APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Expansion of existing capacity (460 metric tons per month –MTPM) to 2100 MTPM of Pesticides Technical, Intermediate & Pesticides Formulation Products | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/WB/IND2/86650/2018 | Project Cost | 16531 lacs | |
| 2. | |
S. No. in the schedule | 5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
| Project Sector | Industrial Projects - 2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 2100 ha. | | 4. | New/Expansion/Modernization | Expansion | Proposal Number | IA/WB/IND2/86649/2008 | MoEFCC file number(Previous EC) | J-11011/914/2008-IA II (I) | Uploaded EC letter | Annexure-Uploaded EC letter | | | 5. | Existing Capacity/Area etc. | 460 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Haldia Industrial Area, East Medinipur, West Bengal | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | RS 12, 14, 15, 16, 17, 18 & 19 of Jagat Chak Mouza and RS 60, 61, 62, 63, 64 & 65 of Barkumar Chak Maouza | Town / Village | Haldia Industrial Area | State of the project | West Bengal | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | West Bengal | East Medinipur | Sutahata - I | | 10. | |
Nearest railway station along with distance in kms | Durgachak, 0.6 km | Nearest airport along with distance in kms | Netaji Shubhas Chandra International Airport, Kolkata, 140 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Durgachak , 0.6 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Haldia Municipality, Ward No 12
PO- Debhog, Haldia, Dist. Purba Medinipur, West Bengal Pin-721657. Phone: 03224- 252996 | | 13. | Name of the Applicant | Subinay | | 14. | Registered Address | UPL Limited, Unit -9, Durgachak, East Medinipur, West Bengal | | 15. | |
Address for correspondance: | Name of the Company | UPL LIMITED UNIT IX | Name of the Applicant | Subinay | Designation (Owner/ Partner/ CEO) | VicePresident | Pin code | 721602 | E-mail | janasb@uniphos.com | Telephone No. | 03224-264826 | Fax No. | 03224- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | Yes | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | The total land of the plant is 60702.82 sq. m (15 acre). This land has been taken long term lease from Kolkata Port Trust Haldia Dock Complex for Industrial use. The land required for proposed expansion unit is 1200 sq. m and same is available within the plant | 1.2 | Clearance of existing land, vegetation and buildings? | No | Proposed expansion unit will be constructed in the existing built-up area of the plant. There is no vegetation and permanent building at proposed expansion site. | 1.3 | Creation of new land uses? | No | The existing unit is in operational and land use is industrial land | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | Topography survey and soil investigation study have already been conducted for existing unit. Hence not proposed. | 1.5 | Construction works? | Yes | Construction of existing unit has been completed. Construction of expansion units and associated facilities shall be undertaken. | 1.6 | Demolition works? | Yes | Industrial shed used for storage of raw materials need to be demolished for proposed expansion unit. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Local Employment of construction labors will be encouraged hence there is no need for temporary sites for housing of construction workers. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | The project includes above ground structures and linear structures of:
Plant building,
DG room and stack
Raw material & finished products storage shed. | 1.9 | Underground works including mining or tunnelling? | No | The proposal involves expansion of pesticide technical unit hence not applicable. | 1.10 | Reclamation works? | No | Not applicable | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | Yes | The Production processes for all Technical grade pesticides is given in Table 2.1 with Pre Feasibility Report. | 1.14 | Facilities for storage of goods or materials? | Yes | A temporary shed would be made for the storage of construction materials during construction as per the requirement for the goods which cannot be stored in open space.
Raw Material Storage Area & Finished Products Area will be developed for proposed expansion activities. Raw material & Finished goods stored separately. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | An effluent treatment plant (230 KLD) shall be constructed for the proposed expansion units for treating the process liquid wastes. Details are provided in PFR Section 3.10.
Additional quantity of Solid/hazardous waste will be sent to approved CHWT&DF Facility operated by West Bengal Waste Management Ltd.
Details of Existing, proposed & total quantity of wastewater, solid and Hazardous waste generation is shown in Section 6.9 In pre-feasibility report. | 1.16 | Facilities for long term housing of operational workers? | No | Exiting man power of the plant is 134. The estimated Manpower requirement for the proposed expansion units shall be about 325 persons.
No residential accommodation has been proposed for the proposed expansion unit. Workers of the plant are residing in the Haldia town. | 1.17 | New road, rail or sea traffic during construction or operation? | No | The proposed expansion project requires road for transportation of materials during construction and operation. Existing roads leading to plant site shall be used for material transportation and no requirements of new roads has been envisaged. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | The equipment and material shall be transported through the existed road/ Haldia Port/ Railways. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not envisaged | 1.20 | New or diverted transmission lines or pipelines? | No | Not envisaged | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | There will not be any change. The required water for proposed expansion unit will be supplied through HDA existing pipeline. | 1.22 | Stream crossings? | No | There are no streams which have to be crossed in the area identified for the proposed unit. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | The Existing water requirement is 60 KLD sourced from HDA and additional requirement of 311 KLD will be sourced from HDA.
Hence After expansion Total 371KLD Water will be required. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not applicable | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | During construction / operation, men and material shall be transported to the site mostly by road | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | No | During construction, on an average about 100 number of temporary labour force will be utilized | 1.29 | Introduction of alien species? | No | Not Envisaged | 1.30 | Loss of native species or genetic diversity? | No | Not Envisaged | 1.31 | Any other actions? | No | Not Envisaged | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | Land requirement for the proposed expansion project is about 1200 sq. m approx. within existing plant site.
The total land area available at existing industrial plot site is 60702.82 sq. m (15 acre). | 2.2 | Water (expected source & competing users) unit: KLD | Yes | The Existing water requirement is 60 KLD sourced from HDA and additional requirement of 311 KLD will be sourced from HDA.
Hence after expansion total 371 KLD water will be required. | 2.3 | Minerals (MT) | No | Not Applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Stone, Aggregates, Sand/Soil, cement, steel will be purchased from local suppliers & the quantity will be decided after the completion of construction drawing & designing. However Minimum quantities of local construction material shall be used during the construction phase of the project | 2.5 | Forests and timber (source – MT) | No | Not Envisaged | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Construction phase- electricity from Grid supply & 500 KVA backup DG.
Power:
Existing – 4250 KW.
Additional – 43530KW
Source: WBSEDCL.
Backup Power DG sets:
Existing: 500 KVA + 600 KVA
Additional: 2000 KVA
Coal fired boiler:
Existing: 1 x 8 TPH
Additional: 2 x 15 TPH
Fuel for boiler (coal):
Existing – 60 MT/day
Additional- 225 MT/day
Source: Imported coal
Fuel for DG sets (HSD):
Existing- 250 L/day
Additional- 455 L/day | 2.7 | Any other natural resources (use appropriate standard units) | No | Nil | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | The use of raw materials for production of Acephate and DESMP are given as in Pre-feasibility Report (Section 3.7). | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | No changes are anticipated | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | TThere will be general upliftment of the social structure of the surrounding area as well as Social upliftment programs will have a positive effect on the local people. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | The site is in industrial estate, Haldia, West Bengal. | 3.5 | Any other causes | No | Not Envisaged | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | It is a pesticide manufacturing project, no over burden or mine waste is generated. However, during construction (excavation) certain amount of excess earth may be available and is proposed to be used for land leveling within the site. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Small quantities of domestic and office waste will be generated. The generated waste will be disposed off suitably in line with MSW Rules, 2016 | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | The details of hazardous waste management as per Hazardous and Other Wastes (management and transboundary movement) rules 2016 are shown in section 6.9 in pre-feasibility report. | 4.4 | Other industrial process wastes | Yes | QQuantity of Existing, Proposed and Total by product generation is shown in pre-feasibility report. Refer Table 2.2 in pre-feasibility report. | 4.5 | Surplus product | No | Not Envisaged | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Existing, Proposed and Total quantity of ETP sludge generation quantities and disposal method is shown in Section 6.9 of Pre-Feasibility Report. | 4.7 | Construction or demolition wastes | Yes | No demolition activity proposed, Only construction waste will be generated and disposed as per construction and demolition waste management rules 2016. | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Envisaged | 4.10 | Agricultural wastes | No | No agricultural wastes shall be generated | 4.11 | Other solid wastes | No | Not Envisaged | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission from coal fired steam Boilers, process, process stacks will be treated in air pollution control devices and clean gas will be discharged to air. For Emission and air pollution control devices Please refer Section 3.10.2 in pre-feasibility report. | 5.2 | Emissions from production processes | Yes | The emission from the process are HCl, NH3, H2,S, HC. Two stage water scrubber followed by alkali scrubber to scrub HCl gas generated from the process. | 5.3 | Emissions from materials handling including storage or transport | Yes | Material handling will be in closed system and Minor fugitive emission for short span of time due to transportation activity only..
Handling of coal for boiler will generate fugitive emission. Fugitive emissions from handling of raw materials and finished products will be less. | 5.4 | Emissions from construction activities including plant and equipment | Yes | During construction Fugitive dust emission will be there due to various construction activities and vehicular movement. The fugitive emissions will be temporary and will be minimized by adoption of good construction practices | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be generated from construction activities which will be minimized by adoption of good construction practices and odorous sewage generation will be treated in effluent treatment plant.
The unit will make efforts for closed handling system to prevent odour generation. | 5.6 | Emissions from incineration of waste | No | The Incinerable waste will be sent to Common Incineration Facility for incineration and disposal. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Envisaged | 5.8 | Emissions from any other sources | No | Not Envisaged | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | The major noise generating source are DG sets, compressor, cooling towers, etc. Adequate noise control measures will be adopted and to control noise levels.
It is to be noted that there will not be any additional source of noise as utilization of existing facility is proposed for proposed project. Acoustic enclosures will be provided wherever possible. | 6.2 | From industrial or similar processes | Yes | Same as 6.1 above | 6.3 | From construction or demolition | Yes | Construction activities will be allowed only during day time and No demolition work will be carried out. | 6.4 | From blasting or piling | No | Not applicable | 6.5 | From construction or operational traffic | Yes | During construction phase, noise due to vehicular movement and construction equipments which will be for short duration. | 6.6 | From lighting or cooling systems | Yes | Noise will be generated from cooling tower operations. However, it is proposed to keep noise level within the plant premises. | 6.7 | From any other sources | No | Nil | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Hazardous materials will be stored in designated storage area. Other materials will be stored in bags/drums on pallets on concrete flooring.
Spillages of raw materials or finished products will be prevented. In case of spillage, materials will be collected and taken for recycle / treatment. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | After expansion, total 200 KLD effluent will be generated from the process. Effluent will be treated through ETP (230 KLD capacity). Part of the treated water will be recycled and reused in cooling make-up water and greenbelt/land scape area. Balance treated water will be discharged into Hooghly river after meeting discharge standard. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | No contamination of land or water by air emission is envisaged as the proposed project. | 7.4 | From any other sources | No | Nil | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | No long term build up of pollutants is envisaged by strictly implementing mitigative measures and continuous monitoring during operation phase | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | The Unit has On-Site emergency plan to take care of various emergency situations. Fire hydrant system is available around the plant premises.
In case of spillages, it will be collected and contained within work area at plant.
Fire incidents will be controlled with fire hydrant system. Required PPEs will be provided to all workers. | 8.2 | From any other causes | No | Nil | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The site lies in Seismic Zone III. As per the IS standard, the use of foundations which are vulnerable to significant differential settlement due to ground shaking need to be avoided for structures constructed in seismic Zones III. The project site is not falling the flood prone zone. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The project will lead to development of infrastructure facilities in the area. The proposed project will result in considerable growth of surrounding areas By generation of employment, economic uplift and growth of service sector will result in increased income in area | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not envisaged | 9.3 | Set a precedent for later developments | No | Not Applicable | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | Yes | The detailed cumulative impact study will be conducted in EIA Report. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | There is no protected area like National Park, Wildlife Sanctuary, Biosphere Reserve, etc. in the study area. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Hooghly River is located at a distance of 0.45 km south of the plant site | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | Ecological study will be conducted during EIA study | 4 | Inland, coastal, marine or underground waters | Yes | Hooghly is located at a distance of 0.45 km south of the plant site | 5 | State, National boundaries | No | None | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | None | 7 | Defence installations | No | None | 8 | Densely populated or built-up area | Yes | Haldia Town, located approximately 6.5 km from site | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Hanuman Mandir (100 m North)
School at Durgachak area (700 m North)
Haldia College (5.3 km, West) | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | The Haldia Block in Purba Medinipur District has been notified by CGWB and embargo has been imposed on withdrawal on further exploitation of fresh water from aquifers occurring within the depth range of 120 to 300m bgl. | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | The current status of proposed project site location and study area does not fall under “ Critically Polluted Area” notified by MoEF&CC | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The site lies in Seismic Zone III. Design shall follow code requirements for Seismic Zone III to make structures earth quake resistant. The mean annual wind speed is around 5.5 to 9.9 km/hr with rare occurrence of cyclones / tornadoes / cloudburst. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Subinay | Designation | VicePresident | Name of Company (Applicant Name should not be given here) | UPL LIMITED UNIT IX | Address | UPL Limited, Unit -9, Durgachak, East Medinipur, West Bengal |
| |
|