Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Laxmi Infobahn Software Technology Park LLP
(b)Name of the Company / Organisation GAR CORPORATION PRIVATE LIMITED
(c)Registered Address 8-2-682, Laxmi Cuber Center, Road No.12, Banjara Hills, Hyderabad,,Hyderabad,Telangana-500034
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Obulreddy Obulreddy
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address 8-2-682, Laxmi Cuber Center, Road No.12, Banjara Hills, Hyderabad,Hyderabad,Telangana-500034
(d)Pin code 500034
(e)E-mail avinash.v@garcorp.in
(f)Telephone No. 40-23303449
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/TG/NCP/57013/2020
(e)Master Proposal Number(Single Window) SW/181621/2020
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 107(P), 108(P)
(b)Pincode 500075
(c)Bounded Latitudes (North)
From
Degree 172412.81
Minutes
Second
From
Degree 172416.48
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 781901.65
Minutes
Second
From
Degree 781959.19
Minutes
Second
(e)Survey of India Topo Sheet No. E44M7(56K/7)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 542
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 5
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaRangareddiRajendranagarKokapet
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number SIA/TG/NCP/57013/2020
(c)Date of Apply of TOR 25 Sep 2020
(d)Date of Issue of TOR / Standard ToR 26 Sep 2020
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As this is Hotel and Commercial Complex comes unde
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Total Built-up Area is - 1,80,313.42 Sq.m1,80,313.42 sq.m
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Total Built-up Area is - 1,80,313.42 Sq.m180313.42Otherssq.mOthersArea
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 15 Sep 2020
(iv)Valid Upto 01 Nov 2020
(v)File No. 0
(vi)Application No. 0
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 240
(b) Funds Allocated for Environment Management (Capital) (in crores) 2.40
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.25
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.26
(e) Funds Allocated for Environment Management Capital(%) 1.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Cement715963.3OthersBagsOpen MarketRoad10 Open MarketCopy of Linkage
(2.)Steel38155.35OthersqtlsOpen MarketRoad30 Open MarketCopy of Linkage
(3.)Sand100544.1Cubic Meter per DayOpen MarketRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube51.833.450.3760
(2.)SO2Micro Gram per Meter Cube25.317.424.4780
(3.)NOxMicro Gram per Meter Cube26.919.326.8180
(4.)PM10Micro Gram per Meter Cube75.852.675.02100
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)Total Hardnessmg/l356239.4200600
(3.)pHNA8.246.286.58.5
(4.)TDSmg/l6844595002000
(5.)Fluoridemg/l0.790.581.01.5
(6.)Chloridesmg/l172.96102.242501000
(7.)Heavy MetalsCoppermg/l0.050.050.051.5
    14.3.     No. of Surface Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l4.84.1B
(2.)CODmg/l4835B
(3.)pHNA7.687.51B
(4.)BODmg/l1713B
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))54.539.655
(2.)Leq(Day)A-weighted decibels(dB(A))61.143.465
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Percent0.0160.010
(2.)pH8.818.25
(3.)K(Potassium)Kilogram per hectare134127
(4.)Electric ConductivityOthersµmhos/cm848264
(5.)P(Phosphorus)Kilogram per hectare4334
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 80 To 250
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 120 To 300
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHMWS&SB5801Copy of Permission LettermodeOthersHMWS&SBOthersHMWS&SB007 Oct 2020580
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic464560STPReuse within the Plant & Recycling464
16.1.
(a)Total Waste Water Generation 464
(b)Total Discharged Water 0
(c)Total Reused Water 464
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Garbage in Kg per dayMunicipal Solid Waste2523.5Tons1RoadOthersSent to solid waste dump site
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube51.800.8652.6660
(2.)SO2Microgram per Meter Cube25.300.425.780
(3.)NOxMicrogram per Meter Cube26.904.3131.2180
(4.)PM10Microgram per Meter Cube75.801.5877.38100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG Sets (6X2250 KVA)Diesel10.01.0NOx2.92
(2.)DG Sets (6X2250KVA))Diesel10.01.0PM100.33
(3.)DG Sets (6X2250 KVA)Diesel10.01.0SO20.085
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 11800
(b)Source TSSPDCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 6X2250
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 1.082
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.082
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 7311.3
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 4176.8
(e)Settlements 15384.9
(f)Industrial 0
(g)Forest 567.7
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Open Scrub 3972.1
    Total 31412.8
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Built Up Area18.03
(2.)Green belt0.128
Total 18.158
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)ESZsNA0NA
(3.)CorridorsNA0NA
(4.)Wildlife CorridorsNA0NA
(5.)NPANA0NA
(6.)WLSNA0NA
(7.)ESAsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestKottaguda RF5.73RF
(2.)Archaeological SitesNA0NA
(3.)Defence InstallationsNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Muskin Cheruvu
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 2.84
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 11396
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 11396
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.128
(b)Percentage of Total Project Area 11.83
(c)No. of Plants to be Planted 100
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProviding Employment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 135.61
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 1
(d)Total plot area (sqm) 10828.4
(e)Total built up area (sqm) 180313.42
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 33.2
    Capacity 2.88
(b)No. of Recharge Pits 11
    Capacity 132.8
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking (Stack car parking) which can accommodate four whe
5.
Energy Saving Measures:
(a)Source/Mode Solar
(b)Percentage 4
(c)Quantity 472
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area NA
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0132
(ii)Name of the EIA Consultant Pridhvi Envirotech Private Limited
(iii)Address 184/C, Lawn House, Vengal Rao Nagar, Hyderabad - 500038, Telangana.
(iv)Mobile No. 9849023662
(v)Landline No. 0404017977
(vi)Email Id info@pridhvienviro.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 03 Jun 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantObulreddy Obulreddy
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)GAR CORPORATION PRIVATE LIMITED
Address8-2-682, Laxmi Cuber Center, Road No.12, Banjara Hills, Hyderabad