Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Establishment of Chlor Alkali and synthetic organics manufacturing units in existing/consented sodium hypochlorite (15%) manufacturing facility of area 42.28 acres by The Andhra Sugars Limited
(b)Name of the Company / Organisation THE ANDHRA SUGARS LIMITED
(c)Registered Address The Andhra sugars Limited, Sy. No.541,545 and 539,Venkatarayapuram industrial area town ship,Venkatarayapuram village,Tanuku mandal,West Godavari District,Andhra Praesh.,,West Godavari,Andhra Pradesh-534215
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Palachandra M
(b)Designation (Owner/ Partner/ CEO) CompanySecretary
(c)Address The Andhra Sugars Limited, Venkatarayapuram Industrial Area Township,Tanuku Mandal,Andhra Pradesh,,Tanuku,West Godavari,Andhra Pradesh-534215
(d)Pin code 534215
(e)E-mail info.tnk@theandhrasugars.com
(f)Telephone No. 8819-224911
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity4(d) Chlor-alkali industry
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/AP/IND2/202216/2021
(e)Master Proposal Number(Single Window) SW/202213/2021
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.20
(b)Pincode 531021
(c)Bounded Latitudes (North)
From
Degree 173934
Minutes
Second
From
Degree 173938.8
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 830513.79
Minutes
Second
From
Degree 830517.26
Minutes
Second
(e)Survey of India Topo Sheet No. 65K/14, O/2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 45
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 13
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Andhra PradeshVisakhapatnamParavadaJN Pharma City
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number NIL
(b)Date of Apply of EC NIL
(c)Date of Issue of EC NIL
(d)Previous EC Letter NIL
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The Project falls under B2 category
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. 494/APPCB/CFE/RO-VSP/HO/2018
(iv)Status of Compliance Non Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Chlorinated Paraffin Wax (52%)02020OthersTPDRoad
(2.)Chlor - Alkali0295295OthersTPDRoad
(3.)Monochloro Acetic Acid02020OthersTPDRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Husk/Coal Fired Boiler2 x 15 TPH--2 x 15 TPH2 x 15 TPH
(2.)DG sets3 x 1250--3 x 12503 x 1250
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 09 Jul 2020
(iv)Valid Upto 30 Jun 2027
(v)File No. 494/APPCB/CFE/RO-VSP/HO/2018
(vi)Application No. 494/APPCB/CFE/RO-VSP/HO/2018
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 300
(b) Funds Allocated for Environment Management (Capital) (in crores) 21
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 2.25
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 8.75
(e) Funds Allocated for Environment Management Capital(%) 7.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 375
(b)Existing quantity of raw material/fuel 106.4
(c)Total quantity of raw material/fuel 481.4
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Muriate of Potash(KCl)24455Tons per AnnumINDEGENIOUSRoad5 Open MarketCopy of Linkage
(2.)Salt135000Tons per AnnumINDEGENIOUSRoad5 Open MarketCopy of Linkage
(3.)Caustic Soda Lye (32%)38836Tons per AnnumINDEGENIOUSRoad5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2020 To 31 May 2020
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube0000
(2.)SO2Micro Gram per Meter Cube0000
(3.)PM2.5Micro Gram per Meter Cube0000
(4.)PM10Micro Gram per Meter Cube0000
    14.2.     No. of Ground Water Monitoring Locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)ChloridesNA0000
(2.)TSSNA0000
(3.)Heavy MetalsNANA0000
(4.)pHNA0000
(5.)Total HardnessNA0000
(6.)FluorideNA0000
(7.)TDSNA0000
    14.3.     No. of Surface Water Monitoring Locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODNA00A
(2.)pHNA00A
(3.)DONA00A
(4.)CODNA00A
    14.4.     No. of Ambient Noise Monitoring Locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))000
(2.)Leq(Night)A-weighted decibels(dB(A))000
    14.5.     No. of Soil Sample Monitored Locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)00
(2.)P(Phosphorus)00
(3.)pH00
(4.)N(Nitrogen)00
(5.)Electric Conductivity00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersJNPC31561 Not Appliacble PipelineOthersJNPC00000000001 Jan 20203156
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Effluent Generation544600CETPOthersCETP, Ramky0544
16.1.
(a)Total Waste Water Generation 544
(b)Total Discharged Water 544
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP SludgeIndustrial Waste2Tons2RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10NA00000
(2.)PM2.5NA00000
(3.)SO2NA00000
(4.)NOxNA00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)2 x 15 TPH Husk/ Coal Fired BoilerCoal/Husk401.2PM100.8g/sec
(2.)3 x 1250 KVA DG SetDiesel180.5PM100.01g/sec
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3750
(b)Source TRANSCO
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3 x 1250 KVA
(e)Stack Height (in m) 18
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 17.1
(d)Revenue Land 0
(e)Other Land 0
    Total Land 17.1
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 17.1
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : NA 0
    Total 17.1
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersTotal site area17.1
Total 17.1
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA00
(2.)WLSNA00
(3.)NPANA00
(4.)ESAsNA00
(5.)ESZsNA00
(6.)Wildlife CorridorsNA00
(7.)CorridorsNA00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNadupuru RF5.75NA
(2.)Defence InstallationsNA00
(3.)Archaeological SitesNA00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 17.1
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired land area of 17.1 ha
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 900
(c)Temporary Employment- During Construction 800
(d)Temporary Employment- During Operation 100
(e)No. of working days 365
(f)Total Manpower 1900 direct and indirect
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt013.9513
(2.)Percentage of Total Project Area03333
(3.)No. of Plants50020002500
(4.)Funds Allocated21012
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment potential
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/SA 0114
(ii)Name of the EIA Consultant Team Labs and Consultants
(iii)Address B-115-117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038
(iv)Mobile No. 4023748555
(v)Landline No. 4023748555
(vi)Email Id teamlabs@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 24 Sep 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)01/04/2021you are requested to Submit the certified compliance report
(2.)18/05/2021The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)14/10/2021The Committee noted that the Jawaharlal Nehru Pharmacity, Visakhapatnam obtained the Environmental Clearance from the MoEF&CC, GoI, New Delhi for entire Pharmacity to establish chemical, bulk drug and pharmaceutical industries but not obtained EC for Chloro Alkali Industry .The proponent proposed to establish Chloro Alkali Industry in the JN Pharmacity, Visakhapatnam. Hence, the JN Pharmacity, Visakhapatnam has to obtain amendment to the EC to establish Chloro Alkali units in JN Phamacity, Visak
(2.)25/02/2022Dear Sir, ADS Response: We thank you for the opportunity provided to us to present our proposal for establishment of Chlor alkali manufacturing unit at Plot No.20, JN Pharma City, Parawada, Visakhapatnam District, Andhra Pradesh. The minutes of the SEAC meeting held on 28.09.2021 indicate that our proposal was deferred, and advised JN Pharma City (JNPC) to obtain inclusion of chloralkali sector in the environmental clearance (EC). In this regard we wish to submit the following for your kind consideration; 1. JNPC obtained the environmental clearance vide letter no. J.12011/1/2004-IA (CIE) dt. 10.03.2005 under EIA notification 27.01.1994. It may be noted that industrial estates were included as a sector mandating environmental clearance on July 7, 2004 vide S.O. 801 (E), MoEFCC. The said notification does not discriminate industrial sectors to be established in the estate and mandated EC for all industrial estates. Accordingly JNPC obtained EC for the industrial estate project mentioning chemicals, bulk drugs and pharmaceuticals, and the same incorporates all chemicals both inorganic and organic chemicals. 2. The EIA notification 2006 exempts new EC for all the old industrial estates notified before 2006, accordingly JNPC obtained EC before EIA 2006 notification. EIA notification 2006 explicitly mentioned that industrial estates can be sectorial and or multi product, while the EIA notification 1994 did not make such distinction. 3. When similar issue were raised in the case of M/s. Sree Venkateswara Bio Management Systems (Proposal no. SIAAP/MIS/6/2019) project, the honorable State Expert Appraisal Committee (SEAC) and State Level Environmental Impact Assessment Authority (SEIAA) accepted the clarifications submitted by the proponent and issued the EC. Considering the above, we request you to give us an opportunity to present our case to the honorable SEAC. Thanking You, Yours faithfully For THE ANDHRA SUGARS LIMITED (Chemicals & Fertilizers Division)ADS Letter
(3.)29/03/2022The Committee noted that the Jawaharlal Nehru Pharmacity, Visakhapatnam obtained the Environmental Clearance from the MoEF&CC, GoI, New Delhi for entire Pharmacity to establish chemical, bulk drug and pharmaceutical industries but not obtained EC for Chloro Alkali Industry .The proponent proposed to establish Chloro Alkali Industry in the JN Pharmacity, Visakhapatnam. Hence, the JN Pharmacity, Visakhapatnam has to obtain amendment to the EC to establish Chloro Alkali units in JN Phamacity, Vis
(4.)29/03/2022Dear Sir, ADS Response: We thank you for the opportunity provided to us to present our proposal for establishment of Chlor alkali manufacturing unit at Plot No.20, JN Pharma City, Parawada, Visakhapatnam District, Andhra Pradesh. The minutes of the SEAC meeting held on 28.09.2021 indicate that our proposal was deferred, and advised JN Pharma City (JNPC) to obtain inclusion of chloralkali sector in the environmental clearance (EC). In this regard we wish to submit the following for your kind consideration; 1. JNPC obtained the environmental clearance vide letter no. J.12011/1/2004-IA (CIE) dt. 10.03.2005 under EIA notification 27.01.1994. It may be noted that industrial estates were included as a sector mandating environmental clearance on July 7, 2004 vide S.O. 801 (E), MoEFCC. The said notification does not discriminate industrial sectors to be established in the estate and mandated EC for all industrial estates. Accordingly JNPC obtained EC for the industrial estate project mentioning chemicals, bulk drugs and pharmaceuticals, and the same incorporates all chemicals both inorganic and organic chemicals. 2. The EIA notification 2006 exempts new EC for all the old industrial estates notified before 2006, accordingly JNPC obtained EC before EIA 2006 notification. EIA notification 2006 explicitly mentioned that industrial estates can be sectorial and or multi product, while the EIA notification 1994 did not make such distinction. 3. When similar issue were raised in the case of M/s. Sree Venkateswara Bio Management Systems (Proposal no. SIAAP/MIS/6/2019) project, the honorable State Expert Appraisal Committee (SEAC) and State Level Environmental Impact Assessment Authority (SEIAA) accepted the clarifications submitted by the proponent and issued the EC. Considering the above, we request you to give us an opportunity to present our case to the honorable SEAC. Thanking You, Yours faithfully For THE ANDHRA SUGARS LIMITED (Chemicals & Fertilizers Division)ADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPalachandra M
DesignationCompanySecretary
Name of Company (Applicant Name should not be given here)THE ANDHRA SUGARS LIMITED
AddressThe Andhra sugars Limited, Sy. No.541,545 and 539,Venkatarayapuram industrial area town ship,Venkatarayapuram village,Tanuku mandal,West Godavari District,Andhra Praesh.