Form-1 | APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE | | 1. Basic Informations | Project Name | M/s. Patel Enterprises | Company/Organisation Name | M/S PATEL ENTERPRISES | Registered Address | E 146(A) RIICO Industrial Area, Gudli, Mavli, Udaipur Rajasthan 313003 | Legal Status of the Company | Private |
| 2. | Address for the correspondence: | (a)Name of the Applicant | KARAN LODHA | (b)Designation (Owner/ Partner/ CEO) | OWNER | (c)Address | E 146(A) RIICO Industrial Area, Gudli, Mavli, Udaipur,Udaipur,Rajasthan-313003 | (d)Pin code | 313003 | (e)E-mail | enterprisespatel68@gmail.com | (f)Telephone No. | 141-2466841 | (g)Fax No. | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 5(f)-API
| (b)Minor Project/Activity | 5(f)-API
| (c)Category | B2 | (d)Proposal Number | SIA/RJ/IND2/175499/2020 | (e)Master Proposal Number(Single Window) | SW/175498/2020 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (g)Project Type(New/Expansion/Modernization) | Expansion |
|
| 4. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Rajasthan | |
| Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Rajasthan | Udaipur | Mavli | Gudli | | 5. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (c)Reason | -1 | (d)Supporting Document | NILL | |
| Location of the project | Plot No.: E /146 (A), RIICO Industrial Estate Area, Road No. 2 RIICO, Vill.: Gudli, Tah.: Mavli, Dist.: Udaipur, State: Rajasthan | | | Town / Village (Name of more than one town may be entered by separating with) | Gudli | Plot/Survey/Khasra No. (Name of more than one town may be entered by separating with) | Plot No.: E /146 (A) | State | Rajasthan | District | Udaipur | Tehshil | Mavli | Pincode | 313024 | Nearest railway station | Khemali Railway Station | Distance from the project site | 4.8 | Nearest airport | Maharana Pratap AirPort (Dabok) | Distance from the project site | 6.1 | Nearest Town/City/District Headquarters | Udaipur City | Distance from the project site | 15 | Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) | Zila Parishad Office, Udaipur Collectorate Road, Delhi Gate Cir, Shakti Nagar, Udaipur, Rajasthan 313001 | Upload GPS file | Copy of Kml File Uploaded GPS file | Shape of the project land | Block (Polygon) | Site alternative under consideration(If any) | Uploaded Site alternative under consideration | Brief summary of project | Uploaded Brief summary of project | | | Does your project location falls under out of any following areas | None of above Areas | | | Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) | 1910 | Existing Built Up Area(In Meter /Sqr) | 1910 | Does it attract any of the general conditions given below? | No | | | Does it attract the specific condition given below? | No | | | Interlinked Projects | No | | | Whether separate application of interlinked projects has been submitted? | | Date of Submission | | Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | | Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | | Whether the proposal involves approval/clearance under the C.R.Z notification,2011? | No | | | Whether there is any Government Order/Policy relevent/relating to the site? | No | | | Forest land involved(hectares) | 0 | | | Is there any litigation pending against the project? | No | | |
1. | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | This is an expansion project within existing premises so no change inland use & topography is expected. However new building/ construction activity will be carried out within existing premises for expansion. Therefore, minor change in land use due to construction activity. | 1.2 | Clearance of existing land, vegetation and buildings? | No | Not applicable. Since proposed expansion project will be set-up within exiting premises. and land is already earmarked for industrial activity by RIICO. No building or vegetation will be clear for construction work. | 1.3 | Creation of new land uses? | No | Not applicable | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | Not applicable | 1.5 | Construction works? | Yes | Construction will be carried required proposed expansion. | 1.6 | Demolition works? | No | Not applicable. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Not applicable. There will be no requirement of temporary sites & housing facility as the labour deployed will be local. | 1.8 | Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations | No | Not applicable. | 1.9 | Underground works including mining or tunneling? | No | Not applicable. | 1.10 | Reclamation works? | No | Not applicable. | 1.11 | Dredging? | No | Not applicable. | 1.12 | Offshore structures? | No | Not applicable. | 1.13 | Production and manufacturing processes? | Yes | For details of production & manufacturing process, kindly refer Annexure - 3 & 4 | 1.14 | Facilities for storage of goods or materials? | Yes | For details of storage facilities for Raw Material, Product, kindly refer Annexure-5 | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | For details of Effluent (Wastewater) Management System & details of Solid/Hazardous Waste and mode of disposal, Kindly refer Annexure-7 & Annexure-6 respectively | 1.16 | Facilities for long term housing of operational workers? | No | -- | 1.17 | New road, rail or sea traffic during construction or operation? | No | -- | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | -- | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | -- | 1.20 | New or diverted transmission lines or pipelines? | No | Not Applicable | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Not Applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Water requirement will be met through RIICO. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | -- | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Transportation activity for personnel or materials or goods will be primarily through road only. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | -- | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | -- | 1.28 | Influx of people to an area in either temporarily or permanently? | No | At present there are 7 persons are employed. After expansion about 5 additional employees will be required. Employees shall be sourced locally from the vicinity of project site. | 1.29 | Introduction of alien species? | No | Only native species of flora will be planted wherever required | 1.30 | Loss of native species or genetic diversity? | No | No effect will be on genetic diversity | 1.31 | Any other actions? | No | It will improve socio economic status of surrounding people | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The proposed expansion project will be set-up with existing premises, kindly refer Annexure-2 & 10 for Land documents and plant layout plan. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Water requirement will be met through RIICO..
For details of Water Consumption & Wastewater Generation kindly refer Annexure–7. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Construction materials such as cement, sand, steel, stone etc. will be required, which will be met from local market/supplier. | 2.5 | Forests and timber (source – MT) | No | -- | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | For details of fuel and electricity requirement, kindly refer Annexure-8 | 2.7 | Any other natural resources (use appropriate standard units) | No | -- | |
3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | For details of storage facilities for Raw Materials and Products, kindly refer Annexure-5. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | -- | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | -- | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | -- | 3.5 | Any other causes | No | -- | |
4 | Production of solid wastes during construction or operation or decommissioning (MT/month) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | -- | 4.2 | Municipal waste (domestic and or commercial wastes) | No | -- | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | For details of the hazardous waste generated due to proposed project are given in Annexure–6. | 4.4 | Other industrial process wastes | Yes | Kindly refer Annexure-6 | 4.5 | Surplus product | No | -- | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Kindly refer Annexure-6 | 4.7 | Construction or demolition wastes | Yes | Construction waste (if any) will be used in filling of low-lying areas within the unit. | 4.8 | Redundant machinery or equipment | No | -- | 4.9 | Contaminated soils or other materials | No | -- | 4.10 | Agricultural wastes | No | -- | 4.11 | Other solid wastes | No | -- | |
5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Kindly refer Annexure-8 | 5.2 | Emissions from production processes | Yes | Kindly refer Annexure-8 | 5.3 | Emissions from materials handling including storage or transport | No | -- | 5.4 | Emissions from construction activities including plant and equipment | No | -- | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | No | -- | 5.6 | Emissions from incineration of waste | No | -- | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | -- | 5.8 | Emissions from any other sources | Yes | Kindly refer Annexure-8 | |
6 | Generation of Noise and Vibration, and Emissions of Light and Heat: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | The Noise level will be within the prescribed limit. At noisy areas adequate preventive & control measures will be taken. No significant noise, vibration or emission of light & heat from the unit | 6.2 | From industrial or similar processes | Yes | The Noise level will be within the prescribed limit. At noisy areas adequate preventive & control measures will be taken. No significant noise, vibration or emission of light & heat from the unit | 6.3 | From construction or demolition | Yes | Proper mitigation measures such as sound enclosures, PPE etc. will be taken to curb the noise level within limit | 6.4 | From blasting or piling | No | -- | 6.5 | From construction or operational traffic | Yes | Proper mitigation measures such as sound enclosures, PPE etc. will be taken to curb the noise level within limit | 6.6 | From lighting or cooling systems | Yes | Proper mitigation measures such as sound enclosures, PPE etc. will be taken to curb the noise level within limit | 6.7 | From any other sources | No | Not Applicable | |
7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | The storage facilities will be constructed/handled as per statutory requirements so as to minimize the chances of risk of contamination of land or water. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | Kindly refer Annexure - 7 | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | -- | 7.4 | From any other sources | No | -- | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | As proper mitigative measure of dust control will be incorporated so that there is no risk of long term buildup off. | |
8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | The storage facilities will be constructed/handled as per statutory requirements so as to minimize the chances of environmental risk health hazard. Kindly refer Annexure- 5 | 8.2 | From any other causes | No | -- | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The proposed project site is located in such a height that no flood is anticipated. Hence, it concluded that proposed project is free from natural disaster also the area falls under Seismic zone III. | |
9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality |
S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | The proposed project will not have any impact on additional development of houses because it shall source local workers. However, local population already has housing facility. It will also increase some transportation facility by increase in movement of raw material and finished products. as well as it will increase some ancillary facility associated with industrial activity like information technology, transport services etc. in fact it shall improve infrastructure, and earning of local people | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | No | It shall increase employment and income of local habitant of area. The increase in income shall improve better life and environment. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | No cumulative effect is expected. Presently there is no other similar type of project is under operation or being planned | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | None | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | KANTIYA RF
3.17 km towards SW direction
NAHAR MAGRA RF
4.26 km towards east direction
MOTA MAGRA NAI GUDLI RF
4.89 km towards SW direction
NAHAR MAGRA RF
4.26 km towards EAST direction
PANWADI RF
5.48 km towards SSW direction
BHAINSADA RF
5.53 km towards WEST direction
NAUVA RF
7.51 km towards NW direction
SEGRIYA RF
7.68 km towards SW direction
DHIKLI RF
7.93 km towards NW direction
AMBERI RF
7.95 km towards NWW direction
BIKARNI RF
9.05 km towards NW direction | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | Area is not used by sensitive species of flora or fauna for breeding resting, nesting, foraging, over wintering migration. No migratory birds come to proposed sites. | 4 | Inland, coastal, marine or underground waters | No | Not Applicable | 5 | State, National boundaries | No | None | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Khemli railway station at an distance of 4.8 Km in South direction. National Highway No. 76 Distance: 3.3 km towards South direction. | 7 | Defence installations | No | None within 15.0 Km radius of the project site. | 8 | Densely populated or built-up area | Yes | Gudli: 3027 | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | All these areas are located around 5-15 Km from proposed site | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Udai Sagar Lake 7.40 km towards SSW direction
Vallabhnagar Reservoir 13.11 km towards East direction | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | None | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | Proposed area is relatively plain. Land slide, flooding was neither noticed nor reported by any agency at proposed site since last decades or so. The area is not affected by flood, subsidence, landslides, erosion and other natural calamities. | | Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 28/09/2020 | the proposals/ application is found deficient /incomplete in respect to following:- a).In case of Expansion-Point wise compliance report of earlier EC duly certified by RSPCB/SEIAA/MoEF. b).Partnership deed/Directors list. c).Disclosure of the consultant engaged including the sector and serial no. in the latest QCI/NABET list. | | (2.) | 30/09/2020 | The correction have been made as per the instruction received | | (3.) | 07/10/2020 | The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:- a). Form- I b).Environment sensitivity portion. c).In case of Expansion-Point wise compliance report of earlier EC duly certified by RSPCB/SEIAA/MoEF. d).Size including Project area and gross builtup area. e).Affidavit regarding violation of EIA notification and regarding correctness of submitted data& document by consultant as well as project proponent —Annx. f). Land documents.
g).Partnership Deed/Directors list. h). Disclosure of the consultant engaged including the sector and serial no. in the latest QCI/NABET list.
i). Water demand and source of water. | | | Additional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | | | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. | | Name of Applicant | KARAN LODHA | Designation | OWNER | Name of Company (Applicant Name should not be given here) | M/S PATEL ENTERPRISES | Address | E 146(A) RIICO Industrial Area, Gudli, Mavli, Udaipur |
|
|