Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Masonry Stone Mining Lease (M.L. Reference No 2019100005769, Area: 1.0769 ha) At Khasra No. 612 & 614 near Village- Toda, Tehsil- Neem Ka Thana, District- Sikar (Rajasthan)
(b)Name of the Company / Organisation SHRI PAPPU RAM
(c)Registered Address Ward No. 3, Panchlangi, Tehsil Udaipurwati, District Jhunjhunu,,Jaipur,Rajasthan-333801
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Pappu Ram
(b)Designation (Owner/ Partner/ CEO) Lessee
(c)Address Ward No 3, Panchlangi, Udaipurwati, Jhunjhunu,,Bhinmal,Jhunjhunu,Rajasthan-333801
(d)Pin code 333801
(e)E-mail pappuramlease@gmail.com
(f)Telephone No. 141-2751990
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/RJ/MIN/127805/2019
(e)Master Proposal Number(Single Window) SW/127804/2019
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra No. 612 & 614 , M.L. Reference No 201910000
(b)Pincode 332713
(c)Bounded Latitudes (North)
From
Degree 27.385291
Minutes
Second
From
Degree 27.385590
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 75.560627
Minutes
Second
From
Degree 76.541177
Minutes
Second
(e)Survey of India Topo Sheet No. 45M/14, 45M/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 492
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 35
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanSikarNeem Ka ThanaToda
6.
Details of Terms of Reference (ToR):
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason B2 Category lease
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Masonry Stone Mining LeaseNATHIS IS A SMALL MINING LEASE OF B2 CATEGORY
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Masonry Stone200000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.40
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.45
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.40
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.45
(e) Funds Allocated for Environment Management Capital(%) 112.50
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel200OthersLPDNARoad2.0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 04 Nov 2019 To 08 Nov 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube78.278.276.636IS : 5182 (PART-23)
(2.)SO2Micro Gram per Meter Cube20.720.720.286IS : 5182 (PART-2)
(3.)PM2.5Micro Gram per Meter Cube38.338.337.534Gravimetric method
(4.)NOxMicro Gram per Meter Cube30.330.329.694IS : 5182 (PART-6)
(5.)OthersNANA0000
    14.2.     No. of Ground Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l355.4355.45002000
(2.)Chloridesmg/l26.826.82501000
(3.)Fluoridemg/l0.50.51.51.5
(4.)OthersturbidityOthersNTU1115
(5.)TSSOthersNTU1115
(6.)Total Hardnessmg/l163.7163.7200600
(7.)Heavy MetalsTotal Alkalinitymg/l119.2119.2200600
(8.)pHNA7.257.256.58.5
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)OthersNANA00E
(2.)CODNA00D
(3.)pHNA00A
(4.)DONA00B
(5.)BODNA00C
    14.4.     No. of Ambient Noise Monitoring Locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))70.270.275/90
(2.)Leq(Night)A-weighted decibels(dB(A))59.559.570
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.27.2
(2.)K(Potassium)Milligram per Kilogram79.279.2
(3.)Electric ConductivityOthersMMHO/CM352.3352.3
(4.)N(Nitrogen)00
(5.)P(Phosphorus)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 90 To 95
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 95
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Otherstankers52.0Copy of Permission LettermodeOthersTankersOthersTankers Via Road111106 Jun 20190
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic effluent0.150.15Septic Tank Soak pitOthersGreen Belt & Plantation0.150
16.1.
(a)Total Waste Water Generation 0.15
(b)Total Discharged Water 0
(c)Total Reused Water 0.15
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OB & MINE WASTEOthersMining Waste10000Tons0RoadOthersHaul road construction etc
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10NA00000
(2.)PM2.5NA00000
(3.)SO2NA00000
(4.)NOxNA00000
(5.)Others(Specify)NANA00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00OthersNA0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 220
(b)Source RSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 1.0769
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.0769
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Pits , Qurries Etc. 1.0769
    Total 1.0769
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersNA00
Total 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0None
(2.)ESZsGanwari PF3.0NW
(3.)CorridorsNA0None
(4.)Wildlife CorridorsNA0None
(5.)ESAsNA0None
(6.)Critically Polluted AreaNA0None
(7.)NPANA0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestGadrata PF6.5NE
(2.)Archaeological SitesNA0None
(3.)Defence InstallationsChhawani, Neem Ka Thana15NW
(4.)OthersProtected ForestDantil PF9.5East
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Buchara Bandh, Sota Nadi, Buchara Main canal
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 2
(b)Permanent Employment-During Operation 3
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 300
(f)Total Manpower 15
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.35
(b)Percentage of Total Project Area 32.50
(c)No. of Plants to be Planted 350
(d)Funds Allocated for Plantation 15000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen Belt & Plantation
(2.)SocialCSR
(3.)FinancialREVENUE
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Masonry StoneMinor
2.
Mine Capacity in ROM (Run of Mine) 200000
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. SME/JP/MP/P-410/19/2447
(b)Date of Approval 27 Sep 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department State
(e)Approved Mining Lease Area 1.0769
(f)Approved Capacity 200000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 1.562
(b)Mineable Reserves (Million Ton) 0.864
(c)Extractable Reserves(Million Ton) 0.779
(d)Percent(%) of Extraction 95
(e)Grade of Coal /Ore /Mineral 1
(f)Stripping Ratio 0.05 : 1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 0
(i)Mining Method Opencast
(j)Life of Mine (Years) 4.5
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1.0769
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 13 Jun 2019
(iii)Validity of LOI 1.5
(iv)Reference No. of LOI 2019100005769
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Fresh
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Fresh
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 0.01
(iii)Height (in meter) 0.001
(iv)Quantity (in Million Cubic meter) 0.001
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0
(b)Depth (in meter) 0
(c)Volume (in Million Cubic meter) 0
12.
Details of Quarry:
(a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0.80
13.
Details of Transportation:
(a)In Pit/Underground to Surface 0
(b)Surface to Siding/Loading 0
(c)Transportation / Conveyor Details 0
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND000
(2.)SETTLEMENTS000
(3.)OTHERS(Specify)Pits, qurries etc.1.076901.0769
(4.)AGRICULTURE LAND000
(5.)WASTE LAND000
(6.)GRAZING LAND000
(7.)SURFACE WATER BODIES000
TOTAL1.076901.0769
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY00.8000.8
(2.)VIRGIN AREA000.03690.0369
(3.)INTERNAL OB DUMPS0000
(4.)BUILT UP AREA (COLONY/OFFICE)0000
(5.)GREEN BELT0.20000.2
(6.)TOP SOIL STORAGE00.0200.02
(7.)ROADS000.020.02
(8.)EXTERNAL OB DUMPS0000
TOTAL0.20.820.056901.0769
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 1
(c)Quarry(in hectare) 0.80
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0.15
(h)Total afforestation plant (in hectare) 0.35
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)2019002000002000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant Meeting is awaited
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPappu Ram
DesignationLessee
Name of Company (Applicant Name should not be given here)SHRI PAPPU RAM
AddressWard No. 3, Panchlangi, Tehsil Udaipurwati, District Jhunjhunu
Print