Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Transfer of EC & Expansion of Production capacity mentioned in earlier granted Environment Clearance for China Clay , Yellow Ochre, Quartz & Red Ochre (Minor Mineral) Mining Project [i.e. From 23338 TPA to 191070 TPA (ROM)] ) { Saleable Mineral - 149989 TPA, Subgrade-9375 TPA , Top Soil- 358 TPA , OB/SB/IB – 3225 TPA & Waste- 28123 TPA} at M.L. No. 02/2006, Near Village- Basni, Tehsil- Hindoli & District – Bundi (Rajasthan) over an area 4.50 Hectare by M/s Shri Krishna Mines
(b)Name of the Company / Organisation SHRI KRISHNA MINES
(c)Registered Address n/v- Basni, Teh- Hindoli, Dist- Bundi.,,Bundi,Rajasthan-323023
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Shri Krishna Mines
(b)Designation (Owner/ Partner/ CEO) Project Proponent
(c)Address n/v- Basni, Teh- Hindoli, Dist- Bundi.,Bundi,Rajasthan-323023
(d)Pin code 323023
(e)E-mail krishnamines123@outlook.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B2
(d)Proposal Number SIA/RJ/MIN/193881/2021
(e)Master Proposal Number(Single Window) SW/193873/2021
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. ML 02/2006
(b)Pincode 341021
(c)Bounded Latitudes (North)
From
Degree 25
Minutes 41
Second 20.15
From
Degree 25
Minutes 41
Second 25.06
(d)Bounded Longitudes (East)
From
Degree 75
Minutes 27
Second 22.5
From
Degree 75
Minutes 27
Second 46.08
(e)Survey of India Topo Sheet No. 45 O 6
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 350
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 40
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanBundiHindoliBasni
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number NIL
(b)Date of Apply of EC NIL
(c)Date of Issue of EC NIL
(d)Previous EC Letter NIL
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason It is a category B2 Project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. 1105-20
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)productio capacity23338191070214408Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)area4.504.504.50
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 26 Dec 2017
(iv)Valid Upto 30 Nov 2022
(v)File No. 1578-1580
(vi)Application No. 3885
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 75
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.0375
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.0375
(e) Funds Allocated for Environment Management Capital(%) 0.05
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3.5
(b)Existing quantity of raw material/fuel 2.8
(c)Total quantity of raw material/fuel 6.3
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Water3.5Kilo Litre per DayNear by VillageRoad2.5 OthersTanker SupplyCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 16 Jan 2021 To 18 Jan 2021
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube32.6532.6532.6560
(2.)SO2Micro Gram per Meter Cube9.249.249.2480
(3.)NOxMicro Gram per Meter Cube17.1417.1417.1480
(4.)PM10Micro Gram per Meter Cube76.4876.4876.48100
    14.2.     No. of Ground Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l266.56266.56200600
(2.)Chloridesmg/l68.9168.912501000
(3.)Heavy MetalsFemg/l0.270.270.30
(4.)TSSmg/l0000
(5.)TDSmg/l5365365002000
(6.)pHNA7.397.396.58.5
(7.)Fluoridemg/l0.500.501.01.5
    14.3.     No. of Surface Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l00B
(2.)CODmg/l00D
(3.)BODmg/l00B
(4.)DOmg/l000D
    14.4.     No. of Ambient Noise Monitoring Locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))43.2843.2870
(2.)Leq(Day)A-weighted decibels(dB(A))64.2164.2175
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare175.03175.03
(2.)pH7.687.68
(3.)P(Phosphorus)46.5346.53
(4.)Electric ConductivityMillisiemens per Centimetre0.3580.358
(5.)K(Potassium)Kilogram per hectare85.0285.02
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 50 To 55
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 55 To 60
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater3.502.5 Not Appliacble modeOtherstanker supplyOtherstanker supplyna20 May 20200
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)0000OthersNA00
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)mineral wasteOthersMINERAL WASTE28123Tons0RoadOthersBACKFILLING
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube32.650032.6560
(2.)NOxMicrogram per Meter Cube17.140017.1480
(3.)SO2Microgram per Meter Cube9.24009.2480
(4.)PM10Microgram per Meter Cube76.480076.48100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source na
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) na
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 4.50
(d)Revenue Land 0
(e)Other Land 0
    Total Land 4.50
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 1.6712
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : non utilised 2.8288
    Total 4.5
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersMINING OF quartz, china clay4.50minig of mineral
Total 4.5
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA00
(2.)ESZsNA00
(3.)CorridorsNA00
(4.)Critically Polluted AreaNA00
(5.)Wildlife CorridorsNA00
(6.)ESAsNA00
(7.)NPANA00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestKishanganj P.f0.03South
(2.)Archaeological SitesNA00
(3.)Defence InstallationsNA00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.50
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired na
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Bajiyan Nadi
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 3.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 30
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 360
(f)Total Manpower 30
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt01.481
(2.)Percentage of Total Project Area03333
(3.)No. of Plants02222022220
(4.)Funds Allocated4000090000130000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialemployment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 4
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)yellow OchreMinor
(2.)China ClayMinor
(3.)Red OchreMinor
(4.)QUARTZMinor
2.
Mine Capacity in ROM (Run of Mine) 23338
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. SME/Kota-circle/M.Plan/2020/2200
(b)Date of Approval 15 Jul 2020
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department SME
(e)Approved Mining Lease Area 4.50
(f)Approved Capacity 23338
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 1066000
(b)Mineable Reserves (Million Ton) 1066000
(c)Extractable Reserves(Million Ton) 1066000
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral 30
(f)Stripping Ratio 1 : 0.1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) na
(h)Average Gradient(Degree) 80
(i)Mining Method Opencast
(j)Life of Mine (Years) 5.5
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 4.50
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof it is an existing project
(c)Whether Lease Deed Executed ? No
(i)Reason thereof NA
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 1.7766
(b)Depth (in meter) 31
(c)Volume (in Million Cubic meter) 310000
12.
Details of Quarry:
(a)Final Void of 1.7766 (hectare) at a Depth of 31 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 4.50
13.
Details of Transportation:
(a)In Pit/Underground to Surface from pits
(b)Surface to Siding/Loading by excavator
(c)Transportation / Conveyor Details to- end -users
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)OTHERS(Specify)non utilesd4.5004.5
(2.)WASTE LAND000
(3.)FOREST LAND000
(4.)SETTLEMENTS000
(5.)AGRICULTURE LAND000
(6.)GRAZING LAND000
(7.)SURFACE WATER BODIES000
TOTAL4.504.5
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)TOP SOIL STORAGE0000
(2.)BUILT UP AREA (COLONY/OFFICE)0000
(3.)INTERNAL OB DUMPS0000
(4.)VIRGIN AREA0000
(5.)EXCAVATION/QUARRY01.776601.7766
(6.)ROADS0000
(7.)EXTERNAL OB DUMPS0000
(8.)GREEN BELT1.48001.48
TOTAL1.481.7766003.2566
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 0
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 1.48
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan 0
Total Area Excavated (in hectare) 2.5177
Total Area Backfilled after Excavation (in hectare) 1.5886
Total Area Reclaimed (in hectare) 0
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)2020233382333819107000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/2023/IA0063
(ii)Name of the EIA Consultant Atmos Sustainable Solutions Pvt. Ltd.
(iii)Address A-73, 3rd Floor, Sector-65, Noida, Uttar Pradesh-201301
(iv)Mobile No. 9929108691
(v)Landline No. 2954638
(vi)Email Id vibranttechnolab@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 08 Sep 2023
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)21/01/2021After examination of the proposal, following discrepancies are found:- 1. District survey report bears no signature. It is not clear whether it is authentic or not.
(2.)27/01/2021The correction have been made as per the instruction received
(3.)31/01/2022Your proposal was examined and it was found that you are required to submit following documents: 1. Filled Form-1 duly signed by PP and Consultant 2. Aravali certificate 3. Cluster certificate not more than 6 months old 4. Certificate from concerned Deputy Conservator of Forest for proposed area not falling within 10 kms of boundary of wildlife Sanctuary/NP/ conservation reserve. 5. Annexure-G
(4.)09/03/2022The correction have been made as per the instruction received
(5.)10/03/20221.Submit a Copy of valid letter of intent . 2.Copy of approved mining plan is not submitted. 3.Submit compliance report of earlier EC duly certified by RSPCB/SEIAA/MoEF. 4.Submit production figure in prescribed format. 5.Submit mining lease documents.
(6.)30/04/2022The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)10/03/2023The Authority took note of this seriously and decided to defer the proposal and call the PP for personal hearing to explain the same.ADS Letter
(2.)16/03/2023we will submit necessary documents before Hon’ble SEIAA while presentation.ADS Letter
(3.)08/06/2023However, CCR is more than one year old. Hence, the Authority decided to defer this proposal for submission of additional information within 45 days.ADS Letter
(4.)15/06/2023We are hereby submitting the requisite documents i.e CCRADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantShri Krishna Mines
DesignationProject Proponent
Name of Company (Applicant Name should not be given here)SHRI KRISHNA MINES
Addressn/v- Basni, Teh- Hindoli, Dist- Bundi.
Print