Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Onshore Oil & Gas Exploration in three OALP Blocks viz. RJ-ONHP-2017/9 (Siyasar), RJ-ONHP-2017/8 (South Baghewala) & RJ-ONHP-2018/2 (Siyasar-II)
(b)Name of the Company / Organisation OIL INDIA LTD RAJASTHAN PROJECT
(c)Registered Address 2A-District Shopping Centre, Saraswati Nagar, Basni, Jodhpur,,Jodhpur,Rajasthan-342005
(d)Legal Status of the Company Central PSU
2.
Address for the correspondence:
(a)Name of the Applicant Tabrez Akhtar Ansari Akhtar Ansari
(b)Designation (Owner/ Partner/ CEO) Dy. General Manager (ES & HSE)
(c)Address 2A-District Shopping Centre, Saraswati Nagar, Basni, Jodhpur,Jodhpur,Rajasthan-342005
(d)Pin code 342005
(e)E-mail siddharth_singh@oilindia.in
(f)Telephone No. 291-2729429
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/RJ/IND2/180147/2020
(e)Master Proposal Number(Single Window) SW/180145/2020
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 15 wells
(b)Pincode 334001
(c)Bounded Latitudes (North)
From
Degree 3060292.76
Minutes
Second
From
Degree 3206739.00
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 232699.49
Minutes
Second
From
Degree 387694.66
Minutes
Second
(e)Survey of India Topo Sheet No. 44D, 44F,45A
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 210
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 10
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanSri GanganagarGharsanaBlock RJ-ONHP-2017/9
(2.)RajasthanBikanerBikanerBlock RJ-ONHP-2017/9 & RJ-ONHP-2018/2
(3.)RajasthanBikanerPoogalBlock RJ-ONHP-2017/9 & RJ-ONHP-2018/2
(4.)RajasthanBikanerLunkaransarBlock RJ-ONHP-2017/9 & RJ-ONHP-2018/2
(5.)RajasthanBikanerKolayatBlock RJ-ONHP-2017/9 & RJ-ONHP-2018/2
(6.)RajasthanBikanerChhatargarhBlock RJ-ONHP-2017/9 & RJ-ONHP-2018/2
(7.)RajasthanJaisalmerPokaranBlock RJ-ONHP-2017/8
6.
Details of Terms of Reference (ToR):
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per MOEF&CC notification S.O.236 (E) dated 16th
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Drilling of exploratory wells15 wells
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)drilling of exploratory wells15OthersnumbersOthersDrilling of wells
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 150
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.27
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.0275
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.2794
(e) Funds Allocated for Environment Management Capital(%) 0.18
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel2.5Kilo Litre per DayLocal Depot/ SuppliersRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 21 Oct 2019 To 25 Jan 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 24
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube17.74.314.280
(2.)PM10Micro Gram per Meter Cube973594.3100
(3.)PM2.5Micro Gram per Meter Cube46144360
(4.)NOxMicro Gram per Meter Cube29.38.621.780
    14.2.     No. of Ground Water Monitoring Locations : 18
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l60020200600
(2.)Chloridesmg/l2067482501000
(3.)pHNA8.456.976.58.5
(4.)TSSmg/l0000
(5.)Fluoridemg/l1.280.0911.5
(6.)TDSmg/l47841765002000
(7.)Heavy MetalsIronmg/l0.280.140.30.3
    14.3.     No. of Surface Water Monitoring Locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.16.7A
(2.)BODmg/l52C
(3.)DOmg/l6.96.2A
(4.)CODmg/l104C
    14.4.     No. of Ambient Noise Monitoring Locations : 23
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))44.542.145
(2.)Leq(Day)A-weighted decibels(dB(A))54.851.455
    14.5.     No. of Soil Sample Monitored Locations : 20
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityOthersdS/m0.7110.194
(2.)pH10.77.1
(3.)K(Potassium)Kilogram per hectare320.5219.5
(4.)N(Nitrogen)Kilogram per hectare160.856.9
(5.)P(Phosphorus)Kilogram per hectare48.512.1
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.85 To 116
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.24 To 110
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface3520 Not Appliacble modeOthersTankerOthersTankerNA18 Dec 202035
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Effluent from Drilling operation710mobile ETPReuse within the Plant & Recycling7
(2.)Domestic45Mobile STPReuse within the Plant & Recycling4
16.1.
(a)Total Waste Water Generation 11
(b)Total Discharged Water 0
(c)Total Reused Water 11
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.55Tons20RoadAuthorized Recyclers
(2.)Drill CuttingsOthersDrill Cuttings generated from water based mud500Tons0OthersAt site in HDPE lined PitOthersDisposal at site in HDPE lined pit
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube43.00.00.043.060
(2.)NOxMicrogram per Meter Cube21.70.02.0123.7180
(3.)SO2Microgram per Meter Cube14.20.00.07614.27660
(4.)PM10Microgram per Meter Cube94.30.00.07694.376100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetHSD90.2SO20.003
(2.)DG SetHSD90.2PM100.003
(3.)DG SetHSD90.2NOx0.079
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1200
(b)Source DG Set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) DG Set
(e)Stack Height (in m) 9
20.
Land Ownership Pattern:
(a)Forest Land 0.0
(b)Private Land 0.0
(c)Government Land 0.0
(d)Revenue Land 0.0
(e)Other Land 2.304
    Total Land 2.304
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 512711.2
(b)Waste/Barren Land 889342.7
(c)Grazing/ Community Land 0.0
(d)Surface Water Bodies 5351.7
(e)Settlements 16240.7
(f)Industrial 1974.1
(g)Forest 0.0
(h)Mangroves 0.0
(i)Marine Area 0.0
(j)Others : Vegetation Cover 30409.3
    Total 1456029.7
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant2.304Land for each drill site
Total 2.304
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNo such area located in study area0.0No such are is located in study area
(2.)Wildlife CorridorsNo such area located in study area0.0No such are is located in study area
(3.)WLSNo such area located in study area0.0No such are is located in study area
(4.)ESZsNo such area located in study area0.0No such are is located in study area
(5.)CorridorsNo such area located in study area0.0No such are is located in study area
(6.)Critically Polluted AreaNo such area located in study area0.0No such are is located in study area
(7.)NPANo such area located in study area0.0No such are is located in study area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological Sitesnone0.0None
(2.)Defence InstallationsDefence installation10area is near the international border
(3.)Forestnone0.0none
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.0
(b)Land yet to be acquired(Ha) 2.304
(c)Status of Land acquisition if not acquired Land will be taken on lease for each well
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Indira Gandhi Canal
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 50
(e)No. of working days 90
(f)Total Manpower 50
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.0
(b)Percentage of Total Project Area 0.00
(c)No. of Plants to be Planted 0
(d)Funds Allocated for Plantation 0
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Financialreduction in oil and gas import
(2.)EnvironmentalClean fuel in terms of gas discovery
(3.)EnvironmentalClean fuel in terms of gas discovery
(4.)Socialtemporary employment to locals
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0138
(ii)Name of the EIA Consultant Kadam Environmental Consultants
(iii)Address 871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
(iv)Mobile No. 9824034709
(v)Landline No. 0265613100
(vi)Email Id kadam@kadamenviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 26 May 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)07/01/2021The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:- a).Form I along with duly filled Environment sensitivity portion. b). Pre Feasibility Report. c).Project area and gross built-up area. d). Affidavit regarding violation of EIA notification and regarding correctness of submitted data& document by consultant as well as project proponent —Annx. e).Land documents. f).Mail id of PP.
(2.)04/02/2021The correction have been made as per the instruction received
(3.)09/02/2021The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:- a).Form I along with duly filled Environment sensitivity portion. b). Pre Feasibility Report. c).Project area and gross built-up area. d). Affidavit regarding violation of EIA notification and regarding correctness of submitted data& document by consultant as well as project proponent —Annx. e).Land documents. f).Mail id of PP.
(4.)10/02/2021The correction have been made as per the instruction received
(5.)11/02/2021Please ensure reply of earlier EDS generated.
(6.)15/02/2021The correction have been made as per the instruction received
(7.)15/02/2021Affidavit by consultant regarding violation of EIA notification and regarding correctness of submitted data & document has not been submitted/uploaded.
(8.)20/02/2021The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantTabrez Akhtar Ansari Akhtar Ansari
DesignationDy. General Manager (ES & HSE)
Name of Company (Applicant Name should not be given here)OIL INDIA LTD RAJASTHAN PROJECT
Address2A-District Shopping Centre, Saraswati Nagar, Basni, Jodhpur