APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| | 2. | |
S. No. in the schedule | 8(b) Townships and Area Development projects.
| Project Sector | INFRA-1 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Built-up area– 835650.00 sq m ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 0 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Survey no 1 (part) Tiruvanmiyur Mylapore - Taluk, Chennai - District. SF No 300/2B 300/2C& 301/3 Kottivakkam Tamabaram - taluk, Kanchipuram - District, Tamilnadu | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Survey no 1(part)Tiruvanmiyur Mylapore Taluk, Chennai District. SF No 300/2B 300/2C& 301/3 Kottivakkam Tamabaram taluk, Kanchipuram District | Town / Village | Survey no 1(part)Tiruvanmiyur Mylapore Taluk, Chennai District. SF No 300/2B 300/2C& 301/3 Kottivakkam Tamabaram taluk, Kanchipuram District, | State of the project | Tamil Nadu | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Tamil Nadu | Kanchipuram | Tambaram | | 10. | |
Nearest railway station along with distance in kms | Guindy Railway station, 4.73 km | Nearest airport along with distance in kms | Chennai International Airport, 7.44 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Chennai , 3.22 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Municipal Corporation of Chennai | | 13. | Name of the Applicant | Arvind | | 14. | Registered Address | Old No.828 & 828 A, New No.268 & 268 A, Sri Ranga, Poonamallee, High Road, Kilpauk, Chennai-600010 | | 15. | |
Address for correspondance: | Name of the Company | M/S DLF INFO PARK DEVELOPERS (CHENNAI) LIMITED | Name of the Applicant | Arvind | Designation (Owner/ Partner/ CEO) | VicePresident | Pin code | 110001 | E-mail | abinash34@gmail.com | Telephone No. | 011-42102030 | Fax No. | 011-23719344 | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Presently, the land is a vacant land the land has been taken on lease from government of Tamilnadu by M/S DLF Info Park developers (Chennai) Limited for development of IT park. Hence, there will be a permanent change in land use from vacant land to IT park. | 1.2 | Clearance of existing land, vegetation and buildings? | No | The proposed site is a vacant land hence, no clearance of existing vegetation shall be required. | 1.3 | Creation of new land uses? | Yes | The vacant land will be developed into IT Park. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Pre-construction Geo-technical investigation has been done. | 1.5 | Construction works? | Yes | Construction will be done as per as per Building plan approved & Master plan of Chennai. | 1.6 | Demolition works? | No | Demolition work is not required. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | The Workers during construction phase will be hired from nearby areas and hence there will be no need of providing housing. Only temporary shelters will be provided. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Above ground, the building will be elevated up-to maximum height of 96.6 m. 729200 cu. m. soil quantity excavation will be done for foundation & 3 level of basements. | 1.9 | Underground works including mining or tunnelling? | No | Not applicable | 1.10 | Reclamation works? | No | No reclamation work will be done | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | No | It is an IT park; hence no production or manufacturing processes shall be carried out. | 1.14 | Facilities for storage of goods or materials? | Yes | During Construction Phase:
• Separate raw material yard shall be made within the project site.
• Cement shall be separately stored under cover in bales.
• Sand shall be stacked nearby under tarpaulin cover.
• Bricks and steel shall be laid in open.
During Operation Phase:
As the project is an IT Park, the raw material will be stationary, goods & food items will be stored in respective IT units only. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid waste generation shall be 23 kg/day, which shall be disposed off at MSW site. 7 KLD of waste water shall be generated from construction site which shall be discharged to septic tank via soak pit. Operation phase: Approx. 6656 Kg/day of solid waste shall be generated. Total waste water generation will be 2225 KLD (1024 KLD from Phase I & 1201 KLD from Phase II) which will be treated in STP of combined capacity 4200 KLD (1500 KLD for Phase I & 2700 KLD for Phase II). | 1.16 | Facilities for long term housing of operational workers? | No | During Construction phase:
The workers during construction phase shall be hired from nearby areas and hence, there is no need of providing long term housing. Only temporary shelters will be provided.
During Operation Phase:
As the project is an IT Park, most of the staff will be from nearby areas. Separate housing will not be provided. | 1.17 | New road, rail or sea traffic during construction or operation? | No | No new road, rail or sea traffic is proposed. Existing transportation facilities will be used during construction or operation phase. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | No new road, rail or sea traffic is proposed.
The transportation measures already existing near site are as follows:
Nearest Highway: NH- 45 (5.57 km NWW)
Railway Station: Guindy Railway station (4.73 Km NW)
Airport: Chennai International Airport (7.44 km W) | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | No closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements will be made. | 1.20 | New or diverted transmission lines or pipelines? | No | No such closure or diversion of transmission lines is required. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | No impoundment, damming, culverting, realignment or other changes to the hydrology of surface water courses is required. | 1.22 | Stream crossings? | No | No stream crossing. | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | No abstraction or transfer of water from ground or surface will be done. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | There will be no change in water bodies or the land surface effective drainage or run-off. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | During Construction phase:
Materials during construction phase shall be transported by truck, trolley etc.
During Operation Phase:
Car, two-wheeler, etc. will be used. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During Construction phase:
Temporary influx of people in the form of labours is envisaged. Approx. 150 no. of local labours shall be employed.
During Operation Phase:
The project will be developed in 2 phases. Influx of people will be
Staff-39690
Visitor-4682 | 1.29 | Introduction of alien species? | No | Not Applicable | 1.30 | Loss of native species or genetic diversity? | No | No tree exists at the site. However, by planting native plants within the project, it will give positive impacts. | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The proposed project is construction of an IT Park. Presently, the land is a vacant land the land has been taken on lease from government of Tamilnadu by M/S DLF Info Park developers (Chennai) Limited for development of IT park.
The Vacant land shall be developed into IT park. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Water during construction phase shall be arranged on temporary basis through tanker supply. During construction phase, the ultimate source of water will be Municipal Supply.
The total water requirement of the proposed project will be 4335 KLD out of which 2331 KLD is fresh water requirement and 2004 KLD will be met through in-house STP treated Water. | 2.3 | Minerals (MT) | No | Not applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | The major materials required for construction of the project are steel, tiles, glass, cement, agate, bricks, flooring tiles / stones, sanitary and hardware items, electrical fittings, etc. | 2.5 | Forests and timber (source – MT) | Yes | Plywood for doors & windows shall be used which shall be procured from local market. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Source of Electricity – Tamil Nadu Electricity Board
Total Electrical load - 26359 KW (Phase I- 8172 KW & Phase II- 18187 KW)
D.G. sets for power back up- 20 x 2000 KVA | 2.7 | Any other natural resources (use appropriate standard units) | No | Not applicable | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | No storage of hazardous substances (as per MSIHC RULES) will be done however, 280 lit/ month used oil from DG sets will be generated. Proper management of used oil shall be taken care of. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Suitable drainage and waste management measures will be adopted during both the construction and operational phase which will restrict stagnation of water or accumulation of water. This will effectively restrict the reproduction and growth of disease vectors. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | During Construction phase:
Employment opportunities provided due to the project will lead to better quality of life & will also set a standard for future developments in the area. Moreover, this project will provide employment to about 150 local labours during construction phase.
During Operation Phase:
As proposed project is an IT Park, there shall be several services required which will generate direct & indirect employment for the people of nearby area. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | No vulnerable group of people will be affected by the project. | 3.5 | Any other causes | No | None | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | During Construction phase:
Solid waste during construction phase will be 23 kg/day which shall be disposed off at municipal solid waste site.
During Operation Phase:
Total 6656 Kg/day of solid waste shall be generated from the project.
Detailed Solid Waste Management is given in Pre-Feasibility Report. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | During Construction phase:
Used oil whenever generated from the DG sets shall be kept in leak proof containers in an isolated area and shall be sent to approved recycler.
During Operation Phase:
280 Lt/month used oil generated from diesel generators will be carefully stored in HDPE drums in isolated covered facility. The used oil will be sold to vendors authorized by Central Pollution Control Board. | 4.4 | Other industrial process wastes | No | Not Applicable | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | About 161 Kg/day of dried sludge will be generated from STP within IT Park during operation phase and this sludge will be passed through filter press where it will be dewatered/ dried to form a cake and then will be used as manure in green areas. The unused sludge shall be given to farmers or nursery. | 4.7 | Construction or demolition wastes | Yes | Construction waste shall be used for flooring & back filling in roads etc & rest of the waste shall be sent to construction & demolition facility. | 4.8 | Redundant machinery or equipment | No | Not applicable | 4.9 | Contaminated soils or other materials | No | Not applicable | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | No | During Construction phase:
No E-waste shall be generated.
During Operation Phase: 12 Kg/month E-waste shall be generated. It shall be given to approved recycler of SPCB.
Battery waste shall be generated from inverters & UPS which shall be disposed off as per the Batteries (Management & Handling) Rules 2001. | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | During Construction phase:
DG sets of capacities 62.5 KVA shall be installed acoustically enclosed with adequate stack height.
During Operation Phase:
The only source of emission from combustion of fuel will be DG sets for common utilities of 20 x 2000 KVA (Phase I- 6 x 2000 KVA & Phase II- 14 x 2000 KVA). Hence, to avoid the emissions, stack height of 6 m above roof level for the D.G. Set shall be provided. The DG set shall meet all the norms prescribed by CPCB. | 5.2 | Emissions from production processes | No | Not applicable | 5.3 | Emissions from materials handling including storage or transport | Yes | Dust shall be generated during construction, from the movement of transport vehicles & other construction activities. The effect will be restricted to construction phase only.
Water sprinklers shall be used for dust suppression.
Material will be transported under covered vehicles & will be stored under Tarpaulin cover. | 5.4 | Emissions from construction activities including plant and equipment | Yes | RMC shall be used for the project. Dust & emissions are likely to be generated during construction activities which shall be reduced by sprinkling of water in a specific time interval & timely maintenance schedule for machinery. Also, the machines shall be shut down during idle period. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | During loading & unloading of construction material dust is likely to be generated during construction phase. Water shall be sprinkled and tarpaulin cover shall be provided over stored raw material to reduce dust emission.
Mobile Toilets during construction phase shall be provided for the construction labour. | 5.6 | Emissions from incineration of waste | No | Not applicable. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Open burning of biomass/ other material will be prohibited. | 5.8 | Emissions from any other sources | No | None | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | During Construction phase:
DG sets of capacities 62.5 KVA shall be installed acoustically enclosed. The equipment such as mixer machines, bulldozers, cranes, compactors & excavators shall be used which will be of highest standard. During Operation Phase: Source of noise in the operational phase will be D.G. set of capacities 20 x 2000 KVA (Phase I- 6 x 2000 KVA & Phase II- 14 x 2000 KVA). The D.G. Set shall be bought acoustically & shall be installed with anti-vibration pads. | 6.2 | From industrial or similar processes | No | Not applicable | 6.3 | From construction or demolition | Yes | Due to various activities, there will be short-term noise impacts in the immediate vicinity of the project site. These shall be restricted to day time only. It has been estimated that during the construction period the average noise level will be 80-100 dB (A) during peak construction hours. However, embankment shall be done to further prevent the noise pollution. | 6.4 | From blasting or piling | No | No blasting or piling will be done. | 6.5 | From construction or operational traffic | Yes | Some amount of noise (70 – 75 dB (A)) will be generated from vehicular movement in the construction and operational phase. Plantation around the boundary wall shall be done to reduce noise from traffic. | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | None | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | The hazardous waste generated will be used oil only and it will be stored in HDPE drums and kept in covered rooms under lock and key and will be sold to authorized vendors only. Special care will be taken to prevent leakages and spills. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | During operational phase STP of combined capacity 4200 KLD (For Phase I-1500 KLD & Phase II- 2700 KLD) shall be installed for treating 2225 KLD waste water & 2004 KLD of treated water from in house STP shall be reused in flushing, gardening, HVAC cooling and Misc. purpose. It will be a zero-discharge complex. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | None | 7.4 | From any other sources | No | Not applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not applicable | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | During Construction Phase:
All appropriate measures shall be taken to avoid accidents.
During Operational Phase:
Proper Disaster management & firefighting system will be installed at site. | 8.2 | From any other causes | Yes | During Construction Phase:
All appropriate measures shall be taken to avoid accidents.
During Operational Phase:
Proper Disaster management & firefighting system will be installed at site. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | The area under study falls in Seismic zone-III, according to the Indian Standard Seismic Zoning Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structure. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | STP will be installed for the treatment of wastewater.
• Housing development-Not Applicable
• Extractive industries-Not Applicable
• Supply industries-Not Applicable
• Other-Not Applicable | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not Applicable | 9.3 | Set a precedent for later developments | Yes | It will attract people to develop organized IT Park. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | No impact | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Bay of Bengal-3.13 Km E | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Guindy Park Reserve Forest-3.03 Km NW
Nanmangalam Reserve Forest-13.50 Km SW
Pallavaram Forest-9.15 Km (SWW)
Pallikaranai Marsh Reserve Forest-2.51 Km (SW)
Open Jungle-12.16 Km W
Adyar River-3.17 Km NNE
Coovam River-8.61 Km (N)
Kallukutai Lake-1.19 Km SW
Pulludivakam Eri-5.14 Km SW
Nanmangalam Lake-9.71 Km SW
Velachary Lake-3.40 Km W-6.27 Km SW
Narayanpuram Lake-1.19 km SSW
Perngudi Lake | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | None | 4 | Inland, coastal, marine or underground waters | Yes | Bay of Bengal-3.13 Km E | 5 | State, National boundaries | Yes | Andhra Pradesh-49.94 Km NNW | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | NH- 45-5.57 km NWW
Southern Arm Inner Ring Road-4.02 Km SW
Rajiv Gandhi IT Expy-0.43 Km NEE
Sardar Patel Rd-2.54 Km NGuindy Railway Station-4.73 Km NW
Chennai International Airport-7.44 km W | 7 | Defence installations | Yes | Tambaram Airforce Station-15.43 Km SW | 8 | Densely populated or built-up area | Yes | Mahatma Gandhi Nagar-0.51 Km W | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | G.S. Hospital-1.23 Km NNE
Taranami Post Office-0.36 Km NNW
Arulmigu Temple-1.31 Km E
Indian bank-1.13 Km NE
Indian School of science and management-2.53 Km SW | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Guindy Park Reserve Forest-3.03 Km NW
Nanmangalam Reserve Forest-13.50 Km SW
Pallavaram Forest-9.15 Km (SWW)
Pallikaranai Marsh Reserve Forest-2.51 Km (SW)
Open Jungle-12.16 Km W
Adyar River-3.17 Km NNE
Coovam River-8.61 Km (N)
Kallukutai Lake-1.19 Km SW
Pulludivakam Eri-5.14 Km SW
Nanmangalam Lake-9.71 Km SW
Velachary Lake-3.40 Km W-6.27 Km SW
Narayanpuram Lake-1.19 km SSW
Perngudi Lake | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | There is no critically polluted area falling within 15 km radius. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | The project area falls in seismic zone –III. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Arvind | Designation | VicePresident | Name of Company (Applicant Name should not be given here) | M/S DLF INFO PARK DEVELOPERS (CHENNAI) LIMITED | Address | Old No.828 & 828 A, New No.268 & 268 A, Sri Ranga, Poonamallee, High Road, Kilpauk, Chennai-600010 |
| |
|