOM NAGAR EXTENSION, GACHIBOWLI, TELANGANA,,Rangareddi,Telangana-500032
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Chandrashekar Vege
(b)Designation (Owner/ Partner/ CEO) director
(c)Address #7G,SEVENTH FLOOR, VAISHNAVI CYNOSURE, OLD MUMBAI HIGHWAY, TELECOM NAGAR EXTENSION, GACHIBOWLI, TELANGANA,Rangareddi,Telangana-500032
(d)Pin code 500032
(e)E-mail gold_1fish@outlook.com
(f)Telephone No. 8632-237293
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/TG/MIS/48585/2019
(e)Master Proposal Number(Single Window) SW/132033/2019
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy. No. 90, Kokapet Village
(b)Pincode 500075
(c)Bounded Latitudes (North)
From
Degree 17.406636
Minutes
Second
From
Degree 17.407722
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.325940
Minutes
Second
From
Degree 78.327848
Minutes
Second
(e)Survey of India Topo Sheet No. 56K/07
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 542
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 1
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaRangareddiRajendranagarKokapet
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number Not Applicable
(c)Date of Apply of TOR 18 Dec 2019
(d)Date of Issue of TOR / Standard ToR 18 Dec 2019
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As Construction projects were exempted from Public
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Total Built-up area191546.50 Sq.m.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Total Site Area13446.64OthersSq.m.OthersNone
(2.)Total Built-up Area191546.50OthersSq.m.OthersNone
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 17 Dec 2019
(iv)Valid Upto 17 Dec 2019
(v)File No. Not Applicable
(vi)Application No. Not Applicable
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 190
(b) Funds Allocated for Environment Management (Capital) (in crores) 2.15
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.31
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.35
(e) Funds Allocated for Environment Management Capital(%) 1.13
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1594.77
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1594.77
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)coarse aggregate1313.49Cubic Meter per DayFrom quarriesRoad45 Open MarketCopy of Linkage
(2.)Bricks573781370.80OthersNumbersLocal suppliersRoad45 Open MarketCopy of Linkage
(3.)Cement8290027.57OthersbagsManufacturing unitsRoad150 Open MarketCopy of Linkage
(4.)Sand1594.77Cubic Meter per DayRobosandRoad150 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube79.2052.4078.9100
(2.)PM2.5Micro Gram per Meter Cube48.5020.9048.3060
(3.)SO2Micro Gram per Meter Cube23.4012.9023.1080
(4.)NOxMicro Gram per Meter Cube25.7013.9025.5080
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l0.790.581.01.5
(2.)TSSmg/l3.01.5200600
(3.)Chloridesmg/l172.96102.242501000
(4.)pHNA8.246.786.508.50
(5.)TDSmg/l6844595002000
(6.)Total Hardnessmg/l370.5239.4200600
(7.)Heavy MetalsAluminiummg/l0.0100.030.02
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l1713A
(2.)pHNA7.687.51A
(3.)DOmg/l4.84.1A
(4.)CODmg/l4835A
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))61.143.465
(2.)Leq(Night)A-weighted decibels(dB(A))54.539.655
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityOthersµmhos/cm848264
(2.)pH8.818.25
(3.)N(Nitrogen)Kilogram per hectare4826
(4.)P(Phosphorus)Kilogram per hectare4334
(5.)K(Potassium)Kilogram per hectare134127
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 25 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 25
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHMWSSB5811Copy of Permission LetterPipelineOthersPublic SuplyNA18 Dec 2019581
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Waste Water500600STPReuse within the Plant & Recycling500
16.1.
(a)Total Waste Water Generation 500
(b)Total Discharged Water 0
(c)Total Reused Water 500
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)GarbageMunicipal Solid Waste1.24Tons1RoadOthersOrganic Waste Convertor
(2.)Inert WateMunicipal Solid Waste0.412Tons2RoadSanitary Landfills
(3.)Recyclable WasteMunicipal Solid Waste2.48Tons10RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube78.900.92.4081.30100
(2.)SO2Microgram per Meter Cube23.100.92.7625.8680
(3.)PM2.5Microgram per Meter Cube48.300.91.5349.8360
(4.)NOxMicrogram per Meter Cube25.50.93.7827.2880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG Set 2000 KVADiesel9.01.0PM100.64
(2.)DG Set 2000 KVADiesel9.01.0SO20.6
(3.)DG Set 2000 KVADiesel9.01.0NOx1.54
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 13635
(b)Source TSCPDCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 4 x 2000 KVA
(e)Stack Height (in m) 9.0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 1.3446
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.3446
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 1.3446
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : None 0
    Total 1.3446
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Built Up Area0.5920
(2.)Green belt0.1349
(3.)OthersRoad Area0.3725
Total 1.0994
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNone0None
(2.)ESZsNone0None
(3.)NPAMrugavani National Park5.2None
(4.)WLSNone0None
(5.)ESAsNone0None
(6.)Wildlife CorridorsNone0None
(7.)Critically Polluted AreaNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0None
(2.)ForestChilkur P.F.5.0None
(3.)Defence InstallationsNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.3446
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired None
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Osman sagar
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 1.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 30
(c)Temporary Employment- During Construction 500
(d)Temporary Employment- During Operation 100
(e)No. of working days 330
(f)Total Manpower 730
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.2693
(b)Percentage of Total Project Area 20.03
(c)No. of Plants to be Planted 270
(d)Funds Allocated for Plantation 20
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment to 730 persons
(2.)EnvironmentalImproved green cover
(3.)FinancialEmployment to 730 persons
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 105.0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 1
(d)Total plot area (sqm) 13446.64
(e)Total built up area (sqm) 191546.50
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
    Capacity 0
(b)No. of Recharge Pits 34
    Capacity 2.16
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2130 -4 wheelers & 710 - 2 wheelers
5.
Energy Saving Measures:
(a)Source/Mode Solar power & energy efficient fixtures
(b)Percentage 6
(c)Quantity 652.24
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area None
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 124
(ii)Name of the EIA Consultant Pridhvi Envirotec (P) Limited
(iii)Address 184/c,Lawn House, 4th floor, Vengalraonagar, Hyderabad - 500 038
(iv)Mobile No. 9849023662
(v)Landline No. 0404017977
(vi)Email Id pvr@pridvienviro.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 03 Jun 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantChandrashekar Vege
Designationdirector
Name of Company (Applicant Name should not be given here)M/S. GOLDFISH ABODE PVT.LTD
Address#7G,SEVENTH FLOOR, VAISHNAVI CYNOSURE, OLD MUMBAI HIGHWAY, TELECOM NAGAR EXTENSION, GACHIBOWLI, TELANGANA
Print