APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s PROPOSED EXPANSION OF PESTICIDE TECHNICALS & PESTICIDE SPECIFIC INTERMEDIATES PRODUCTS - M/s. Tagros Chemicals India Private Limited [Unit-I]
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/TN/IND2/111357/2019
Project Cost 15000 lacs
2.
S. No. in the schedule5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 1073.75 MTPM ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/TN/IND2/111355/2008
MoEFCC file number(Previous EC)J-11011/453/2008-IA II (I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 273.75 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectSIPCOT Industrial Complex
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.A4/1-2 & 4-5, SIPCOT Industrial Complex,
Town / VillagePachayankuppam
State of the projectTamil Nadu
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Tamil NaduCuddaloreCuddalore
10.
Nearest railway station along with distance in kms Cuddalore Port Junction, 2.7 km
Nearest airport along with distance in kms Pondicherry, 32.5 km
11. Nearest Town/City/District Headquarters along with distance in kms Cuddalore , 8.6 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) SIPCOT Industrial Complex
13. Name of the Applicant M
14. Registered Address Plot No. A4/1-2 & 4-5, SIPCOT Industrial Complex, Vill: Pachayankuppam, Tehsil: Cuddalore, Dist. Cuddalore
15.
Address for correspondance:
Name of the Company TAGROS CHEMICALS INDIA PRIVATE LIMITED [UNIT-I]
Name of the Applicant M
Designation (Owner/ Partner/ CEO) Director
Pin code 607005
E-mail nagaraj@tagros.com
Telephone No. 4142-239373
Fax No. 4142-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No Proposed expansion project is located in SIPCOT Industrial Complex. Expected cost of the project is Rs. 319.82 Crores (Existing = Rs. 169.82 Crores + Additional Proposed = Rs. 150 Crores). Total Plot Area = 33,676.11 m2 Green Belt = 11,109.31 m2 (33%)
1.2 Clearance of existing land, vegetation and buildings? No -
1.3 Creation of new land uses? No -
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes For details refer Annexure-II
1.5 Construction works? Yes For details refer Annexure-II
1.6 Demolition works? No -
1.7 Temporary sites used for construction works or housing of construction workers? No -
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes For details refer Annexure-II
1.9 Underground works including mining or tunnelling? No -
1.10 Reclamation works? No -
1.11 Dredging? No -
1.12 Offshore structures? No -
1.13 Production and manufacturing processes? Yes For detail Please refer Annexure –III
1.14 Facilities for storage of goods or materials? Yes Specified storage area shall be provided for storage of goods, Raw materials & Finished products.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes For detail please refer Annexure – IV & V.
1.16 Facilities for long term housing of operational workers? No -
1.17 New road, rail or sea traffic during construction or operation? No -
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No -
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No -
1.20 New or diverted transmission lines or pipelines? No -
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No -
1.22 Stream crossings? No -
1.23 Abstraction or transfers of water from ground or surface waters? No No ground water shall be used. The raw water shall be supplied by SIPCOT Industrial Complex.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No -
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transportation of personnel, raw materials and products will be primarily by road only.
1.26 Long-term dismantling or decommissioning or restoration works? No -
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No -
1.28 Influx of people to an area in either temporarily or permanently? No -
1.29 Introduction of alien species? No -
1.30 Loss of native species or genetic diversity? No -
1.31 Any other actions? No -
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Proposed Expansion project is located in SIPCOT Industrial Complex.
2.2 Water (expected source & competing users) unit: KLD Yes The entire water requirement will be met through SIPCOT Industrial Complex. For detail please refer Annexure – VI
2.3 Minerals (MT) No -
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction materials, like steel, cement, crushed stones, sand, rubble, etc. required for the project shall be procured from the local market of the region.
2.5 Forests and timber (source – MT) No -
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes For detail please refer Annexure – VI
2.7 Any other natural resources (use appropriate standard units) No -
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes For detail please refer Annexure –VII.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No -
3.3 Affect the welfare of people e.g. by changing living conditions? No -
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No -
3.5 Any other causes No -
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No -
4.2 Municipal waste (domestic and or commercial wastes) No -
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Please refer Annexure – V
4.4 Other industrial process wastes No -
4.5 Surplus product No -
4.6 Sewage sludge or other sludge from effluent treatment Yes Please refer Annexure – V
4.7 Construction or demolition wastes No -
4.8 Redundant machinery or equipment No -
4.9 Contaminated soils or other materials No -
4.10 Agricultural wastes No -
4.11 Other solid wastes Yes Please refer Annexure – V
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes For details Please refer Annexure – VIII
5.2 Emissions from production processes Yes For details Please refer Annexure – VIII
5.3 Emissions from materials handling including storage or transport Yes For details Please refer Annexure – VIII
5.4 Emissions from construction activities including plant and equipment Yes During construction work, only dust contamination will be there, water sprinklers shall be utilized whenever necessary.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No -
5.6 Emissions from incineration of waste No -
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No -
5.8 Emissions from any other sources No -
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Please refer Annexure – IX
6.2 From industrial or similar processes Yes Please refer Annexure – IX
6.3 From construction or demolition No -
6.4 From blasting or piling No -
6.5 From construction or operational traffic No -
6.6 From lighting or cooling systems Yes Please refer Annexure – IX
6.7 From any other sources No -
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Hazardous material shall be stored in designated storage area with bund walls for tanks. Other material will be stored in bags/drums on pallets with concrete flooring. All liquid raw materials shall be transported through pumps and closed pipelines and no manual handling shall be involved. For details please refer Annexure – VII
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Out of 612 KLD Industrial Effluent, Low TDS effluent 222 KLD will be treated in Reverse Osmosis Plant after pretreatment. High TDS effluent 390 KLD will be treated in Multiple Effect Evaporator/Forward Osmosis after pretreatment. The Condensate of Multiple Effect Evaporator will be further treated in Reverse Osmosis Plant. The concentrate generated will be treated in VTFD and the salt recovered will be sent to TSDF. The water recovered from Forward OsmosisPlant and ReverseOsmosis Plant ie 413 KL
7.3 By deposition of pollutants emitted to air into the land or into water No -
7.4 From any other sources No -
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No -
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes For detail please refer Annexure – VII
8.2 From any other causes No -
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No -
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
No Site is located in SIPCOT Industrial Complex, having the entire required infrastructure. This industrial zone is having existing road infrastructure & power supply are to be utilized. Local people will be employed and no housing is required. For detail please refer Annexure – X
9.2 Lead to after-use of the site, which could have an impact on the environment No -
9.3 Set a precedent for later developments No -
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No -
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Proposed project is located in SIPCOT Industrial Complex.
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests No -
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No -
4 Inland, coastal, marine or underground waters Yes No inland, costal or marine within 5 km from the proposed expansion project.Inland, costal or marine within 3 km from the proposed expansion project
5 State, National boundaries No -
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No -
7 Defence installations No -
8 Densely populated or built-up area Yes Cuddalore
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No -
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No -
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No -
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No -
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) NIL
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantM
DesignationDirector
Name of Company (Applicant Name should not be given here)TAGROS CHEMICALS INDIA PRIVATE LIMITED [UNIT-I]
AddressPlot No. A4/1-2 & 4-5, SIPCOT Industrial Complex, Vill: Pachayankuppam, Tehsil: Cuddalore, Dist. Cuddalore
Print