1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | SAND AND GRAVEL PERMIT AREA AT BORGANG RIVER BED | (b)Name of the Company / Organisation | SRI RATUL BASUMATARY | (c)Registered Address | Kuwari Village, po: Kuwari, ps: Halem, District- Biswanath,,Biswanath,Assam-784176 | (d)Legal Status of the Company | Private | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ratul Basumatary | (b)Designation (Owner/ Partner/ CEO) | Proprietor | (c)Address | kuwari gaon, po-kuwari, ps- halem, District- Biswanath,,Biswanath,Biswanath,Assam-784176 | (d)Pin code | 784176 | (e)E-mail | ratul.ec2020@gmail.com | (f)Telephone No. | 376-2327150 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 1(a) Mining of minerals
| (b)Minor Project/Activity | NIL | (c)Category | B2 | (d)Proposal Number | SIA/AS/MIN/227550/2021 | (e)Master Proposal Number(Single Window) | SW/227549/2021 | (f)EAC concerned (for category A Projects only) | Non-Coal Mining | (g)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | BORGANG RIVER BED | (b)Pincode | 784176 | (c)Bounded Latitudes (North) | | From | | Degree | 26 | Minutes | 52 | Second | 15.09 | From | | Degree | 26 | Minutes | 52 | Second | 22.53 | (d)Bounded Longitudes (East) | | From | | Degree | 93 | Minutes | 15 | Second | 29.10 | From | | Degree | 93 | Minutes | 15 | Second | 33.38 | (e)Survey of India Topo Sheet No. | 83F/5 OF ZONE 46 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 60 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.5 | (j)Seismic Zone | 5 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Assam | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Assam | Biswanath | Biswanath | KUWARI | |
|
6. | Details of Terms of Reference (ToR): | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | CATEGORY B2 PROJECT WITH AREA LESS THAN 5 Ha WHICH | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | N/A | N/A | N/A | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | 2.43 | 4 | Cubic Meter per Day | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 0.034 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 0.0004148 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.0008466 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 0.0000952 | (e) Funds Allocated for Environment Management Capital(%) | 1.22 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | NA | 0 | Cubic Meter per Day | | 0 | Road | | 0 | Others | n/a | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 02 Sep 2021 To 02 Sep 2021 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | NA | 0 | 0 | 0 | 0 | (2.) | NOx | | NA | 0 | 0 | 0 | 0 | (3.) | PM10 | | NA | 0 | 0 | 0 | 0 | (4.) | PM2.5 | | NA | 0 | 0 | 0 | 0 | |
14.2. No. of Ground Water Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | NA | | 0 | 0 | 0 | 0 | (2.) | pH | | | NA | | 0 | 0 | 0 | 0 | (3.) | TSS | | | NA | | 0 | 0 | 0 | 0 | (4.) | TDS | | | NA | | 0 | 0 | 0 | 0 | (5.) | Total Hardness | | | NA | | 0 | 0 | 0 | 0 | (6.) | Fluoride | | | NA | | 0 | 0 | 0 | 0 | (7.) | Heavy Metals | | 0 | NA | | 0 | 0 | 0 | 0 | |
14.3. No. of Surface Water Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | NA | | 0 | 0 | A | (2.) | pH | | NA | | 0 | 0 | A | (3.) | DO | | NA | | 0 | 0 | A | (4.) | COD | | NA | | 0 | 0 | A | |
14.4. No. of Ambient Noise Monitoring Locations : 0 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | |
14.5. No. of Soil Sample Monitored Locations : 0 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | | | 0 | 0 | (2.) | P(Phosphorus) | | | 0 | 0 | (3.) | K(Potassium) | | | 0 | 0 | (4.) | pH | | | 0 | 0 | (5.) | N(Nitrogen) | | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0 To 0 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0 To 0 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 0.5 | 0.5 | Copy of Permission Letter | modeOthers | TANKER | Others | TANKER | N/A | 02 Sep 2021 | 0.5 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | 0 | 0 | 0 | 0 | Others | N/A | 0 | 0 | |
|
16.1. | (a)Total Waste Water Generation | 0 | (b)Total Discharged Water | 0 | (c)Total Reused Water | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | 0 | Others | 0 | 0 | Tons | 0 | Others | N/A | Others | N/A | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | NA | 0 | 0 | 0 | 0 | 0 | (2.) | SO2 | | NA | 0 | 0 | 0 | 0 | 0 | (3.) | PM2.5 | | NA | 0 | 0 | 0 | 0 | 0 | (4.) | NOx | | NA | 0 | 0 | 0 | 0 | 0 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | Others | N/A | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 0 | (b)Source | 00 | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 0 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 2.43 | Total Land | 2.43 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 0 | (b)Waste/Barren Land | 0 | (c)Grazing/ Community Land | 0 | (d)Surface Water Bodies | 0 | (e)Settlements | 0 | (f)Industrial | 0 | (g)Forest | 0 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : 0 | 0 | Total | 0 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Others | 0 | 0 | 0 | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESAs | N/A | 0 | 0 | (2.) | Corridors | n/a | 0 | 0 | (3.) | Wildlife Corridors | N/A | 0 | 0 | (4.) | ESZs | N/A | 0 | 0 | (5.) | Critically Polluted Area | N/A | 0 | 0 | (6.) | WLS | N/A | 0 | 0 | (7.) | NPA | N/A | 00 | 0 | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | N/A | 0 | 0 | (2.) | Archaeological Sites | | N/A | 0 | 0 | (3.) | Defence Installations | | N/A | 0 | 0 | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 50 | (e)No. of working days | 200 | (f)Total Manpower | 50 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt (in hectare) | 0 | (b)Percentage of Total Project Area | 0.00 | (c)No. of Plants to be Planted | 0 | (d)Funds Allocated for Plantation | 0 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | IT WILL GENERATE EMPLOYMENT LOCALLY | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Non-Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | RIVER BED SAND | Minor | |
|
2. | Mine Capacity in ROM (Run of Mine) | 32 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | GM/MM/86-B (40)/Pt II/4317-21 | (b)Date of Approval | 24 Oct 2019 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | State | (e)Approved Mining Lease Area | 2.43 | (f)Approved Capacity | 1700 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 0.13122 | (b)Mineable Reserves (Million Ton) | 0.118098 | (c)Extractable Reserves(Million Ton) | 0.06471 | (d)Percent(%) of Extraction | 49.31 | (e)Grade of Coal /Ore /Mineral | 0 | (f)Stripping Ratio | 0 : 0 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | 0 | (h)Average Gradient(Degree) | 0 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 2 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | No | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 2.43 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | Yes | (i)Copy of Letter of Intent | Copy of Letter of Intent | (ii)Date of issue of LOI | 27 Sep 2019 | (iii)Validity of LOI | 2 | (iv)Reference No. of LOI | FSET/B/PERMIT/2019/5182 | (c)Whether Lease Deed Executed ? | No | (i)Reason thereof | FRESH EC | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | FRESH EC | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | 0 | (ii)Total Area (in Hectare) | 0 | (iii)Height (in meter) | 0 | (iv)Quantity (in Million Cubic meter) | 0 | (v)No. of year back fill up | 0 | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | 0 | (ii)Total Area (in Hectare) | 0 | (iii)Height (in meter) | 0 | (iv)Quantity (in Million Cubic meter) | 0 | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 0 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 0 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | 0 | (b)Depth (in meter) | 0 | (c)Volume (in Million Cubic meter) | 0 | |
|
12. | Details of Quarry: | (a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 0 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | 0 | (b)Surface to Siding/Loading | 0 | (c)Transportation / Conveyor Details | 0 | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | GRAZING LAND | | 0 | 0 | 0 | (2.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (3.) | SETTLEMENTS | | 0 | 0 | 0 | (4.) | WASTE LAND | | 0 | 0 | 0 | (5.) | AGRICULTURE LAND | | 0 | 0 | 0 | (6.) | FOREST LAND | | 0 | 0 | 0 | |
TOTAL | 0 | 0 | 0 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | EXTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (2.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (3.) | ROADS | | 0 | 0 | 0 | | 0 | (4.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 0 | | 0 | (5.) | EXCAVATION/QUARRY | | 0 | 0 | 0 | | 0 | (6.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (7.) | GREEN BELT | | 0 | 0 | 0 | | 0 | (8.) | VIRGIN AREA | | 0 | 0 | 0 | | 0 | |
TOTAL | 0 | 0 | 0 | 0 | 0 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 0 | (b)Internal Dump(in hectare) | 0 | (c)Quarry(in hectare) | 0 | (d)Safety Zone(in hectare) | 0 | (e)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 0 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 0 | (h)Total afforestation plant (in hectare) | 0 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 2021 | 0 | 0 | 0 | 0 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | No | (i)Reason for not Hiring the Consultant | NO CONSULTANT IN ASSAM | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 28/02/2022 | Please upload documents as attached. | EDS Letter | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ratul Basumatary | Designation | Proprietor | Name of Company (Applicant Name should not be given here) | SRI RATUL BASUMATARY | Address | Kuwari Village, po: Kuwari, ps: Halem, District- Biswanath |
|