APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Proposed expansion & modernization of the existing Unit to produce Mild Steel Billets/Ingots and MS Bars/Sections (Capacity – 2,00,000 MTPA each) through augmentation in the existing Induction Furnaces capacity by M/s Kashi Vishwanath Steels Private Limited at Narain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/UK/IND/75122/2018
Project Cost 1200 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Mild Steel Billets/Ingots - 200000 MTPA, Mild Steel Bars/Sections - 200000 MTPA and Modernization of existing Continuous Casting M/c (CCM) & Rolling Mill is proposed. ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 5.981 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify Yes
d) Inter-State boundaries and international boundaries
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectNarain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand.
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Khasra No. 64, 65, 66 min, 22, 25/1& 25/3, Narain Nagar Industrial Estate
Town / VillageKashipur
State of the projectUttarakhand
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)UttarakhandUdham Singh NagarKashipur
10.
Nearest railway station along with distance in kms Kashipur, 4.50 km
Nearest airport along with distance in kms Pant Nagar, 48.71 km
11. Nearest Town/City/District Headquarters along with distance in kms Kashipur , 4.49 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Narain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand.– 244713
13. Name of the Applicant Devendra
14. Registered Address Narain Nagar Industrial Estate, Bazpur Road, Kashipur
15.
Address for correspondance:
Name of the Company KASHI VISHWANATH STEELS PVT. LTD.
Name of the Applicant Devendra
Designation (Owner/ Partner/ CEO) MD
Pin code 244713
E-mail kvspremiereia@gmail.com
Telephone No. 05947-262109
Fax No. 05947-262103
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No No Need of additional Land. Proposed Expansion of existing facility will be carried out within the existing Unit located at Narain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand.
1.2 Clearance of existing land, vegetation and buildings? No There will be no clearance of buildings and vegetation required for the proposed augmentation, as the site required for few building sheds / infrastructure in the vacant land which devoid of any vegetation & building structure.
1.3 Creation of new land uses? No There would be no change in the land use pattern of the area as the proposed expansion will be carried out within the existing premises only.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes CBR testing to determine the load bearing capacity of soil shall be done and construction of buildings shall be done accordingly.
1.5 Construction works? Yes Construction would be carried out on 3705.4 sqm which is a part of the existing land.
1.6 Demolition works? No No demolition work is required, however replacement of 04 Nos. existing Furnaces is proposed.
1.7 Temporary sites used for construction works or housing of construction workers? Yes There will be no temporary sites created as the Labour deployed will be local. Thus, there will be no housing facility or temporary site required for the same. Existing Storage Yard will be used for the Storage of Construction Material.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes The Project will involve excavation of soil during foundation purposes. The excavated soil will be utilized within the site by balancing with scrap and fill operations.
1.9 Underground works including mining or tunnelling? No Not Required.
1.10 Reclamation works? No Not Required.
1.11 Dredging? No Not Required.
1.12 Offshore structures? No NA
1.13 Production and manufacturing processes? Yes The proposed expansion of the existing Unit to produce MS Billets/Ingots and MS Bars/Sections through augmentation in the existing Induction Furnaces will not contribute any significant change in the physical environment since proposed project shall undertake adequate environment control measures.
1.14 Facilities for storage of goods or materials? Yes Construction Phase: - Temporary storage yard will be provided for the storage of construction material. Storage yard will be covered from all the sides. Operation Phase: - During operation phase, existing storage facility will be utilized for storage of Raw materials as well as Finished products. Due to these facilities, changes in physical environment will not be envisaged.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste:- Construction Waste will be generated, out of which:- • Recyclable waste (Metal, Plastic Bags etc) will be segregated & sold to the respective vendors. • The inert waste (Brick, Masonry, Aggregates Concrete etc.) will be used for filling of Low lying Areas. Liquid Effluents:- • Domestic waste water will be generated to the tune of 1.8 KLD. • The same will be treated in septic tank followed by soak pit. • Overflow will be used for irrigation in the green belt.Metals i.e. Zinc
1.16 Facilities for long term housing of operational workers? No Housing provision will not be provided at the site as the labor employed will be from local area.
1.17 New road, rail or sea traffic during construction or operation? Yes Minor Traffic will be increase due to construction & operation phase of the proposed expansion.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Existing Road Infrastructure is sufficient to cater the additional load.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Due to the proposed expansion project, there will be no closure of existing transport routes or infrastructures leading to changes in traffic movements.
1.20 New or diverted transmission lines or pipelines? No Project will not involve any diversion of transmission lines for power supply.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No Impoundment, damming, culverting, realignment activity is proposed
1.22 Stream crossings? No Stream Crossings are not involved.
1.23 Abstraction or transfers of water from ground or surface waters? Yes Initially total water demand is 506.0 KLD and recycled water is 305.0 KLD. Fresh Water required for Production of Mild Steel Billets/Ingots and Bars/Sections will be 201.0 KLD after proposed expansion, which will be met from existing Bore well.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No NA
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes The existing road network will be utilized for the transportation of materials. Due to the Proposed expansion & modernization Project, there will be movement of material and man power. Involving movement of vehicles in and out of the Plant. Thus, contributing to fugitive emissions and noise in the area. This will be effectively managed by proper plantation and maintenance of vehicle.
1.26 Long-term dismantling or decommissioning or restoration works? No No such activity is proposed
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No No such activity is proposed
1.28 Influx of people to an area in either temporarily or permanently? Yes During construction phase, there will be temporary influx of semi-skilled and unskilled labor from the nearby villages. Local people based on their skill will be employed. Around 500 (Available 400 and required 100) person will be employed.
1.29 Introduction of alien species? No NA
1.30 Loss of native species or genetic diversity? No Not Applicable
1.31 Any other actions? No NA
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Proposed expansion & modernization will be carried out within the existing complex at Narain Nagar Industrial Estate (Total Land area of the existing unit - 59817.00 Sq.m). Land Possession documents is attached as Annexure- II.
2.2 Water (expected source & competing users) unit: KLD Yes Initially total water demand is 506.0 KLD and recycled water is 305.0 KLD. Fresh Water required for Production of Mild Steel Billets/Ingots and Bars/Sections will be 201.0 KLD after proposed expansion, which will be met from existing Bore well. Approval for additional abstraction of water to be taken from CGWA.
2.3 Minerals (MT) No There is no usage of minerals in the proposed project
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Materials like Brick, Steel, Cement, Sand aggregates, Tiles etc shall be procured locally from the open Market in the desired quantity as and when required.
2.5 Forests and timber (source – MT) No NA
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes After proposed expansion, the Unit at full capacity will demand 26.5 MW of power, which shall be supplied through Grid (UPCL). Existing power demand is 16.5 MW. Fuel as LPG: 3.33 KG/ day. Natural Gas: 12000 SCM/day Fuel as HSD: 112 LIT/ hr. Alternate Power: Existing DG Set: 63 KVA (which to be replaced). Green insulated DG Set of 685 KVA (125, 160 & 400 KVA on standby basis) is proposed (Proposed DG Set to be operated during emergency in case of power failure only).
2.7 Any other natural resources (use appropriate standard units) No NA
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes APC’s Dust and Spent Oil are only hazardous materials that will be generated on site and will be stored and transported to TSDF site as per CPCB guidelines. However APC’s Dust will be processed further to extract metals thru’ dust processing unit.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Sewage Treatment Plant (Capacity – 25.0 KLD) will be installed to treat the Domestic sewage. No waste water generation from industrial process except CT & Softener Plant Bleed which shall be reused in the green belt development & Dust Suppression respectively. Treated sewage will be reused in green belt for irrigation purpose. No effluent will be discharged outside the premises.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The proposed project would have positive impact on the socioeconomic status, thus contributing to the marginal growth and improvement in the living Standards of the nearby area. Increased employment opportunities, Indirect employment for truck drivers, Periodic medical check-up will be followed. The proposed project is a Long- term Project thus, would serve as a stable source of employment.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No NA
3.5 Any other causes No NA
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No NA
4.2 Municipal waste (domestic and or commercial wastes) Yes The municipal waste generated from domestic purpose will be segregated & disposed as per CPCB Norms.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Hazardous Wastes i.e. spent oil, APC’s dust generated during Operation phase dealt as per Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016.
4.4 Other industrial process wastes Yes Solid waste produced from proposed expansion is dust, scrap i.e. end cuttings and slag. Iron bearing dust will be reused in the IF’s itself. Slag from melting process will be granulated and after iron recovery, residue will be send for road development. Metals i.e. Zinc & Lead will be extracted from APC’s dust generated during process.
4.5 Surplus product No Nil
4.6 Sewage sludge or other sludge from effluent treatment Yes Domestic effluent will be subjected to proposed Sewage Treatment Plant (Capacity – 25.0 KLD) & generated sewage sludge shall be utilized in the green belt development.
4.7 Construction or demolition wastes Yes Demolition Wastes: No demolition work is required, however replacement of 04 Nos. existing Furnaces is proposed. Construction Waste: Construction debris will be generated out of which recyclable waste (Plastic Bags etc) will be sold to the vendors. The inert waste (Brick, Concrete, Masonry, Aggregates etc.) will be used for making of driveway and pathway within the site.
4.8 Redundant machinery or equipment No NA
4.9 Contaminated soils or other materials No NA
4.10 Agricultural wastes No NA
4.11 Other solid wastes No NA
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Stack attached to existing/proposed Furnaces are lead to emission. Particulate matter, Sulphur dioxide and Nitrogen oxides will be the major pollutants. Cyclone separator and Bag Filter are installed to mitigate the emissions. Suitable APC’s will be provided rest of the Furnace. However electricity will be used for melting in the proposed furnaces. Only “PUC” vehicles will be allowed for raw material & products transportation.
5.2 Emissions from production processes Yes There will be some dust emission from flame emission in mild steel ingots/billet production process in IF”s. This will be controlled by suitable APC’s like Cyclone separator and Bag Filter with smoke hood and ID /FD fan connected to 30 m height of chimney.
5.3 Emissions from materials handling including storage or transport Yes The material handling including storage and transportation may contribute to fugitive emissions. The materials will be stored under shed. To control the fugitive emissions for proposed expansion, following measures will be adopted:- • Storage and material handling will be carried out in closed trucks. • In plant training will be provided to the plant personnel on operation and maintenance of Bag Filter, Cyclone separator and wet scrubber. • Water spraying will be adopted in dust prone areas
5.4 Emissions from construction activities including plant and equipment Yes Fugitive dusts from various activities of construction & plying of vehicles are expected, which will be temporary in nature.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Construction phase:- During the construction of plant area, dust will become air borne Adequate precautions shall be taken to reduce these impacts on construction workers and the surrounding environment. Operation phase:- No dust will be generated in the proposed unit, during construction & operation phase as adequate precautions shall be adopted. There will be no odor problem to the best of knowledge.
5.6 Emissions from incineration of waste No Incinerator will not be used at the site.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No No such activity is proposed.
5.8 Emissions from any other sources No Nil
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise will be generated from plants activity but will be restricted to the plant area only during operational phase. However, the DG sets shall have the acoustic enclosures and will be operated only during power failures. All the machinery will comply with national/international standards.
6.2 From industrial or similar processes Yes Noise will be generated mainly from induction furnaces panel, Rolling mill & other moving equipment such as EOT Cranes, Shearing machine, workshop etc. Acoustic enclosures/noise curtail shall be provided accordingly.
6.3 From construction or demolition Yes Noise would be generated during construction activity but adequate precautions shall be taken to reduce the noise generation.
6.4 From blasting or piling No No blasting will be involved.
6.5 From construction or operational traffic Yes During the construction phase, noise will be generated from movement of vehicles, earth work, etc. The construction site will be shielded to avoid the noise propagation and transportation of the material & machineries will be carried out at the peak time of the day. During operation phase, raw material and products will be transported at the peak time of the day. Acoustic enclosures/noise curtail shall be provided. PUC checked vehicle will be used for transportation purposes.
6.6 From lighting or cooling systems Yes Heat generated in the vicinity of IF’s, reheating furnace etc and from higher temperature emissions from stacks. Cooling towers of latest technology will be installed in order to suppress noise and vibrations.
6.7 From any other sources No NA
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No APC’s Dust & spent oil are the hazardous materials that are generated on site and proper handling would be done at site. Separate storage area provides for the same and transported to the TSDF Site as per CPCB guidelines.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Domestic sewage will be at the tune of 18.0 KLD. The same will be treated in the proposed STP & will be reused in the green belt. Zero liquid discharge will be maintained.
7.3 By deposition of pollutants emitted to air into the land or into water Yes 1. Air Control of fugitive dust emission by Dust suppression system in coal handling area using bag filter, cyclone separator & wet scrubber. 2. Water Sewage Treatment Plant (Capacity – 25.0 KLD) will be installed to treat the Domestic sewage. No waste water generation from industrial process except CT & Softener Plant Bleed which shall be reused in the green belt development & Dust Suppression respectively. Treated sewage will be reused in green belt for irrigation purpose.
7.4 From any other sources No NA
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No NA
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Fuels such as LPG/HSD/Natural Gas will be used which are potential fire hazards. There can be explosion or fire in plant equipment. It is incorporated in the onsite emergency preparedness plan however for safe Storage, Handling & Operation following measures will be adopted:- • On-site emergency preparedness plan will be prepared. • Fire extinguisher will be installed at strategic points all over the premises, checked at regular intervals and a record will be made and maintained.
8.2 From any other causes Yes Due to normal industrial operation such as electrical shock, fire, mechanical injuries, hot metal splash may takes place. Suitable PPE’s will be provided to the workers & shall ensure that they will use the same.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes Project Site falls in Udham Singh Nagar district in Uttarakhand which falls in Seismic Zone IV. Secondary data reveals that no major natural calamity has been recorded so far in the proposed project area.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No This Project is located in the Notified Industrial Area (Narain Nagar Industrial Estate). Therefore no further supporting utilities development is envisaged and no adverse impact on the environment is expected.
9.2 Lead to after-use of the site, which could have an impact on the environment No Nil
9.3 Set a precedent for later developments No Nil
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No There would not be any negative impact. Cumulative effect will be noted but will be within norms/tolerance limit.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No NA
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No NA
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Jim Corbett National Park – 24.05 km N
4 Inland, coastal, marine or underground waters Yes Bahella River – 0.50 km W Dhela River – 5.74 km NW Kosi River – 5.97 km E Under ground water table – 25.0 Feet (in summer)
5 State, National boundaries No Utter Pradesh & Uttarakhand border is within 2.84 km SE towards Moradabad.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH – 309: 0.30 km S
7 Defence installations No Hempur Depot – 12.31 km N
8 Densely populated or built-up area Yes Kashipur – 4.49 km NW Sultanpur patti – 6.7 km SE
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Hospitals, Recreational Places, Temples, Shops, and Educational & Institution Facilities are not existing in the immediate vicinity of the project, whereas these facilities are well developed in Kashipur City, which is 4.49 Km NW away from this site.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No NA
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Project Site falls in Udham Singh Nagar district in Uttarakhand which falls in Seismic Zone IV. Secondary data reveals that no major natural calamity has been recorded so far in the proposed project area.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe correction have been made as per the instruction received 24 Oct 2018
2.NAMay kindly refer to your application. Instant proposal is for expansion of existing project but made application under new category. Pl make application under expansion category along with details of earlier clearance. If there is no clearance for the existing project, mention the same along with reason and substantiating evidence. 24 May 2018
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NAAfter detailed deliberations the committee advised to submit the revised layout showing the details of internal roads suitable for movement of fire tender and ambulances in case of emergency, storage yard, parking, etc. The configuration Induction Furnaces may be explored to plan for bigger size of IF i.e. 4X10 T in place of 3X6 T+ 3X10 T Induction Furnaces. Therefore, the proposal is deferred for additional information 29 Nov 2018
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantDevendra
DesignationMD
Name of Company (Applicant Name should not be given here)KASHI VISHWANATH STEELS PVT. LTD.
AddressNarain Nagar Industrial Estate, Bazpur Road, Kashipur