APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Modification in 125 KLPD Distillery (Grain to Dual mode of operation - Grain & Molasses based) at Village Borali, Tehsil Badnawar, District Dhar, Madhya Pradesh by Oasis Distilleries Limited
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MP/IND2/83256/2018
Project Cost 2200 lacs
2.
S. No. in the schedule5(g) Distilleries
Project Sector Industrial Projects - 2
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 125 KLPD Grain and Molasses based Distillery & 3.0 MW Co-generation Power Plant Total area for distillery: 35 ha (86.48 acres) ha.
4.
New/Expansion/ModernizationModernization
Proposal NumberIA/MP/IND2/72495/2016
MoEFCC file number(Previous EC)J-11011/257/2015-IA II (I)
Uploaded EC letterAnnexure-Uploaded EC letter
5. Existing Capacity/Area etc. 35 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectVillage Borali, Tehsil Badnawar, District Dhar, Madhya Pradesh
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.355, 356, 357, 368/1, 368/2, 370/1, 371, 382, 383, 386, 394/1, 394
Town / VillageBorali
State of the projectMadhya Pradesh
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Madhya PradeshDharBadnawar
10.
Nearest railway station along with distance in kms Ratlam, 49 km
Nearest airport along with distance in kms Devi Ahilya Bai Holkar Airport, Indore, 62 km
11. Nearest Town/City/District Headquarters along with distance in kms Badnawar Town , 9 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Sarpanch:- Shri Jagdish Lal (Mob. 7974116449) Village: - Bukadawda Khedi, Post-Ghatgara, Distt. Dhar (M.P.) - 454660
13. Name of the Applicant Satish
14. Registered Address H 102, B2 Metro Towers, First Floor, Vijay Nagar, Indore (MP)
15.
Address for correspondance:
Name of the Company OASIS DISTILLERIES LIMITED
Name of the Applicant Satish
Designation (Owner/ Partner/ CEO) Director
Pin code 452010
E-mail oasisindore2014@gmail.com
Telephone No. 0731-4007838
Fax No. 0731-4007844
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The total plant area is 35 ha (86.48 acres). Existing land use of the area is industrial. Modification will be done within the existing plant premises. Hence, no change in land use, land cover or topography. The company has already developed greenbelt & plantation in 33% of the total plant area and the same will be further maintained.
1.2 Clearance of existing land, vegetation and buildings? No The proposed modification will be done within the existing plant premises. Therefore, no clearance of existing land, vegetation and buildings is required.
1.3 Creation of new land uses? No Existing land use of the area is industrial. Since proposed modification will be done within the existing plant premises, there will be no creation of new land uses outside plant area. Only intensity of the existing land use will increase.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Pre-construction investigations have already been carried out. Thus, they are not required for modification project.
1.5 Construction works? Yes The proposed modification will be done within the existing plant. Construction work will be carried out for molasses-based operation (Molasses Handling System, Storage tank, Incineration boiler with MEE and Ethanol Storage tanks).
1.6 Demolition works? No Demolition of the redundant plant will not cause physical change in the locality.
1.7 Temporary sites used for construction works or housing of construction workers? No During construction work, local people will be hired from the nearby areas; therefore, no additional housing facilities will be developed.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes There will be above ground buildings, structures or earthworks including linear structures, cut and fill or excavations.
1.9 Underground works including mining or tunnelling? No No underground works including mining or tunneling is required.
1.10 Reclamation works? No No reclamation work is required.
1.11 Dredging? No No dredging is involved.
1.12 Offshore structures? No No offshore structures will be developed.
1.13 Production and manufacturing processes? Yes Grain Based Distillery Process: • Grain milling • Slurry preparation & liquefaction • Fermentation • Multi Pressure Distillation • Decanters, MEE & Dryer • Alcohol Receiver & storage Molasses Based Distillery process: • Molasses Storage • Yeast Propagation • Fermentation • Multi Pressure Distillation & MEE • Incineration Boiler • Alcohol Receiver & storage Detailed production and manufacturing process is incorporated in Pre-Feasibility Report.
1.14 Facilities for storage of goods or materials? Yes For existing grain based operation storage facilities are already available. For proposed molasses based operation, molasses and ethanol storage tanks will be constructed.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes 1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid Waste 1. Fly ash will be given to brick manufacturers & used in land application/ as per CPCB guidelines. 2. DWGS is being /will be sold as Cattle feed. Liquid effluent 1. Grain based operation - Spent Wash is being taken through Centrifuge Decanters for separation of Suspended Solids separated as Wet Cake & will then be treated in MEE. 2. Molasses based operation - The spent wash will be sent to MEE for
1.16 Facilities for long term housing of operational workers? No No long-term housing facilities will be provided to the operational workers as they will come from nearby areas.
1.17 New road, rail or sea traffic during construction or operation? No The plant is well connected with State Highway and the proposal is for modification within existing plant therefore, there will be no additional traffic on existing road due to plant operations.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No No new infrastructure is required. Existing facilities will be used.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No No closure or diversion of existing transport routes or infrastructure will be done.
1.20 New or diverted transmission lines or pipelines? No No new or diverted transmission lines or pipelines will be laid.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No There has no impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers.
1.22 Stream crossings? No There is no stream crossing through the plant area.
1.23 Abstraction or transfers of water from ground or surface waters? Yes The existing water requirement (As per EC granted for 125 KLPD Grain Based Distillery) is 1115 KLD; source of which is Ground water. There will be no additional water requirement for proposed modification project.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No No change in drainage pattern of the area is envisaged.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transport of personnel or materials for construction, operation or decommissioning will be done via existing facilities.
1.26 Long-term dismantling or decommissioning or restoration works? No Not envisaged
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No Not Applicable
1.28 Influx of people to an area in either temporarily or permanently? Yes Local people from the nearby villages have been given employment during construction and operation phase.
1.29 Introduction of alien species? No Introduction of alien species is not envisaged.
1.30 Loss of native species or genetic diversity? No Not Applicable
1.31 Any other actions? No Not Applicable
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Not applicable as the area is already developed for industrial use. The modification will be done within the existing plant premises. The existing plant area is 35 ha (86.48 acres).
2.2 Water (expected source & competing users) unit: KLD Yes The existing water requirement (As per EC granted for 125 KLPD Grain Based Distillery) is 1115 KLD; source of which is Ground water. There will be no additional water requirement for proposed modification project.
2.3 Minerals (MT) Yes Coal will be used as a fuel in the Co-generation Power Plant.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction material such as stone, aggregates, and/ soil etc. to be used for the modification project will be sourced locally.
2.5 Forests and timber (source – MT) No No forests and timber will be used during construction / operation of the project activity.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes The existing power requirement for the existing plant is 2.8 MW. The total power requirement after modification will remain the same. Source - 3.0 MW cogeneration power plant, State Electricity Board & D.G. Sets (for back up) Fuel: Biomass/Rice Husk & Coal (Existing) and after modification Con. Spent wash along with biomass/ Coal in the Incineration boiler.
2.7 Any other natural resources (use appropriate standard units) No Not Applicable
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes The hazardous chemicals used in the plant have been provided with proper storage facilities as per MSIHC rules to avoid any harm to environment or human health. The use, storage, transport & handling is being/ will be done carefully by qualified and trained personal.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No No effect is envisaged
3.3 Affect the welfare of people e.g. by changing living conditions? Yes The company is already involved in the social welfare activities for the upliftment of the nearby areas.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No effect envisaged.
3.5 Any other causes No Not Applicable
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No Not Applicable
4.2 Municipal waste (domestic and or commercial wastes) Yes Municipal solid waste generated from plant is being / will be collected, segregated and disposed off scientifically. Domestic waste water generated from the plant is being treated in STP and treated water reused in plantation.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Used oil generated is being/ will be given to authorized recyclers.
4.4 Other industrial process wastes No No other industrial process waste will be generated.
4.5 Surplus product No There will be no surplus product.
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge is being/will be used as manure.
4.7 Construction or demolition wastes Yes Construction waste like soil, brick bats, etc. will be utilized in leveling of land and construction of roads. No demolition wastes will be generated. Mostly fabrication work will be done.
4.8 Redundant machinery or equipment No There will no redundant machinery or equipment.
4.9 Contaminated soils or other materials No There will be no contamination of soil or any other material.
4.10 Agricultural wastes No There will not be any agricultural waste.
4.11 Other solid wastes Yes DWGS is being/will be sold as Cattle feed. Ash from the boiler is being/will be sold to brick manufacturers or used in land application.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes The major pollutants of the plant are particulate matter from the boiler. ESP is being/will be installed to maintain the emission levels within prescribed standards.
5.2 Emissions from production processes Yes CO2 generated during fermentation process is/ will be collected, purified, liquefied and sold to vendors.
5.3 Emissions from materials handling including storage or transport Yes Fugitive dust emissions occur due to transportation activity, vehicular movements and material handling activities. Proper mitigation measures are being/ will also be adopted for the modification project.
5.4 Emissions from construction activities including plant and equipment Yes Fugitive dust emissions occur due to construction activities and vehicular movement. The fugitive dust emissions during construction will be temporary and will be minimized by regular water sprinkling on the roads and other dust generating areas.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes During loading & unloading of raw material dust is likely to be generated during construction phase. Water will be sprinkled and covered will be provided for construction materials to reduce dust emission. Odour problems will be properly controlled at source by good operational practices, including physical and management control measures.
5.6 Emissions from incineration of waste Yes During Molasses based operation - Spent wash will be concentrated in MEE and the concentrated spent wash will be mixed with Biomass or Coal and burnt in the incinerator boiler. The emissions will be almost negligible. High efficiency ESP will be installed to maintain the emission levels within prescribed standards.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No Not applicable as there will be no burning of waste in open air.
5.8 Emissions from any other sources No There will be no emissions from any other sources.
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise is/will be generated from operation of plant machineries and equipment. However, as adopted in the existing plant, all heavy machineries is being/will be provided with acoustic enclosures and padding to reduce noise generation.
6.2 From industrial or similar processes Yes Noise is/ will be generated due to operation of the additional plant machineries. High noise generating machines are/will be provided with acoustic enclosures to control the noise generation. To attenuate the impact of high noise level, workers have been/will be provided with personal protective equipment.
6.3 From construction or demolition No No demolition work will be involved for the project and the noise generated (if any) during the construction work will be maintained within the prescribed noise standards.
6.4 From blasting or piling No Not Applicable
6.5 From construction or operational traffic Yes Noise during construction activities will be temporary & will be maintained within the prescribed noise standards.
6.6 From lighting or cooling systems No No noise will be generated from lighting or cooling systems
6.7 From any other sources No There are no other sources of noise generation.
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No The hazardous materials are being/will be stored in a proper storage facility designed with protective measures to avoid any risk of contamination to the land or to the human through leakage or spillages.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No The distillery is/ will be based on the concept of “Zero Effluent Discharge” hence no sewage or other effluent is being/ will be discharged outside the plant premises.
7.3 By deposition of pollutants emitted to air into the land or into water Yes There is likely hood of increase of air emissions. But proper mitigating measures such as regular dust suppression by sprinkling water will help in reducing the effect. However, periodical monitoring will be done and results will be analyzed. In case any change shows adverse effects, it will be attended for improvements.
7.4 From any other sources No Not Applicable.
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No There will be no long-term build-up of pollutants in the environment.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes The hazardous materials are being/will be stored in a proper storage facility designed with protective measures to avoid risks due to spillages and leakages. Proper handling and storage practices will eliminate risk of accidents. However; in an emergency, fire-fighting equipment have been/will be provided near all risk prone areas. Workers have been/will be properly trained to use fire-fighting system to quench the fire at source itself.
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No No such case has been reported in the area and chances are minimal. However, we are having Emergency and Contingency plans in place.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Modification project will result in considerable growth of the surrounding areas • By generating direct and indirect employment opportunities in the region including ancillary development. • Promoting Education • Health and Family Welfare • Social Welfare Services • Infrastructure development • Sustainable livelihood (women empowerment) • Overall growth of the surrounding area in terms of socio economic status and standard of living.
9.2 Lead to after-use of the site, which could have an impact on the environment No Not applicable.
9.3 Set a precedent for later developments Yes This project has/will have positive effect on the living standards of local people in terms of employment, infrastructure and overall development of the area.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No No environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality as in the vicinity of plant site.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Not applicable
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Forest - Bharatgarh Reserve Forest (~9.0 km in West) Rivers • Balwant River(~3.5 km in North) • Chamla River (~5.5 km in ESE) • Bageri River (~5.5 km in West) • Harkajhar Dam (~6.0 km in NW) • Gangi River (~7.7 km in SSE)
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Not applicable
4 Inland, coastal, marine or underground waters No Not applicable
5 State, National boundaries No Not applicable
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes • NH -79 (adjacent to plant site in West) • SH -18 (~8.7 km in North)
7 Defence installations No Not applicable
8 Densely populated or built-up area Yes Badnawar Town (~9 km in NNW)
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes There are many schools, College, dispensaries, hospitals, Post offices, Banks, Market and places of worship within 15 km radius area.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No Not applicable
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Not applicable
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No Not applicable
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantSatish
DesignationDirector
Name of Company (Applicant Name should not be given here)OASIS DISTILLERIES LIMITED
AddressH 102, B2 Metro Towers, First Floor, Vijay Nagar, Indore (MP)