APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | KAMANDO & KULA MANGANESE MINES | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/OR/MIN/75367/2018 | Project Cost | 85.00 lacs | |
| 2. | |
S. No. in the schedule | 1(a) Mining of minerals
| Project Sector | Non-Coal Mining | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 20000 TPA ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 60.70 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | Yes | d) | Inter-State boundaries and international boundaries | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Village-Kamando & Kula Tehsil-Koira ,District-Sundergarh | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Kamando Khata No.- 2, 88, 138, 140, Plot No.- 213/P, 213/1270/P, 209/P, 1/P, 212/P ,210/P, 212/1249/P, 212/1250/P
Kula : Khata No.- 45, Plot – 1/p and RF | Town / Village | Koira | State of the project | Orissa | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Jharkhand | West Singhbhum | Chaibasa | | 10. | |
Nearest railway station along with distance in kms | Barbil Railway Station, 30 km | Nearest airport along with distance in kms | Ranchi Air Port, 160 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Koira Town , 8 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village: Kamando & Kula
Block: Koira
Sub-Division: Bonai | | 13. | Name of the Applicant | UMESH | | 14. | Registered Address | Shyam Medical Store, Sadar Bazar, Chaibasa, | | 15. | |
Address for correspondance: | Name of the Company | Shri Umesh Chandra Mishra | Name of the Applicant | UMESH | Designation (Owner/ Partner/ CEO) | LESSEE | Pin code | 833201 | E-mail | uc.mishra@rediffmail.com | Telephone No. | 06582-255100 | Fax No. | 06582- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | Yes | Status | Application for Forest Clearance yet to be submitted | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | 22. | Whether there is any Government Order/Policy relevant/relating to the site? | No | |
| 23. | Whether any Forest Land Involved? | Yes | Area of Forest land Involved (hectares) | 47.81 ha. ha. | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Lease area contains 12.89 ha of non forest land 47.81 of forest land. Lessee has surrendered 16.04 ha of forest area which is under consideration by State Govt. Details of land use pattern is attached in Annexure-1 | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Diversion of forest land has been applied & is under process at the level of DFO, Bonai Sundargarh District. | 1.3 | Creation of new land uses? | Yes | Semi mechanized mining method will be adopted. The land use change will be temporary in nature .The mined out area will be technically and biologically reclaimed. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | 40 nos. of bore holes will be drilled only after obtaining Clearance from the Forest Dept. | 1.5 | Construction works? | Yes | Development of approach road & mine road are proposed. Site services like mine office, first-aid centre, rest shed & site store shall be provided. | 1.6 | Demolition works? | No | There is no demolition work involved. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | No such sites required. | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Mining activities like excavation and dumping will be encountered during plan period. | 1.9 | Underground works including mining or tunnelling? | No | Not applicable | 1.10 | Reclamation works? | Yes | Mining pit and dump area will be reclaimed. Backfilling will be done and plantation will be done. | 1.11 | Dredging? | No | No dredging involved. | 1.12 | Offshore structures? | No | No offshore structure involved. | 1.13 | Production and manufacturing processes? | Yes | Semi mechanized mining method will be adopted. | 1.14 | Facilities for storage of goods or materials? | Yes | Mined out Manganese will be transported by tippers / trucks and stored in mineral yard after sizing, sorting . | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | The solid waste generated during the course of mining will be dumped in an earmarked area and will be used for reclamation. | 1.16 | Facilities for long term housing of operational workers? | No | There is no proposal for construction of any captive colony. | 1.17 | New road, rail or sea traffic during construction or operation? | No | During scheme period road will be constructed. Total 1.512 ha will be used for road construction | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | Approach Road to the lease area will be constructed | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not applicable. | 1.20 | New or diverted transmission lines or pipelines? | No | Not applicable. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not applicable. | 1.22 | Stream crossings? | Yes | One seasonal nalla is situated at the middle of lease area | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Water will be required 80 m3/day
Domestic = 50 m3/day
Industrial = 30 m3/day
Domestic water will be drawn from ground water and industrial water will be used from rain water harvesting pond & surface water | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | There is a seasonal nalla which flows at the middle of lease area. | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The mine would be worked under the charge of a qualified mines manager & other supervisory staffs residing at Koira. Company vehicles will be used for transport of personnel. Local Persons employed from the near by villages. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not envisaged. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | No decommissioning envisaged. | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Not envisaged. | 1.29 | Introduction of alien species? | No | Only native species of flora will be planted along the safety zone of the mining lease. | 1.30 | Loss of native species or genetic diversity? | No | Not envisaged. | 1.31 | Any other actions? | No | Nil | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Lease area is general of hilly nature. Non forest area is 12.89 ha. The area is not suitable for agriculture. | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Water requirement for domestic use, dust suppression and plantation will be about 80 m3/day (Domestic-30 m3/day , Industrial 50 m3/day) | 2.3 | Minerals (MT) | Yes | During scheme period (2018-19 to 2022-23) about 43200 MT will be excavated | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | No | Not envisaged. | 2.5 | Forests and timber (source – MT) | No | No use envisaged. | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Approximately 40 Kl will be required per annum as fuel energy. Electricity consumption will be 3 MW/month which will be sourced from electricity board. | 2.7 | Any other natural resources (use appropriate standard units) | No | Nil | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | Not applicable. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Project activities are not likely to cause changes in occurrence of disease or affect disease vectors. | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | No habitation in the lease area. However,
it will be benefited by direct & indirect employment leading to better lifestyles of surrounding people. | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | No effect envisaged. | 3.5 | Any other causes | No | However, regular medical check-up of
mine workers will be done as per statue. | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | Yes | During scheme period about 18,450m3 top soil and about 2,20,260 m3 over burden will be generated | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Only the domestic effluent/waste of
Workers which will be discharged to septic tank, soak pit as per BIS specifications. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | Not applicable. | 4.4 | Other industrial process wastes | No | Not applicable. | 4.5 | Surplus product | No | Nil | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Domestic water will be treated in septic tank soak pit combination. Garland drain will be provided around OB dump areas. | 4.7 | Construction or demolition wastes | No | Not envisaged. | 4.8 | Redundant machinery or equipment | No | No redundant machinery envisaged. | 4.9 | Contaminated soils or other materials | No | Not envisaged as the area is devoid of soil | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | No | No other solid waste will be generated. | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Diesel is being used to run HEMM and
transport vehicles, all of being mobile source.
They are likely to produce SO2 & NOx. | 5.2 | Emissions from production processes | Yes | The project proposal is for opencast
mechanized mining. Thus mainly PM10 & PM2.5 generation is envisaged. | 5.3 | Emissions from materials handling including storage or transport | Yes | Mining & Transportation will generate
PM10, PM2.5 and SO2 & NOx. | 5.4 | Emissions from construction activities including plant and equipment | No | Nil | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be generated from mining, drilling & blasting | 5.6 | Emissions from incineration of waste | No | Not envisaged. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | No such activity is involved. | 5.8 | Emissions from any other sources | No | No such activity is proposed or involved. | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated by mining activities and vehicular movements for transportation. | 6.2 | From industrial or similar processes | No | No other industrial process envisaged. | 6.3 | From construction or demolition | No | No such activity le noise or vibration envisaged. | 6.4 | From blasting or piling | Yes | Control blasting will be adopted | 6.5 | From construction or operational traffic | Yes | Noise will be generated during transportation. | 6.6 | From lighting or cooling systems | No | No cooling system required. | 6.7 | From any other sources | No | No other sources envisaged. | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | No such activity envisaged. . Used lubricants will be stored in drums and will be auctioned to authorized reprocessors. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | During rainy season, surface drainage by garland drains/storm water drains with check dams are planned to check surface run off and stored in settling tank for future use. So there will be no chance of discharge of mine water. | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | Deposition of dust on land due to mining & transportation will have negative effect on flora-fauna . Plantation along safety zone barrier of the lease hold will be done to arrest the fugitive dust. | 7.4 | From any other sources | No | Not envisaged. | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not envisaged. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | All safety rules as laid down by DGMS will be complied. No hazardous substances envisaged to be generated or used | 8.2 | From any other causes | No | No, there are no other sources which could affect human health or the environment. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | Yes | The project may be affected by natural disasters; Low earth quake envisaged in the area as it falls in low seismic zone. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | Development of approachroad (Yes)
Development of houses for site services near the mining area (Yes)
The finished product shall be utilised in lessee’s own construction company which is far from mine(No)
No, as above (No)
Indirect Employment/Engagement for transportation of material (Yes) | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | After reaching the maximum depth at ultimate stage, the work out voids shall be reclaimed by backfilling up to ground level and rehabilitated by plantation. | 9.3 | Set a precedent for later developments | No | Not envisaged. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Nil | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Torha R. F.-Adjacent W
Kathamal R. F.-3.25 Km E
Karo R. F.-2.5 Km NE
Sarkanda R. F.-7.5 Km S
Khajurdihi R. F.-5.75 Km SE
Mendhmaruni R. F.-6 Km E | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Karo nala -2.75 Km E
Samij nala Tehrai nala -0.75 Km E
Kurarhi Jhor-2.69 Km SE
Karo nadi-6.54 Km NE | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Above Forest & Water resources | 4 | Inland, coastal, marine or underground waters | No | Nil | 5 | State, National boundaries | Yes | Jharkhand State Boundary- 7.6 km | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | NH-215- 5.1 km E | 7 | Defence installations | No | Nil | 8 | Densely populated or built-up area | Yes | Koira- 4.5 Km
Tensa- 6 Km | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Koira- 4.5 Km
Tensa- 6 Km
Kamando -1 Km
Kula-1.5 Km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Forest & water resources as above . | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Nil | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | The project area is not falling under the seismic zone. | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The correction have been made as per the instruction received | 19 Nov 2018 | 2. | NA | EDS was sought on 4.07.2018 with regard to application of forest clearance and lease details. After examination it is noted that PP has not submitted the forest clearance application yet( Column 21 of Form-I). further the lease validity document issued by government of Odisha has not submitted. In view of the above pp is requested to submit the earlier EDS as sought by the Ministry on 4.07.2018, otherwise your proposal may be rejected/delisted. | 03 Aug 2018 | 3. | NA | The correction have been made as per the instruction received | 09 Jul 2018 | 4. | NA | The proposal contains the involvement of Forest Land as per the details of Form I. However, PP in Colum 21 of the form I mentioned that Forest Clearance is not required as per the instant guidelines of 2011, the proposal involving forest land can only will consider in such cases when the PP has applied the proposal of Forest clearance.
2. PP need to submit the LOI/Lease documents which is not uploaded in additional attachments | 04 Jul 2018 | | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | UMESH | Designation | LESSEE | Name of Company (Applicant Name should not be given here) | Shri Umesh Chandra Mishra | Address | Shyam Medical Store, Sadar Bazar, Chaibasa, |
|
|