Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Jaipur Pipeline Terminal by installation of 3 Nos of Aviation Turbine Fuel (ATF) tanks of 8050 KL in Jobner Installation at village Asalpur Tehsil Phulera (Sambhar), District Jaipur Rajas
(b)Name of the Company / Organisation BPCL JOBNER
(c)Registered Address Bharat Petroleum Corporation Ltd. Village & Post Asalpur, Near Asalpur, Near Asalpur-Jobner Railway Station, Tehsil- Phulera (Sambhar), Jaipur. Rajasthan,,Jaipur,Rajasthan-303331
(d)Legal Status of the Company Central Government
2.
Address for the correspondence:
(a)Name of the Applicant kumar Nandan Singh
(b)Designation (Owner/ Partner/ CEO) tm
(c)Address Bharat Petroleum Corporation Ltd. Village & Post Asalpur, Near Asalpur, Near Asalpur-Jobner Railway Station, Tehsil- Phulera (Sambhar), Jaipur. Rajasthan,Jaipur,Rajasthan-303331
(d)Pin code 303331
(e)E-mail ecbpcljobner@gmail.com
(f)Telephone No. 1428-239970
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/RJ/IND2/43955/2019
(e)Master Proposal Number(Single Window) SW/119999/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1325.1326,1331/1,1331/2,1330,1344,1343,1339,1347/2
(b)Pincode 303328
(c)Bounded Latitudes (North)
From
Degree 265337.83
Minutes
Second
From
Degree 26542.87
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 752540.81
Minutes
Second
From
Degree 752617.11
Minutes
Second
(e)Survey of India Topo Sheet No. 45N/5,45N/9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 378
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanJaipurPhulera (HQ.Sambhar)Asalpur
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number F1 (4)/SEIAA/SEAC-Raj/Sectt/Project / Cat. 7(d) B1
(b)Date of Apply of EC 23 Jan 2019
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As this is an Expansion case
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. NA
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Oil Storage Unit971138050105163Kilo Litre per Day(KLD)Pipe Conveyor
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Oil Storage unit971138050105163Oil Supply
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 30 Mar 2015
(iv)Valid Upto 28 Feb 2018
(v)File No. 2014/15/SWM/1825
(vi)Application No. 2014/15/SWM/1825
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 275.7
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.17
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.34
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.017
(e) Funds Allocated for Environment Management Capital(%) 0.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Page 52, Chapter 2.8.2, EIA0Kilo Litre per DayOil StoragePipe Conveyor1 Fuel Supply AgreementCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2016 To 31 Dec 2016
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube36.1716.3535.2160
(2.)SO2Micro Gram per Meter Cube103.789.7280
(3.)NOxMicro Gram per Meter Cube15.558.5115.5080
(4.)PM10Micro Gram per Meter Cube91.5944.6589.89100
    14.2.     No. of Ground Water Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.347.818.50
(2.)TDSmg/l40326245002000
(3.)Fluoridemg/l6.45.1115
(4.)TSSNA0000
(5.)Chloridesmg/l2074952501000
(6.)Total Hardnessmg/l620240200600
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA00A
(2.)BODmg/l00A
(3.)DOmg/l00A
(4.)CODmg/l00A
    14.4.     No. of Ambient Noise Monitoring Locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))53.243.770
(2.)Leq(Day)A-weighted decibels(dB(A))65.757.675
    14.5.     No. of Soil Sample Monitored Locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram162128
(2.)P(Phosphorus)Milligram per Kilogram4120
(3.)Electric ConductivityCentimeter per Second368.245.1
(4.)pH8.697.4
(5.)K(Potassium)Milligram per Kilogram220190
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 60 To 65
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 55 To 60
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater51Copy of Permission LetterPipelineOthersBore wellNA30 Jun 20145
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic3.23.2septic tankReuse within the Plant & Recycling3.20
16.1.
(a)Total Waste Water Generation 3.2
(b)Total Discharged Water 0
(c)Total Reused Water 3.2
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Domestic WasteMunicipal Solid Waste2Kilolitre1RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube75.200.375.5100
(2.)SO2NA00000
(3.)NOxMicrogram per Meter Cube14.10317.180
(4.)PM2.5Microgram per Meter Cube36.200.1336.360
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDG Fuel80.15NOx9.2
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source JVVNL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2 DG Set 1150 KVA
(e)Stack Height (in m) 8
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 38.74
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 38.74
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 38.74
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : 0 0
    Total 38.74
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant38.74NA
Total 38.74
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA00
(2.)CorridorsNA00
(3.)ESZsNA00
(4.)WLSNA00
(5.)ESAsNA00
(6.)Wildlife CorridorsNA00
(7.)Critically Polluted AreaNA00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA00
(2.)Archaeological SitesNA00
(3.)Defence InstallationsNA00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 38.74
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 80
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 80
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt31.59031
(2.)Percentage of Total Project Area33033
(3.)No. of Plants1000100
(4.)Funds Allocated65100065000716000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialemployment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET Accredited NABET / EIA / 1619 / IA / 0019
(ii)Name of the EIA Consultant M/s. N.S. ENVIRO-TECH LABORATORIES & CONSULTANTS
(iii)Address Add.:- P. No. 69/318, V.T Road Chouraha, Madham Marg, Mansarovar Jaipur - 302 020.)
(iv)Mobile No. 9829930877
(v)Landline No. 2781959
(vi)Email Id nsnaruka@nsenvirotech.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 17 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)22/10/2019The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete.EDS Letter
(2.)31/10/2019The correction have been made as per the instruction received
(3.)05/11/2019the proposals/ application is found deficient /incomplete in respect to following:- a).Compliance report of earlier EC duly CERTIFIED by RSPCB/SEIAA/MoEF. b).Affidavit regarding violation of EIA notification and regarding correctness of submitted data & document by consultant as well as project proponent.
(4.)12/11/2019The correction have been made as per the instruction received
(5.)15/10/2022while uploading aforesaid documents you are required to check for any overwriting of existing files. you are advised not to overwrite existing documents. You have not yet submitted the requested yet. kindly submit.
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicantkumar Nandan Singh
Designationtm
Name of Company (Applicant Name should not be given here)BPCL JOBNER
AddressBharat Petroleum Corporation Ltd. Village & Post Asalpur, Near Asalpur, Near Asalpur-Jobner Railway Station, Tehsil- Phulera (Sambhar), Jaipur. Rajasthan