APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | No |
| | Whether proposal involved violation of EIA notification | Yes | tr > | Weather Consent to Establishment Obtained | Yes | | Upload copy of CTE | Upload copy of CTE |
| 1. | |
Name of the Project/s | Sitapuram Limestone Mines Ml-2 of Zuari Cement Ltd. | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/TG/MIN/255765/2022 | Project Cost | 0.246 cr | |
| 2. | |
S. No. in the schedule | 1(a) Mining of minerals
| Project Sector | Non-Coal Mining | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 303750T ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 558.71 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | 16°48'12.29"N to 16°49'51.18"N 79°58'14.6"Eto80° 02'11.42"E | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | 56 P/13 and 65D/1 | Town / Village | Dondapadu | State of the project | Telangana | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Telangana | Suryapet | Chinthalapalem | | 10. | |
Nearest railway station along with distance in kms | Bona Kaluat, 32 km | Nearest airport along with distance in kms | Vijayawada, 87.5 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Kodad , 17 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village-Dondapadu & Panchayat-Suryapet Zilla Parisad- Suryapet Local Body | | 13. | Name of the Applicant | SUSHIL | | 14. | Registered Address | AT-SITAPURAMDONDAPADU,MANDAL-MELLACHERUVU DIST-NALGONDA | | 15. | |
Address for correspondance: | Name of the Company | ZUARI CEMENT LTD | Name of the Applicant | SUSHIL | Designation (Owner/ Partner/ CEO) | DIRECTOR | Pin code | 516311 | E-mail | zuaricement111@gmail.com | Telephone No. | 674-2552544 | Fax No. | 674- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Mining 9.24
Infrastructure- Workshop, Administrative Building etc. 0.05
Roads 3.36
Railway ---
Township Area 5.5
Other specify (Plantation) 3.4
Magazine 0.4
Sub Total 21.95
Area remained untouched 536.76
Total 558.71 | 1.2 | Clearance of existing land, vegetation and buildings? | No | The mining lease area is not cover any forest land. | 1.3 | Creation of new land uses? | Yes | Mining 9.24
Infrastructure- Workshop, Administrative Building etc. 0.05
Roads 3.36
Railway ---
Township Area 5.5
Other specify (Plantation) 3.4
Magazine 0.4
Sub Total 21.95
Area remained untouched 536.76
Total 558.71 | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Geological survey and Mining Plan has been prepared after conducting different tests. | 1.5 | Construction works? | No | No construction is involved during the project. | 1.6 | Demolition works? | No | No demolition has been done. However opencast mining method will be adopted as per the mining plan. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Local manpower will be utilized for construction work if required. Therefore, no housing facility at construction site. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Mining will be carried out as per the approved mining Scheme. | 1.9 | Underground works including mining or tunnelling? | No | Mining of limestone is accomplished by Opencast Fully-mechanized Method. | 1.10 | Reclamation works? | Yes | At the end of Mining, the Work out area would be reclaimed by Water storage for fishery ponds after exploitation of Limestone reserves and plantation as per the modified Scheme of Mining. | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | Open-cast fully - mechanized (OTFM-A) method for mining of limestone. | 1.14 | Facilities for storage of goods or materials? | Yes | Limestone will be mined and transported to own cement manufacturing plant adjoining to the mines. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | No | No solid waste generation and there is no liquid effluents generation. | 1.16 | Facilities for long term housing of operational workers? | No | As the local labors available, no housing facility will be required. | 1.17 | New road, rail or sea traffic during construction or operation? | No | The site is well connected by fair weather road from Jaggayyapet Haul roads inside mine lease area also exists. Therefore, no new road, rail or sea traffic required. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Existing facilities are sufficient. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | There is no closure or diversion of existing routes or infrastructure for the proposed project. | 1.20 | New or diverted transmission lines or pipelines? | No | There are no new or diverted transmission lines or pipelines in the project site. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | Yes | A garland channel will be constructed around the pit to pass the rain water to the natural stream after passing through the settling tank. | 1.22 | Stream crossings? | No | Not applicable | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Accumulated rain water is proposed to be utilized for plantation & water sprinkling. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not applicable | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | No | There is no construction operation involved. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No dismantling work will be carried in the project. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | No decommissioning activity proposed. | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | For employment and for business opportunities. | 1.29 | Introduction of alien species? | No | There would be no introduction of any alien species since local species would be preferred for the plantation. | 1.30 | Loss of native species or genetic diversity? | No | There will not be any loss of native species or genetic diversity. | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | The total ML area over 558.71Ha of M.L- 2 is totally non-forest area. As the total area falls under private land. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | 50 m3/day of water is required. Mines water sump which is collected at lower level of the mine pit during rains. | 2.3 | Minerals (MT) | No | Not applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | No | There is no construction needed in the lease area, hence no construction material is used. | 2.5 | Forests and timber (source – MT) | No | No forest and timber products are involved in the proposed project. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | No | Not Applicable | 2.7 | Any other natural resources (use appropriate standard units) | No | No other natural resources are used. | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | The project does not involve any hazardous materials as per MSIHC rules. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not envisaged. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Due to this facility, living standards of surrounding people will increase. i.e.,
? Work will be generated for unemployed.
? Educational facilities will be provided.
? The socio-economic benefits arising out of this project for the local people will include creation of direct and indirect jobs and consequent rise in the income levels, associated commercial and Social infrastructure development. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | No Vulnerable group of people is being affected by the project. | 3.5 | Any other causes | No | Not Available. | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | No Over Burden/Wastes | 4.2 | Municipal waste (domestic and or commercial wastes) | No | Nil | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | No Hazardous waste (as per Hazardous Waste Management Rules) is being generated. | 4.4 | Other industrial process wastes | No | There is no industrial process involved in the project. | 4.5 | Surplus product | No | Not Applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | No | Not Applicable | 4.7 | Construction or demolition wastes | No | No construction or demolition work involved. | 4.8 | Redundant machinery or equipment | Yes | Majority of the dumpers and excavating equipment’s will be of the Lessee. Majority of the Dumpers and Excavating equipment are lessee and discard as per the standards. | 4.9 | Contaminated soils or other materials | No | Nil | 4.10 | Agricultural wastes | No | Nil | 4.11 | Other solid wastes | No | No other solid waste is generated. | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emissions during operation of diesel driven HEMM etc. is envisaged.
Details of emission and impact will be provided in EIA report. | 5.2 | Emissions from production processes | Yes | This open-cast fully-mechanized mining will result in generation of fugitive dust, emissions during excavation,loading, unloading activities and transportation. | 5.3 | Emissions from materials handling including storage or transport | Yes | Emission will be released from storage / handling / transport of mining material & vehicular movement only. | 5.4 | Emissions from construction activities including plant and equipment | No | No construction activity has been carried out at site so there are no emissions from any such activities. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust arises from Materials will be suppressed by water sprinkling. Proper care will be taken during handling of material. During unloading of mineral, water will be sprayed. Therefore no fugitive emissions will be released. The sewage generated from mine site will be properly routed to septic tank followed by soak pit. | 5.6 | Emissions from incineration of waste | No | Not Applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not Applicable | 5.8 | Emissions from any other sources | No | There is no other source of emission. | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated due to mining activities like drilling, blasting excavation, loading, transportation activity. However, all the equipment’s are equipped with Acoustic enclosure to maintain the ambient noise level with prescribed limits of CPCB. | 6.2 | From industrial or similar processes | No | No industrial processes are involved. | 6.3 | From construction or demolition | No | No construction or demolition is involved. | 6.4 | From blasting or piling | No | Controlled blasting will be done. Dumpers are fitted with Big Cam Engine Which produce less sound.
Regular maintained of machinery. | 6.5 | From construction or operational traffic | No | Marginal increase in noise level due to transportation of mineral. Meager noise can be anticipated from the traffic.
Measures have been taken to control noise with proper preventive maintenance and lubrications. | 6.6 | From lighting or cooling systems | No | No lighting or cooling systems are involved. | 6.7 | From any other sources | No | There are no any other sources which generate noise and vibration. | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | No hazardous materials will be used except explosives during Controlled blasting which is being done with all precautions. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | The domestic wastewater will be disposed to septic tank followed by soak pit | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | Airborne dust may deposit on leaves of plantation affecting their growth. | 7.4 | From any other sources | No | There is no other source from which risk of contamination is anticipated. | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | It is only mining site. The only emission is in the form of fugitive dust during excavation and it will be suppressed by water sprinkling. No fuel burning will occur. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | No hazardous materials will be used except explosives during Controlled blasting Which is being done with all precautions. | 8.2 | From any other causes | Yes | Due to vehicle movement and it would be avoided by taking proper precautions and mitigation | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | No as the area falls under the zone II as per the Seismic Zone Map of India. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | There is no impact on the environment.
These facilities will be strengthened. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | The mining area will be used for water reservoir and fishery ponds after mining is completely over. No impact will occur. | 9.3 | Set a precedent for later developments | Yes | A better after use scenario, which is likely to increase aesthetic beauty of the area by doing plantation on reclaimed area. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | There will be no cumulative effects due to proximity to other existing or planned projects with similar effects. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | ---- | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Krishna River Approx. 3.9 Km in East direction. | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Venkatayapalem Reserve Forest Approx. 6.5 Km in SE direction. | 4 | Inland, coastal, marine or underground waters | No | Nil | 5 | State, National boundaries | No | --- | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Dondapadu Road Adjacent to Project Site. NH-9 Approx. 11.4 Km in NE direction. | 7 | Defence installations | No | Nil | 8 | Densely populated or built-up area | Yes | Revoor Adjacent to Project Site. | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Govt. High School, Revuru Adjacent to Project Site. St. Anns School, Dondapadu Approx. 1.0 Km in East direction Venugopala Swamy Temple Revuru Adjacent to Project Site. Veerabramhendra Swamy Temple Revuru Adjacent to Project Site. Zuari Hospital Adjacent to Project Site. Revuru Primary Health Centre Adjacent to Project Site. | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | --- | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | --- | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | The proposed project area comes under Seismic Zone-II i.e.Least active zone prone to earthquakes. Reference: Seismic Zone Map of India. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 11 Mar 2024 | 2. | NA | Deferred | 18 Dec 2023 | 3. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 20 Nov 2023 | 4. | NA | Sir,
The proposal was earlier considered in the 6th EAC (Non-Coal Mining) meeting held during 9th -11th November, 2022 wherein the EAC noted that that the Project Proponent vide email dated 27.10.2022 informed the Ministry that the authorisation process of the nominated owner is not completed yet due to personal difficulties and hence requested to adjourn the meeting. Therefore, the EAC deferred the proposal based on the request of the Project Proponent vide email dated 27.10.2022. Again, the Project Proponent vide letter dated 10.02.2023, 01.05.2023 and 07.08.2023 informed the Ministry stating that the authority & responsible of top management is not decided yet due to retirement of Managing Director. It is to informed that the authorized person must be present before the EAC to commit and to take any decision w.r.t. project proposal. The proposal may be considered only after the request of the Project Proponent and after the authorized person nominated by the Project Proponent to present the case before the EAC. | 06 Sep 2023 | 5. | NA | Sir,
The proposal was earlier considered in the 6th EAC (Non-Coal Mining) meeting held during 9th -11th November, 2022 wherein the EAC noted that that the Project Proponent vide email dated 27.10.2022 informed the Ministry that the authorisation process of the nominated owner is not completed yet due to personal difficulties and hence requested to adjourn the meeting. Therefore, the EAC deferred the proposal based on the request of the Project Proponent vide email dated 27.10.2022. Again, the Project Proponent vide letter dated 10.02.2023, 01.05.2023 and 07.08.2023 informed the Ministry stating that the authority & responsible of top management is not decided yet due to retirement of Managing Director. It is to informed that the authorized person must be present before the EAC to commit and to take any decision w.r.t. project proposal. The proposal may be considered only after the request of the Project Proponent and after the authorized person nominated by the Project Proponent to present the case before the EAC. | 06 Sep 2023 | 6. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 09 Aug 2023 | 7. | NA | Sir, The proposal was earlier considered in the 6th EAC (Non-Coal Mining) meeting held during 9th -11th November, 2022 wherein the EAC noted that that the Project Proponent vide email dated 27.10.2022 informed the Ministry that the authorisation process of the nominated owner is not completed yet due to personal difficulties and hence requested to adjourn the meeting. Therefore, the EAC deferred the proposal based on the request of the Project Proponent vide email dated 27.10.2022. Again, the Project Proponent vide letter dated 10.02.2023, 01.05.2023 and 07.08.2023 informed the Ministry stating that the authority & responsible of top management is not decided yet due to retirement of Managing Director. It is to informed that the authorized person must be present before the EAC to commit and to take any decision w.r.t. project proposal. The proposal may be considered only after the request of the Project Proponent and after the authorized person nominated by the Project Proponent to present the case before the EAC. | 08 Aug 2023 | 8. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 08 Aug 2023 | 9. | NA | Sir,
The proposal was earlier considered in the 6th EAC (Non-Coal Mining) meeting held during 9th -11th November, 2022 wherein the EAC noted that that the Project Proponent vide email dated 27.10.2022 informed the Ministry that the authorisation process of the nominated owner is not completed yet due to personal difficulties and hence requested to adjourn the meeting. Therefore, the EAC deferred the proposal based on the request of the Project Proponent vide email dated 27.10.2022. Again, the Project Proponent vide letter dated 10.02.2023 & 01.05.2023 informed the Ministry stating that the authority & responsible of top management is not decided yet due to retirement of Managing Director. It is to informed that the authorized person must be present before the EAC to commit and to take any decision w.r.t. project proposal. The proposal may be considered only after the request of the Project Proponent and after the authorized person nominated by the Project Proponent to present the case before the EAC. | 16 May 2023 | 10. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 05 May 2023 | 11. | NA | Sir,
The proposal was earlier considered in the 6th EAC (Non-Coal Mining) meeting held during 9th – 11th November, 2022 wherein the EAC noted that that the Project Proponent vide email dated 27.10.2022 informed the Ministry that the authorisation process of the nominated owner is not completed yet due to personal difficulties and hence requested to adjourn the meeting. Therefore, the EAC deferred the proposal based on the request of the Project Proponent vide email dated 27.10.2022. Again, the Project Proponent vide letter dated 10.02.2023 informed the Ministry stating that the authority & responsible of top management is not decided yet due to retirement of Managing Director. It is to informed that the authorized person must be present before the EAC to commit and to take any decision w.r.t. project proposal. The proposal may be considered only after the request of the Project Proponent and after the authorized person nominated by the Project Proponent to present the case before the EAC. | 15 Feb 2023 | 12. | ADS Reply Letter | The authority & responsible of top management yet to be decided. | 10 Feb 2023 | 13. | NA | Deferred | 16 Nov 2022 | 14. | ADS Reply Letter | Information For Joining of Vimal Kumar Jain as Nominated Owner of ZCL | 11 Oct 2022 | 15. | NA | Deferred | 09 Aug 2022 | 16. | ADS Reply Letter | We are in process, till date we have not received the letter from the Ministry . The details correspondence are attached herewith for your reference. So it request to maintain not to delete our proposal from the portal. | 19 May 2022 | 17. | NA | Deferred | 17 Mar 2022 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | SUSHIL | Designation | DIRECTOR | Name of Company (Applicant Name should not be given here) | ZUARI CEMENT LTD | Address | AT-SITAPURAMDONDAPADU,MANDAL-MELLACHERUVU DIST-NALGONDA |
|
|