APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Change in Configuration and Modification for 1.4 MTPA Integrated Steel project by M/s Shyam Metalics & Energy Ltd
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/OR/IND/75198/2018
Project Cost 389300 lacs
2.
S. No. in the schedule3(a) Metallurgical industries (ferrous & non ferrous)
Project Sector Industrial Projects - 1
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 1.4 MTPA ha.
4.
New/Expansion/ModernizationModernization
Proposal NumberIA/OR/IND/5330/2008
MoEFCC file number(Previous EC)J-11011/495/2006-IA.II(I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 1.4 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectlatitude:21 40’ 50.43’’ N and longitude:84 02’ 30.63’’ E
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.1,7,11,12,13,17,20,23,30,32,39,58,59,245/111,51,54,245/112,76,79,84
Town / VillagePandloi, PO-Rengali, Sambalpur, Odisha
State of the projectOrissa
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)OrissaSambalpurRengali
10.
Nearest railway station along with distance in kms Rengali, 2.52 km
Nearest airport along with distance in kms Biju pattnaik International Airport, 242 km
11. Nearest Town/City/District Headquarters along with distance in kms Sambalpur , 22 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) pandloi, PO-Rengali, Sambalpur, Odisha
13. Name of the Applicant Dev
14. Registered Address Shyam Metalics & Energy Limited Pandoloi, Rengali, Sambalpur
15.
Address for correspondance:
Name of the Company SHYAM METALICS AND ENERGY LIMITED
Name of the Applicant Dev
Designation (Owner/ Partner/ CEO) Director
Pin code 758212
E-mail shyammetalics05@gmail.com
Telephone No. 674-2397786
Fax No. 674-06742397786
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?Yes
Area of Forest land Involved (hectares)38.39 ha.
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes The local landuse is converted to Industrial usage and additional land shall be converted to Industrial Land.
1.2 Clearance of existing land, vegetation and buildings? No Not Envisaged
1.3 Creation of new land uses? Yes The local landuse is converted to Industrial usage and additional land shall be converted to Industrial Land.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Geo logical investigations and soil testing has been carried out for the existing premises.
1.5 Construction works? Yes Minor construction activities will be carried out as per the requirement of the project.
1.6 Demolition works? No Not Envisaged
1.7 Temporary sites used for construction works or housing of construction workers? No Local people will be employed as daily wages workers.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Shades above ground will be made to accommodate the proposed modification units. The amount of excavations found will be used for filling the low lying area.
1.9 Underground works including mining or tunnelling? No Not Applicable
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing processes? Yes Process involves production of billets. Finished products will be disposed off.The solid waste generated will be recycled. be no impact on land use.
1.14 Facilities for storage of goods or materials? No Existing plant facilities will be used for the storage of goods and products of expansion plant.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes The solid wastes will be recycled and reused and the effluents after treatment in ETP or STP will be reused.
1.16 Facilities for long term housing of operational workers? No Local people will be employed as daily wages workers.So, temporary sheds will not be constructed.
1.17 New road, rail or sea traffic during construction or operation? No Existing infrastructures will be used for the proposed project.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Existing infrastructures will be used for the proposed project.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not Required
1.20 New or diverted transmission lines or pipelines? No Not required
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not Envisaged
1.22 Stream crossings? No Not present
1.23 Abstraction or transfers of water from ground or surface waters? Yes 55702 KLD of Surface water will be drawn from Hirakud reservoir
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Not envisaged
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Existing road network will be used for transportation
1.26 Long-term dismantling or decommissioning or restoration works? No Not envisaged
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not envisaged
1.28 Influx of people to an area in either temporarily or permanently? Yes Temporary relocation of employee base for the plant operation.
1.29 Introduction of alien species? No Local species will be planted
1.30 Loss of native species or genetic diversity? No Not Envisaged
1.31 Any other actions? No Not Applicable
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Total land has been converted to be used for industrial purpose.
2.2 Water (expected source & competing users) unit: KLD Yes 55702 KLD of fresh water will be drawn from Hirakud Reservoir
2.3 Minerals (MT) Yes Cooking Coal-774,648 TPA; Chrome ore-612,500 TPA; I/O fines-1,838,660 TPA; I/O lumps-168,923TPA; Coke fines-57,500TPA; Coal-1625877 TPA; Lime-13,800 TPA; Dolomite-180,685 TPA; Quartzite-141,460 TPA, Magnesite-25000 TPA, Bentonite-8970 TPA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Brick and Mortar will RCC & Steel fabrications will be procured locally.
2.5 Forests and timber (source – MT) No Not Envisaged
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Total power requirement is 216 MW out of which 175 MW is from own captive generation and the balance 40 MW will be procured from state power grid.
2.7 Any other natural resources (use appropriate standard units) No Not Applicable
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes All hazardous waste will be handles as per the The Hazardous Waste" (Management, Handling and TransBoundary Movement) rules, 2016
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Not envisaged
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The engagement of local people in operation and production shall enhance the socio-economic status and strnthen the social infrastructure.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not envisaged
3.5 Any other causes No Not applicable
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes All domestic waste is treated in a centralized STP facility
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes No hazardous waste is used in production as raw material, however few hazardous waste are generated as lubricants, contaminated cottons, spent oil, ETP sludge, spent resins etc which shall be handled and disposed off as per the Hazardous Waste Management rules, 2016
4.4 Other industrial process wastes Yes Middlings & Rejects will be used in FBC Boiler, Coal fines from washery will be used in sinter and pellet plants, Bottom diust will be used in land fill,Fly ash will be used for brick manufacturing, dolchar will be consumed in AFBC boiler, BF slag will be used in cement plant, all generated scraps will be used in IF, tar and tar oil from PGP will be used in the pellet kiln, all the rejects and residues of pellet plant will be utilized in sinter plant
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes The sewage sludge will be blended with organic compost and used as manure and the ETP sludge will be treated as per the Hazardous Waste Management rules,2016
4.7 Construction or demolition wastes Yes The construction wastes will be used for filling the low lying areas and as appropriate shall be sold.
4.8 Redundant machinery or equipment No Not envisaged
4.9 Contaminated soils or other materials No Not envisaged
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No Not envisaged
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Particulate matter, So2, NOx and Co will be released from the process. So, Bag filters, Venturi Scrubbers and ESPs will be minimize pollution.
5.2 Emissions from production processes No The production emissions are either utilized for power generation or for heat recovery and usage in SMS sections.
5.3 Emissions from materials handling including storage or transport Yes Emissions from Raw Material Handling will be suppressed by use of bag filters and sprinkling of water.
5.4 Emissions from construction activities including plant and equipment No Not Envisaged
5.5 Dust or odours from handling of materials including construction materials, sewage and waste No Not Envisaged
5.6 Emissions from incineration of waste No Not Envisaged
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not Envisaged
5.8 Emissions from any other sources No Not Envisaged
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Due noise attenuation measures are taken in material handling area, furnaces, sinter plant, pelletization unit and vehicles are regulated as per the British India Standards for controlled noise generation.
6.2 From industrial or similar processes Yes Industrial noise is overally controlled through closed systems as well as thick plantations around the boundary wall for noise attenuation measure.
6.3 From construction or demolition Yes Temporary noise is generation and engaged machineries are mandated with noise control systems
6.4 From blasting or piling No Not envisaged
6.5 From construction or operational traffic Yes Traffic noise shall be from human as well as raw material transporting vehicles and initially being controlled through speed limit and appropriate lubrications of engine
6.6 From lighting or cooling systems No Not envisaged
6.7 From any other sources No Not applicable
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Hazardous wastes will be handled as per "The Hazardous Waste" (Management, Handling and TransBoundary Movement) rules, 2016
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes The liquid wastes will be treated in ETP and will be reused in the process. Discharge of effluent is not envisaged.
7.3 By deposition of pollutants emitted to air into the land or into water Yes Pollutant emission control devices will be installed to have the GLC under NAAQS norm. Hence the effects will have negligible impact.
7.4 From any other sources No Not Envisaged
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No Not Envisaged
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No No storage of explosive materials or lubricants within the facility and are procured as on need basis.
8.2 From any other causes No Company has a safety guideline and SOPs to deal with probable risk and appropriate mitigation measures
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No Not Envisaged
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Employment opportunity and business opportunity is improving the socioeconomic aspects of the people. There is overall development the region with respect to transportation, communication, education, health etc and other socioeconomic aspects, extraction and supply industries which will improve the socioeconomic of the region.
9.2 Lead to after-use of the site, which could have an impact on the environment No As the life of the plant is for next 30 yrs, the long term impacts on environment and socio-economy is not envisioned at this point in time.
9.3 Set a precedent for later developments Yes Appropriate control measures and being a compliant industry.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No Not Envisaged
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Nil
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Hirakud Dam-2.57 km
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Nil
4 Inland, coastal, marine or underground waters No Nil
5 State, National boundaries No Nil
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No Nil
7 Defence installations No Nil
8 Densely populated or built-up area Yes Sambalpur-22 km
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Surajmal College- 3.66 km
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Nil
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Nil
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Nil
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) NIL
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantDev
DesignationDirector
Name of Company (Applicant Name should not be given here)SHYAM METALICS AND ENERGY LIMITED
AddressShyam Metalics & Energy Limited Pandoloi, Rengali, Sambalpur
Print