Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Modification and Expansion of Raidurg IT Office Tower Blocks for Transit Oriented Development - L&T METRO RAIL (Hyderabad) Limited
(b)Name of the Company / Organisation L T METRO RAIL HYDERABAD LIMITED
(c)Registered Address 4th Floor, Cyber Towers, HITECH City, Madhapur, Hyderabad 500081,,Rangareddi,Telangana-500081
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant RAVI SHANKAR P
(b)Designation (Owner/ Partner/ CEO) Vice President & Head – TOD
(c)Address 4th Floor, Cyber Towers, HITECH City, Madhapur, Hyderabad 500081,,Serilingampalle,Rangareddi,Telangana-500081
(d)Pin code 500081
(e)E-mail udaya.bhaskar@ltmetro.com
(f)Telephone No. 40-67295697
(g)Fax No. 04023123015
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/TG/MIS/61756/2013
(e)Master Proposal Number(Single Window) NA
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 83/1
(b)Pincode 500039
(c)Bounded Latitudes (North)
From
Degree 1929680.96
Minutes
Second
From
Degree 1930044.26
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 221202.72
Minutes
Second
From
Degree 221538.53
Minutes
Second
(e)Survey of India Topo Sheet No. 56 K/7
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 585
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number SEIAA/AP/RRD-318/2013-3915
(b)Date of Apply of EC 10 Jun 2013
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The proposed project is building project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. NA
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Area Development Project81754385240466994Otherssq.mOthersNot Applicable
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Area Development Project81754385240466994Builtup Area in Sq.m
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 12 Feb 2021
(iv)Valid Upto 19 Jul 2025
(v)File No. Not Applicable
(vi)Application No. None
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 40.45
(b) Funds Allocated for Environment Management (Capital) (in crores) 40.45
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 1.335
(e) Funds Allocated for Environment Management Capital(%) 100.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1831816
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 1831816
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Sand77048OtherscumPurchaseRoad20 Open MarketCopy of Linkage
(2.)Steel21188OthersTonsPurchaseRoad20 Open MarketCopy of Linkage
(3.)Cement1540960OthersBagsPurchaseRoad20 Open MarketCopy of Linkage
(4.)Concrete192620OtherscumPurchaseRoad10 Open MarketCopy of Linkage
(5.)FLY ASH BRICKS1381050OthersNumbersPurchaseRoad20 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2020 To 28 Feb 2021
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube17.610.217.480
(2.)PM2.5Micro Gram per Meter Cube43.725.143.260
(3.)PM10Micro Gram per Meter Cube71.444.770.8100
(4.)NOxMicro Gram per Meter Cube20.211.719.780
    14.2.     No. of Ground Water Monitoring Locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.507.066.58.5
(2.)Chloridesmg/l1257.02501000
(3.)Fluoridemg/l0.480011.5
(4.)TDSmg/l372845002000
(5.)TSSmg/l10002000
(6.)Total Hardnessmg/l17548200600
(7.)Heavy Metalsironmg/l0.0601.00
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l00A
(2.)CODmg/l00A
(3.)pHmg/l00A
(4.)DOmg/l00A
    14.4.     No. of Ambient Noise Monitoring Locations : 2
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))64.863.765
(2.)Leq(Night)A-weighted decibels(dB(A))54.954.255
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.360
(2.)N(Nitrogen)Kilogram per hectare850
(3.)Electric ConductivityMillisiemens per Centimetre2270
(4.)K(Potassium)Kilogram per hectare920
(5.)P(Phosphorus)Kilogram per hectare320
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 30 To 50
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHMWSSB19360Copy of Permission LetterPipelineOthersPipelineNot Applicable02 May 20211936
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Waste13492200MBBR- STPReuse within the Plant & Recycling1349
16.1.
(a)Total Waste Water Generation 1349
(b)Total Discharged Water 0
(c)Total Reused Water 1349
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Domestic waste per dayMunicipal Solid Waste10.804Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube70.8000100
(2.)PM2.5Microgram per Meter Cube43.200060
(3.)SO2Microgram per Meter Cube17.400080
(4.)NOxMicrogram per Meter Cube19.700080
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG setDiesel300.5PM10,SO2
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 17000
(b)Source Metro Power/TSSPDCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 23000
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 3.64
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 3.64
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : 9 Acres Plot Area 3.64
    Total 3.64
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersPlot Area3.649 acres
Total 3.64
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0-
(2.)WLSNone0-
(3.)ESZsNone0-
(4.)NPANone0-
(5.)ESAsNone0-
(6.)Wildlife CorridorsNone0-
(7.)CorridorsNone0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestChilkur PF7.7SSW
(2.)Defence InstallationsMehdipatnam6.5SE
(3.)Archaeological SitesQutub Shahi Tombs5.0SE
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? Selec
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 3.64
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Pangolin (Manis crassicaudata) Monitor lizard (Varanus bengalensis) and Indian Peafowl (Pavo cristatus)
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Pedda Cheruvu
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 0.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 48300
(c)Temporary Employment- During Construction 350
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 48650
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt00.9040
(2.)Percentage of Total Project Area010.110
(3.)Funds Allocated05050
(4.)No. of Plants0200200
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalA budget of Rs 4045 Lakhs is earmarked towards implementation of EMP. L&T Metro Rail (Hyderabad) Limited is proposing to develop Greenbelt in an area of 3,661 Sq.m (0.904 Acres), which is 10.1 % of t
(2.)FinancialThe estimated capital investment for the proposed Expansion Project is INR 380 Crores. The Project will generate taxes and duties to Government of India and Government of Telangana. The Project will
(3.)SocialThe Project after completion of the expansion will provide total employment to about 48,300 persons.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 103
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 3
(d)Total plot area (sqm) 36421.71
(e)Total built up area (sqm) 466994
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 3
    Capacity 330
(b)No. of Recharge Pits 45
    Capacity 7000
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 5150
5.
Energy Saving Measures:
(a)Source/Mode Solar Energy
(b)Percentage 13
(c)Quantity 7544
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Not Applicable
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0174
(ii)Name of the EIA Consultant B. S. Envi-Tech Pvt. Ltd.
(iii)Address 12-13-1270/71/73, Amity Ville, 4th Floor, Beside Spencer Super Market, St. Ann’s Road, Tarnaka, Secunderabad-500017
(iv)Mobile No. 9848053011
(v)Landline No. 4049783062
(vi)Email Id info@bsenvitech.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 16 Nov 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRAVI SHANKAR P
DesignationVice President & Head – TOD
Name of Company (Applicant Name should not be given here)L T METRO RAIL HYDERABAD LIMITED
Address4th Floor, Cyber Towers, HITECH City, Madhapur, Hyderabad 500081