Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Enhancement in production capacity {China Clay from 5000 TPA to 17,58,163 TPA) and Quartz (from 2000 TPA (ROM) to 10,829 TPA)} & Transfer of EC with Mine Lease Area 61.0 Ha. at Near village – Lohari K
(b)Name of the Company / Organisation BR MINERALS
(c)Registered Address Village Lohari Khurd (Deva Ka Khera) Tehsil Hindoli District Bundi State Rajasthan,,Bundi,Rajasthan-323001
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Ratneshwar Kumar Maheshwari
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Suzuki Textiles Village Gudda,PO Mandal Distt. Bhilwara,Bhilwara,Bhilwara,Rajasthan-311403
(d)Pin code 311403
(e)E-mail brminerals165@gmail.com
(f)Telephone No. 124-4291036
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B1
(d)Proposal Number SIA/RJ/MIN/43210/2000
(e)Master Proposal Number(Single Window) SW/118689/2019
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No.
(b)Pincode
(c)Bounded Latitudes (North)
From
Degree
Minutes
Second
From
Degree
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree
Minutes
Second
From
Degree
Minutes
Second
(e)Survey of India Topo Sheet No.
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL)
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area
(j)Seismic Zone
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanBundiHindoliLohari Khurd (Deva Ka Khera)
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/349/2007-IA.II(M)
(b)Date of Apply of EC 07 Jun 2000
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :20 Jun 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :22 Jul 2019
Distance of Public Hearing Venue from the Proposed Project :1.80
Atal Seva Cendra, at Gram Pnchayat, Deva Ka Khera, Tehsil-Hindoli, Dist-Bundi (Rajasthan)
State :Rajasthan
District :Bundi
Tehsil :Hindoli
Village :DEVA KA KHERA
50Public Hearing is conducted on dated 22/07/2019 at Rajeev Gandhi Seva Cendra, at Alniya, Bundi in the chairmanship of ADM Bundi. The advertising regarding the public hearing is given in two news paperOthers
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By NIL
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on NIL
(iii)Letter No.
(iv)Status of Compliance
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)MINERAL CHINA CLAY500017531631758163Tons per Annum(TPA)Road
(2.)MINERAL QUARTZ2000882910829Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Excavator156Capacity 300 pc
(2.)Dumber3172030 tons
(3.)Diesel Pump (Dewatering)14515 HP
(4.)Jack Hammer281033 mm dia
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ?
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue NA
(iv)Valid Upto NA
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores)
(b) Funds Allocated for Environment Management (Capital) (in crores)
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores)
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores)
(e) Funds Allocated for Environment Management Capital(%)
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 500
(b)Existing quantity of raw material/fuel 200
(c)Total quantity of raw material/fuel 700
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD700OthersKLNEAR MARKETRoad1.8 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube26.0517.9625.8380
(2.)PM2.5Micro Gram per Meter Cube40.028.2239.2460
(3.)PM10Micro Gram per Meter Cube80.6051.2076.86100
(4.)SO2Micro Gram per Meter Cube14.08.013.5580
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.907.086.58.5
(2.)TSSmg/l21110
(3.)TDSmg/l8583605002000
(4.)Total Hardnessmg/l389220.42200600
(5.)Heavy MetalsIRONmg/l0.310.200.300.30
(6.)Fluoridemg/l0.760.3411.50
(7.)Chloridesmg/l190.3570.502501000
    14.3.     No. of Surface Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l12.301E
(2.)CODmg/l38.016.0E
(3.)pHNA7.907.40E
(4.)DOmg/l5.85.0E
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))65.256.175
(2.)Leq(Night)A-weighted decibels(dB(A))44.839.170
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.907.50
(2.)N(Nitrogen)Kilogram per hectare268215
(3.)P(Phosphorus)Kilogram per hectare29.8725.50
(4.)Electric ConductivityMillisiemens per Centimetre0.450.24
(5.)K(Potassium)Kilogram per hectare206.0126.0
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 280 To 285
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 285 To 290
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTANKER WATER SUPPLY58.01.80 Not Appliacble modeOthersTANKER WATER SUPPLYOthersTANKER WATER SUPPLYNA01 Sep 201958
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)NOT ANY00NAOthersNOT ANY00
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)SOLID WASTEOthersMINERAL WASTE595603Tons0RoadOthersSOLD TO END USER
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube42.6000.0003942.6003960
(2.)SO2Microgram per Meter Cube14.02500.00214.02780
(3.)NOxMicrogram per Meter Cube26.0500.008026.05880
(4.)PM10Microgram per Meter Cube77.8600.1978.05100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source 0
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 61.0
    Total Land 61.0
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : MINE LEASE AREA 61.0
    Total 61
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersFOR MINING ACTIVITY61.0NA
Total 61
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NOT ANY
(2.)WLSNA0NOT ANY
(3.)ESZsNA0NOT ANY
(4.)ESAsNA0NOT ANY
(5.)CorridorsNA0NOT ANY
(6.)NPANA0NOT ANY
(7.)Wildlife CorridorsNA0NOT ANY
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestDeva ka Khera PF0.25NA
(2.)Defence InstallationsNOT ANY0NA
(3.)OthersAGRICULTURE AREANOT ANY0NA
(4.)Archaeological SitesNOT ANY0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl (Pavo cristatus)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 15 LAKHS
(iii)Period of Implementation 5 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Danta Sagar
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 9.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 62
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 62
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt2.0118.1220
(2.)Percentage of Total Project Area3.3029.8032
(3.)No. of Plants10001148012480
(4.)Funds Allocated2.01315
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialEMPLOYMENT GENERATION
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 2
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CHINA CLAYMinor
(2.)QUARTZMinor
2.
Mine Capacity in ROM (Run of Mine) 1768992
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 5235
(b)Date of Approval 21 Dec 2017
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department State
(e)Approved Mining Lease Area 61.0
(f)Approved Capacity 1768992
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 25246277
(b)Mineable Reserves (Million Ton) 20622208
(c)Extractable Reserves(Million Ton) 20622208
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral 52
(f)Stripping Ratio 1 : 0.3
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 12
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 61.0
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof SANCTIONED LEASE
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 61.0
(iii)Validity of the lease deed From : 23 Nov 2001 To : 22 Nov 2051
(iv)Date of Execution of Mining Lese 16 Feb 2015
(v)Reference Number 776
(d)Whether Lease Deed Renewed ? Yes
     8.1.    Earlier Renewals:
S. No.Lease Details Date of Renewal Period Copy of Earlier Lease Letter No.Area Remarks
(1.)Transfer 30 Oct 2013 From : 23 Nov 2001 To : 22 Nov 2051 Copy of Earlier Lease49 61.0 NA
(2.)Initial 01 Jan 1900 From : 19 Nov 2001 To : 18 Nov 2031 Copy of Earlier Lease2746 61.0 NA
(3.)Renewal 30 Dec 2010 From : 23 Nov 2001 To : 22 Nov 2031 Copy of Earlier Lease1975 61.0 NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 42.10
(b)Depth (in meter) 35
(c)Volume (in Million Cubic meter) 421000000
12.
Details of Quarry:
(a)Final Void of 42.10 (hectare) at a Depth of 35 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 61.0
13.
Details of Transportation:
(a)In Pit/Underground to Surface from pits
(b)Surface to Siding/Loading by ecxavator
(c)Transportation / Conveyor Details transported to end user by trucks/dumpers
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND000
(2.)GRAZING LAND000
(3.)OTHERS(Specify)gair mumkin pahar61.0061
(4.)SURFACE WATER BODIES000
(5.)AGRICULTURE LAND000
(6.)WASTE LAND000
(7.)SETTLEMENTS000
TOTAL61061
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY042.10042.1
(2.)EXTERNAL OB DUMPS0000
(3.)INTERNAL OB DUMPS0000
(4.)ROADS0000
(5.)BUILT UP AREA (COLONY/OFFICE)0000
(6.)GREEN BELT18.120018.12
(7.)VIRGIN AREA0.78000.78
(8.)OtherNA0000
(9.)TOP SOIL STORAGE0000
TOTAL18.942.10061
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 0
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 20.13
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan NA
Total Area Excavated (in hectare) 42.10
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 0
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)200450005000500023000
(2.)200550005000500000
(3.)200650005000500016800
(4.)2007700070007000285.6600
(5.)200850005000500000
(6.)20125000500050001250
(7.)201350005000500049800
(8.)201550005000500000
(9.)201650005000500000
(10.)200150005000500011640
(11.)20025000500050004290
(12.)200950005000500000
(13.)201050005000500000
(14.)20115000500050002500
(15.)200350005000500000
(16.)201470007000700067400
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0037
(ii)Name of the EIA Consultant VARDAN ENVIRONET
(iii)Address D-142, SUSHANT LOK-III, GURGAON, HARYANA
(iv)Mobile No. 8005707098
(v)Landline No. 0141298340
(vi)Email Id jaipur@vardanenvironet.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 09 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)16/10/2019After examination of the proposal, following discrepancies are found:- 1. Affidavit regarding violation of EIA notification and regarding correctness of submitted data & documents by consultant as well as by PP not submitted. 2. District survey report as per MOEF notification is not submitted. 3. Cluster certificate is not submitted duly certified by ME/AME in prescribed format. 4. Copy of Topo Sheet is not uploaded. 5. Copy of letter of intent is not submitted.
(2.)26/11/2019The correction have been made as per the instruction received
(3.)29/11/2019After examination of the proposal, following discrepancies are found:- 1. Affidavit regarding violation of EIA notification and regarding correctness of submitted data & documents by consultant as well as by PP not submitted. 2. Copy of letter of intent is not submitted. 3. Copy of Topo Sheet is not uploaded.
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRatneshwar Kumar Maheshwari
DesignationPartner
Name of Company (Applicant Name should not be given here)BR MINERALS
AddressVillage Lohari Khurd (Deva Ka Khera) Tehsil Hindoli District Bundi State Rajasthan