Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of “Ashiana Umang”
(b)Name of the Company / Organisation ASHIANA HOUSING LTD
(c)Registered Address 304, Southern Park Building, Saket District Centre, Saket, Delhi,,New Delhi,Delhi-110017
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant SK Palit
(b)Designation (Owner/ Partner/ CEO) VPOperations
(c)Address 304, Southern Park Building, Saket District Centre, Saket, Delhi,,Hauz Khas,South,Delhi-110017
(d)Pin code 110017
(e)E-mail narender.singh@ashianahousing.com
(f)Telephone No. 11-42654265
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/Activity8(b) Townships and Area Development projects.
(c)Category B1
(d)Proposal Number SIA/RJ/MIS/45414/2019
(e)Master Proposal Number(Single Window) SW/122981/2019
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 453,454,454/1,454/2,432,433,478,479,480,484,485, 4
(b)Pincode 302033
(c)Bounded Latitudes (North)
From
Degree 29669790.69
Minutes
Second
From
Degree 2967543.24
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 565370.42
Minutes
Second
From
Degree 565434.95
Minutes
Second
(e)Survey of India Topo Sheet No. 45 N/9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 376
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 7.56
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanJaipurSanganerJhai
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat.8(b)(914
(b)Date of Apply of EC 20 May 2019
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As the proposed project is Building Construction (
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. SCL-RAJ/1629/2019
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Plot Area51213.5227930.779144.22OtherssqmOthersNA
(2.)Built- up Area110207.8274608.67184816.49OtherssqmOthersNA
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)No of floorsS+12B+S+14B+S+14
(2.)No. of Block198- residential, 1 commercial, 1 change room27 buildings+1 club+1 commercial+1 change room
(3.)Dwelling Units9125041416
(4.)Level of Basement011
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 May 2019
(iv)Valid Upto 28 May 2021
(v)File No. 0
(vi)Application No. 242223
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 136.45
(b) Funds Allocated for Environment Management (Capital) (in crores) 1.578
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 1.023
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.05278
(e) Funds Allocated for Environment Management Capital(%) 1.16
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building Construction Material (Sand & other materials)0Otherscftopen marktRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube40.13037.280
(2.)PM10Micro Gram per Meter Cube115.487.7107.6100
(3.)OthersCOMili Gram per Meter Cube1.10.81.04
(4.)PM2.5Micro Gram per Meter Cube49.33445.760
(5.)SO2Micro Gram per Meter Cube13.810.312.880
    14.2.     No. of Ground Water Monitoring Locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Heavy MetalsNimg/l0.00200.020.02
(2.)Total Hardnessmg/l1620132200600
(3.)pHNA7.97.36.58.5
(4.)TDSmg/l41465845002000
(5.)Fluoridemg/l0.410.1411.5
(6.)TSSmg/l0000
(7.)Chloridesmg/l21221502501000
(8.)OthersAlkalinitymg/l568284200600
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.47.2E
(2.)DOmg/l4.54.3E
(3.)BODmg/l706E
(4.)CODmg/l17648E
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))66.446.145-55
(2.)Leq(Day)A-weighted decibels(dB(A))72.349.355-65
    14.5.     No. of Soil Sample Monitored Locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.76.9
(2.)N(Nitrogen)Milligram per Kilogram72.446.8
(3.)P(Phosphorus)Milligram per Kilogram47.925.5
(4.)Electric ConductivityOthersMicrosiemens per centimeter135.955.43
(5.)K(Potassium)Milligram per Kilogram41.216.7
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 7.08 To 84.00
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.15 To 82.8
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTanker Supply9910Copy of Permission LettermodeOthersTankerOtherstanker Supply10126 Sep 201999
(2.)OthersPHED Supply4861Copy of Permission LetterPipelineOthersPHED Supply water-20 Dec 2018685
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)domestic flushing and washing550700STPOthersgardening365185
16.1.
(a)Total Waste Water Generation 550
(b)Total Discharged Water 185
(c)Total Reused Water 365
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Plastic WastePlastic Waste373Tons10RoadAuthorized Recyclers
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.384Kilolitre10RoadAuthorized Recyclers
(3.)Non Biodegradable WasteMunicipal Solid Waste373Tons10RoadAuthorized Recyclers
(4.)E- WasteE Waste0.73Tons10RoadAuthorized Recyclers
(5.)bio degradable wasteMunicipal Solid Waste497.13Tons0Otherswithin complexOthersComposting
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube38.90.250.1539.0560
(2.)PM10Microgram per Meter Cube92.50.250.5593.05100
(3.)NOxMicrogram per Meter Cube31.80.253.335.180
(4.)SO2Microgram per Meter Cube10.90.252.1613.0680
(5.)Others(Specify)COMicrogram per Meter Cube9000.2539034000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG set (320 KVA)LSD48.450.3SO20.09
(2.)DG set (320 KVA)LSD48.450.3PM2.50.01
(3.)DG set (500 KVA)LSD49.350.3PM100.025
(4.)DG set (500 KVA)LSD49.350.3SO20.09
(5.)DG set (500 KVA)LSD49.350.3NOx0.175
(6.)DG Set (500 KVA)LSD49.350.3PM2.50.01
(7.)DG set (320 KVA)LSD48.450.3PM100.025
(8.)DG set (380 KVA)LSD48.750.3NOx0.175
(9.)DG set (380 KVA)LSD48.750.3PM100.025
(10.)DG set (380 KVA)LSd48.750.3SO20.09
(11.)DG set (380 KVA)LSD48.750.3PM2.50.01
(12.)DG set (320 KVA)LSD48.450.3NOx0.175
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 12112
(b)Source Jaipur Vidyut Vitran Nigam Ltd.
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 3 x 500, 1 x 320, 1 x 380
(e)Stack Height (in m) 49.35
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 7.91442
    Total Land 7.91442
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 24814.18
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 91.29
(e)Settlements 5028.17
(f)Industrial 0
(g)Forest 208.52
(h)Mangroves 0
(i)Marine Area 0
(j)Others : scrub land 2756.12
    Total 32898.280000000006
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Otherstotal Plot area7.91442Total Plot area
Total 7.91442
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANone00
(2.)ESAsNone00
(3.)Wildlife CorridorsNone00
(4.)WLSNone00
(5.)ESZsNone00
(6.)CorridorsNone00
(7.)Critically Polluted AreaNone00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNone00
(2.)ForestMuhana Reserve Forest4.99SE direction of project site
(3.)Archaeological SitesNone00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 7.914422
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired -
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Zoological Name- Pavo cristatus, Common Name- Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Drain near Khatwara
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 1.39
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 150
(d)Temporary Employment- During Operation 50
(e)No. of working days 365
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Percentage of Total Project Area16824
(2.)No. of Plants8371941031
(3.)Funds Allocated150000054226206922620
(4.)Total Area of Green Belt12585.236737.3419322
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental24.4 % of total plot area will be developed as green area. This will result in decrease in pollution load.
(2.)SocialEmployment will be generated
(3.)FinancialRevenue will be generated
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 44.85
(b)Total No. of Flats to be Build 1416
(c)No. of Buildings 30
(d)Total plot area (sqm) 79144.22
(e)Total built up area (sqm) 184816.49
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
    Capacity 0
(b)No. of Recharge Pits 27
    Capacity 650.7
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2235 ECU
5.
Energy Saving Measures:
(a)Source/Mode Jaipur Vidyut Vitran Nigam Ltd.
(b)Percentage 6.1
(c)Quantity 734
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area There will be of extraction of ground water.
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Rev. 81, November 2019, Serial No.-116
(ii)Name of the EIA Consultant Perfact Enviro Solutions Pvt. Ltd.
(iii)Address 5th Floor, NN Mall, Mangalam Palace, Sector-3, Rohini, New Delhi, 110085
(iv)Mobile No. 9818362330
(v)Landline No. 0114928136
(vi)Email Id info@perfactgroup.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 21 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSK Palit
DesignationVPOperations
Name of Company (Applicant Name should not be given here)ASHIANA HOUSING LTD
Address304, Southern Park Building, Saket District Centre, Saket, Delhi
Print