EC Report
1. Project Details
   i. Proposal No. : SIA/JK/IND2/17125/2016    ii. File No. : SEAC/2017/11    iii.Short narrative of the project: Development of LPG Storage Terminal (3X500 MT) At HPCL LPG Bottling Plant, Lane no 3, SIDCO Complex, Bari Brahmana, Jammu – 181133    iv. Project Sector : Industrial Projects - 2    v. Subcategory : B1    vi. Company/Proponent : Hindustan etroleum Corporation Limited
  vii.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.Jammu and KashmirJammuSamba
 
   viii.Date of TOR Granted 29 Mar 2017 ix.TOR letter issued by Ministry: Annexure-TOR letter
  Important Dates
Important Dates
Accepted by SEIAA and forwarded to SEAC Accepted by SEAC EC Granted
19 May 201720 May 201706 Apr 2018
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing
  i.EIA/EMP: Nil   ii.Risk Assessment: Nil   iii.Public Hearing: Nil    iv. Date of Public Hearing: 04 Apr 2017   ix. Uploaded Cover Letter: Nil   x. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Nil   xi. Remarks: Industrial II Committee MINUTES OF 23rd EXPERT APPRAISAL COMMITTEE (INDUSTRY-2) MEETING HELD DURING 3rd to 5th May, 2017: Considered TWO HPCL Project in B2 Category: Copy enclosed
3. Additional Detail Sought
Additional Detail Sought
S.no. Ads Letter Remarks Date of Submission
1. Additional Information by SEACThe HPCL has been advised to respond to the queries raised by the Hon'ble Members of SEAC during its meeting on 13.06.2017.01 Jul 2017
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 64    iii. Name of Consultant: EQMS INDIA PVT LTD   iv. Address : 05- 306, 3rd Floor, Plot No. 16, Rishabh Corporate Towers, Community Centre, Karkardooma, Delhi, 110092   v. Mobile No.: 8890836012   vi. Landline No.: 01130003200   vii. Email Id: alok@eqmsindia.org
Essential Details Sought
Essential Details Sought
S.no. EDS Sought Date EDS Sought Letter
1.01/01/1900The corrections have been made as per the instruction received.2.03/10/2017Your case shall be complied only when all the points raised by SEAC are complied with. Please do needful and comply point No.3 of letter dt.30/07/2017EDS Letter
3.01/01/1900The corrections have been made as per the instruction received.4.19/08/2017Please upload your response on SEAC link of EC portal instead of SEIAA link of the EC portal against Additional details sought.EDS Letter
 
Additional Details Sought
Additional Details Sought
S.no. ADS Sought Date ADS Sought Letter
1.07/02/2018Risk analysis report Have been revised and ERDMP of proposed Mound storage Jammu Plant integrated with State disaster Management plant.The same has been uploaded on www Dc office sambha website under circulars & orders. Our portion has been incorporated from pg no 78 to 83.EDS Letter
2.07/02/2018Risk analysis report Have been revised and ERDMP of proposed Mound storage Jammu Plant integrated with State disaster Management plant.The same has been uploaded on www Dc office sambha website under circulars & orders. Our portion has been incorporated from pg no 78 to 83.EDS Letter
3.07/02/2018As telephonically desired by the consultant, the ADS is uploaded afreshEDS Letter
4.01/07/2017The HPCL has been advised to respond to the queries raised by the Hon'ble Members of SEAC during its meeting on 13.06.2017.EDS Letter
 
5. Undertaking
The aforesaid application and documents furnished here with are true to my knowledge
   i. Name : Hindustan etroleum Corporation Limited    ii. Designation : Plant Manager    iii. Company : Hindustan etroleum Corporation Limited    iv. Address : HPCL LPG BOTTELING PLANT, SIDCO COMPLEX BARI Brahmana Jammu 181133 J&K
6. Recommendation by SEAC/SEIAA :   NIL
Print