APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Proposed Bulk Drugs manufacturing unit by YS Drugs | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/TG/IND2/93173/2019 | Project Cost | 1100 lacs | |
| 2. | |
S. No. in the schedule | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Project Sector | Industrial Projects - 2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 50 MT/Month Bulk Drugs ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 0 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Sy No: Parts of 344,345 &347, Pyararam Village , Bommalaramaram Mandal, Yadadri Bhongir district, Telangana State | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Parts of 344,345 &347 | Town / Village | Sy No: Parts of 344,345 &347, Pyararam Village , Bommalaramaram Mandal, Yadadri Bhongir district, Telangana State | State of the project | Telangana | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Telangana | Yadadri Bhuvanagiri | Bommalaramaram | | 10. | |
Nearest railway station along with distance in kms | Medchal Railway Station, 26 Kms (W) km | Nearest airport along with distance in kms | Rajiv Gandhi International Airport, 51 Kms (SW) km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Bommalaramaram , 7 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Sy No: Parts of 344,345 &347, Pyararam Village , Bommalaramaram Mandal, Yadadri Bhongir district, Telangana State | | 13. | Name of the Applicant | ChandraSekhar | | 14. | Registered Address | #2-2-186/17/C/1, Baghamberpet, Bharathnagar, Amberpet, Hyderabad | | 15. | |
Address for correspondance: | Name of the Company | YS DRUGS | Name of the Applicant | ChandraSekhar | Designation (Owner/ Partner/ CEO) | ManagingPartner | Pin code | 508116 | E-mail | ysdrugs@gmail.com | Telephone No. | 040-23060702 | Fax No. | 040- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The present site is located at Pyararam Village, the 4.72 Acres Agricultural land will be converted to Industrial land and the land use will be permanently changed to industrial purpose. | 1.2 | Clearance of existing land, vegetation and buildings? | No | No tree felling or clearance of buildings is envisaged | 1.3 | Creation of new land uses? | Yes | The 4.72 Acres land will be converted to Industrial land | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | No | Not Applicable | 1.5 | Construction works? | Yes | Construction work will be done as per the requirement of the proposed project. Plant Layout is Enclosed as Annexure -II in Additional information. | 1.6 | Demolition works? | No | No demolition work | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Majority of the labor will be hired from nearby villages so no housing or shelter facilities required for construction workers. However temporary campsites will be provided with a minimum requirement of drinking and sanitation facilities for workers during working hours. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | No | Not Applicable | 1.9 | Underground works including mining or tunnelling? | No | Not Applicable | 1.10 | Reclamation works? | No | Not Applicable | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | Yes | List of products & Manufacturing processes Enclosed as Annexure - I & III. | 1.14 | Facilities for storage of goods or materials? | Yes | Common facility for storage of raw materials and finished products will be provided | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste: The Solid & hazardous waste generated in the plant will be disposed as per rules. Liquid waste: Industrial effluent of 27.27 KLD is generated and will be treated in ZLD System. | 1.16 | Facilities for long term housing of operational workers? | No | Employees will be hired from nearby Village Town & City. No housing facilities will be require | 1.17 | New road, rail or sea traffic during construction or operation? | No | Road traffic is likely to increase both during construction and operation stage for transportation of man and material.
However, existing transport routes are adequate for the increase in traffic. No additional transport infrastructure is required due to the proposed project | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | No additional transport infrastructure is required due to the proposed project | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not Required | 1.20 | New or diverted transmission lines or pipelines? | No | Not Required | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Required | 1.22 | Stream crossings? | No | Not Required | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | The total water requirement of 77.17 KLD for the project will be met from ground water | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Nill | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The raw materials and products will be transported through Keesara - Yadagirigutta Raod during construction and operation phase | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | The Estimated employment generation for this proposed project is about 45 Direct and 15 indirect employees. | 1.29 | Introduction of alien species? | No | No alien species will be introduced. | 1.30 | Loss of native species or genetic diversity? | No | There will be no loss of native species or genetic diversity. | 1.31 | Any other actions? | No | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Total 4.72 Acres (19101 Sq.m) agricultural land will be converted to Industrial land | 2.2 | Water (expected source & competing users) unit: KLD | Yes | The total water requirement will be 77.17 KLD. Required water will be sourced from Groundwater supply. The detailed water balance is enclosed in Annexure - IV | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Construction materials like stone, steel aggregates, sand & cement will be sourced locally. | 2.5 | Forests and timber (source – MT) | No | | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Boiler Details: 3 TPH Coal-fired Boiler, Electricity from TSPDCL
Total power will be 800 KVA.
D. G. Sets:500 KVA | 2.7 | Any other natural resources (use appropriate standard units) | No | | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | A number of chemicals will be used for the production of Synthetic Organic Chemicals, Drugs, Drug Intermediates
and Excipients, which have been mentioned in the list of raw materials are given in the Additional Information as Annexure-
VIII. They shall be managed as per provision of the MSIHC rules. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The proposed project will generate direct and indirect employment opportunities during construction as well as operation phase for the local people based on their
qualification and work experience. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | Not applicable | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Commercial waste like empty cement bags, Iron scrap etc.
will be sold to scrap buyers after the construction phase.
Domestic waste like used paper, label, cartoons will be
disposed to the scrap buyers. Organic waste from canteen
will be disposed as per the local Panchayath / Municipal
disposal mechanism. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Hazardous wastes Details are Enclosed as Annexure - V | 4.4 | Other industrial process wastes | Yes | The detailed Solid & Hazardous wastes Details are Enclosed as Annexure - V | 4.6 | Sewage sludge or other sludge from effluent treatment | No | | 4.7 | Construction or demolition wastes | Yes | Minimal quantity of debris, scraps, excavated soil, used
cement bags, iron/steel scrap, and cardboards waste could be generated during additional construction. | 4.8 | Redundant machinery or equipment | No | | 4.9 | Contaminated soils or other materials | No | | 4.10 | Agricultural wastes | No | | 4.11 | Other solid wastes | No | | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Gaseous emission like SO2, NOx, CO and the particular matter
shall be generated from Boiler and DG set which will be
maintained under prescribed limit. DG set will be used
during only power break down. Adequate stack height of
Boiler and DG set provided for effective dispersion of
pollutants. | 5.2 | Emissions from production processes | Yes | Proper control will be adopted to control emission as per prescribed Standard | 5.3 | Emissions from materials handling including storage or transport | Yes | Fugitive emissions from material handling, loading
/unloading and transport of material will be minimal due to closed loop system. | 5.4 | Emissions from construction activities including plant and equipment | Yes | This will be restricted to the construction phase and to the construction site only. It will be minimized by sprinkling water. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be generated from loading and unloading of raw material and finished products | 5.6 | Emissions from incineration of waste | No | | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | | 5.8 | Emissions from any other sources | No | | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Material transport shall be a source of noise during
construction, while transfer pumps, vacuum systems are the
sources of noise during operation. The equipment in the
plant is designed for noise levels not exceeding 90 dB (A).
Proper encasement of noise generating sources is done to
control the noise levels below 75 dB (A) at plant boundary.
Maintenance of all equipment is carried out regularly to
reduce noise. A proper green belt is developed which acts as
a noise barrier. | 6.2 | From industrial or similar processes | Yes | Pumps, motors, gearboxes etc will generate a little bit of noise
and will be mitigated with regular maintenance. Apart from
all these a thick plantation of green belt is developed along
the periphery of the compound wall to arrest the noise
nuisance during the operation phase. | 6.3 | From construction or demolition | Yes | Temporary noise generation during construction activities | 6.4 | From blasting or piling | No | Not applicable | 6.5 | From construction or operational traffic | Yes | Noise due to the movement of trucks during construction and operation phase | 6.6 | From lighting or cooling systems | Yes | Noise generation from cooling tower fans and chilled water system is envisaged | 6.7 | From any other sources | No | Not applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Hazardous materials will be used and stored with due safety and care at the site. All the norms under the Manufacture, Storage and Import Of Hazardous Chemicals (MSIHC) Rules and amendments thereafter will be compiled. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | ETP will be installed and will be designed for zero effluent discharge | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | All possible air pollutants will be scrubbed/ filtered properly by various pollution control equipment before emitting into the atmosphere. The norms will be maintained through regular monitoring and analysis of vent gases | 7.4 | From any other sources | No | | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | No explosions will occur during construction. During production operations, all inbuilt safety precautions will be adopted and there will not be any damage to the environment or human health | 8.2 | From any other causes | No | | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | As the area is plain, there are no chances of landslides & there is no history of a cloud burst. No natural disasters are envisaged since the site is in an area where such occurrences do not arise. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The proposed project will prove beneficiary for the localities as it provides: Additional direct and indirect employment. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | | 9.3 | Set a precedent for later developments | No | | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Water Bodies:
Shameerpet Vagu – 1.0 Kms (SSW)
Waterbody near Jalalpur – 1.6 Kms (SSW)
Water Body Near Pyararam Village – 1.7 Kms (ENE)
Kotta Cheruvu Near Madhapuram – 4.8 Kms (E)
Water Body Near Chikatimamid – 5.4 Kms (ESE)
Jaggayya Cheruvu Near Madhapuram – 6.4 Kms (ENE)
Reserved Forests:
Somajpalli RF – 2.3 Kms (NW)
Gopalpur RF – 8.1 Kms (NNE)
Karkupatla RF – 7.9 Kms (NNE)
Chinnalakshmapuram RF – 8.2 Kms (ENE)
Vasalamarri RF – 8.7 Kms (ENE)
Kondapuram RF – 9.0 Kms (NE) | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | | 4 | Inland, coastal, marine or underground waters | No | | 5 | State, National boundaries | No | | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Keesara Gutta Ramalingeswara Devasthanam - 10.1Kms (SSW) | 7 | Defence installations | No | | 8 | Densely populated or built-up area | Yes | Bommalaramaram - 7.0 Km (SSE) | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Bommalaramaram - 7.0 Km (SSE) | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Water Bodies:
Shameerpet Vagu – 1.0 Kms (SSW)
Waterbody near Jalalpur – 1.6 Kms (SSW)
Water Body Near Pyararam Village – 1.7 Kms (ENE)
Kotta Cheruvu Near Madhapuram – 4.8 Kms (E)
Water Body Near Chikatimamid – 5.4 Kms (ESE)
Jaggayya Cheruvu Near Madhapuram – 6.4 Kms (ENE)
Reserved Forests:
Somajpalli RF – 2.3 Kms (NW)
Gopalpur RF – 8.1 Kms (NNE)
Karkupatla RF – 7.9 Kms (NNE)
Chinnalakshmapuram RF – 8.2 Kms (ENE)
Vasalamarri RF – 8.7 Kms (ENE)
Kondapuram RF – 9.0 Kms (NE) | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The area under study falls in Zone-II
(least active), according to the Indian
Standard Seismic Zoning Map. | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | ChandraSekhar | Designation | ManagingPartner | Name of Company (Applicant Name should not be given here) | YS DRUGS | Address | #2-2-186/17/C/1, Baghamberpet, Bharathnagar, Amberpet, Hyderabad |
| |
|