Project Name Proposed Affordable Housing Project “Ashirwad Residency” under provision 3A of CMJAY 2015 at Khasra No. 1839/702, Vill Radhakishanpura, Tehsil & Dist. Sikar (Rajasthan) of M/s. Ashirwad Builders & Dev Company/Organisation Name MS ASHIRWAD BUILDERS AND DEVELOPERS
Registered Address Prem Nagar, Radhakishanpura, Sikar Rajasthan 332001 Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Vijay Kumar Saini
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Khasra No. 1839/702, Vill Radhakishanpura, Tehsil Dist Sikar,,Sikar,Sikar,Rajasthan-332001
(d)Pin code 332001
(e)E-mail ashirwadresidency8a@outlook.com
(f)Telephone No. 141-2983404
(g)Fax No.
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(a) Building and Construction projects
(b)Minor Project/Activity8(a) Building and Construction projects
(c)Category B2
(d)Proposal Number SIA/RJ/MIS/119876/2019
(e)Master Proposal Number(Single Window) SW/119875/2019
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type(New/Expansion/Modernization) Fresh EC
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanSikarSikarRadhakisanpura
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document NILL
Project Profile
Location of the project Khasra No. 1839/702, Vill Radhakishanpura, Tehsil & Dist. Sikar (Rajasthan)
Town / Village
(Name of more than one town may be entered by separating with)
Sikar District Plot/Survey/Khasra No.
(Name of more than one town may be entered by separating with)
Khasra No. 1839/702
State Rajasthan District Sikar
Tehshil Sikar Pincode 332001
Nearest railway station Sikar Distance from the project site 2.7
Nearest airport Jaipur airport Distance from the project site 125
Nearest Town/City/District Headquarters Sikar Distance from the project site 2.5
Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) Zila Parishad Sikar (~3.0 km in W direction) Add.: Opposite Santoshi Mata Mandir, Devipura, Sikar, Rajasthan 332001 Upload GPS file Copy of Kml File     
Uploaded GPS file
Shape of the project land Block (Polygon) Site alternative under consideration(If any) Uploaded Site alternative under consideration
Brief summary of project Uploaded Brief summary of project
Does your project location falls under out of any following areas None of above Areas
Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) 21250.32 Existing Built Up Area(In Meter /Sqr) 0
Does it attract any of the general conditions given below? No
Does it attract the specific condition given below? No
Interlinked Projects No
Whether separate application of interlinked projects has been submitted? Date of Submission
Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? No
Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? No
Whether the proposal involves approval/clearance under the C.R.Z notification,2011? No
Whether there is any Government Order/Policy relevent/relating to the site? No
Forest land involved(hectares) 0
Is there any litigation pending against the project? No


Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes The proposed project is an Affordable Housing Project on 6086 sq. m. total plot area. There will be green-area development on area 914.25 sq. m. (15.02% of total plot area) to provide beautiful and natural environment to the site.
1.2 Clearance of existing land, vegetation and buildings? No None
1.3 Creation of new land uses? Yes The proposed project is an Affordable Housing Project on 6086 sq. m. total plot area. There will be green-area development on area 914.25 sq. m. (15.02% of total plot area) to provide beautiful and natural environment to the site.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil investigation was carried out and the results were found satisfactory.
1.5 Construction works? Yes The construction activities will be confined within the project site; there will be no physical changes due to project development activities outside the project boundary.
1.6 Demolition works? No None
1.7 Temporary sites used for construction works or housing of construction workers? Yes The construction activities will be confined within the project site only. Temporary local hutments will be provided to the workers including all the domestic facilities during construction phase.
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations Yes Excavation will be carried out for foundation and leveling. The total soil generated through digging will be used at the site itself for the purpose of development of project site and horticultural development.
1.9 Underground works including mining or tunneling? No No underground works including mining / tunneling is required except excavation of soil is required to be carried out for the purpose of construction.
1.10 Reclamation works? No No reclamation work required.
1.11 Dredging? No No dredging required, as case of construction of new Affordable Housing project.
1.12 Offshore structures? No No offshore structures required.
1.13 Production and manufacturing processes? No Since, it is a construction of residential project, hence, no production / manufacturing process shall be done in the project premises.
1.14 Facilities for storage of goods or materials? Yes Separate raw material storage yard will be made during construction phase: • Cement will be separately stored under cover. • Sand will be stacked neatly under tarpaulin cover. • Bricks and steel will be laid in open. • The raw material handling yard will be located within the project site and separated by enclosures.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste During operation Phase: The solid waste generated from the project will be domestic in nature which will be given to authorized vendors. Liquid Effluent During operation phase: • Waste water generated will be treated in the Sewage Treatment Plant (STP). • Treated water will be recycled & reused for flushing and gardening purpose. • Dewatered/ dried sludge from STP will be used as manure in horticulture after proper digestion.
1.16 Facilities for long term housing of operational workers? No No facilities for long term housing of operational worker are proposed as this is construction project for construction worker temporary local hutments will be provided to the workers including all the domestic facilities during construction phase.
1.17 New road, rail or sea traffic during construction or operation? No The project site is well connected by network of roads leading to various parts of state. Thus, no new road will be laid during construction or operation of the project activities except internal roads & pathways for smooth movement of Vehicles & personals.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No The proposed site is well connected by roads to whole of the city.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No There will be no need for diversion or closure of existing traffic routes.
1.20 New or diverted transmission lines or pipelines? No There will not be any provision for new or diverted transmission lines or pipelines for proposed project.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No None
1.22 Stream crossings? No No river or drain is passing through the project site.
1.23 Abstraction or transfers of water from ground or surface waters? Yes Total water requirement of proposed project will be met by fresh water and treated water. Waste water generated will be treated in STP. The fresh water requirement of the project will be reduced by adopting Water Conservation Measures in proposed construction project. The water will be sourced from Ground Water after obtaining permission for the same from the authority.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? Yes Runoff will increase due to increased paved surface. However, increased runoff will be managed by well-designed rain water harvesting system and storm water management plan.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transport of personnel/ material during construction and operation phase are envisaged. Road network for smooth flow of traffic and adequate parking space will be provided for operational phase.
1.26 Long-term dismantling or decommissioning or restoration works? No No long term dismantling/ decommissioning is Proposed.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No No long term dismantling/ decommissioning is Proposed.
1.28 Influx of people to an area in either temporarily or permanently? Yes All the workers employed / hired will be from nearby areas. Hence, there will be minor influx of people in the area. Temporarily approx. 100-150 influx of labours at site during the construction phase. Since the proposed project is of Affordable Group housing, thus permanent influx of people will be there.
1.29 Introduction of alien species? No The landscaping will be carried out with mainly local species with a few ornamented varieties of flora that are well suited to the local condition.
1.30 Loss of native species or genetic diversity? No No loss of native species or genetic diversity has been reported so far.
1.31 Any other actions? No No other action will be undertaken except the above mentioned for proposed construction project.
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes The proposed project is an Affordable Housing Project on 6086 sq. m. total plot area. There will be green-area development on area 914.25 sq. m. (15.02% of total plot area) to provide beautiful and natural environment to the site.
2.2 Water (expected source & competing users) unit: KLD Yes Total water requirement of proposed project will be met by fresh water and treated water. Waste water generated will be treated in STP. The fresh water requirement of the project will be reduced by adopting Water Conservation Measures in proposed construction project. The water will be sourced from Ground Water after obtaining permission for the same from the authority.
2.3 Minerals (MT) Yes Sand and stone aggregates will be used as Construction material.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes The conventional construction material will be used. Energy efficient building materials will be used as specified in the Energy Conservation Building Code. The major materials used for the construction of the proposed project shall be steel, cement, bricks, metal, flooring tiles/stones, sanitary and hardware items, electrical fittings and water etc. Source: Steel and cement will be procured from authorized vendors. Sand & aggregate will be procured from local material suppliers.
2.5 Forests and timber (source – MT) Yes Timber required will be taken from nearby markets.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Electricity will be sourced from Govt. supply.
2.7 Any other natural resources (use appropriate standard units) No No other natural resource will be involved in the project except the mentioned above.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No The proposed project is an affordable Housing project, and hence no storage of hazardous chemicals (as per MSIHC rules) will be done.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Suitable drainage and waste management measures will be adopted in both construction and operational phase, which will restrict the stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Socio-economic standard of people will increase due to increase employment opportunity provided by this project. This will lead to better quality of life and will also set a standard for future development in the area.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No effect is envisaged due to this project, as this is a housing Project.
3.5 Any other causes No No, other causes are involved except the mentioned above.
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No No such spoil, overburden, or mine wastes will be generated as this is a Group Housing Project. There will be excavation activity done for construction of building. The total soil generated will be used at the site itself for the purpose of horticulture, landscaping, Backfilling activities.
4.2 Municipal waste (domestic and or commercial wastes) Yes The solid waste generated from the project will be domestic in nature which will be given to authorized vendors.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No Production of Hazardous wastes is not envisaged due to this project, as this is a housing Project.
4.4 Other industrial process wastes No Not applicable, as this is a building construction project.
4.5 Surplus product No Not applicable, as this is a building construction project.
4.6 Sewage sludge or other sludge from effluent treatment Yes Dewatered/ dried sludge from STP will be used as manure in horticulture after proper digestion
4.7 Construction or demolition wastes Yes Construction waste generation will be limited to the construction phase only and will be limited to project site only. These will be reused for backfilling after manual segregation. Unusable and excess construction debris will be disposed at designated places in tune with the local norms. These wastes will be used for road development activities.
4.8 Redundant machinery or equipment No No Redundant machinery or equipment is involved.
4.9 Contaminated soils or other materials No No Contaminated soils or other materials are involved.
4.10 Agricultural wastes No No agricultural waste will be generated during construction phase.
4.11 Other solid wastes No Not applicable, as this is construction of Group Housing project.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes The operation of proposed project does not envisage any major air pollutant generating sources vehicular movement. The Pollution generated from the vehicular movement will be kept in check by regular maintenance of vehicle & Local native plants will be used in tree plantation all around the project site and road side to reduce the impact of pollution.
5.2 Emissions from production processes No No production process involved. Hence, there will be no such emission.
5.3 Emissions from materials handling including storage or transport Yes Small quantity of fugitive emission is envisaged during transport and handling of construction material. Such emission will be temporary and controlled by providing water sprinkling and other viable technique. Regular water sprinkling & tarpaulin covers will be provided to prevent dust emissions.
5.4 Emissions from construction activities including plant and equipment Yes This will be restricted to the construction phase and to the construction site only. Though, it will be negligible in amount as it will occur from the equipments movement involved in the construction, still suitable preventive measure will be taken.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust is likely to be generated during construction. Water sprinkler and tarpaulin covers will be provided over stored raw material to reduce dust emission. On site sanitation facilities will be provided for construction workers during construction phase. Hence, no odor generation is envisaged.
5.6 Emissions from incineration of waste No Not applicable, as this is Group Housing project and there will be not any incineration waste involved in this project.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not applicable, as this is a Group Housing project. So, Open burning of biomass / other material will be prohibited.
5.8 Emissions from any other sources No No other Emissions from any other sources, except mentioned above.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes The machinery which will be used for construction will be of high standard and will adhere to international standard. These standards itself take care of noise pollution control / vibration control and air emission control. Hence insignificant impacts due to construction machinery are envisaged. Apart from this, the construction activities will be restricted to daytime only.
6.2 From industrial or similar processes No Not applicable, as this is Group Housing project.
6.3 From construction or demolition Yes Due to the various construction activities, there will be short-term noise impacts in the immediate vicinity of the project site. The construction activities will include the following noise generating activities: • Excavation activities • Concreting and mixing • Construction work • Heavy vehicle movement
6.4 From blasting or piling No No blasting or mechanized piling will be done as this a building construction project.
6.5 From construction or operational traffic No Some noise will be generated from vehicular movement in the construction and operational phase. Local native plants will be used in tree plantation all around the project site and road side to reduce the impact of the air and Noise pollution.
6.6 From lighting or cooling systems No No significant noise impact will result from lightening or cooling system.
6.7 From any other sources No There will be no other sources for noise & vibration generation except the mentioned above.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No Usage of Hazardous materials is not envisaged due to this project, as this is a housing Project.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No There will be no discharge of untreated sewage on land. Adequate treatment of sewage will be carried out in STP for entire land area, proposed within the project premises. Treated sewage will be reused for flushing & green area development.
7.3 By deposition of pollutants emitted to air into the land or into water Yes Minor Air emissions will be generated due to increased vehicular movement for which effective measures will be taken like adequate greenbelt development. So there would not be any deposition of pollutants emitted to air, land or water.
7.4 From any other sources No No any other sources are involved except the mentioned above.
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Likelihood of such an event is not foreseen till now in the area and suitable measures will be adopt to control and reduce emission, so that there will be no such risk in the coming future.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No This is a Housing project and does not involve major hazardous construction activity. Hence chances of explosions, spillages, fires etc. are minimal. During construction, suitable personal protective equipment will be provided to all construction workers as required under the health & safety norms. Awareness & Training about safety norms will be provided to all the supervisors and construction workers involved in construction activities.
8.2 From any other causes No No any other causes are involved except the mentioned above.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The area is not prone to flood, landside. There has been no report of earth quake or cloud burst in the area. Structural design has been done to take care of Seismic Zone requirements.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The proposed project is for Residential use; it may lead to development of supporting services and infrastructure in and around the area.
9.2 Lead to after-use of the site, which could have an impact on the environment No Negligible impact is envisaged on air, noise and aesthetic parameters due to the proposed project.
9.3 Set a precedent for later developments No Not applicable
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not applicable
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Not located within 15 km of the proposed project location
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Water Bodies: • Sobawati Nadi (~13.2 km in SE) Forests: • Sikar PF (~5.3 km in W) • Devgarh PF (~6.1 km in SSE) • Habshnath Block PF (~10.2 km in S) • Rewasa PF (~7.3 km in SE)
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Not located within 15 km of the proposed project location
4 Inland, coastal, marine or underground waters No Not located within 15 km of the proposed project location
5 State, National boundaries No Not located within 15 km of the proposed project location
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes • SH 37B (~0.5 km in E) • SH 8 (~2.8 km in N) • SH 7 (~6.0 km in WSW) • SH 8A (~5.2 km in SSW) • SH 20 (~9.4 in WNW)
7 Defence installations Yes Not located within 15 km of the proposed project location
8 Densely populated or built-up area Yes Sikar (~2.7 km in W) Dujod (~7.5 in SSW)
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes All necessary facilities are available in Sikar District.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes Water Bodies: • Sobawati Nadi (~13.2 km in SE) Forests: • Sikar PF (~5.3 km in W) • Devgarh PF (~6.1 km in SSE) • Habshnath Block PF (~10.2 km in S) • Rewasa PF (~7.3 km in SE)
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No No Environmental damage has been reported from the area so far. All parameters of Air, Water, and Noise etc. will be maintained within permissible limits specified by SPCB / CPCB with proper mitigation measures.
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No The area under study falls in Zone-II, according to the Indian Standard Seismic Zoning Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structures to mitigate the seismic impacts. There are no possibilities of the proposed project site getting flooded as per records available.
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVijay Kumar Saini
DesignationPartner
Name of Company (Applicant Name should not be given here)MS ASHIRWAD BUILDERS AND DEVELOPERS
AddressPrem Nagar, Radhakishanpura, Sikar
Print