APPENDIX I | (See Paragraph-6) | FORM 1 | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | NA |
| | Whether proposal involved violation of EIA notification | N/A | | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| 1. | |
Name of the Project/s | Indian Oil Corporation Limited LPG Bottling Plant Barapani, Meghalaya | Brief summary of project | Annexure-Brief summary of project | Proposal Number | IA/ML/IND2/82553/2018 | Project Cost | 7398 lacs | |
| 2. | |
S. No. in the schedule | 6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
| Project Sector | Industrial Projects - 2 | |
| 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | 450 MT LPG MSV ha. | | 4. | New/Expansion/Modernization | New | | | 5. | Existing Capacity/Area etc. | 6.879 ha. | | 6. | Category of project i.e. 'A' or 'B' | A | | 7. | Does it attract the general condition? If yes, please specify | No | | | 8. | Does it attract the specific condition? If yes, please specify | No | | | 9. | |
Location of the project | IOCL LPG Bottling Plant, Umium, Ri-Bhoi, Meghalaya | Shape of the project land | Block (Polygon) | Uploaded GPS file | Annexure-GPS file | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | Plot/Survey/Khasra No. | . | Town / Village | umium | State of the project | Meghalaya | |
| Details of State of the project |
---|
S.no | State Name | District Name | Tehsil Name |
---|
(1.) | Meghalaya | Ri Bhoi | Umsning | | 10. | |
Nearest railway station along with distance in kms | Tetelia railway station, 47 km | Nearest airport along with distance in kms | Shillong, 7.2 km | |
| 11. | Nearest Town/City/District Headquarters along with distance in kms | Shillong , 11.6 km | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Umium village | | 13. | Name of the Applicant | Parthiv | | 14. | Registered Address | IOCL LPG Bottling Plant, Umium, Near Shillong, Ri-Bhoi, Meghalaya | | 15. | |
Address for correspondance: | Name of the Company | INDIAN OIL CORPORATION LIMITED MEGHALAYA | Name of the Applicant | Parthiv | Designation (Owner/ Partner/ CEO) | CMLPGE | Pin code | 781020 | E-mail | pdhar@indianoil.in | Telephone No. | 0891-2755528 | Fax No. | 0891- | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| 16. | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| 17. | Whether part of Interlinked projects? | No | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | 19. | If Yes, MoEF file number | N/A | Date of submission | N/A | | | | 21. | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | 23. | Whether any Forest Land Involved? | No | Area of Forest land Involved (hectares) | N/A | |
| 24. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | (a) Name of the Court | N/A | (b) Name of the Sub court | N/A | (c) Case No. | N/A | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | No | Bottling plant is proposed in Old
decommissioned POL depot land and Proposed
LPG plant will have storage of 3 x150 MT MSV
(Mounded Storage Vessel) | 1.2 | Clearance of existing land, vegetation and buildings? | No | Not Applicable | 1.3 | Creation of new land uses? | No | No change in land use. | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil testing were done. | 1.5 | Construction works? | Yes | Construction of MSV for LPG Storage(3x150
MT) mounded storagevessels, LPG Bottling Shed
and other auxiliary facilities. | 1.6 | Demolition works? | Yes | Old structures will be demolished. | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Not Applicable | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | The proposed structures are above ground | 1.9 | Underground works including mining or tunnelling? | No | The proposed structures are above ground | 1.10 | Reclamation works? | No | Not Applicable | 1.11 | Dredging? | No | Not Applicable | 1.12 | Offshore structures? | No | Not Applicable | 1.13 | Production and manufacturing processes? | No | Only Bottling of LPG | 1.14 | Facilities for storage of goods or materials? | Yes | Mounded Storage Vessels for bulk LPG storage
(3x150MT) | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | Septic Tank –4 KL followed by soak pit
ETP – 9 KL Treatment and Recycling | 1.16 | Facilities for long term housing of operational workers? | No | Majority of manpower will be recruited from
local people only. | 1.17 | New road, rail or sea traffic during construction or operation? | No | The site is well connected to roadway. | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Not Applicable | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | No closure or diversion of existing transport
routes or infrastructure will take place. | 1.20 | New or diverted transmission lines or pipelines? | No | Not required to divert transmission lines/
Pipelines. | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Not Applicable | 1.22 | Stream crossings? | No | Nil | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Existing Bore-well | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | Not Applicable | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | During construction private trucks will beused
for supply of metal, sand, cement andiron bar.
During operation Bulk LPG will be broughtto
through bulk tank trucks. | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not Applicable | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | Not Applicable | 1.28 | Influx of people to an area in either temporarily or permanently? | No | Semi-Skilled, Un skilled manpower from nearby
localvillages during construction
phasetemporarily. | 1.29 | Introduction of alien species? | No | No alien species will be introduced / encouraged. | 1.30 | Loss of native species or genetic diversity? | No | There will be no loss of native or genetic
diversity. | 1.31 | Any other actions? | No | Not Applicable | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 2.1 | Land especially undeveloped or agricultural land (ha) | No | Not Applicable | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Daily water requirement is met by own tube
wells. During operation water consumption will
be 5 KL for domestic. | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Mounds will be provided using sand and
protected by a retaining wall. Stone, aggregate,
sand, steel etc will be used for construction. | 2.5 | Forests and timber (source – MT) | No | Nil | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | 250 KVA from State Electricity Board
Alternatively, D.G set of capacity 1x160KVA
&2x250kVA will be installed as emergency
backup power supply. | 2.7 | Any other natural resources (use appropriate standard units) | No | No other natural resources will be usedexcept as
mentioned above. | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Bottling of LPG will be handled as per
OISD norms. | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Not Applicable | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | Available of LPG and reduction
inuse of fire wood.
? Employment directly and
indirectly
? Energy Security | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | Not Applicable | 3.5 | Any other causes | No | Not Applicable | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 4.1 | Spoil, overburden or mine wastes | No | No mine waste / mine activity. No
overburden soil. The excavatedmaterial,
during the foundation will be used for
filling. | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Municipal solid waste is disposedthrough
ULB. | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Old unused batteries shall be disposed
offthrough the buyback policy / authorized
agencies.
Used Lubricating Oil will bedisposed to
AuthorizedRecyclers. | 4.4 | Other industrial process wastes | No | Nil | 4.5 | Surplus product | No | No surplus product will be produced. | 4.6 | Sewage sludge or other sludge from effluent treatment | No | Not Applicable | 4.7 | Construction or demolition wastes | No | Not Applicable | 4.8 | Redundant machinery or equipment | No | Not Applicable | 4.9 | Contaminated soils or other materials | No | Not Applicable | 4.10 | Agricultural wastes | No | Not Applicable | 4.11 | Other solid wastes | No | Not Applicable | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | A. Point sources: D.G sets
1. 1 x 160 kVA
2. 2x250 kVA
3. Fire Engines.
B. Vehicular emissions: Movement of
trucks used for transportation of LPG | 5.2 | Emissions from production processes | No | No production process is involved | 5.3 | Emissions from materials handling including storage or transport | No | Not Applicable | 5.4 | Emissions from construction activities including plant and equipment | No | Not Applicable | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | No | Proper care should be taken during
construction for control of fugitive
emissions. | 5.6 | Emissions from incineration of waste | No | Will not be permitted. | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | No open air burning. | 5.8 | Emissions from any other sources | No | Will not be permitted. | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | DG set with acoustic enclosures as per
statuary norms. | 6.2 | From industrial or similar processes | Yes | Noise from operation of
processequipment, compressors, pumps,
etc. within permissible limits. | 6.3 | From construction or demolition | Yes | The construction work will be
restrictedfrom dawn to dusk. Measures
will be taken to limit the noise due to
construction equipment and movement of
vehicles. | 6.4 | From blasting or piling | No | No blasting or piling operation required. | 6.5 | From construction or operational traffic | Yes | There will be temporary increase in traffic
during construction stage and during
operating stage. During operational stage
parking facility will be there for TT and
bulk trucks | 6.6 | From lighting or cooling systems | No | Not Applicable | 6.7 | From any other sources | No | Not Applicable | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 7.1 | From handling, storage, use or spillage of hazardous materials | No | 0.5 KL of waste oil will be generated and
will be disposed through authorized
recyclers. | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | No | Domestic effluent will be treated in septic
tank followed by soak pit and cylinder
washing will be recycled. | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | D.G sets are fitted with stacks as per
CPCB guidelines. | 7.4 | From any other sources | No | Will not arise | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | No pollutants will be built up in the
Environment. Therefore no risk from
anysources. | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | All facilities will be operated as per OISD
norms | 8.2 | From any other causes | No | Will not arise. | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The project site falls under Seismic Zone
V as per Indian Standard Seismic Zoning
Map. All proposed structures as per
applicable norms. | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| No | Nil | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | No impact envisaged | 9.3 | Set a precedent for later developments | No | Positive Development in terms
ofEnvironment by end use of LPG
insteadof fossil fuels and through indirect
employment opportunities due to thePlant. | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | No cumulative effects will occur. | | (III) | Environmental Sensitivity | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | None within 15km radius from the
proposed project site. | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Upper Shillong Forest – 14 Km | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | None within 15km radius from the
proposed project site. | 4 | Inland, coastal, marine or underground waters | Yes | Umiam Lake – 1.1 Km | 5 | State, National boundaries | No | None within 15km radius from the
proposed project site | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | Yes | Umiam lake – 1.1 Km | 7 | Defence installations | No | None within 15km radius from the
proposed project site. | 8 | Densely populated or built-up area | Yes | Shillong is at 11.6 km from proposed
project site.
Umiam – 1.7 Km | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Hospitals, schools etc., are located in
Shillong which is within 15 Km of the
proposed project site.
ICAR Research Complex, Barapani is
adjacent to project site.
KendriyaVidyalaya, UmroiCantt. –
3.4 Km | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | Yes | Umiam Lake – 1.1 Km | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | None within 15km radius from the
proposed project site. | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | Project is falling under Seismic Zone -
V | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The correction have been made as per the instruction received | 22 Oct 2018 | 2. | NA | The project requires appraisal at State level by the SEAC/SEIAA | 17 Oct 2018 | | Additional Detail Sought : NIL | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | V.(i) | Name of Applicant | Parthiv | Designation | CMLPGE | Name of Company (Applicant Name should not be given here) | INDIAN OIL CORPORATION LIMITED MEGHALAYA | Address | IOCL LPG Bottling Plant, Umium, Near Shillong, Ri-Bhoi, Meghalaya |
|
|