APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Expansion of existing Steel Plant to Integrated Steel Plant for production of various Steel Rolled Products of 3,00,000 TPA by expansion of Sponge Iron Plant by new installation of 1 X 350 TPD DRI (from 1,60,000 TPA to 2,60,000 TPA), Steel Melt Shop (Zero to 3,00,000 TPA) by new installation of 8 X 12 T capacity Induction Furnace, 1 X15 T LRF, 3.00,000 TPA Rolling Mill, 2 X 9 MVA Sub Merged Arc Furnace for production of either or combination of High Carbon Ferro Chrome/Ferro Manganese/ Sill
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/OR/IND/89100/2018
Project Cost 18636 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled New installation of 1 X 350 TPD DRI (from 1,60,000 TPA to 2,60,000 TPA), Steel Melt Shop (Zero to 3,00,000 TPA) by new installation of 8 X 12 T capacity Induction Furnace, 1 X15 T LRF, 3.00,000 TPA Rolling Mill, 2 X 9 MVA Sub Merged Arc Furnace for production of either or combination of High Carbon Ferro Chrome/Ferro Manganese/ Sillico Manganese along with expansion of Captive Power Plant from 18 MW to 78 MW (WHRB from 12 MW to 20 MW & AFBC from 6 MW to 58 MW). ha.
4.
New/Expansion/ModernizationExpansion
Proposal NumberIA/OR/IND/89098/2007
MoEFCC file number(Previous EC)J-11011/60/2007-IA.II (I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 160000 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify Yes
b) Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectVillage : Bomaloi, Tehsil : Rengali, Dist: Sambalpur, Odisha
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Khata No: 276/17, 270/173, 270/175, 270/198 and 275
Town / VillageVillage : Bomaloi
State of the projectOrissa
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)OrissaSambalpurRengali
10.
Nearest railway station along with distance in kms Lapanga Railway Station, 1.4 km
Nearest airport along with distance in kms Vir Surendra Sai Air Port, 22 km
11. Nearest Town/City/District Headquarters along with distance in kms Jharsuguda , 15 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Village Panchayat: The Sarapanch, Bomaloi Gram Panchyat, At/PO- Bomaloi, Dist – Sambalpur – 768212 Zilla Parishada: The President, Zilla Parishada, Sambalpur District, At/PO- Sambalpur, Dist – Sambalpur – 768001
13. Name of the Applicant KAILASH
14. Registered Address VILL-BOMALOI, TEHSIL-RENGALI, DIST-SAMBALPUR, PIN-768212
15.
Address for correspondance:
Name of the Company ARYANISPATANDPOWERPVTLTD
Name of the Applicant KAILASH
Designation (Owner/ Partner/ CEO) PRESIDENT
Pin code 768212
E-mail ARYANISPAT@GMAIL.COM
Telephone No. 0663-2590390
Fax No. 0663-2590379
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The category of present land use is industrial and it will continue to be industrial use only.
1.2 Clearance of existing land, vegetation and buildings? No Not applicable as it is an expansion project within the same premises of the existing plant.
1.3 Creation of new land uses? Yes The breakup of land use of total project area of 82.78 Ha. is as follows; Plant & Building:24.28 Ha Solid Waste Disposal Site : 8.09 Ha. Open Area : 23.08 Ha. Area under Plantation : 27.33 Ha.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No For the said expansion no such pre-construction investigations required as the same are already carried out during the 1st phase installation.
1.5 Construction works? Yes Construction work will include, site grading, civil, mechanical & electrical works as required.
1.6 Demolition works? No As proposed area do not have any significant structures need demolition.
1.7 Temporary sites used for construction works or housing of construction workers? Yes Temporary will be made with all minimum required facilities like water, power, fuel and adequate sanitary system.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Exact estimation is not available at present. However, there will be excavation work, concrete works of all types, reinforcement job, structural steel works and roof & side sheeting job.
1.9 Underground works including mining or tunnelling? No Not applicable
1.10 Reclamation works? No Not applicable
1.11 Dredging? No Not applicable
1.12 Offshore structures? No Not applicable
1.13 Production and manufacturing processes? Yes DRI – Coal Based Rotary Kiln Process Captive Power – WHRB (DRI Waste Gas) & AFBC Steel Melt Shop –IF with LRF and Rerolling. Ferro Alloys (SAF): HCFeCr /FeMn / SiMn
1.14 Facilities for storage of goods or materials? Yes Temporary bonded storage area shall be provided for storage of plant equipment. For the main plant, fuel oil storage tanks, and water storage tanks have been provided.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Coal Char will be used in AFBC Boiler. Dust from APC Devices will be disposed off at Solid Waste Disposal Site. Coal dust will be sold to brick manufacturer. SMS slag will be used in road making as well as in filling the low level areas of the plant. Fly and bottom ash from AFBC Boiler will partly be disposed off to Brick Manufacturing Units and partly in the designated dumping yard . Ferro Chrome slag will be used in road making after TELP test. FeMn slag will be reused in SiMn production.
1.16 Facilities for long term housing of operational workers? Yes Presently, we have 16 (sixteen) numbers of flats and 8 (eight) numbers of bungalows in the vicinity. Besides we have got 100 bedded bachelor hostel inside the Company premises.
1.17 New road, rail or sea traffic during construction or operation? Yes New internal road shall be made. The existing road in the vicinity shall be used to some extent.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? Yes New Railway siding has been constructed for transport of raw material and finished product. However, new internal road shall be made. The existing road in the vicinity shall be used to some extent.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not required
1.20 New or diverted transmission lines or pipelines? Yes New Water pipelines as well as Power Transmission line has been constructed.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No No changes is envisaged.
1.22 Stream crossings? Yes One perennial Nala is passing through the project area.
1.23 Abstraction or transfers of water from ground or surface waters? Yes The total water requirement is approximately 560 M3 / Hr for existing as well as proposed expansion. Permission for drawl of 4.41 cusecs or say 450 M3 /hr water from Hirakud Reservoir has already been allocated by Water Resources Dept. Govt. Of Odisha vide letter no. 13667/WR dated 05/06/2014. Further, ground water drawl permission for abstract of 1820 m3/day has been obtained from Central Ground Water Authority, Ministry of Water Resources, Govt. of India vide letter no. 21-4(65)/CGWA/SER/20
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No There is provision of Storm run-off drain inside the factory premises with facilities of settling tanks and recharge wells.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transport of materials will be by as per required vehicles depending upon the size of the material. And transport of personnel is mostly their own or available public transport.
1.26 Long-term dismantling or decommissioning or restoration works? No Not applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not applicable
1.28 Influx of people to an area in either temporarily or permanently? Yes The manpower requirement for the project is 804 numbers which include both direct and indirect employees. During construction approximately 200 numbers of workers will be engaged. The construction workers will be sourced from local villages which are temporarily in nature.
1.29 Introduction of alien species? No Plantation has been done with local species only. As rate of survival growth of local species is much higher than any alien species.
1.30 Loss of native species or genetic diversity? No No vegetation of the project area and buffer area of the project site is going to be affected by the proposed project.
1.31 Any other actions? No Not applicable
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes Total area requirement is 82.78 Ha or 204.56 Acres. Total land is already acquired and possession is also taken through IIDCO. There is no undeveloped or agricultural land involved in the project.
2.2 Water (expected source & competing users) unit: KLD Yes Total water requirement is approximately 560 M3 / Hr for existing as well as proposed expansion. It will be sourced from Hirakud Reservoir which has already been allocated by Water Resources Dept. Govt. Of Odisha. Further, ground water drawl permission for abstract of 1820 m3/day has been obtained from Central Ground Water Authority, Ministry of Water Resources, Govt. of India. Competing Users: Villagers in the riverbank for agriculture & Other Industries (Other industries in the vicinity).
2.3 Minerals (MT) Yes Iron Ore : 231000 TPA, Coal :881000 TPA, Quartzite : 9850 TPA, Coal Char : 300000TPA, Waste Gas from WHRB : 75CUMPH, Cr / Mn ore 92125 TPA, Molasses 2400TPA, Lime 960TPA, Coke 25125TPA, Carbon Paste 837.5 TPA, Qurzite 6700TPA, Mill Scale 240TPA,Bauxite 1800 TPA, Magnesite 600TPA, Dolomite 1675 TPA, Magnesite 600 TPA and FeMn Slag 11600 TPA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction material like Course aggregate, fine aggregate, sand, soil, Cement, steel will be required for the proposed construction. The exact estimation is not available at this point of time.
2.5 Forests and timber (source – MT) No No Timbers will be used for any construction work.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Total power requirement including existing unit is 78.0 MW. Present in house generation is 18 MW. Balance power of 60 MW will be generated in house.
2.7 Any other natural resources (use appropriate standard units) Yes HSD : 450 KL per Annum only as start up fuel and for emergency operation of DG Set from local Authorized dealer.
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes HSD requirement is 450 KL per Annum.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No As the Storage, Transfer and Handling of the said material will be strictly as per MSIHC Rules and Guidelines.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes There is and will be significant improvement in the living standards of the people in the vicinity.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No As the Storage, Transfer and handling of the said material will be strictly as per MSIHC Rules and Guidelines.
3.5 Any other causes No Not applicable
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes Yes During Construction only
4.2 Municipal waste (domestic and or commercial wastes) Yes During Construction as well during operation domestic wastes are depending upon the people engaged.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes During Construction : 1. Oily Sludge 2. Used Oil 3. Residue of Container of Petroleum Oil Storage Tank 4. Spent Solvents 5. Container with residue of hazardous waste/chemicals discarded container. During Operation : 1. Used Oil 2. Oily Sludge 3. Process Dust 4. Decanter Tank Sludge 5. Spent Resin 6. Spent Solvents 7. Container with residue of hazardous waste/chemicals discarded container.
4.4 Other industrial process wastes Yes Dolo Char, Furnace Slag, IF Slag, Fly Ash, Bottom Ash, Coal Dust, Liquid Waste from Water Treatment Plant, Boiler Blow down, Coal yard runoff, Cooling Tower Blow down and Clarifier Sludge.
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes For sanitary waste of the plant the provision of septic tank and soak pit are provided. And sludge from water treatment plant is disposed off at designated disposal site and shall be continued for expansion project.
4.7 Construction or demolition wastes Yes Soil
4.8 Redundant machinery or equipment Yes Equipment will be replaced and sold as scrap when it will be of not in working or discarded condition.
4.9 Contaminated soils or other materials No Not Applicable
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No Not Applicable
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes PM, SO2, NOX, Hg, CO and other trace elements.
5.2 Emissions from production processes Yes PM, SO2, NOX, Hg, CO and other trace elements.
5.3 Emissions from materials handling including storage or transport Yes Fugitive Emission
5.4 Emissions from construction activities including plant and equipment Yes Fugitive Emission
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Fugitive Emission
5.6 Emissions from incineration of waste No No provision for Incinerator in the Project
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No No provision for Incinerator in the Project
5.8 Emissions from any other sources No Not Applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes By selecting low noise prone equipment which would have leq level below 85 dB(A) at 1 meter distance. By dampening the vibrations providing anti-vibration pads. By isolating the noise prone unit from the working personnel’s continuous exposure. By administrative control, the administrative control would have a major role to monitor the noise, take remedial measures and ensure that no plant personnel is over exposed to noise. By providing acoustic enclosure at the source of noise generation.
6.2 From industrial or similar processes Yes Same as above
6.3 From construction or demolition Yes Same as above
6.4 From blasting or piling No Not Applicable
6.5 From construction or operational traffic Yes Same as above
6.6 From lighting or cooling systems Yes Same as above
6.7 From any other sources No Not Applicable
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No Handling and storage of hazardous materials will be strictly followed as per Hazardous and Other Waste (Management, Handling & Transboundary Movement) Rules, 2016. So no significant risk in this regard is envisaged.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No Sewage and all other effluents are being treated and are meeting the norms specified by CPCB as well as OSPCB. So no risk envisage in this regard.
7.3 By deposition of pollutants emitted to air into the land or into water No All emissions to air, water and land are strictly followed as per the provisional limits. Thus there is no risk of contamination in this regard.
7.4 From any other sources No Not Applicable
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Situation of any long-term risk is ruled out as the project proposed all adequate remedial measures for control of pollution.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes But all preventive as well incidental measures are being followed. All provisions of Boiler & Factories Rules, Personnel & Safety Rules, Fire Safety Rules are being strictly observed from the very inception of project construction and operational phases.
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? Yes The ML area falls in Seismic Zone – III Which is under Moderate Damage Risk Zone. The Project area is not prone to subsidence, landslides, erosion and flooding or adverse climatic conditions.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes All those developmental activities will follow as per related environmental guideline to protect the environment.
9.2 Lead to after-use of the site, which could have an impact on the environment No Not Applicable
9.3 Set a precedent for later developments Yes We follow all statutory provisions
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Distance is maintained
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Not applicable
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes There is no such Ecologically Sensitive area as per Hon’ble Supreme Court Civil writ petition No.460 of 2004. The following physical features exist in the buffer of the Project Site. Hirakud Reservoir which is at 2.5 kms from the project site. Other water sources are River Matwali is at distance of 3 kms in South of the project site and River Bheden is at 7 kms in the North of the project site. Nearest Dense forest is Ghichamura Reserve Forest at 6 kms in the east of Project site.
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Not Applicable
4 Inland, coastal, marine or underground waters Yes Hirakud reservoir is at 2.5 kms, River Matwali is at distance 3 kms and River Behden is at 7 kms from project site.
5 State, National boundaries No No State Boundary is within 15 kilometers radius of the project site.
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes State Highway No. 10 at a distance of 0.2 kms from the boundary of the project site.
7 Defence installations No Not applicable
8 Densely populated or built-up area Yes Village Rengali at 7.5 Kms from project site with population 5000 to 8.5 thousand.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Such facilities at Rengali Which are at 5 to 6 kms distance from proposed project site
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes Hirakud reservoir is at 2.5 Kms. River Matwali is at distance 3 kms and River Behden is at 7 kms from project site.
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Not applicable
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No The project area falls in Seismic Zone – III which is the Moderate Damage Risk Zone as per Odisha Seismic Zone Map. The area is not prone to subsidence, landslides, erosion and flooding or adverse climatic conditions.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
Plantation Map
Google Map of Project Site
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantKAILASH
DesignationPRESIDENT
Name of Company (Applicant Name should not be given here)ARYANISPATANDPOWERPVTLTD
AddressVILL-BOMALOI, TEHSIL-RENGALI, DIST-SAMBALPUR, PIN-768212