Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) SAND STONE MINING PROJECT
(b)Name of the Company / Organisation DEVI BAI
(c)Registered Address SMT. DEVI W/o SHRI ANOP RAM, N/V- DERIYA & PABUNAGAR, TEHSIL- BALESAR, DISTRICT- JODHPUR, RAJASTHAN,,Jodhpur,Rajasthan-342306
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant DEVI BAI
(b)Designation (Owner/ Partner/ CEO) OWNER
(c)Address DHOLIYA NAGAR, KHETASAR, TEHSIL- OSIYA, DISTRICT- JODHPUR,,Osian,Jodhpur,Rajasthan-342303
(d)Pin code 342303
(e)E-mail devianop1234@gmail.com
(f)Telephone No. 141-4036199
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B2
(d)Proposal Number SIA/RJ/MIN/44281/2019
(e)Master Proposal Number(Single Window) SW/120620/2019
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. PLOT NO-29, KHASRA NO- 530 & 166
(b)Pincode 342303
(c)Bounded Latitudes (North)
From
Degree 26.581535
Minutes
Second
From
Degree 72.608291
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 26.581740
Minutes
Second
From
Degree 72.609434
Minutes
Second
(e)Survey of India Topo Sheet No. 45 B/10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 300
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 3.0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanJodhpurbalesarDERIYA & PABUNAGAR
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SW/120620/2019
(b)Date of Apply of TOR 04 Oct 2019
(c)Date of Issue of TOR / Standard ToR 04 Oct 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason THIS IS A B2 CATEGORY PROJECT
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Generator-----Diesel
(2.)Mobile Crane40 tonesDiesel
(3.)CompressorCPS--325Diesel
(4.)Jack Hammer6-7 Kgf/cm2Compressed Air
(5.)Wire Saw60 HPDiesel
(6.)ExcavatorBucket Capacity (1.5 cum)Diesel
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)SAND STONE53775Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 04 Oct 2019
(iv)Valid Upto 04 Oct 2019
(v)File No. SIA/RJ/MIN/44281/2019
(vi)Application No. SW/120620/2019
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.30
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.0115
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.0070
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.0115
(e) Funds Allocated for Environment Management Capital(%) NaN
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 400
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 400
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel400Tons per AnnumN/ARoad2.0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 09 May 2019 To 13 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube22.5022.5022.5080
(2.)PM10Micro Gram per Meter Cube71.6871.6871.68100
(3.)PM2.5Micro Gram per Meter Cube35.0535.0535.0560
(4.)SO2Micro Gram per Meter Cube14.0614.0614.0680
    14.2.     No. of Ground Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOthersOTHER7.277.276.58.5
(2.)TSSmg/l0.000.0001.03.0
(3.)Fluoridemg/l0.570.571.01.5
(4.)Total Hardnessmg/l315.24315.24200600
(5.)Chloridesmg/l132.25132.252501000
(6.)OthersCALCIUMmg/l75.1075.1075200
(7.)TDSmg/l690.0690.05002000
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHOthersOTHER0.000.00A
(2.)DOmg/l0.000.00A
(3.)CODmg/l0.000.00A
(4.)BODmg/l0.000.00A
    14.4.     No. of Ambient Noise Monitoring Locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))66.166.175
(2.)Leq(Night)A-weighted decibels(dB(A))52.852.870
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram408.56408.56
(2.)P(Phosphorus)Milligram per Kilogram318.50318.50
(3.)Electric ConductivityMillisiemens per Centimetre0.470.47
(4.)pHOthersOTHER7.687.68
(5.)K(Potassium)Milligram per Kilogram134.74134.74
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 60 To 65
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 65 To 70
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater5.02.0Copy of Permission LettermodeOtherswater tanker from near by villageOthersOTHERN/A04 Oct 20190.00
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)N/A0.000.00N/AOthersOTHER0.000.00
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)N/AOthersOTHER0.00Tons0.00RoadOthersROAD MAINTENANCE
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube71.682.071.680.01100
(2.)PM2.5Microgram per Meter Cube35.052.035.050.0160
(3.)SO2Microgram per Meter Cube14.060.0014.060.0280
(4.)NOxMicrogram per Meter Cube22.502.022.500.0280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)N/A0.000.000.00PM10,SO2,NOx0.00
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0.00
(b)Source N/A
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) N/A
(e)Stack Height (in m) 0.00
20.
Land Ownership Pattern:
(a)Forest Land 0.00
(b)Private Land 0.00
(c)Government Land 0.00
(d)Revenue Land 0.00
(e)Other Land 1.00
    Total Land 1.00
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0.00
(b)Waste/Barren Land 0.00
(c)Grazing/ Community Land 0.0
(d)Surface Water Bodies 0.00
(e)Settlements 0.00
(f)Industrial 0.00
(g)Forest 0.00
(h)Mangroves 0.0
(i)Marine Area 0.00
(j)Others : MINING LEASE AREA 1.00
    Total 1
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant0.00----
(2.)Township0.00---
(3.)Green belt0.00----
(4.)Ash Pond0.00----
(5.)Quarry Area0.00----
(6.)OB Dump Area0.00----
(7.)Safety Zone0.00----
(8.)Tailing Pond0.00----
(9.)LandFill0.00----
(10.)Water Reservoir0.00---
(11.)Desalination Plant0.00-----
(12.)Area for Solid Waste Management0.00----
(13.)Built Up Area0.00----
(14.)OthersMINING LEASE1.00---
Total 1
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSN/A0.00NONE WITHIN 10 KM RADIUS
(2.)ESZsN/A0.00NONE WITHIN 10 KM RADIUS
(3.)Critically Polluted AreaN/A0.00NONE WITHIN 10 KM RADIUS
(4.)CorridorsN/A0.00NONE WITHIN 10 KM RADIUS
(5.)NPAN/A0.00NONE WITHIN 10 KM RADIUS
(6.)Wildlife CorridorsN/A0.00NONE WITHIN 10 KM RADIUS
(7.)ESAsN/A0.00NONE WITHIN 10 KM RADIUS
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsN/A0.00NONE WITHIN 10 KM RADIUS
(2.)ForestN/A0.00NONE WITHIN 10 KM RADIUS
(3.)Archaeological SitesN/A0.00NONE WITHIN 10 KM RADIUS
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0.00
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.00
(b)Land yet to be acquired(Ha) 0.00
(c)Status of Land acquisition if not acquired 0.00
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0.00
(b)No. of Households 0.00
(c)No. of PDFs (Project Displaced Families) 0.00
(d)No. of PAFs (Project Affected Families) 0.00
(e)Funds Allocated for R&R(in Rs) 0.00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area BOI NADI
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 3.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 11
(e)No. of working days 300
(f)Total Manpower 26
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.33
(b)Percentage of Total Project Area 33.00
(c)No. of Plants to be Planted 132
(d)Funds Allocated for Plantation 0.079
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialTAXES, ROYALTY, CESS ETC.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)sand stoneMinor
2.
Mine Capacity in ROM (Run of Mine) 53775
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. SME/JO/CC/BALESAR/MINOR/PLOT NO /29/2018/5561
(b)Date of Approval 12 Oct 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department State
(e)Approved Mining Lease Area 1.00
(f)Approved Capacity 53775
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 593750
(b)Mineable Reserves (Million Ton) 348828
(c)Extractable Reserves(Million Ton) 348828
(d)Percent(%) of Extraction 50
(e)Grade of Coal /Ore /Mineral 0.00
(f)Stripping Ratio 9 : 1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) N/A
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 8
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1.00
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 06 Jul 2018
(iii)Validity of LOI 1.5
(iv)Reference No. of LOI AME/JODH/CC/BALE/MINOR/PLOT NO/29/2018/2049
(c)Whether Lease Deed Executed ? No
(i)Reason thereof LEASE DEED WILL BE EXECUTED AFTER GEETING EC
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof THERE IS NO NEED TO RENEWED LEASE DEED IN ABSENCE
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0.00
(ii)Total Area (in Hectare) 0.00
(iii)Height (in meter) 0.00
(iv)Quantity (in Million Cubic meter) 0.00
(v)No. of year back fill up 0.00
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0.00
(ii)Total Area (in Hectare) 0.00
(iii)Height (in meter) 0.00
(iv)Quantity (in Million Cubic meter) 0.00
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.00
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.00
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0.00
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0.00
(b)Depth (in meter) 0.00
(c)Volume (in Million Cubic meter) 0.00
12.
Details of Quarry:
(a)Final Void of 0.00 (hectare) at a Depth of 0.00 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0.00
13.
Details of Transportation:
(a)In Pit/Underground to Surface 0.00
(b)Surface to Siding/Loading 0.00
(c)Transportation / Conveyor Details 0.00
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND0.000.000
(2.)SETTLEMENTS0.000.000
(3.)FOREST LAND0.000.000
(4.)WASTE LAND0.000.000
(5.)GRAZING LAND0.000.000
(6.)SURFACE WATER BODIES0.000.000
TOTAL000
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0.000.58750.000.5875
(2.)TOP SOIL STORAGE0.000.000.000
(3.)INTERNAL OB DUMPS0.000.000.000
(4.)EXTERNAL OB DUMPS0.000.000.000
(5.)ROADS0.000.000.000
(6.)BUILT UP AREA (COLONY/OFFICE)0.000.000.000
(7.)GREEN BELT0.330.000.000.33
(8.)VIRGIN AREA0.000.000.08250.0825
TOTAL0.330.58750.082501
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0.00
(b)Internal Dump(in hectare) 0.00
(c)Quarry(in hectare) 0.00
(d)Safety Zone(in hectare) 0.00
(e)Final Void of 0.00 (hectare) at a Depth of 0.00 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 0.00
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0.00
(h)Total afforestation plant (in hectare) 0.00
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20180.000.000.000.000.00
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/IA 0015
(ii)Name of the EIA Consultant RAMJI MINES ENVIROTECH
(iii)Address 22 - AARNA 2 TOWER, KARTARPURA INDUSTRIAL AREA, 22 GODOWN, JAIPUR, RAJASTHAN
(iv)Mobile No. 9799744347
(v)Landline No. 0141403619
(vi)Email Id rme.envirotech@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 09 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)14/10/2019After examination of the proposal, following discrepancies are found:- 1. Affidavit regarding violation of EIA notification and regarding correctness of submitted data & documents by consultant as well as by PP not submitted.
(2.)31/10/2019The correction have been made as per the instruction received
(3.)08/11/20191. Affidavit regarding violation of EIA notification and regarding correctness of submitted data & documents by consultant as well as by PP not submitted.
(4.)13/11/2019The correction have been made as per the instruction received
(5.)13/11/20191. Affidavit regarding violation of EIA notification and regarding correctness of submitted data & documents by consultant as well as by PP not submitted.
(6.)13/11/2019The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDEVI BAI
DesignationOWNER
Name of Company (Applicant Name should not be given here)DEVI BAI
AddressSMT. DEVI W/o SHRI ANOP RAM, N/V- DERIYA & PABUNAGAR, TEHSIL- BALESAR, DISTRICT- JODHPUR, RAJASTHAN
Print