Form-1
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1. Basic Informations
Project Name Archi Royal City Company/Organisation Name ARCHI CIVIL CONSTRUCTIONS PVT LTD
Registered Address Ground Floor, Archi Building, 100 ft road, Sobhagpura Circle Rajasthan 313011 Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Rishabh Kumar Bhanawat
(b)Designation (Owner/ Partner/ CEO) DIrector
(c)Address Ground Floor, Archi Building, 100 ft road,,Udaipur,Rajasthan-313011
(d)Pin code 313011
(e)E-mail goyal_deepak22@yahoo.com
(f)Telephone No. 141-4020820
(g)Fax No.
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(a) Building and Construction projects
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/RJ/MIS/137569/2020
(e)Master Proposal Number(Single Window) SW/137567/2020
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type(New/Expansion/Modernization) Fresh EC
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanUdaipurGirwaDholi
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document NILL
Project Profile
Location of the project 1454/1, 1458/1, 1462/1
Town / Village
(Name of more than one town may be entered by separating with)
Dholi Magra Plot/Survey/Khasra No.
(Name of more than one town may be entered by separating with)
1454/1, 1458/1, 1462/1
State Rajasthan District Udaipur
Tehshil Girwa Pincode 313001
Nearest railway station Udaipur Railway Station Distance from the project site 8.5
Nearest airport Maharan Pratap Airport Distance from the project site 12
Nearest Town/City/District Headquarters Udaipur Distance from the project site 9
Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) UIT Upload GPS file Copy of Kml File     
Uploaded GPS file
Shape of the project land Strip Site alternative under consideration(If any) Uploaded Site alternative under consideration
Brief summary of project Uploaded Brief summary of project
Does your project location falls under out of any following areas None of above Areas
Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) 41817.07 Existing Built Up Area(In Meter /Sqr) 2000
Does it attract any of the general conditions given below? No
Does it attract the specific condition given below? No
Interlinked Projects No
Whether separate application of interlinked projects has been submitted? Date of Submission
Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? No
Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? No
Whether the proposal involves approval/clearance under the C.R.Z notification,2011? No
Whether there is any Government Order/Policy relevent/relating to the site? No
Forest land involved(hectares) 0
Is there any litigation pending against the project? No


Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No
1.2 Clearance of existing land, vegetation and buildings? No
1.3 Creation of new land uses? No construction will done only
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes soil has been done
1.5 Construction works? Yes it is building project
1.6 Demolition works? No
1.7 Temporary sites used for construction works or housing of construction workers? Yes housing for construction workers at site
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations No
1.9 Underground works including mining or tunneling? No
1.10 Reclamation works? No
1.11 Dredging? No
1.12 Offshore structures? No
1.13 Production and manufacturing processes? No
1.14 Facilities for storage of goods or materials? No
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes in waste water treatment plant will be installed
1.16 Facilities for long term housing of operational workers? No
1.17 New road, rail or sea traffic during construction or operation? No
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No
1.20 New or diverted transmission lines or pipelines? No
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No
1.22 Stream crossings? No
1.23 Abstraction or transfers of water from ground or surface waters? Yes ground water will be abstracted
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No
1.25 Transport of personnel or materials for construction, operation or decommissioning? No
1.26 Long-term dismantling or decommissioning or restoration works? No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No
1.28 Influx of people to an area in either temporarily or permanently? No
1.29 Introduction of alien species? No
1.30 Loss of native species or genetic diversity? No
1.31 Any other actions? No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No
2.2 Water (expected source & competing users) unit: KLD Yes 110 KLD fresh water from ground water
2.3 Minerals (MT) No
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) No
2.5 Forests and timber (source – MT) No
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) No
2.7 Any other natural resources (use appropriate standard units) No
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No
3.3 Affect the welfare of people e.g. by changing living conditions? Yes project will provide jobs to local
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No it will not demolish any ones house
3.5 Any other causes No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) Yes Domestic Waste will generated and collected at site and will be disposed in municipal vain
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No
4.4 Other industrial process wastes No
4.5 Surplus product No
4.6 Sewage sludge or other sludge from effluent treatment Yes sewage sludge will be disposed at the authorized land with prior permission
4.7 Construction or demolition wastes No
4.8 Redundant machinery or equipment No
4.9 Contaminated soils or other materials No
4.10 Agricultural wastes No
4.11 Other solid wastes No
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources No
5.2 Emissions from production processes No
5.3 Emissions from materials handling including storage or transport No
5.4 Emissions from construction activities including plant and equipment No
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No
5.6 Emissions from incineration of waste No
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No
5.8 Emissions from any other sources Yes DG Set and vehicles
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers No
6.2 From industrial or similar processes No
6.3 From construction or demolition No
6.4 From blasting or piling No
6.5 From construction or operational traffic No
6.6 From lighting or cooling systems No
6.7 From any other sources No
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No no water will be discharged outside premises, excess treated water will be utilized in house in flushing and gardening
7.3 By deposition of pollutants emitted to air into the land or into water No
7.4 From any other sources No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No
8.2 From any other causes No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No
9.2 Lead to after-use of the site, which could have an impact on the environment No
9.3 Set a precedent for later developments No
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Bordi RF at 1.5 Kamlodia RF at 3
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Fateh Sagar at 7.8 Pichhola at 8.5
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Yes Begra Magra RF at 3.5 Panwari RF at 3.5
4 Inland, coastal, marine or underground waters No
5 State, National boundaries No
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH-27 in front of project
7 Defence installations No
8 Densely populated or built-up area Yes Pratap Nagar at 3.00 Fatehsagar at 6.00
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Hospital in Pratap nagar at 6 School in Dholi at 1
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? Yes
6. Upload EIA Report
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)27/01/2020The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:-EDS Letter
(2.)27/01/2020The correction have been made as per the instruction received
(3.)28/01/2020Please upload the documents as asked in EDS generated earlier.
(4.)28/01/2020The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRishabh Kumar Bhanawat
DesignationDIrector
Name of Company (Applicant Name should not be given here)ARCHI CIVIL CONSTRUCTIONS PVT LTD
AddressGround Floor, Archi Building, 100 ft road,
Print