APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Proposed expansion of existing Steel Plant by installation of Sponge Iron Plant with 5x100 TPD DRI Kilns, 4x15 T Induction Furnaces, 50 TPH Coal Washery, Iron Ore Beneficiation & Palletization Plant & 22 MW capacity Captive Power Plant along with the product mix change of existing 2x7 MVA Submerged Arc furnaces | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/WB/IND/77814/2018 | Project Cost | 33200 lacs | |
| 2. | |
S. No. in the schedule | 3(a) Metallurgical industries (ferrous & non ferrous)
| Project Sector | Industrial Projects - 1 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | The company has an operating steel iron plant at Mangalpur Industrial Complex, P.O.- Baktarnagar, Raniganj, District – Paschim Bardhaman of West Bengal. Now, the company has decided for further expansion of its existing plant along with the change of product-mix in its existing Ferro alloy plant, the details of which are presented in the following table: S.N. Facilities Existing Capacity (Having NOC) Proposed Capacity Ultimate Capacity 1. DRI Plant 7 X 50 TPD or 1,05,000 TPA 5 X 100 TPD or ha. | | 4. | New/Expansion/Modernization | Expansion | Proposal Number | IA/WB/IND/77812/1999 | MoEFCC file number(Previous EC) | 2174-51/WPB-NOC/40/99 | Uploaded EC letter | Annexure-Uploaded EC letter | | | 5. | Existing Capacity/Area etc. | 105000 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | G-1, Mangalpur Industrial Complex, P.O.-Baktarnagar, P.S. Raniganj, District – Burdwan, West Bengal | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Plot G1 | Town / Village | Mangalpur Industrial Complex, Raniganj | State of the project | West Bengal | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | West Bengal | Barddhaman | Raniganj | | 10. | |
Nearest railway station along with distance in kms | Raniganj, 3.3 km | Nearest airport along with distance in kms | NSCBI Airport, Kolkata, 170 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Raniganj , 2.0 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Asansol Municipal Corporation,
Station Road, Asansol – 713301,
Burdwan, West Bengal | | 13. | Name of the Applicant | Gaurav | | 14. | Registered Address | 5, Bentinck Street, 1st Floor, Kolkata-700001 | | 15. | |
Address for correspondance: | Name of the Company | JAI BALAJI INDUSTRIES LIMITED | Name of the Applicant | Gaurav | Designation (Owner/ Partner/ CEO) | Director | Pin code | 700001 | E-mail | sankar.hazarika@jaibalajigroup.com | Telephone No. | 033-22489808 | Fax No. | 033- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The proposed expansion project will be installed on 34.8 hectares (86 acres) of land within the existing plant premises. The land is generally flat and does not come under flood zone. Said plot of land will be reformed /developed from its existing land use.
This project will be developed following a land use plan, which will be made taking into consideration relevant guidelines /stipulations of the concerned Authorities. Moreover, the planning of the project, development of green belt and oth | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Site clearing and preparation activities will involve removal of scanty vegetation on the proposed plant site. | 1.3 | Creation of new land uses? | No | - | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | - | 1.5 | Construction works? | Yes | The civil works for the construction and development of the proposed expansion project include bulk earthworks; construction of factory sheds & utilities; internal roads & parking areas; drainage system; underground & overhead tanks etc. | 1.6 | Demolition works? | No | - | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Suitable temporary accommodation for workers will be made within the project site. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Please refer Pre-feasibility Report. | 1.9 | Underground works including mining or tunnelling? | No | - | 1.10 | Reclamation works? | No | - | 1.12 | Offshore structures? | No | - | 1.13 | Production and manufacturing processes? | Yes | Please refer Pre-feasibility Report. | 1.14 | Facilities for storage of goods or materials? | Yes | All construction materials will be handled through site store within the project boundary. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Wastewater:
The plant will be designed as a zero discharge plant as far as the process effluents are concerned. The water will be re-circulated through cooling and treatment. The entire wastewater after necessary treatment will be recycled for various purposes inside the plant.
Domestic wastewater will be treated in septic tank-soak pit system.
Solid Waste:
Dolochar from Sponge iron plant will be used in AFBC Boiler.
Tailing from Iron Ore Beneficiation Plant will be disposed in the ab | 1.16 | Facilities for long term housing of operational workers? | No | Most of the workers employed shall be from nearby villages. | 1.17 | New road, rail or sea traffic during construction or operation? | No | The site will be developed with all infrastructure facilities and is well connected to main road way. No new road, rail or sea traffic during construction or operation. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | - | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | - | 1.20 | New or diverted transmission lines or pipelines? | No | - | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | - | 1.22 | Stream crossings? | No | - | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Daily water requirement in the proposed project for industrial purpose will be around 1140 m3/day and 35 m3/day for drinking and sanitary use.
Domestic and Industrial water will be supplied by Asansol Durgapur Development Authority (ADDA). | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | - | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The plant location has proper road and rail linkages. These systems will be used for transportation of materials, equipment and personnel during construction operation phases. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | - | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | - | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | The proposed project shall increase the employment potential and hence may lead to migration to surrounding villages. Manpower, to the tune of 800 persons will be required for the plant operations. Attempt will made to maximize utilization of local population during the construction activities. | 1.29 | Introduction of alien species? | No | - | 1.30 | Loss of native species or genetic diversity? | No | - | 1.31 | Any other actions? | No | - | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The proposed expansion project will be installed on 34.8 hectares (86 acres) of land within the existing plant premises. The land is generally flat and does not come under flood zone. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | 1175 KLD water will be required for the project which will be supplied by Asansol Durgapur Development Authority (ADDA) water supply system. | 2.3 | Minerals (MT) | Yes | Refer Pre-feasibility Report, Chapter-3.0. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | The construction materials such as cement, MS, sand, aggregates etc. will be sourced locally. | 2.5 | Forests and timber (source – MT) | No | - | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Around 42.5 MW power will be required for the proposed expansion project, which will be sourced from Captive Power Plant & rest from DVC, DPL. | 2.7 | Any other natural resources (use appropriate standard units) | No | - | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | - | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | - | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | The implementation of the proposed expansion project will increase the employment potential for locals with the improvement in their living conditions. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | - | 3.5 | Any other causes | No | - | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | - | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Solid waste of domestic/commercial origin that would be generated in the Plant will be disposed of suitably in consultation with the concerned Civic body. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | - | 4.4 | Other industrial process wastes | Yes | Dolochar from Sponge iron plant will be used in AFBC Boiler.
Tailing from Iron Ore Beneficiation Plant will be disposed in the abandoned mines.
Slag from Induction Furnaces & Bottom ash from AFBC Boiler will be used for Land filling / Road Construction purpose.
Fly ash from AFBC boiler will used in Cement Plant.
End cuts, scales and scraps etc. from CCM will be used in the Induction Furnaces. | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sewage sludge will be disposed off-site in consultation with the concerned local authority. | 4.7 | Construction or demolition wastes | No | Small quantity of construction waste only would be generated and same will be reused for filling. | 4.8 | Redundant machinery or equipment | No | - | 4.9 | Contaminated soils or other materials | No | - | 4.10 | Agricultural wastes | No | - | 4.11 | Other solid wastes | No | - | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Hot gases to be generated during DRI manufacture would be used for raising steam in waste heat recovery boilers. Such steam will be used as fuel in the proposed captive power plant for power generation.
Stacks of adequate height as per relevant norms will be provided. | 5.2 | Emissions from production processes | Yes | Electrostatic Precipitator (ESP) & Bag filter system will be installed to control the particulate emission from the process. | 5.3 | Emissions from materials handling including storage or transport | Yes | Bag filter &dust suppression system will be installed in the raw material handling site. | 5.4 | Emissions from construction activities including plant and equipment | Yes | Water sprinkling arrangement will be provided to reduce dust during construction. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust suppression system will be provided. There will be no odour problem from handling of construction materials, sewage and other wastes. | 5.6 | Emissions from incineration of waste | No | - | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | - | 5.8 | Emissions from any other sources | No | - | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Mainly Noise and vibration. However, all the machinery will be of highest standard of reputed make and will comply with national / international standards that take care of air and noise pollution control / vibration control. | 6.2 | From industrial or similar processes | Yes | Noise and vibration | 6.3 | From construction or demolition | Yes | Best practices will be followed during all construction and installation activities to maintain noise level within permissible limit. | 6.4 | From blasting or piling | Yes | Traffic movement will generate sound. However, best practices will be followed to maintain noise level within 75 dB (A). | 6.5 | From construction or operational traffic | Yes | Best noise abatement measures will adopted to control noise from the cooling systems. | 6.6 | From lighting or cooling systems | No | - | 6.7 | From any other sources | No | - | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | - | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | No effluent or treated sewage will be let out into any water body or land. Sewage will be treated in septic tank and soak pit. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | Dust will be generated to some extent due to different project activities. During the construction phase, proper care will be taken to reduce dust emission, wherever possible. | 7.4 | From any other sources | No | - | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | - | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | - | 8.2 | From any other causes | No | - | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | The area falls under Earthquake Zone-III as per Indian Standard Seismic Zoning Map. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | The project will have insignificant impact on the road network around the project site. The project is not expected to have any impact of concern on the power supply system, housing and wastes management system of the area. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | - | 9.3 | Set a precedent for later developments | Yes | Best practices will be followed during all construction and installation activities to maintain noise level within permissible limit. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | - | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | - | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Damodar River - 5.0 km approx.. in south direction
Ajay River - 14.5 km approx.. in north direction | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | - | 4 | Inland, coastal, marine or underground waters | Yes | Damodar River - 5.0 km approx.. in south direction
Ajay River - 14.5 km approx.. in north direction | 5 | State, National boundaries | No | - | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | - | 7 | Defence installations | No | - | 8 | Densely populated or built-up area | Yes | Raniganj - WiWithin 6.0 km approx.thin 2.5 km approx.
Andal - Within 6.0 km approx. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | ? Belunia Hospital – 3.7 km
? SKS Public School - 0.50 km
? TDB College - 2.60 km
? Dev Public School – 2.50 km
? Gyan Bharati School - 2.75 km
? Searsole Raj High School - 2.65 km
? Anjuman high school - 2.60 km
? Raniganj High School – 3.25 km
? Ballavpur Primary School - 2.8 km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Damodar River - 5.0 km approx.. in south direction
Ajay River - 14.5 km approx.. in north direction | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | - | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | - | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Gaurav | Designation | Director | Name of Company (Applicant Name should not be given here) | JAI BALAJI INDUSTRIES LIMITED | Address | 5, Bentinck Street, 1st Floor, Kolkata-700001 |
| |
|