Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Clay(brick earth) mining project by Smt rekha Joshi
(b)Name of the Company / Organisation SMT REKHA JOSHI PROP MS KIRAN BRICKS KILN
(c)Registered Address village and P.O Badhera,,Una,Himachal Pradesh-177220
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Rekha Joshi
(b)Designation (Owner/ Partner/ CEO) owner
(c)Address village and P.O Badhera,,Una/Haroli,Una,Himachal Pradesh-177220
(d)Pin code 177220
(e)E-mail rekhajoshi1122una@gmail.com
(f)Telephone No. 0-00000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B2
(d)Proposal Number SIA/HP/MIN/43042/2019
(e)Master Proposal Number(Single Window) SW/118367/2019
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1796 AND 1800
(b)Pincode 177220
(c)Bounded Latitudes (North)
From
Degree 31
Minutes 26
Second 51
From
Degree 31
Minutes 26
Second 55
(d)Bounded Longitudes (East)
From
Degree 76
Minutes 11
Second 45
From
Degree 76
Minutes 11
Second 46
(e)Survey of India Topo Sheet No. H43E3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 454
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 3.5
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Himachal Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Himachal PradeshUnaUna/HaroliBadhera
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number NA
(b)Date of Apply of TOR 30 Aug 2019
(c)Date of Issue of TOR / Standard ToR 06 Sep 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason as this is less than 5ha
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)MANUAL MININGNANA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1.2728 AREA19.8Cubic Meter per DayRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 10 Sep 2019
(iv)Valid Upto 08 Nov 2019
(v)File No. 0
(vi)Application No. 0
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.087
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.012
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.006
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.057
(e) Funds Allocated for Environment Management Capital(%) 13.79
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)00Cubic Meter per Day0Road0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 05 Jun 2019 To 08 Jun 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube61.844021.4100
(2.)SO2Micro Gram per Meter Cube10.2282.180
(3.)NOxMicro Gram per Meter Cube19.9316480
(4.)PM2.5Micro Gram per Meter Cube29.58191160
    14.2.     No. of Ground Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.436.66.58.5
(2.)Total Hardnessmg/l6459200600
(3.)Fluoridemg/l0.150.1211.5
(4.)Heavy MetalsLEADmg/l0.0100.010.05
(5.)TSSmg/l0000
(6.)TDSmg/l3602805002000
(7.)Chloridesmg/l35.57292501000
    14.3.     No. of Surface Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.356.9A
(2.)BODmg/l3.83.5A
(3.)DOmg/l7.15.9A
(4.)CODmg/l2418A
    14.4.     No. of Ambient Noise Monitoring Locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.652.675
(2.)Leq(Night)A-weighted decibels(dB(A))585170
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.597.1
(2.)K(Potassium)Milligram per Kilogram293.99250
(3.)Electric ConductivityMillisiemens per Centimetre362.2300
(4.)N(Nitrogen)Percent0.0970.08
(5.)P(Phosphorus)Milligram per Kilogram73.8969
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 45
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.5 To 42
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2.01.4Copy of Permission LettermodeOthersrented tankOthersborewell005 Sep 20192.0
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)0000Discharge into Surface Water Body0
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)0OthersMINE WASTE0Tons0RoadOthersNOT APPLICABLE
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube00000
(2.)SO2Microgram per Meter Cube00000
(3.)NOxMicrogram per Meter Cube00000
(4.)PM10Microgram per Meter Cube00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
(2.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source 0
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 1.2728
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.2728
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 3807.94
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 453.8
(e)Settlements 45.56
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : khad and scrub land 3768.19
    Total 8075.49
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Othersnot required0
Total 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA0NA
(2.)ESZsNA0NA
(3.)CorridorsNA00
(4.)Wildlife CorridorsNA00
(5.)Critically Polluted AreaNA0NA
(6.)WLSNA0NA
(7.)NPANA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0NA
(2.)ForestNA00
(3.)Defence InstallationsNA00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area swan river
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 3.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 10
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 20
(e)No. of working days 270
(f)Total Manpower 30
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 1.2728
(b)Percentage of Total Project Area 100.00
(c)No. of Plants to be Planted 150
(d)Funds Allocated for Plantation 1.5
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialwill provide employment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)clayMinor
2.
Mine Capacity in ROM (Run of Mine) 5342
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. udyog-bhu(khani-4)laghu-78/17-2593
(b)Date of Approval 05 Jul 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department department of industries
(e)Approved Mining Lease Area 1.2728
(f)Approved Capacity 5342
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 61500
(b)Mineable Reserves (Million Ton) 26710
(c)Extractable Reserves(Million Ton) 5342
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral 0
(f)Stripping Ratio 1 : 16
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) 0
(h)Average Gradient(Degree) 60
(i)Mining Method Opencast
(j)Life of Mine (Years) 5
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1.2728
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 13 Aug 2018
(iii)Validity of LOI 1
(iv)Reference No. of LOI udyog bhu(khani-4)laghu 78/17-4753
(c)Whether Lease Deed Executed ? No
(i)Reason thereof na
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof nA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0
(b)Depth (in meter) 0
(c)Volume (in Million Cubic meter) 0
12.
Details of Quarry:
(a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0
13.
Details of Transportation:
(a)In Pit/Underground to Surface 0
(b)Surface to Siding/Loading 0
(c)Transportation / Conveyor Details 0
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)SETTLEMENTS045.5645.56
(2.)AGRICULTURE LAND03807.943807.94
(3.)OTHERS(Specify)KHAD AND SCRUB LAND03768.193768.19
(4.)WASTE LAND000
(5.)GRAZING LAND000
(6.)FOREST LAND000
(7.)SURFACE WATER BODIES0453.8453.8
TOTAL08075.498075.49
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)VIRGIN AREA0000
(2.)GREEN BELT15000150
(3.)EXTERNAL OB DUMPS0000
(4.)INTERNAL OB DUMPS0000
(5.)ROADS0000
(6.)BUILT UP AREA (COLONY/OFFICE)0000
(7.)EXCAVATION/QUARRY15000150
(8.)TOP SOIL STORAGE0000
TOTAL300000300
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 0
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 150
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 0
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant as this is small mining project
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)19/09/2019Kindly resubmit proposal as per following: Sr. No. 4 : Attach valid KML file indicating boundary of mining area. Sr. No. 35(8) Attach valid letter of intent.
(2.)09/10/2019The correction have been made as per the instruction received
(3.)18/10/2019KML file is not matching with layout plan kindly submit revised KML file.
(4.)24/10/2019The correction have been made as per the instruction received
(5.)10/02/2020Letter attached for further n/aEDS Letter
(6.)16/08/2021The correction have been made as per the instruction received
(7.)20/09/2021Kindly submit the hard copy and softcopy of proposal number SIA/HP/MIN/43042/2019 size less than 50mb.
(8.)27/11/2021The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)08/12/2021Kindly resubmit with observations of 83rd meeting of SEAC.ADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRekha Joshi
Designationowner
Name of Company (Applicant Name should not be given here)SMT REKHA JOSHI PROP MS KIRAN BRICKS KILN
Addressvillage and P.O Badhera
Print