1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s Indorama Industries Private Limited located at Plot No. 10, Village- Lodhimajra, Tehsil-Baddi, District-Solan, Himachal Pradesh | (b)Name of the Company / Organisation | M/S INDORAMA INDIA PRIVATE LIMITED | (c)Registered Address | Plot No. 10, Village- Lodhimajra, Tehsil- Baddi, District- Solan, Himachal Pradesh,Chandigarh,Chandigarh-160101 | (d)Legal Status of the Company | Private | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Mr Sandeep Shelke | (b)Designation (Owner/ Partner/ CEO) | Business Head and Director | (c)Address | Plot No. 10, Village- Lodhimajra, Tehsil- Baddi, District- Solan, Himachal Pradesh,Chandigarh,Chandigarh-160101 | (d)Pin code | 160101 | (e)E-mail | indoramaindia101@gmail.com | (f)Telephone No. | 172-4616225 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 5(d) Manmade fibres manufacturing
| (b)Minor Project/Activity | 5(d) Manmade fibres manufacturing
| (c)Category | B1 | (d)Proposal Number | SIA/HP/IND2/67828/2021 | (e)Master Proposal Number(Single Window) | SW/231055/2021 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (g)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. 10 | (b)Pincode | 174101 | (c)Bounded Latitudes (North) | | From | | Degree | 30 | Minutes | 59 | Second | 52.10 | From | | Degree | 30 | Minutes | 59 | Second | 59.09 | (d)Bounded Longitudes (East) | | From | | Degree | 76 | Minutes | 46 | Second | 20.28 | From | | Degree | 76 | Minutes | 46 | Second | 32.53 | (e)Survey of India Topo Sheet No. | H43E/12, H43E/16, H43K9 & H43K/13 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 406.9 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Himachal Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Himachal Pradesh | Solan | Baddi | Lodhimajra | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | HPSEIAA/2021/834-904 | (b)Date of Apply of EC | 24 Jul 2021 | (c)Date of Issue of EC | 31 Dec 1899 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | The project falls located within the Notified Indu | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Dehradun | (iii)Letter No. | NC-RO/ENV/IND/HP/8/2015/2407 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | N/A | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Spandex Yarn | 16500 | 12000 | 28500 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Plant Area (in sq.m.) | 1,00,000 | 0 | 1,00,000 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 01 Apr 2020 | (iv)Valid Upto | 31 Mar 2022 | (v)File No. | HPSPCB No.: 1375 | (vi)Application No. | 1950070 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 971 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 2.45 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.104 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 0.42 | (e) Funds Allocated for Environment Management Capital(%) | 0.25 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 13187.815 | (b)Existing quantity of raw material/fuel | 18016.4 | (c)Total quantity of raw material/fuel | 31204.215000000004 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | List of RM is enclosed | 31204.21 | Others | MTA | Korea, Taiwan, America | Others | through roads & port services | 1390.67 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 22 Jan 2021 To 13 Feb 2021 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 17 | 8 | 15.7 | 80 | (2.) | PM10 | | Micro Gram per Meter Cube | 127 | 60 | 120 | 100 | (3.) | Others | CO | Mili Gram per Meter Cube | 0.83 | 0.43 | 0.8 | 4.0 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 75 | 35 | 73 | 60 | (5.) | NOx | | Micro Gram per Meter Cube | 35 | 16 | 33 | 80 | |
14.2. No. of Ground Water Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.41 | 7.19 | 6.5 | 8.5 | (2.) | Others | Total Alkalinity | | mg/l | | 196 | 14 | 200 | 600 | (3.) | TDS | | | mg/l | | 486 | 37 | 500 | 2000 | (4.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (5.) | Total Hardness | | | mg/l | | 192 | 180 | 200 | 600 | (6.) | Chlorides | | | mg/l | | 110 | 2 | 250 | 1000 | (7.) | Heavy Metals | | Zn | mg/l | | 0.05 | 0.05 | 5 | 15 | (8.) | Fluoride | | | mg/l | | 0.68 | 0.18 | 1.0 | 1.5 | |
14.3. No. of Surface Water Monitoring Locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 9.9 | 6.2 | E | (2.) | pH | | NA | | 7.65 | 7.28 | E | (3.) | DO | | mg/l | | 5.7 | 4.6 | E | (4.) | COD | | mg/l | | 32 | 20 | E | |
14.4. No. of Ambient Noise Monitoring Locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.1 | 53.2 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 57.1 | 42.1 | 70 | |
14.5. No. of Soil Sample Monitored Locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Percent | | 9.2 | 6.7 | (2.) | pH | | | 7.36 | 7.15 | (3.) | P(Phosphorus) | Milligram per Kilogram | | 140 | 115 | (4.) | K(Potassium) | Milligram per Kilogram | | 47 | 34 | (5.) | Electric Conductivity | Millisiemens per Centimetre | | 0.75 | 0.68 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 5.01 To 28.76 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 27.57 To 3.02 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 858 | 0 | Copy of Permission Letter | Pipeline | | Others | Borewells | IPH-SE-P&I-II-EE(M)-GWA/2010 383-85 | 28 Apr 2011 | 3120 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic Waste water, Process Waste Water | 128 | 100 | ETP cum STP & STP of 100 KLD | Others | Reuse in gardening | 128 | 0 | |
|
16.1. | (a)Total Waste Water Generation | 128 | (b)Total Discharged Water | 0 | (c)Total Reused Water | 128 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Chemical sludge from waste water treatment | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 603.5 | Tons | 0 | Road | | Others | HDPE bags & sent to TSDF site for disposal | (2.) | Still bottom from distillation process | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 603.5 | Tons | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Ash | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 11315 | Tons | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Municipal Solid Waste | Municipal Solid Waste | | 39 | Tons | 0 | Road | | Authorized Recyclers | | (5.) | Bag filter residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1.1 | Tons | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (6.) | Waste Yarn & Packaging Material | Industrial Waste | | 384 | Tons | 0 | Road | | Others | Waste yarn recycling plant | (7.) | Used oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.03 | Kilolitre | 0 | Road | | Others | Sold to authorized vendors | (8.) | Chemical Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 724 | Tons | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | Others(Specify) | CO | NA | 0.8 | 1.4 | 0.0362 | 0.83 | 4 | (2.) | NOx | | Microgram per Meter Cube | 33 | 1.1 | 35.82 | 68.82 | 80 | (3.) | SO2 | | Microgram per Meter Cube | 15.7 | 1.1 | 5.81 | 21.51 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 120 | 1.4 | 22.96 | 142.96 | 100 | (5.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 0 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 7 D.G sets of 2000kVA | low sulphur | 30 | 0.6 | NOx | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 11250 | (b)Source | HPSEBL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 7 D.G sets of capacity 2000kVA each | (e)Stack Height (in m) | 30 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 10 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 0 | Total Land | 10 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 0 | (b)Waste/Barren Land | 0 | (c)Grazing/ Community Land | 0 | (d)Surface Water Bodies | 0 | (e)Settlements | 0 | (f)Industrial | 0 | (g)Forest | 0 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : Total Plot Area | 10 | Total | 10 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Others | Total Plot area | 10 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | NA | 0 | Not found within 10km radius of the project area | (2.) | ESAs | NA | 0 | Not found within 10km radius of the project area | (3.) | ESZs | NA | 0 | Not found within 10km radius of the project area | (4.) | Wildlife Corridors | NA | 0 | Not found within 10km radius of the project area | (5.) | Corridors | NA | 0 | Not found within 10km radius of the project area | (6.) | Critically Polluted Area | NA | 0 | Not found within 10km radius of the project area | (7.) | NPA | NA | 0 | Not found within 10km radius of the project area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Palahwala PF | 1.9 | Protected forest | (2.) | Others | NA | NA | 0 | Not found within 10km radius of the project area | (3.) | Defence Installations | | NA | 0 | Not found within 10km radius of the project area | (4.) | Archaeological Sites | | NA | 0 | Not found within 10km radius of the project area | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 10 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Phula Nala, Sirsa Nadi | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 500 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 13 | (e)No. of working days | 365 | (f)Total Manpower | 523 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 36405 | 0 | 36405 | (2.) | Percentage of Total Project Area | 36.4 | 0 | 36 | (3.) | No. of Plants | 2296 | 3167 | 5463 | (4.) | Funds Allocated | 1000000 | 0 | 1000000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Landscapping | (2.) | Social | Direct or Indirect Employment generation | (3.) | Financial | Revenue generation | (4.) | Others | NA | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1922/RA 0163 | (ii)Name of the EIA Consultant | Enviro Techno Consult Private Limited | (iii)Address | 68, Mahakali Nagar-2, Near Manewada Square, Nagpur-440020 | (iv)Mobile No. | 9326466633 | (v)Landline No. | 0 | (vi)Email Id | etcpl@envirotechnoconsult.in | (vii)Category of Accreditation | B | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 25 Feb 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 04/10/2021 | Kindly submit the hard copy and soft copy size less then 50MB. | | (2.) | 08/10/2021 | The correction have been made as per the instruction received | | (3.) | 08/10/2021 | Kindly submit the hard copy of proposal and soft copy size less then 50MB. | | (4.) | 08/10/2021 | The correction have been made as per the instruction received | | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Mr Sandeep Shelke | Designation | Business Head and Director | Name of Company (Applicant Name should not be given here) | M/S INDORAMA INDIA PRIVATE LIMITED | Address | Plot No. 10, Village- Lodhimajra, Tehsil- Baddi, District- Solan, Himachal Pradesh |
|