APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | EXPANSION & CHANGE IN PRODUCT MIX | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/TN/IND2/83875/2018 | Project Cost | 425 lacs | |
| 2. | |
S. No. in the schedule | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Project Sector | Industrial Projects - 2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Existing capacity: 250 MT/Month with 5 products By products: 141 MT/Month with 2 products. Proposed capacity 112.85 MT/Month with 10 new products. By product: 81 MT/Month Product details: S. No Products Quantity (MT/Month) Total quantity after expansion Existing Products Proposed Products 1. Poly allamine hydrochloride 20 - 20 2. Isopropanol Hydrochloride 40 - 40 3. Non ferric alum 90 - 0 4. Basic chromium sulphate 90 - 0 5. Spent caustic lye solution 10 - 0 6. Linagliptin - 0.15 0 ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 0.3745 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | b) | Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | SF No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (part) Ammoor village, 12/5 (Part) Chettithangal village | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | SF No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (part) Ammoor village,
12/5 (Part) Chettithangal village | Town / Village | Chettithangal | State of the project | Tamil Nadu | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Tamil Nadu | Vellore | Wallajah | | 10. | |
Nearest railway station along with distance in kms | Walajah road Junction, 2.08 km | Nearest airport along with distance in kms | Vellore Airport, 30.40 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Ranipet , 2.67 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Ranipet Municipality office,
Muthukadai,
Ranipet,
Tamil Nadu 632401 | | 13. | Name of the Applicant | Dinesh | | 14. | Registered Address | S.F. No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (Part), Ammoor village, | | 15. | |
Address for correspondance: | Name of the Company | SANSKAR CHEMICALS AND DRUGS PRIVATE LIMITED | Name of the Applicant | Dinesh | Designation (Owner/ Partner/ CEO) | Owner | Pin code | 632403 | E-mail | karthik@sanskarchemicals.com | Telephone No. | 044-00000000 | Fax No. | 044- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | No changes in the land use.
Land use detail is given in table below
S. No Description Area (Ha.) % area
1 Building area 0.114 30.68
2 Open area 0.172 46.15
3 Green belt area* 0.147 15.95
4 Road area 0.026 7.208
Total 0.3745 100
*Note: In order to fulfill the mandatory requirement of 33% of green belt, an additional land of 900 sq. m will be allotted (15.95% +24.03%= 39.98 approx 40%) at Survey no 254/3B, Kolatheri village, Sholinghur Panchayat Union, Walajah Taluka, Vellore district | 1.2 | Clearance of existing land, vegetation and buildings? | No | The proposal does not involve any additional construction or building.
No, Clearance of land and vegetation. | 1.3 | Creation of new land uses? | No | Proposed project is Expansion & change in product mix within the existing facility.
There is no creation of new land uses. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil investigation report attached as Annexure XII. | 1.5 | Construction works? | No | Proposed project is Expansion & change in product mix within the existing facility.
No construction works are envisaged. | 1.6 | Demolition works? | No | Nil | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Nil | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | No | Nil | 1.9 | Underground works including mining or tunnelling? | No | Nil | 1.10 | Reclamation works? | No | Nil | 1.12 | Offshore structures? | No | Nil | 1.13 | Production and manufacturing processes? | Yes | Production and manufacturing process details are attached as Annexure X. | 1.14 | Facilities for storage of goods or materials? | Yes | Sufficient space is available at existing facility for storage of additional tanks for goods and storage. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste Generation and Management
S. No Waste Quantity (kg/day) Collection
method Treatment / disposal method
Existing Proposed
1 Organic 4.5 1.8 Bins Municipal bin including food waste
2 Inorganic 6.75 2.7 Bins TNPCB Authorized dealers
3 Ash from Fire wood (Kg/Month) 1500 1750 Bins Sold to brick manufacturer
a. Man power existing 25; proposed 10 numbers
b. Ash utilization letter attached as Annexure XI.
Hazardous Waste generation and Management
Schedule Type of the Hazardo | 1.16 | Facilities for long term housing of operational workers? | No | As workers from the nearby location will be employed so no housing facility for operational workers. | 1.17 | New road, rail or sea traffic during construction or operation? | No | Not required as the existing road facilities will be used for the proposed project. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Nil | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Nil | 1.20 | New or diverted transmission lines or pipelines? | No | There are no such kinds of activities involved. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | There are no such kinds of activities involved. | 1.22 | Stream crossings? | No | Nil | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Nil | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Nil | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | • The workforce is sourced locally who come to the factory in their own transport arrangements by road.
• Fire wood is transported through trucks by road.
• Raw materials and finished products are transported through trucks by road. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Nil | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Nil | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Nil | 1.29 | Introduction of alien species? | No | Nil | 1.30 | Loss of native species or genetic diversity? | No | Nil | 1.31 | Any other actions? | No | Nil | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The land document is attached as Annexure I.
Land use details given below
S. No Description Ha. Acre Sq. m %
1 Building area 0.1149 0.283 1149.17 30.68
2 Open area 0.1728 0.425 1728.63 46.15
3 Green belt area* 0.0597 0.147 597.40 15.95
4 Road area 0.0269 0.066 269.98 7.20
Total land area 0.3745 0.924 3745.18 100
*Note: In order to fulfill the mandatory requirement of 33% of green belt, an additional land of 900 sq. m will be allotted (15.95% +24.03%= 39.98 approx 40%) at Survey no 254/3B | 2.2 | Water (expected source & competing users) unit: KLD | Yes | The existing water requirement is 5KLD.
The total water requirement for the proposed expansion is 29 KLD.
Fresh water requirement is 14.6 KLD.
Source: Private water tankers./ Ground water (under approval) | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | No | Nil | 2.5 | Forests and timber (source – MT) | No | Nil | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Power requirement:
Details Power requirement (kVA) After Expansion
Existing Proposed
Power Requirement 116.56 23.31 139.87
Backup 100 50 150
DG set used as an alternate source of power during power failure.
Fuel requirement:
Diesel and Fire wood are the major fuels for Existing and Proposed expansion facility.
Details Existing Proposed After Expansion
Fire wood (MT/Month) 75 25 100
Diesel (Lit/Month) 400 100 500 | 2.7 | Any other natural resources (use appropriate standard units) | No | Nil | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Separate storage facility is provided for the storage of raw materials and products.
Chemicals are handled as per MSDS | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Nil | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | Proposed project is Expansion and change in product mix within the existing facility.
Employment will be provided for local people. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Nil | 3.5 | Any other causes | No | Nil | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not Applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Solid Waste Generation & Management:
S. No Waste Quantity (kg/day) Collection
method Treatment / disposal method
Existing Proposed
1 Organic 4.5 1.8 Bins Municipal bin including food waste
2 Inorganic 6.75 2.7 Bins TNPCB Authorized dealers
3 Ash from Fire wood (kg/month) 1500 1750 Bags Brick manufacture | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Hazardous Waste Management:
Schedule Type of the Hazardous waste Quantity Mode of Disposal
Existing Proposed
33.1 Discarded containers/ barrels/liners contaminated with hazardous wastes / chemicals (kg/month) -- 40 Will be disposed to TNPCB authorized recyclers
17.2 Spent catalyst (T/Annum) 972 -
A4 Chromium and/or Chromium (III) compounds concentration limit equal to (or) more than 5mg/l (T/Annum) 4320 -
5.2 Spent oil (lit/Annum) -- 60
Note: Hazardous waste authorization letter | 4.4 | Other industrial process wastes | No | No generation of process waste. | 4.5 | Surplus product | No | Nil | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sewage Treatment
S. No Description Domestic
(KLD) Disposal
1 Existing 2.5 Septic tank
2 Proposed 2.5
3 Total 5
Industrial Effluent Treatment
S .No Description Ind. Effluent Generation(KLD) Treatment Units
1 Existing 3 Solar evaporation pond
2 Proposed 8 MEE
3 Total 11 MEE | 4.7 | Construction or demolition wastes | No | Nil
There is no construction or Demolition activities involved. | 4.8 | Redundant machinery or equipment | No | Nil | 4.9 | Contaminated soils or other materials | No | Nil | 4.10 | Agricultural wastes | No | Nil | 4.11 | Other solid wastes | No | Nil | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission Sources:
• Construction phase: Nil
• Operation Phase:
• DG sets which will be utilized for a short duration and during power failure scenario.
• Diesel Oil will be used as fuel for the DG sets.
Control Measures:
s. no Source Stack height (m) Pollution control measures
1 Boiler 20 Stack
2 Reactor vessel 6 Common scrubber with stack
3 D.G. set 4 Exhaust pipe | 5.2 | Emissions from production processes | Yes | • Existing: No process emission is being generated.
• Proposed : No change | 5.3 | Emissions from materials handling including storage or transport | No | Raw materials are stored in closed system hence no emission during handling. | 5.4 | Emissions from construction activities including plant and equipment | Yes | • There are no construction activities involved. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | No | Not envisaged. | 5.6 | Emissions from incineration of waste | No | No incineration activity involved. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | No burning activity is involved. | 5.8 | Emissions from any other sources | No | S. No Source Stack height (m) Pollution control measures
1 Boiler 20 stack
2 Reactor vessels 6 Common scrubber with stack
3 D.G. sets 4 Exhaust pipe | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | • DG sets will be in operation during power failure
• DG sets provided with acoustic enclosure. | 6.2 | From industrial or similar processes | Yes | Noise generation at source will be complied by keeping the Noise within the prescribed limits. | 6.3 | From construction or demolition | No | No new construction or demolition carried out. | 6.4 | From blasting or piling | No | No blasting or piling activities involved | 6.5 | From construction or operational traffic | No | Does not arise | 6.6 | From lighting or cooling systems | Yes | • Will be regulated as per guidelines
• LED lights have been provided/proposed | 6.7 | From any other sources | No | Nil | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | All Storages and chemicals handling areas are properly protected and strict SOP is being followed to avoid any spillages etc. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | • Existing domestic waste water is sent to septic tank
• Blow down water will be treated in MEE | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | Nil | 7.4 | From any other sources | No | Nil | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Nil | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | Nil | 8.2 | From any other causes | No | Nil | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | • The project site falls under Seismic Zone-III (Moderate risk)
• Necessary Disaster Management plans will be followed for preventing any disasters during natural / accidental calamity. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | Nil | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Nil | 9.3 | Set a precedent for later developments | No | Not envisaged | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Nil | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Nil within 15km radius of the project boundary | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | S. No Name of the Location Distance
(~ km) Direction
Rivers
1 West bank main canal 12.28 NW
2 Palar river 5.06 WSW
3 Ponnai river 7.29 SW
Lakes
1. Kaveripakkam lake 9.93 ESE
2. Chettithangal lake 0.60 WSW
3. Kugayanellore lake 8.79 NW
4. Channasamudram Eri 7.24 SE
5. Lake 3.64 SSW
Reserve forest
1. Punganur RF 8.84 SW
2. Tiruvalam RF 7.89 WSW
3. Kil Minnal RF 10.96 WSW
4. Ammoor RF 1.82 ENE | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | S. No Reserve forest Distance (~km) Direction
1 Punganur RF 8.84 SW
2 Tiruvalam RF 7.89 WSW
3 Kil Minnal RF 10.96 WSW
4 Ammoor RF 1.82 ENE | 4 | Inland, coastal, marine or underground waters | No | not applicable | 5 | State, National boundaries | No | Nil within 15 Km radius from the project site | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | Nil within 15 Km radius from the project site | 7 | Defence installations | No | Nil within 15 Km radius from the project site | 8 | Densely populated or built-up area | Yes | Wallajapet at a distance of 3.43 km in SE direction | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | S.No
Hospitals
Distance (~km)
Direction
1.
Government Ammoor PH center
2.94
NE
2.
Sangeeths hospital
2.34
ENE
3.
Nithya sugam clinic
1.85
E
4.
Thirumalai mission hospital
2.38
SW
5.
MM hospital
2.92
SSE
6.
Dr.L.S hanthi Vimala clinic
3.70
SSW
7.
Scudder memorial hospital
3.76
SW
8.
Government urban primary health center
4.44
SE
9.
Kavitha hospital
4.65
SE
10.
Government headquarter hospital
4.64
SE
11.
Dr. Ganesh hospital
4.76
SSE
12. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | S. No Name of the Location Distance
(~ km) Direction
Rivers
1 West bank main canal 12.28 NW
2 Palar river 5.06 WSW
3 Ponnai river 7.29 SW
Lakes
1. Kaveripakkam lake 9.93 ESE
2. Chettithangal lake 0.60 WSW
3. Kugayanellore lake 8.79 NW
4. Channasamudram Eri 7.24 SE
5. Lake 3.64 SSW
Reserve forest
1. Punganur RF 8.84 SW
2. Tiruvalam RF 7.89 WSW
3. Kil Minnal RF 10.96 WSW
4. Ammoor RF 1.82 ENE | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | Yes | SIPCOT Ranipet is ~2.88 km in WSW direction, having CEPI score 79.67.
Comprehensive Environmental Pollution Index (CEPI) attached as Annexure XIV. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The project site falls under seismic zone-III according to the Indian Standard Seismic Zoning Map. However suitable seismic coefficients have been considered for building and structures design. Further it is not flood prone or landslide prone areas. Hence, no risk due to natural hazards is envisaged. | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The correction have been made as per the instruction received | 15 Nov 2018 | 2. | NA | Please confirm that the project site is not located in the notified Industrial area estate. Also, please provide copy of existing EC/CTO | 05 Nov 2018 | | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Dinesh | Designation | Owner | Name of Company (Applicant Name should not be given here) | SANSKAR CHEMICALS AND DRUGS PRIVATE LIMITED | Address | S.F. No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (Part), Ammoor village, |
|
|