APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | M/s S.R. MINERALS,Laterite Mine over an Extent of 9.915 Hectares, in Sy. No. 41 /P of Mirzapur Village, Pudur Mandal, Vikarabad District, Telangana State. | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/TG/MIN/107169/2019 | Project Cost | 90 lacs | |
| 2. | |
S. No. in the schedule | 1(a) Mining of minerals
| Project Sector | Non-Coal Mining | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 253456.25 TPA ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 00 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Sy. No. 41/P Mirzapur Village, Pudur Mandal, Vikarabad District Telangana State. | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Sy. No. 41/P
Mirzapur Village,
Pudur Mandal,
Vikarabad District
Telangana State | Town / Village | Mirzapur at 0.8 Km,Vikarabad at a distance of 09 km | State of the project | Telangana | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Telangana | Rangareddi | Vicarabad | | 10. | |
Nearest railway station along with distance in kms | Vikarabad, 9 km | Nearest airport along with distance in kms | Hyderabad, 75 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Mirzapur , 0.8 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Smt. P. Syamala Rani
Proprietor
M/s S.R. Minerals
D.No.8-2-268/1/2, Flat No 101,
Uma Park Side Apartments,
Road No. 5, Banjarahills,
Hyderabad – 500034
Mobile : 9849123450 | | 13. | Name of the Applicant | PSyamalaRani | | 14. | Registered Address | D.No.8-2-268/1/2, Flat No:101,Uma Park Side Apartments,Road No:05,Banjara Hills, Hyderabad-500034 | | 15. | |
Address for correspondance: | Name of the Company | M/S S.R. MINERALS | Name of the Applicant | PSyamalaRani | Designation (Owner/ Partner/ CEO) | Proprietor | Pin code | 500034 | E-mail | ecsrminerals9@gmail.com | Telephone No. | 040-27407969 | Fax No. | 040- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Mining will be done in the lease area by manual opencast other then fully Mechanized without drilling & blasting.
The present topography of the area is a part of rocky and barren rugged uneven land with high gradient slope. Because of mining except degradation of height from existing level, no land use and land cover will be changed. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | There will be clearance of existing vegetation wherever required. However, as the existing vegetation density in the mine lease is only about 0.4, no heavy clearance of vegetation will be required.
There are no existing buildings in the lease area and hence no proposal of clearance of existing buildings is made | 1.3 | Creation of new land uses? | Yes | Present land use will be changes with commencement of mining activities. After completion of mining activities, the land will be reused for forest growth. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | The lessee conducted preliminary exploration work and after satisfying quality and quantity of the mineral available in the area they have applied for mining lease. | 1.5 | Construction works? | Yes | There will be no major civil works, other than the following:
Office Building;
Dispensary; Rest house etc. | 1.6 | Demolition works? | Yes | There are no existing buildings in the lease area. Hence, no demolition works involved | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | No major housing for construction workers is envisages at the mines | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | No tall buildings are proposed in the site.
Opencast mining (excavations) will be done in the lease area. | 1.9 | Underground works including mining or tunnelling? | Yes | Opencast manual mining will be done by ripping the hillock.
However, no underground mining or tunneling is anticipated. | 1.10 | Reclamation works? | Yes | Phase-wise reclamation of mined out blocks will be practiced | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | About 253456.25 TPA of Laterite from this opencast Mining
However, no beneficiation including manufacturing is done in the lease area. | 1.14 | Facilities for storage of goods or materials? | Yes | Facilities will be provided for storage of excavated mineral in designated areas.
There will no other major storage facilities in the lease area. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Back filled in the lease area | 1.16 | Facilities for long term housing of operational workers? | No | No separate township is proposed for the mining project. | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | Haul roads will be constructed in the lease area.
No new rail network or sea route is proposed for the mining project. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | Approach road for the mine lease from the foothill will be constructed.
No other major road, rail, air or waterborne transport network is envisaged for the mining project. | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | No such diversions are envisaged. | 1.20 | New or diverted transmission lines or pipelines? | No | No such diversions are envisaged. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | No such diversions are envisaged. | 1.22 | Stream crossings? | No | No streams exist on the hillock | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | Part of the water required for the mining activities will be sourced from nearby villages. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | The rainwater constitutes the drainage system of the area. Except this no other perennial watercourses exist in this area. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The mined out minerals will be transported to consumers by trucks directly manually. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No dismantling works are envisaged. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | Yes | Temporary change in land use pattern occurs. The existing scanty vegetative land will be converted into lush green cover. | 1.28 | Influx of people to an area in either temporarily or permanently? | No | No major influx is envisaged due to the mining project, as the total manpower required during operational stage will be only 18 including labour & will be met from the local area only. | 1.29 | Introduction of alien species? | No | Not envisaged | 1.30 | Loss of native species or genetic diversity? | No | Not envisaged | 1.31 | Any other actions? | No | Not envisaged | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | 9.915 Ha | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Total water requirement of the mining operations including dust suppression is about 10 KLD and majority of this is proposed to be met from the bore well. | 2.3 | Minerals (MT) | No | Not applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | The construction material
required for the project shall be
Sourced locally. However, no
major constructional material
requirement is envisaged | 2.5 | Forests and timber (source – MT) | No | Not applicable | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | No | This is manual open cast mining
And no blasting is involved. Hence,
energy and fuels consumption is not
Required. | 2.7 | Any other natural resources (use appropriate standard units) | No | - | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | No major storage of fuel oils | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not envisaged | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Living standards of the surrounding, villagers will improved due to availability of better infrastructure, health care and educational facilities. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not envisaged | 3.5 | Any other causes | No | - | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | No waste will be generate from this mine | 4.2 | Municipal waste (domestic and or commercial wastes) | No | No generation of municipal waste is envisaged | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | No generation of hazardous waste is envisaged | 4.4 | Other industrial process wastes | No | No other major solid wastes are envisaged | 4.5 | Surplus product | No | Not envisaged | 4.6 | Sewage sludge or other sludge from effluent treatment | No | Not envisaged | 4.7 | Construction or demolition wastes | No | Not envisaged | 4.8 | Redundant machinery or equipment | No | Not envisaged | 4.9 | Contaminated soils or other materials | No | Not envisaged | 4.10 | Agricultural wastes | No | Not envisaged | 4.11 | Other solid wastes | No | Not envisaged | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | No | - | 5.2 | Emissions from production processes | Yes | Fugitive dust will only be generated from mining activities. Adequate control measures will be taken to control fugitive dust. | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive dust will be generated from material handling activities.
Dust Suppression by water sprinklers will be provided to prevent the fugitive dust emissions | 5.4 | Emissions from construction activities including plant and equipment | No | No major construction activities are envisaged | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be generated during excavation and transportation of minerals and it will be controlled.
However, there is no possibility of any odor generation as there are no organic solvents / processes involved. | 5.6 | Emissions from incineration of waste | No | Not envisaged | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not envisaged | 5.8 | Emissions from any other sources | No | Not envisaged | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated from vehicles and machinery activities. The noise level at source will range in | 6.2 | From industrial or similar processes | No | Not envisaged | 6.3 | From construction or demolition | No | No major construction / demolitions are envisaged | 6.4 | From blasting or piling | Yes | Noise (below 75 dB(A) will be generated during mining operation, which will be instantaneous in nature. | 6.5 | From construction or operational traffic | No | Not envisaged | 6.6 | From lighting or cooling systems | No | Not envisaged | 6.7 | From any other sources | No | Not envisaged | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | No major storages are envisaged and hence, no risk of contamination of land or contamination of land or water is envisaged. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | No wastewater generation is envisaged from mining activities.
There will not be any external discharge or wastewater. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | Not envisaged | 7.4 | From any other sources | No | - | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | - | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | No risk of accidents is envisaged as there will be no major storage of hazardous substances. | 8.2 | From any other causes | No | - | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The proposed project sits is a hillock area, hence, there is no possibility of site get affected by floods, cloud bursts etc. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | Supporting and ancillary development will take place.
No major developments envisaged. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | Not envisaged | 9.3 | Set a precedent for later developments | Yes | Ancillary industries will be developed as a consequence. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | - | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | No protected areas exist in 10-km radius area | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | There are no wetlands, major water bodies, coastal zones, biospheres or mountains in 10-km radius. | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | - | 4 | Inland, coastal, marine or underground waters | No | - | 5 | State, National boundaries | No | Telangana State and Karnataka Interstate boundary -38 Km. | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | - | 7 | Defence installations | No | - | 8 | Densely populated or built-up area | Yes | Mirzapur is the nearest village located at a distance of 0.8 km from ML area . | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Small hospitals small schools and small temples are existing within 10 km radial distance from the proposed mine area | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | - | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | - | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The area is not known for these natural hazards | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | PSyamalaRani | Designation | Proprietor | Name of Company (Applicant Name should not be given here) | M/S S.R. MINERALS | Address | D.No.8-2-268/1/2, Flat No:101,Uma Park Side Apartments,Road No:05,Banjara Hills, Hyderabad-500034 |
| |
|