APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Bigodi Limestone Mine with a production capacity of 0.85 MTPA spread over an area of 184.149 ha at Dithora, Sannehi Singti and Karaundi villages, Amarpatan Tehsil, Satna District, Madhya Pradesh | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/MP/MIN/100548/2019 | Project Cost | 11000 lacs | |
| 2. | |
S. No. in the schedule | 1(a) Mining of minerals
| Project Sector | Non-Coal Mining | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 0.85 MTPA ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 184.149 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | Dithora, Sannehi Singti and Karaundi villages, Amarpatan Tehsil, Satna District, Madhya Pradesh | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | Annexure-1 | Town / Village | Dithora, Sannehi Singti and Karaundi villages | State of the project | Madhya Pradesh | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Madhya Pradesh | Satna | Amarpatan | (2.) | Madhya Pradesh | Satna | Amarpatan | | 10. | |
Nearest railway station along with distance in kms | Rewa, 14.6 km | Nearest airport along with distance in kms | Khajuraho, 135 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Rewa , 16 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Satna Municipal Corporation
MP Nagar, Satna, MP-485001 | | 13. | Name of the Applicant | Hemantha | | | 15. | |
Address for correspondance: | Name of the Company | RCCPL PRIVATE LTD | Name of the Applicant | Hemantha | Designation (Owner/ Partner/ CEO) | AVP | Pin code | 400020 | E-mail | hemantha.kumar@birlacorp.com | Telephone No. | 22-43435405 | Fax No. | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | Yes | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | There will be permanent change in land use and topography due to proposed mining activity. | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | Existing vegetation from the proposed mining area will be cleared for mining activities | 1.3 | Creation of new land uses? | Yes | The present land will be converted to mining area. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Detailed prospecting has been carried out. | 1.5 | Construction works? | Yes | Construction works involves establishment of the mine office, rest shelter, workshop, crusher (300 TPH) and other site services | 1.6 | Demolition works? | No | Not envisaged | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Not envisaged | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Construction work as given in 1.5 above will involve minor earthwork. | 1.9 | Underground works including mining or tunnelling? | No | Open cast mechanized mining is proposed. | 1.10 | Reclamation works? | Yes | Mined out area will be reclaimed and rehabilitated as per approved mining plan | 1.11 | Dredging? | No | Not applicable | 1.12 | Offshore structures? | No | Not applicable | 1.13 | Production and manufacturing processes? | Yes | Excavation of limestone by mechanized mining method involving dozing, drilling, blasting, loading, transportation and crushing | 1.14 | Facilities for storage of goods or materials? | Yes | Top soil and overburden will be stored separately at earmarked sites and reused for backfilling of mined out pits. Storage facilities are planned for goods or materials as per approved mining plan. | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Solid Waste: Solid Waste like reject produced during mining activity will be utilized for back filling in the worked-out pit. Top soil generated will be used for plantation activity. Subgrade mineral will be stored separately.
Liquid Effluent: Construction of oil-grease trap to treat wastewater generated from mine work shop due to maintenance of machinery. Domestic wastewater will be sent to septic tank followed by soak pits. Used oil will be stored and sold to authorized dealer. | 1.16 | Facilities for long term housing of operational workers? | No | Not envisaged | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | There will be increase in road traffic during operational phase. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Not applicable | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | Not envisaged | 1.20 | New or diverted transmission lines or pipelines? | Yes | Diversion of transmission line will be done, whenever required, after obtaining prior permission from authorities concerned. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not envisaged | 1.22 | Stream crossings? | No | There is no stream inside ML area, however, Bihar river is flowing adjacent to SE boundary of ML area. | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | 183 KLD for dust suppression, washing of mining machinery, plantation and domestic purpose, initially from ground water. | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | During mining operation, the surface will be altered thereby affecting the existing run off during active monsoons.
Bihar nadi (river), which is flowing adjacent to SE boundary of ML area, will not be disturbed | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | Transportation of man-power and material is envisaged. | 1.26 | Long-term dismantling or decommissioning or restoration works? | Yes | It will be carried out as per approved mine closure plan. | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Not envisaged | 1.29 | Introduction of alien species? | No | Not envisaged | 1.30 | Loss of native species or genetic diversity? | No | Not envisaged | 1.31 | Any other actions? | No | Not envisaged | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The proposed land area comprises of:
Forest land –Nil
Govt. land- 14.409 ha
• Private – 169.74 ha | 2.2 | Water (expected source & competing users) unit: KLD | Yes | 183 KLD for dust suppression, washing of mining machinery, plantation and domestic purpose from own source, initially from ground water and later from pit and harvested water | 2.3 | Minerals (MT) | No | Not applicable | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Materials for construction of mine office, rest shelter, workshop etc. will be utilized. Estimated quantity of stone / aggregates is 2,000 m3, to be sourced locally. | 2.5 | Forests and timber (source – MT) | No | Not envisaged | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Electricity: 1.0 MW from grid
Diesel: 3.4 KLD
One DG set (250 KVA) will also be installed to meet the demand required during the emergency period for lighting and pumping purposes. | 2.7 | Any other natural resources (use appropriate standard units) | No | Not envisaged | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | HSD (~3.4 KLD) and explosives (~1.7 TPD) | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not envisaged | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The project will provide direct as well as indirect employment to the local people. It can help in improving socio- economic status and the living standards of people.
CER activity will help in infrastructure development, and improve educational & medical facilities | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not applicable | 3.5 | Any other causes | Yes | Mining of limestone and its transport may create dust and noise pollution, if not handled properly. | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | Yes | Soil / Reject: 1,81,666 Tonnes / Month | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | ~0.42 tonnes / month municipal (domestic or commercial) waste per month generated will be segregated and disposed | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | ~ 0.18 tonnes/month used oil will be generated. | 4.4 | Other industrial process wastes | No | Not applicable | 4.5 | Surplus product | No | Not applicable | 4.6 | Sewage sludge or other sludge from effluent treatment | No | Not applicable | 4.7 | Construction or demolition wastes | No | Not applicable | 4.8 | Redundant machinery or equipment | No | Not applicable | 4.9 | Contaminated soils or other materials | No | Not applicable | 4.10 | Agricultural wastes | No | Not applicable | 4.11 | Other solid wastes | No | Not applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emission from DG and HEMMs is envisaged | 5.2 | Emissions from production processes | Yes | Emission from mining operation is envisaged | 5.3 | Emissions from materials handling including storage or transport | Yes | Emission from transportation, dumping and mineral stacking is envisaged and will be quantified during detailed EIA study. | 5.4 | Emissions from construction activities including plant and equipment | Yes | There will be fugitive emissions during construction of rest shelter, mines office, crusher etc. | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust emission is envisaged. There will be no odour generation. | 5.6 | Emissions from incineration of waste | No | Not applicable | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | Not applicable | 5.8 | Emissions from any other sources | No | Not applicable | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise is anticipated from Heavy Earth Moving Machinery, movement of vehicles and crusher. | 6.2 | From industrial or similar processes | No | Not envisaged | 6.3 | From construction or demolition | Yes | Short-term noise will be generated during construction of mine office etc. | 6.4 | From blasting or piling | Yes | Noise and vibration will occur during blasting operations. It will be assessed during detailed EIA study. | 6.5 | From construction or operational traffic | Yes | Noise will be generated from additional traffic. It will be assessed during detailed EIA study. | 6.6 | From lighting or cooling systems | No | Not envisaged | 6.7 | From any other sources | No | Not envisaged | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | Not applicable | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Not applicable | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | There will be incremental increase in ground level concentrations of air pollutants (dust) | 7.4 | From any other sources | No | Not applicable | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not applicable | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | Explosive materials will be used for blasting in the mine. All precautions as prescribed in Metalliferous Mines Regulation (MMR) and Explosive rules will be adopted. | 8.2 | From any other causes | Yes | There is a risk of accident during operation, transportation etc. however, proper safety measures will be taken as per applicable rules and regulation. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The mine lease area is in Seismic zone–II (IS 1893 Part-1) wherein the seismic activity falls in safe norms. The area is not in flood prone region | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The mining project will have beneficial impact on socioeconomic development of local communities. | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | Reclamation and rehabilitation of mined out area for gainful use | 9.3 | Set a precedent for later developments | Yes | Creation of water body and plantation | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not envisaged | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | Not applicable | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Wetland – None
Water course
Bihar nadi (Adjacent SE)
Bichia nadi (14 km, NE)
Many seasonal nallahs exist within study area.
Water body:
Govindgarh lake (7.7 km, SE)
Coastal zone – None
Biosphere – None
Mountain- None
No National Park, wild life sanctuary | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | Yes | Mand RF (1.8 km, E), Papra RF (4.8 km, S),
Govindgarh RF (4.9 km, SSE), Gidhaila RF (14.3 km, S) | 4 | Inland, coastal, marine or underground waters | Yes | Water course
Bihar nadi (Adjacent SE)
Bichia nadi (14 km, NE)
Many seasonal nallahs exist within study area. | 5 | State, National boundaries | No | Nil | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | NH-7 (Katni – Rewa) (7.6 km, NW)
NH-75 (Satna – Rewa) (8.8 km, N) | 7 | Defence installations | No | Not applicable | 8 | Densely populated or built-up area | Yes | Rewa (16 km, NE) | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Hospitals, schools, places of worship, community facilities etc. are available at Rewa (16 km, NE) | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | Not applicable | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not applicable | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | The project area falls under seismic zone-II as per IS: 1893 (Part-1) | | (IV) | Proposed Terms of Reference for EIA studies | Essential Detail Sought : NIL | | Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | ADS reply - Copy of Affidavit for the project - Bigodi Limestone Mine | 16 Oct 2019 | 2. | ADS Raise Letter | Please upload the additional information as sought by the EAC/Ministry | 15 Oct 2019 | 3. | ADS Reply Letter | Reply to Additional Details sought by EAC. | 01 Aug 2019 | 4. | NA | deferred the proposal
| 10 May 2019 | 5. | NA | deferred the proposal
| 10 May 2019 | 6. | NA | deferred the proposal
| 10 May 2019 | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Hemantha | Designation | AVP | Name of Company (Applicant Name should not be given here) | RCCPL PRIVATE LTD | Address | |
|
|