1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Enhancement in production capacity from 29,000 TPA MS Ingots to 86,400 TPA MS Billets and 85000 TPA TMT Bars/ structure from MS Billets | (b)Name of the Company / Organisation | SHRI JINDAL TOR INDIA PVT LTD | (c)Registered Address | A- 385, A- 386, A- 388, RIICO, Growth Centre, Hamirgarh, Bhilwara,,Bhilwara,Rajasthan-311001 | (d)Legal Status of the Company | Private | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Anup Kumar Jindal | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | A- 385, A- 386, A- 388, RIICO, Growth Centre, Hamirgarh, Bhilwara,Bhilwara,Rajasthan-311001 | (d)Pin code | 311001 | (e)E-mail | sjtbhilwara@gmail.com | (f)Telephone No. | 1482-289141 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 3(a) Metallurgical industries (ferrous & non ferrous)
| (b)Minor Project/Activity | NIL | (c)Category | B1 | (d)Proposal Number | SIA/RJ/IND/58262/2018 | (e)Master Proposal Number(Single Window) | SW/183047/2020 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (g)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | A-385, 386 & 388, RIICO Growth Centre, Hamirgarh, | (b)Pincode | 311028 | (c)Bounded Latitudes (North) | | From | | Degree | 25.21437 | Minutes | | Second | | From | | Degree | 25.2163 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 74.62354 | Minutes | | Second | | From | | Degree | 74.62575 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 45K/11 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 178 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Rajasthan | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Rajasthan | Bhilwara | Bhilwara | Hamirgarh | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | F1 (15459)/SEIAA/SEAC-Raj/Sectt/Project / Cat. 3(a | (b)Date of Apply of TOR | 10 Sep 2018 | (c)Date of Issue of TOR / Standard ToR | 20 Nov 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 21 Aug 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| A-385, 386 & 388, RIICO Growth Centre, Hamirgarh, Tehsil & District – Bhilwara, (Raj) | State : | Rajasthan | District : | Bhilwara | Tehsil : | Bhilwara | Village : | Hamirgarh |
| 49 | Is there employment generate from proposed project.What impacts will be done from project.Is there any adverse impact on air cause people suffered from disease?How to be managed solid waste generated | Others | Additional district collector and additional district Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Induction furnace | 2*12 TPD capacity | upgraded 8 TPD Furnace to 12 TPD | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | TMT Bars/structure | 85000 | Tons per Annum | | Road | | (2.) | MS Ingots | 86400 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 02 Aug 2017 | (iv)Valid Upto | 28 Feb 2022 | (v)File No. | F(Tech)/Bhilwara(Bhilwara)/65(1)/2010-2011/4019-40 | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 30 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 0.45 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.023 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 0.04 | (e) Funds Allocated for Environment Management Capital(%) | 1.50 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 91960 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 91960 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Iron Sponge | 23040 | Tons per Annum | | Domestic Market | Road | | 10 | Others | Domestic Market | Copy of Linkage | (2.) | Scaling from Rolling mill | 1400 | Tons per Annum | | Domestic Market | Road | | 10 | Others | Domestic Market | Copy of Linkage | (3.) | Iron Scrap | 66782.72 | Tons per Annum | | Domestic Market | Road | | 10 | Others | Domestic Market | Copy of Linkage | (4.) | Silico Manganese | 737.28 | Tons per Annum | | Domestic Market | Road | | 10 | Others | Domestic Market | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Apr 2018 To 30 Jun 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 9.45 | 4.01 | 9.41 | 80 | (2.) | NOx | | Micro Gram per Meter Cube | 19.52 | 7.86 | 19.06 | 80 | (3.) | Others | CO | Mili Gram per Meter Cube | 460 | 240 | 446.2 | 2000 | (4.) | PM10 | | Micro Gram per Meter Cube | 86.58 | 59.36 | 80.53 | 100 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 30.20 | 15.77 | 29.47 | 60 | |
14.2. No. of Ground Water Monitoring Locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | mg/l | | 401.88 | 379.88 | 250 | 1000 | (2.) | Fluoride | | | mg/l | | 0.73 | 0.68 | 1 | 1.5 | (3.) | pH | | | NA | | 7.89 | 7.36 | 8.5 | 8.5 | (4.) | TSS | | | mg/l | | 8.5 | 5.2 | 0.00 | 0.00 | (5.) | TDS | | | mg/l | | 501 | 453 | 500 | 2000 | (6.) | Total Hardness | | | mg/l | | 556 | 420 | 200 | 600 | |
14.3. No. of Surface Water Monitoring Locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.1 | 4.4 | C | (2.) | COD | | mg/l | | 24.0 | 16.0 | E | (3.) | pH | | NA | | 7.54 | 7.43 | A | (4.) | BOD | | mg/l | | 6.3 | 5.8 | C | |
14.4. No. of Ambient Noise Monitoring Locations : 6 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 50.4 | 40.4 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 60.8 | 51.5 | 70 | |
14.5. No. of Soil Sample Monitored Locations : 6 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | K(Potassium) | Others | Microgram per ml | 5.3 | 2.0 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 0.440 | 0.415 | (3.) | pH | | | 7.84 | 7.83 | (4.) | P(Phosphorus) | Percent | | 0 | 0 | (5.) | N(Nitrogen) | Percent | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 20 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Bore Well | 30 | 0 | Copy of Permission Letter | modeOthers | N.A | Others | bore well | 0 | 26 Jun 2018 | 24.5 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic Activities | 1.6 | 1.6 | NA | Others | Discharge into septic Tank | 0 | 1.6 | |
|
16.1. | (a)Total Waste Water Generation | 1.6 | (b)Total Discharged Water | 1.6 | (c)Total Reused Water | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | slag | Industrial Waste | | 5510 | Tons | 2 | Road | | Others | Sold to Cement /bricks Industries | (2.) | Domestic Waste | Municipal Solid Waste | | 6.75 | Tons | 1.5 | Road | | Others | Disposed as per MSW Rules | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 81.72 | 0.5 | 0.03 | 81.75 | 100 | (2.) | SO2 | | Microgram per Meter Cube | 8.6 | 0.5 | 0.1 | 8.7 | 80 | (3.) | NOx | | Microgram per Meter Cube | 17.66 | 0.5 | 0.1 | 17.67 | 80 | (4.) | PM2.5 | | Microgram per Meter Cube | 25.51 | 0.5 | 0.08 | 25.59 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | stack 2 | Electricity | 30 | 0.7 | PM2.5 | | 0.011 | (2.) | stack 2 | Electricity | 30 | 0.7 | PM10 | | 0.021 | (3.) | stack 2 | Electricity | 30 | 0.7 | Others | CO | 0.0009 | (4.) | stack 2 | Electricity | 30 | 0.7 | SO2 | | 0.1 | (5.) | stack 2 | Electricity | 30 | 0.7 | NO2 | | 0.2 | (6.) | stack 1 | Electricity | 31.5 | 0.7 | PM2.5 | | 0.01 | (7.) | stack 1 | Electricity | 31.5 | 0.7 | NO2 | | 0.2 | (8.) | stack 1 | Electricity | 31.5 | 0.7 | Others | CO | 0.0009 | (9.) | stack 1 | Electricity | 31.5 | 0.7 | PM10 | | 0.021 | (10.) | stack 1 | Electricity | 31.5 | 0.7 | SO2 | | 0.1 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 10000 | (b)Source | GSS RIICO Hamirgarh (Bhilwara) | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2 | (e)Stack Height (in m) | 15 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 0 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 2.8530 | Total Land | 2.8530 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 0 | (b)Waste/Barren Land | 0 | (c)Grazing/ Community Land | 0 | (d)Surface Water Bodies | 0 | (e)Settlements | 0 | (f)Industrial | 2.8530 | (g)Forest | 0 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : na | 0 | Total | 2.853 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Main Plant | | 0.9704 | | (2.) | Green belt | | 0.9415 | | (3.) | Built Up Area | | 0.2671 | | (4.) | Others | open area | 0.6740 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | NA | 0 | NA | (2.) | NPA | NA | 0 | NA | (3.) | ESAs | NA | 0 | NA | (4.) | ESZs | NA | 0 | NA | (5.) | Wildlife Corridors | NA | 0 | NA | (6.) | WLS | NA | 0 | NA | (7.) | Corridors | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | NA | 0 | NA | (2.) | Archaeological Sites | | NA | 0 | NA | (3.) | Others | NA | NA | 0 | 0 | (4.) | Defence Installations | | NA | 0 | NA | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 2.8530 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Banas river | (ii)Direction of Water Bodies in Buffer Area | South | (iii)Distance of Water Bodies in Buffer Area | 0.75 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 150 | (e)No. of working days | 300 | (f)Total Manpower | 150 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt (in hectare) | 0.95 | (b)Percentage of Total Project Area | 33.30 | (c)No. of Plants to be Planted | 470 | (d)Funds Allocated for Plantation | 500000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Increase in the employment for the local people | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1922/RA 0171 | (ii)Name of the EIA Consultant | Global Management and Engineering Consultants Inte | (iii)Address | Saharan Tower, 308, Officers Campus Extension, Sirsi Road, Khatipura, Jaipur-302012 | (iv)Mobile No. | 9928599571 | (v)Landline No. | 0141235324 | (vi)Email Id | info@gmecinternational.com | (vii)Category of Accreditation | B | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 06 Feb 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 16/12/2020 | The proposals/ application is found deficient /incomplete in respect to following:- a).Form- I along with Duly filled environment sensitivity portion. b).Affidavit regarding violation of EIA notification and regarding correctness of submitted data& document by consultant as well as project proponent —Annx. c).Project area and gross built-up area. d). Land documents. e). Water demand and source of water with copy of application submitted to CGWA for withdrawal of ground water. | | (2.) | 24/12/2020 | The correction have been made as per the instruction received | | (3.) | 30/12/2020 | Affidavit by consultant regarding violation of EIA notification and regarding correctness of submitted data & document has not been submitted/uploaded. | | (4.) | 11/03/2021 | The correction have been made as per the instruction received | | (5.) | 25/03/2021 | The proposals/ application is found deficient /incomplete in respect to following:- a). Affidavit by consultant regarding violation of EIA notification and regarding correctness of submitted data& document —Annx. | | (6.) | 27/03/2021 | The correction have been made as per the instruction received | | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Anup Kumar Jindal | Designation | Director | Name of Company (Applicant Name should not be given here) | SHRI JINDAL TOR INDIA PVT LTD | Address | A- 385, A- 386, A- 388, RIICO, Growth Centre, Hamirgarh, Bhilwara |
|