APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of M/s Kashi Vishwanath Steels Private Limited for MS Ingot / MS Billet production from 57,600 TPA to 204,200 TPA and Rolled Production from 88,200 TPA to 200,000 TPA at Narain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/UK/IND/101521/2019
Project Cost 2000 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Rolled Product – 2,00,000 TPA ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/UK/IND/101520/2005
MoEFCC file number(Previous EC)NOC-187/85-5
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 5.981 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify Yes
d) Inter-State boundaries and international boundaries
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectNarain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Khasra No. 64, 65, 66 min, 22, 25/1 & 25/3
Town / VillageNarain Nagar Industrial Estate
State of the projectUttarakhand
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)UttarakhandUdham Singh NagarKashipur
10.
Nearest railway station along with distance in kms Kashipur, 4.5 km
Nearest airport along with distance in kms Pant Nagar, 48 km
11. Nearest Town/City/District Headquarters along with distance in kms Kashipur , 4.5 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Kashipur, 4.5 km in NW direction from the project
13. Name of the Applicant Devendra
14. Registered Address Narain Nagar Industrial Estate, Bazpur Road, Kashipur
15.
Address for correspondance:
Name of the Company KASHI VISHWANATH STEELS PVT. LTD.
Name of the Applicant Devendra
Designation (Owner/ Partner/ CEO) MD
Pin code 244713
E-mail kvspremiereia@gmail.com
Telephone No. 05947-262109
Fax No. 05947-262103
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No No change in land use as the project will be installed within the existing plant area which is in Narain Nagar Industrial Estate
1.2 Clearance of existing land, vegetation and buildings? No Not required
1.3 Creation of new land uses? No The proposed expansion project will be incorporated in the existing plant premises therefore there will be no new land use creation.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Not Required
1.5 Construction works? Yes Additional civil or Structural works are involved for the installation of additional units.
1.6 Demolition works? Yes Demolition of existing Induction Furnaces are required.
1.7 Temporary sites used for construction works or housing of construction workers? No No Temporary sites or Housing of construction workers are required since the workers for the construction work will be sourced from the nearby villages. Provision for rest shelters, drinking water, washroom etc. are already available at the existing plant premises
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations No No building, structures or earthworks are required.
1.9 Underground works including mining or tunnelling? No Not Applicable
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing processes? Yes Production process is: Production of Rolled Products through Induction Furnaces, Billet Caster and Rolling Mill. Cold Drawing Complex for production of Ribbed Bars.
1.14 Facilities for storage of goods or materials? Yes Storage facilities are available for the existing plant. Apart from this, the additional storage facilities for storage of raw materials and shed for finished products will be provided under expansion.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes The treatment facilities shall be proposed for Rolling Mill waste water, Softening plant back wash and DM Plant waste water. Induction Furnace slag, Bag Filter dust, Mill scales shall be recycled / reused or suitably disposed of
1.16 Facilities for long term housing of operational workers? No Operational workers are living in the nearby villages or within plant premises, hence no long term housing for operational workers is required.
1.17 New road, rail or sea traffic during construction or operation? No Not Required
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not Required
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not Required
1.20 New or diverted transmission lines or pipelines? No Not Required
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not Required
1.22 Stream crossings? No No stream crossing
1.23 Abstraction or transfers of water from ground or surface waters? Yes Total water requirement after the proposed expansion shall be 295 KLD. Water will be sourced from deep bore wells
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No No change envisaged.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transportation of material for construction and operations are required. No decommissioning envisaged
1.26 Long-term dismantling or decommissioning or restoration works? No No long term dismantling. Existing Induction Furnace will be replaced with new higher capacity Induction Furnaces No decommissioning works required
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No No decommissioning activity is involved which will have impact on environment
1.28 Influx of people to an area in either temporarily or permanently? Yes The additional manpower will be required for proposed expansion which will create influx of people from the nearby villages
1.29 Introduction of alien species? No None
1.30 Loss of native species or genetic diversity? No No loss of native species or genetic diversity due to the project
1.31 Any other actions? No None
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No No additional land will be required for the proposed project.
2.2 Water (expected source & competing users) unit: KLD Yes Present water requirement is 105 KLD. Total water requirement will be 295 KLD after the proposed expansion. Water will be sourced from ground water
2.3 Minerals (MT) Yes The details of minerals required for the project are. Sponge iron – 17130 TPA, Ferro Alloys – 1130 TPA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes The construction material used during construction phase of the proposed project will be sourced from the local market
2.5 Forests and timber (source – MT) No Not Applicable
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Total power requirement after the proposed expansion will be 26.5 MW which will be supplied through Grid (UPCL) for which permission shall be obtained. Fuel - 100 liters/hr of LDO shall be used for emergency power
2.7 Any other natural resources (use appropriate standard units) No No other natural resources are used.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No hazardous substance as per MSIHC Rules shall be used
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No No Changes
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The proposed project shall improve the living conditions and welfare of the people.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not applicable
3.5 Any other causes No None
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes The Municipal waste generated during the proposed expansion project will be segregated and disposed-of as per the MSW rules
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No No Hazardous waste shall be generated from the project, except Used Oil, approx. 600 LPA, shall be sold to the registered recycler.
4.4 Other industrial process wastes Yes IF Slag – 13340 TPA, APCD Dust – 680 TPA, Mill Scale – 1700 TPA. All the waste generated shall be / reused or disposed-of, suitably
4.5 Surplus product No None
4.6 Sewage sludge or other sludge from effluent treatment No No sludge generation
4.7 Construction or demolition wastes Yes Minimal quantity of Construction waste will be generated which will be used for landfilling and leveling
4.8 Redundant machinery or equipment No No Redundant machinery.
4.9 Contaminated soils or other materials No No contamination of soil or other materials.
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes No No other solid waste generation
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources No No combustion of fossil fuel. LDO will be used in DG set during emergency power requirement
5.2 Emissions from production processes Yes Primary & Secondary emissions (fugitive) from Induction Furnace, Gas Oxygen Refining Unit and Reheating Furnace
5.3 Emissions from materials handling including storage or transport Yes Dust emission during transportation and storage, Gases emissions, SO2, NOx & HC during transportation
5.4 Emissions from construction activities including plant and equipment Yes From construction equipment aided with fossil fuel (diesel) are Cranes, Compressor, Mortar mixing drums etc.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Dust generation as mentioned above. No odour problems.
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not applicable
5.8 Emissions from any other sources No Not applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Overall noise level shall be limited to 85 dB(A)
6.2 From industrial or similar processes Yes Noise will be generated from Rolling Mill, Induction Furnace Exhauster etc. Suitable measures shall be taken to control the noise at source
6.3 From construction or demolition Yes Noise due to operation of Cranes, Trucks, Dumpers, Construction machineries etc. The noise generated from the construction activities will be confined to the plant premises. The workers will be provided with PPEs
6.4 From blasting or piling No Not Applicable.
6.5 From construction or operational traffic Yes Overall noise levels shall be limited to 85 dB (A).
6.6 From lighting or cooling systems No Not Applicable.
6.7 From any other sources No No other sources.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Hazardous wastes (Used Oil) shall be suitably disposed-off through registered recyclers, as per Hazardous and Other Wastes (Management & Transboundary Movement) Rules, 2016 and subsequent amendments
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No For sewage discharge shall be treated in septic tanks with soak pits, overflow, if any shall be used for horticulture. Effluent from Rolling Mill shall be treated in ETP and recycled. Waste water from other sources shall be used in the plant for different purposes. Zero Liquid Discharge (ZLD) from the plant.
7.3 By deposition of pollutants emitted to air into the land or into water No State of art pollution control facilities will be installed. Stacks of adequate height will be provided for proper dispersion of pollutants
7.4 From any other sources No No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No No long term built-up of pollutants.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No Not applicable
8.2 From any other causes No None
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No No such event is known to have occurred in the area. Area falls under Seismic Zone IV as per Indian Standard Seismic Zoning Map
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No The development of the project does not envisage any impact on supporting facilities like road, power, housing, extractive or supply industries. Supporting facilities are available as it is an operating plant. No additional supporting facilities proposed. The proposed project will have a positive effect and enhance the growth of the region The industry will provide employment to the locals and likely to improve the socio-economic status of the area
9.2 Lead to after-use of the site, which could have an impact on the environment No No impact on environment is envisaged due to after use of the site
9.3 Set a precedent for later developments Yes Gas Oxygen Refining Unit and Metal Recovery Plant shall be installed which will have unique and state of art technologies for liquid steel refining and metal recovery from Bag Filter dust, respectively. These technologies likely to set a precedent for later development in steel industries
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not envisaged
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No None
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No None
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None
4 Inland, coastal, marine or underground waters No None
5 State, National boundaries No Uttar Pradesh and Uttarakhand State Boarder is 2.6 km from the project site
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH-74 at 0.3 km in South
7 Defence installations No None
8 Densely populated or built-up area Yes Kashipur at 4.5 km in NW direction from plant site.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Indian Institute of Management at 0.4 km in SW. Institute of Management and Technology at 0.5 km in NE. Utkarsh Heart Hospital at 2.4 km in NE
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No None
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No None
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No None Area comes under Seismic Zone-IV
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
Reply of EDS generated on 16/04/2019
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantDevendra
DesignationMD
Name of Company (Applicant Name should not be given here)KASHI VISHWANATH STEELS PVT. LTD.
AddressNarain Nagar Industrial Estate, Bazpur Road, Kashipur
Print