APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of “Info Technology Park”
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/TN/NCP/76743/2018
Project Cost 75000 lacs
2.
S. No. in the schedule8(b) Townships and Area Development projects.
Project Sector INFRA-1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Total Built-up area after Expansion – 917772 sqm ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/TN/NCP/947/2007
MoEFCC file number(Previous EC)21-202/2007-IA.III
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 88.7211 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the project1/124 Shivaji Gardens, Moonlight Stop, Nandapakkam Post, Manapakkam Village, Sriperumbudur Taluk, Kancheepuram District Chennai, Tamil Nadu
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.1/124 Shivaji Gardens, Moonlight Stop, Nandapakkam Post
Town / VillageManapakkam Village
State of the projectTamil Nadu
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Tamil NaduKanchipuramSriperumbudur
10.
Nearest railway station along with distance in kms Guindy Railway Station, 4.36 km
Nearest airport along with distance in kms Chennai International Airport, 3.14 km
11. Nearest Town/City/District Headquarters along with distance in kms Chennai , 1 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Municipal Corporation of Chennai
13. Name of the Applicant Arvind
14. Registered Address 9th Floor, DLF Centre, Sansad Marg, New Delhi
15.
Address for correspondance:
Name of the Company DLF HOME DEVELOPERS LTD.
Name of the Applicant Arvind
Designation (Owner/ Partner/ CEO) Authorisedsignatory
Pin code 110001
E-mail yadav-abinash@dlf.in
Telephone No. 011-42102030
Fax No. 011-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No Extension of Environmental Clearance was granted by SEIAA, Tamil Nadu vide letter no. SEIAA-TN/F-1926/2013/EC-Ext/2015. After expansion also, the plot area will remain the same as 172248 sqm. At present, out of 18 blocks, 10 blocks are already operational, 4 blocks are partially constructed and rest of 4 blocks are yet to be constructed. The land-use for existing land has already been changed from vacant land to IT park. The expansion shall be done on existing land only.
1.2 Clearance of existing land, vegetation and buildings? No Not Applicable
1.3 Creation of new land uses? No At present, out of 18 blocks, 10 blocks are already operational, 4 blocks are partially constructed and rest of 4 blocks are yet to be constructed. The land-use for existing land has already been changed from vacant land to IT park. The expansion shall be done on existing land only.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Pre-construction Geo-technical investigation had been done.
1.5 Construction works? Yes Till date construction has been done as per Building sanction plan & Master plan of Kancheepuram, Chennai. The same shall be followed for further construction also.
1.6 Demolition works? No Not applicable.
1.7 Temporary sites used for construction works or housing of construction workers? No Workers during construction phase were hired from nearby areas and hence no housing provisions was made. Only temporary shelters were provided. The same shall be followed for further construction also.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Above ground, the building shall be elevated up to maximum height of 42 m. Excavation up to 3 level of basement was done for blocks already constructed and shall be done up to 3 level of basement for further blocks to be constructed
1.9 Underground works including mining or tunnelling? No It is a construction project. Hence no underground works will be required except for excavation of basements and foundation.
1.10 Reclamation works? No No reclamation work will be done
1.11 Dredging? No Not applicable
1.12 Offshore structures? No Not applicable
1.13 Production and manufacturing processes? No It is a construction project; hence no production or manufacturing processes shall be carried out.
1.14 Facilities for storage of goods or materials? Yes During Construction Phase: • Separate raw material yard was made within the project site. The same shall be followed for further construction also. During Operation Phase: As the project is a IT park, the raw material will be goods & food items which has been stored in respective Commercial blocks. The same shall be followed for further blocks to be constructed.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes At present, approx. 9180 Kg/day of solid waste is being generated from the blocks which are operational. After expansion, total 11963 Kg/day of solid waste shall be generated from the IT Park. at present 867 KLD of sewage is generated from the blocks which are operational and is treated in STP of 3200 KLD. After expansion, total generated sewage will be 1132 KLD which will be treated in already installed in-house Sewage Treatment Plant capacity of 3200 KLD.
1.16 Facilities for long term housing of operational workers? No During Construction phase: The workers during construction phase were hired from nearby areas and hence no provision of long term housing was made. Only temporary shelters were provided. The same shall be followed for further construction also. During Operation Phase: As this is an IT Park, staff is needed in the commercial as well as IT units. Staff is from the nearby areas. Separate housing has not been provided. The same shall be followed for further blocks to be constructed.
1.17 New road, rail or sea traffic during construction or operation? No No new road, rail or sea traffic is proposed. Existing transportation facilities is used during construction or operation phase.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No No new road, rail, or sea traffic is proposed. The transportation measures already existing near site are as follows: Nearest Railway Station- Guindy Railway Station-4.36 Km SEE Saidapet Railway Station-5.29 km E Nearest Highway- NH- 205-6.64 Km NNE NH- 4-4.74 km N SN -113-2.08 km (N) Mt Poonamalle High road-0.33 Km NE Chennai Bypass Road-3.08 Km NWW NH- 45-3.21 Km SE Nearest Airport- Chennai International Airport -3.14 km S
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No No closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements will be made.
1.20 New or diverted transmission lines or pipelines? No No such closure or diversion of transmission lines is required.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No impoundment, damming, culverting, realignment or other changes to the hydrology of surface water courses is required.
1.22 Stream crossings? No No stream crossing.
1.23 Abstraction or transfers of water from ground or surface waters? No No abstraction or transfer of water from ground or surface will be done.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No There will be no change in water bodies or the land surface effective drainage or run-off.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes During Construction phase: Materials during construction phase were transported by tractor, trolley etc. The same shall be followed for further construction also. During Operation Phase: Car, two-wheeler, etc. is being used.
1.26 Long-term dismantling or decommissioning or restoration works? No Not Applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not Applicable
1.28 Influx of people to an area in either temporarily or permanently? No During Construction phase: Temporary influx of people in the form of labors is there. Approx. 150 no. of local labors were employed. The same shall be followed for further construction also. During Operation Phase: As this is a IT park, after expansion 3902 no. of staff working for 8-12 hours, & visitors of approx. 68046 no. is envisaged. Out of the total, at present 700 staff are working in the operational part of the project & 59100 no. of visitors is envisaged.
1.29 Introduction of alien species? No Not Applicable
1.30 Loss of native species or genetic diversity? No Not Applicable
1.31 Any other actions? No Not Applicable
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes The proposed project is an expansion of IT Park. The land has been allotted to M/s DLF Info City Developers (Chennai) Ltd. (Now known as M/s DLF Home Developers Ltd.) by Chennai Metropolitan Development Authority for area admeasuring 172248 sqm for the development of IT Park. The expansion shall be done on existing land only of 172248 sqm.
2.2 Water (expected source & competing users) unit: KLD Yes Construction phase: Water during construction phase was taken from tanker water supplier which supply treated water from STP of nearby area. The same shall be followed for further construction also. Operation Phase: source of water is Municipal Supply. At present for operational blocks, total water requirement is 1752 KLD, out of which fresh requirement water is 928 KLD. Total water requirement of the project after expansion will increase to 2574 KLD out of which 1499 KLD will be fresh wate
2.3 Minerals (MT) No Not applicable
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes The major materials required for construction of the project are steel, tiles, glass, cement, agate, bricks, flooring tiles / stones, sanitary and hardware items, electrical fittings, etc.
2.5 Forests and timber (source – MT) Yes Plywood for doors & windows has been used which shall be procured from local market. Same shall be followed for further blocks which will be constructed.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Source of Electricity – Tamil Nadu Electricity Board (TNEB) Total Power load after expansion: - 75 MVA No. of DG sets installed - 31 X 2000 KVA & 2 x 1500 KVA No. of DG Sets proposed- None
2.7 Any other natural resources (use appropriate standard units) No Not applicable
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes No storage of hazardous substances (as per MSIHC rules) will be done however, 458 litr/month used oil from DG sets and 25 Tonnes/annum of E-waste will be generated from the complex after expansion. Proper management of Used oil & E-waste shall be taken care of. Details are given Pre-feasibility Report.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Suitable drainage and waste management measures has been adopted in construction phase and it is being maintained during operational phase which restrict stagnation of water or accumulation of water. This effectively restrict the reproduction and growth of disease vectors. The same shall be followed after expansion also.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes During Construction phase: Employment opportunities provided due to the project has led to better quality of life. this project had provided employment to about 150 no. of local labors during construction phase. The same shall be followed for further construction also. During Operation Phase: As it is a IT Park there are several services required which generates direct & indirect employment for the people of nearby area. The employment shall increase after expansion.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No vulnerable group of people will be affected by the project.
3.5 Any other causes No None
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes During Operation Phase: Total 11963 kg/day solid waste will be generated from the IT Park after expansion including 9180 kg/day waste generated in existing. It is being properly managed and given to approved vendor/recycler. After expansion 8374 kg/day of bio-degradable waste generated will be sent to organic waste convertor while 2991 kg/day of Recyclable waste shall be given to approved recycler & 598 kg/day of plastic waste shall also be given to approved recycler.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes During Construction phase: Used oil whenever generated from the DG sets was kept in leak proof containers in an isolated area and was sent to approved recycler. The same shall be followed for further construction also. During Operation Phase: Used oil from diesel generators is being carefully stored and is given to vendors authorized by CPCB for the treatment of the same.
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes After expansion, about 82 Kg/day of dried sludge will be generated from STP within complex during operation phase and this sludge will be passed through filter press where it will be dewatered/ dried to form a cake and then will be used as manure in green areas. The unused sludge shall be given to farmers or nursery.
4.7 Construction or demolition wastes Yes Construction waste was used for flooring & Back filling in roads etc. The same shall be followed for further construction also.
4.8 Redundant machinery or equipment No Not applicable
4.9 Contaminated soils or other materials No Not applicable
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes No Not applicable
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes During Construction phase: DG sets of capacity 125 KVA was installed acoustically enclosed with adequate stack height. The same shall be followed for further construction also. During Operation Phase: The only source of emission in existing is from combustion of fuel of DG sets of capacity 31 X 2000 KVA & 2 x 1500 KVA. Hence, to avoid the emissions, stack height of 6 m above roof level for each D.G. sets has been provided meeting all the norms prescribed by CPCB.
5.2 Emissions from production processes No Not applicable
5.3 Emissions from materials handling including storage or transport Yes Dust was generated during construction, from the movement of transport vehicles & other construction activities. The effect was restricted to construction phase only. Water sprinklers was used for dust suppression. Material was stored under Tarpaulin cover. The same shall be followed for further construction also.
5.4 Emissions from construction activities including plant and equipment Yes RMC was used. Dust & emissions are generated during construction activities which were reduced by sprinkling of water in a specific time interval & timely maintenance schedule for machinery. Also the machines were kept shut down during idle period. The same shall be followed for further construction also.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes During loading & unloading of construction material dust was generated during construction phase. Water was sprinkled and tarpaulin cover was provided over stored raw material to reduce dust emission. The same shall be followed for further construction also. During Operation Phase: • In-house STP has been provided to treat wastewater. Proper ventilation has been provided in STP room. • On accumulation area, waste is being given to authorized vendor on daily basis. The same shall be followed
5.6 Emissions from incineration of waste No Not applicable.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Open burning of biomass/ other material will be prohibited.
5.8 Emissions from any other sources No None
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes During Construction phase: The equipment such as mixer machines, bulldozers, cranes, compactors & excavators were used which were of highest standard. During Operation Phase: After expansion, source of noise in the operational phase will be already existing D.G. Set of capacity 31 X 2000 KVA & 2 x 1500 KVA. The D.G. Sets has been bought acoustically enclosed & kept in acoustically treated room & and will be used during Power failure only. No further DG set is proposed.
6.2 From industrial or similar processes No Not applicable
6.3 From construction or demolition Yes Due to the various activities there are short-term noise impacts in the immediate vicinity of the project site. These are restricted to day time only. It has been estimated that during the construction period the average noise level is 70-75 dB (A) during peak construction hours. However, embankment was done to further prevent the noise pollution. The same shall be followed for further construction also.
6.4 From blasting or piling No No blasting or piling is required.
6.5 From construction or operational traffic Yes Some amount of noise (70 – 75 dB (A)) is generated from vehicular movement in the construction phase and operational phase. Plantation around the boundary wall has been done to reduce noise from traffic. The same shall be followed after expansion also.
6.6 From lighting or cooling systems No Not Applicable
6.7 From any other sources No None
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No The hazardous waste generated during operation phase is Used oil. Used oil generated is stored in HDPE drums and kept in covered rooms under lock and key and is being sold to authorized vendors only. Special care is being taken to prevent leakages and spills. The same shall be followed after expansion also.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes At present 824 KLD of sewage is generated from the blocks which are operational and is treated in STP of 3200 KLD. During operational phase after expansion, waste water of 1132 KLD shall be treated in already installed STP of 3200 KLD. All the treated water generated of 1075 KLD shall be reused within the complex in flushing, gardening, DG Cooling & misc. purpose. It will be a zero-discharge complex.
7.3 By deposition of pollutants emitted to air into the land or into water No None
7.4 From any other sources Yes E-waste is being generated from the complex & is given to approved recycler of SPCB. The same shall be followed after expansion also.
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not applicable
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes During Construction Phase: All appropriate measures were taken to avoid accidents. The same shall be followed for further construction also. During Operation phase: Proper disaster management & fire-fighting system has been installed at site in blocks which are operational. The same shall be followed for further blocks to be constructed.
8.2 From any other causes Yes During Construction Phase: All the labors were provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms were provided to all supervisors and labors involved in construction activity. The same shall be followed for further construction also.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The area under study falls in Seismic zone-III, according to the Indian Standard Seismic Zoning Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structure.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes STP of 3200 KLD capacity has already been installed for the treatment of wastewater. • Housing development-Not Applicable • Extractive industries-Not Applicable • Supply industries-Not Applicable • Other-Not Applicable
9.2 Lead to after-use of the site, which could have an impact on the environment No Not Applicable
9.3 Set a precedent for later developments Yes It will attract people to develop organized IT Park.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No No impact
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No None
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Vandalur Reserve Forest-16.49 km (SW) Guindy Park Reserve Forest-5.33 Km (SE) Nanmangalam Reserve Forest-9.43 Km (S) Pallavaram Forest-5.54 Km (SSW) Pallikaranai Marsh Reserve Forest-8.90 Km (SSE) Pullikkuradu Reserve Forest-10.00 Km SW Tambaram Reserve Forest-11.49 km (SW) Adyar River-0.92 Km SE Coovam River-4.90 Km (N) Ambattur Lake-8.91 Km (N) Thiruverkadu Lake-6.80 Km (NNW) Nanmangalam Lake-8.98 Km S Velachary Lake-5.18 Km SE Porur (Metro water Lake)-2.60 Km (NW) Kilkattalai la
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No None
4 Inland, coastal, marine or underground waters Yes Bay of Bengal-10.86 Km SEE
5 State, National boundaries No Andhra Pradesh-49.13 Km NW
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes NH- 205-6.64 Km NNE NH- 4-4.74 km N SN -113-2.08 km (N) Mt Poonamalle High road-0.33 Km NE Chennai Bypass Road-3.08 Km NWW NH- 45-3.21 Km SE Railway Station Guindy Railway Station-4.36 Km SEE Saidapet Railway Station-5.29 km E Airport Chennai International Airport-3.14 km S
7 Defence installations No None
8 Densely populated or built-up area Yes Sri Laxmi Nagar-Adjacent to project
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Kedar Hospital- 0.87 Km W Mugalivakkam Post Office-0.60 Km NWW Nespakam Church-1.86 Km NE Ravindra Bharathi Global School-1.11 Km SEE ICICI Bank-0.15 Km SWW
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No None
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No None
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects Yes The project area falls in seismic zone –III.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantArvind
DesignationAuthorisedsignatory
Name of Company (Applicant Name should not be given here)DLF HOME DEVELOPERS LTD.
Address9th Floor, DLF Centre, Sansad Marg, New Delhi